CN106121707A - The most two-tube municipal administration and highway are grown up the ventilating system of shield tunnel and method of ventilation - Google Patents

The most two-tube municipal administration and highway are grown up the ventilating system of shield tunnel and method of ventilation Download PDF

Info

Publication number
CN106121707A
CN106121707A CN201610685662.6A CN201610685662A CN106121707A CN 106121707 A CN106121707 A CN 106121707A CN 201610685662 A CN201610685662 A CN 201610685662A CN 106121707 A CN106121707 A CN 106121707A
Authority
CN
China
Prior art keywords
shield
section
tunnel
civil engineering
smoke duct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610685662.6A
Other languages
Chinese (zh)
Other versions
CN106121707B (en
Inventor
梁艳
唐上明
范国刚
谢朝军
朱世友
贺维国
徐韬
姜宝臣
丁远见
褚凯
何潇剑
张瑞
魏雪
胡建国
曾亮
王东伟
曹楷
李金龙
魏志华
杨孝军
赖永进
廖荣
徐美智
余露茜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
Original Assignee
CRTG Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRTG Survey and Design Institute Co Ltd filed Critical CRTG Survey and Design Institute Co Ltd
Priority to CN201610685662.6A priority Critical patent/CN106121707B/en
Publication of CN106121707A publication Critical patent/CN106121707A/en
Application granted granted Critical
Publication of CN106121707B publication Critical patent/CN106121707B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/003Ventilation of traffic tunnels

Abstract

The invention belongs to municipal administration and vcehicular tunnel technical field, it is specifically related to the most two-tube a kind of municipal administration and highway is grown up the ventilating system of shield tunnel and method of ventilation, it is characterized in that, the top of described shield tunnel is provided with civil engineering smoke duct, the two ends of described shield tunnel are provided with the smoke evacuation ventilating shaft being connected with civil engineering smoke duct, are provided with smoke exhaust fan and air-valve in described smoke evacuation ventilating shaft;The middle part of described shield tunnel is longitudinally divided into shield A section, shield B section, shield C section successively along tunnel, described shield A section, the civil engineering smoke duct area equation of shield C section, described shield B section civil engineering smoke duct area is the 2/5 3/5 of shield A section civil engineering smoke duct area, and described shield B section and the shield tunnel two ends open cut secretly section of burying are respectively provided with jet blower.The present invention reduces the ventilation scheme dimensional requirement to shield section of growing up, reduce engineering construction difficulty and construction risk, saved engineering-built cost.

Description

The most two-tube municipal administration and highway are grown up the ventilating system of shield tunnel and method of ventilation
Technical field
The invention belongs to municipal administration and vcehicular tunnel technical field, be specifically related to the most two-tube municipal administration of one and highway is grown up shield The ventilating system in structure tunnel and method of ventilation.
Background technology
The selection of submerged tunnel air vent mode, with length of tunnel, traffic flow, running mode, hole environmental requirement, tunnel The many factors such as construction method are relevant.The current tunnel ventilation mode commonly used has complete horizontal, half horizontal, longitudinal ventilation mode and indulges Discharge fume to ventilation+emphasis.
Complete horizontal and semi-transverse ventilation mode need to arrange special air duct and Ventilator Room, and civil engineering costs investment is big, and the later stage ventilates Running cost is high, can effectively keep backlayering during fire, but owing to its air-flow provided is horizontal, climing with flue gas in tunnel Prolong direction vertical, it is impossible to effectively control flue gas and longitudinally spreading along tunnel.
Longitudinal ventilation mode can give full play to the traffic of automobile and rise pressure (Piston Action Wind), has good to upstream flue gas control Effect processed, has good flue gas for normal one-way traffic and controls effect.But under traffic jam and two-direction road operating mode, The upstream and downstream of burning things which may cause a fire disaster all there is a need to personnel and the vehicle evacuated, and longitudinal direction is the most distinguished and the most admirable is full of the whole Close Tunnel in burning things which may cause a fire disaster downstream by fire smoke Territory, personnel escape and fire suppression to downstream bring the biggest threat, thus longitudinal smoke evacuation system does not ensures that under burning things which may cause a fire disaster The safety of wind direction driver and conductor.
Longitudinal ventilation+emphasis fume exhausting type, arranges civil engineering smoke duct at tunnel upper, carries out longitudinal ventilation at ordinary times, can To give full play to the traffic liter pressure of automobile, during fire, carry out emphasis smoke evacuation, by opening the multiple exhaust openings near burning things which may cause a fire disaster, just Closely flue gas is discharged vehicular tunnel via smokejack, reduce the impact on staff in tunnel escape to greatest extent.
Based on this, current domestic the most two-tube a lot of shield tunnels the most all have employed longitudinal ventilation+point type central exhaust Scheme.Jet blower divides two sections of layouts (arranging along two ends, tunnel toward middle part), arranges civil engineering smoke duct in shield section simultaneously And jet blower, cause shield section bigger.The increase of shield section will bring engineering construction difficulty, construction risk and engineering The increase of cost, constrains shield method application in submerged tunnel of growing up to a certain extent.
Summary of the invention
In order to solve the problems referred to above, the invention provides a kind of jet blower and divide three sections of layouts, jet blower position and soil Build the ventilating system of shield tunnel under water and the method for ventilation that mutually stagger in smoke duct position.
The technical solution adopted in the present invention is:
The most two-tube a kind of municipal administration and highway are grown up the ventilating system of shield tunnel, it is characterised in that include shield tunnel, described The top of shield tunnel is provided with civil engineering smoke duct, and the two ends of described shield tunnel are provided with and are connected with civil engineering smoke duct Smoke evacuation ventilating shaft, be provided with smoke exhaust fan and air-valve in described smoke evacuation ventilating shaft;The middle part of described shield tunnel longitudinally depends on along tunnel Secondary shield A section, shield B section, the shield C section of being divided into, described shield A section, the civil engineering smoke duct area equation of shield C section, described Shield B section civil engineering smoke duct area is the 2/5-3/5 of shield A section civil engineering smoke duct area, described shield B section and shield tunnel The open cut secretly section of burying in two ends, road is respectively provided with jet blower.
The more excellent area of described shield B section civil engineering smoke duct is the 1/2 of shield A section civil engineering smoke duct area.
Mutually stagger with civil engineering smoke duct position in the jet blower position being positioned at described shield B section, described shield B section Have overlapping in jet blower and shield A section, the projection of shield C section civil engineering smoke duct transverse section.
The most two-tube a kind of municipal administration and highway are grown up the method for ventilation of shield tunnel, comprise the following steps:
(1) described shield tunnel is carried out longitudinal induced draught by arranging jet blower;
(2) by the civil engineering smoke duct being arranged in described shield tunnel, and the shield being connected with this civil engineering smoke duct The smoke evacuation of two ends, tunnel ventilating shaft, smoke exhaust fan, air-valve, carry out emphasis smoke evacuation during fire;
(3) the shield section longitudinal direction whole process of described shield tunnel is provided with separate civil engineering smoke duct, and longitudinally divides along tunnel Become three sections;The civil engineering smoke duct area of three sections is unequal, when shield A section or the section breaking out of fire of shield C, selects from burning things which may cause a fire disaster relatively Near jet blower carries out single-ended smoke evacuation;When the section breaking out of fire of shield B, the jet blower at shield tunnel two ends is arranged simultaneously Cigarette.
The invention have the benefit that
1, the submerged tunnel draft type of the present invention is simple, on the basis of conventional longitudinal ventilation+emphasis smoke-discharging and ventilating mode, logical Cross the method that jet blower divides three sections of layouts, jet blower position mutually to stagger with civil engineering smoke duct position, both ensure that logical Wind and the functional effect of smoke evacuation, decrease again the dimensional requirement to shield section, reduces engineering construction difficulty and construction risk, Save engineering-built cost;
2, the present invention is applicable to the most two-tube municipal administration and highway shield tunnel, and two ends, tunnel exist the open cut secretly section of burying.
Accompanying drawing explanation
Fig. 1: Tunnel Ventilation System arranges schematic diagram;
Fig. 2: Tunnel Ventilation System fire working smoke evacuation schematic diagram (fire is positioned at shield A section or C section);
Fig. 3: Tunnel Ventilation System fire working smoke evacuation schematic diagram (fire is positioned at shield B section);
Fig. 4-Fig. 5: shield A section, shield C section schematic cross-sectional view (shield Blower-free section);
Fig. 6-Fig. 7: shield B section schematic cross-sectional view (shield has fan section).
Detailed description of the invention
In Fig. 1-7,1-jet blower, 2-discharges fume ventilating shaft, 3-runway, 4-civil engineering smoke duct, 5-smoke exhaust fan and wind Valve, 6-shield tunnel, 7-shield A section, 8-shield B section, 9-shield C section, the 10-open cut secretly section of burying, 11-tunnel lower floor evacuates logical Road, 12-tunnel bottom structure line, 13-airflow direction, 14-fire point, 15-tunnel roof construction line.
Embodiment
The most two-tube a kind of municipal administration and highway are grown up the ventilating system of shield tunnel, including shield tunnel 6, shield tunnel 6 Top be provided with civil engineering smoke duct 4, the two ends of shield tunnel 6 are provided with the Smoke being connected with civil engineering smoke duct 4 Well 2, is provided with smoke exhaust fan and air-valve 5 in smoke evacuation ventilating shaft 2;The middle part of shield tunnel 6 is longitudinally divided into shield A section successively along tunnel 7, shield B section 8, shield C section 9, shield A section 7, civil engineering smoke duct 4 area equation of shield C section 9, the civil engineering row of shield B section 8 Cigarette air channel 4 area is the 2/5-3/5 of civil engineering smoke duct 4 area of shield A section 7, shield B section 8 and shield tunnel 6 two ends open cut Secretly the section of burying 10 is respectively provided with jet blower 1.
The 1/2 of civil engineering smoke duct 4 area that more excellent area is shield A section 7 of the civil engineering smoke duct 4 of shield B section 8.
Mutually stagger with civil engineering smoke duct 4 position in jet blower 1 position being positioned at shield B section 8, the jet of shield B section 8 Have overlapping in blower fan 1 and shield A section 7, the projection of shield C section 9 civil engineering smoke duct 4 transverse section.
The most two-tube a kind of municipal administration and highway are grown up the method for ventilation of shield tunnel, comprise the following steps:
(1) shield tunnel 6 is carried out longitudinal induced draught by arranging jet blower 1;
(2) by the civil engineering smoke duct 4 being arranged in shield tunnel 6, and the shield tunnel being connected with this civil engineering smoke duct 4 Two ends, road 6 smoke evacuation ventilating shaft 2, smoke exhaust fan and air-valve 5, carry out emphasis smoke evacuation during fire;
(3) shield section longitudinal direction whole process is provided with separate civil engineering smoke duct 4, and is divided longitudinally into three sections along shield tunnel 6;Three Civil engineering smoke duct 4 area of section is unequal, when shield A section 7 or section 9 breaking out of fire of shield C, selects penetrating close to burning things which may cause a fire disaster Flow fan 1 carries out single-ended smoke evacuation;When the section breaking out of fire of shield B8, the jet blower 1 at shield tunnel 6 two ends is arranged simultaneously Cigarette.
Below by combining accompanying drawing, the present invention is described further.
The invention discloses a kind of 1 point three sections layouts of jet blower, jet blower 1 position and civil engineering smoke duct 4 position The most two-tube shield tunnel ventilating system and the method for ventilation (referring to Fig. 1) of growing up mutually staggered, is specifically described as follows:
1) to the most two-tube shield tunnel of growing up, in often pipe tunnel row track 3, carry out longitudinally luring by arranging jet blower 1 Conducting wind, direction of ventilation is consistent with garage direction, is aerated taking a breath by vehicle Piston Action Wind during nominal situation, unlatching during obstruction Jet blower 1 is aerated ventilation.
2) to the most two-tube shield tunnel of growing up, in often pipe tunnel row track 3, by being arranged in shield tunnel 6 Civil engineering smoke duct 4, and two ends, tunnel smoke evacuation ventilating shaft 2, smoke exhaust fan and the air-valve 5 etc. being connected with this civil engineering smoke duct 4 Assembly, carries out emphasis smoke evacuation during fire.
3) two-tube shield section runway longitudinal direction whole process is provided with separate civil engineering smoke duct 4, and longitudinally divides along tunnel Become three sections (shield A section 6, shield B section 7, shield C sections 8).When shield A section 6 or section 9 breaking out of fire of shield C, select from burning things which may cause a fire disaster Nearer jet blower 1 carries out single-ended smoke evacuation (referring to Fig. 2);When section 8 breaking out of fire of shield B, the jet blower 1 at two ends, tunnel Carry out discharge fume (referring to Fig. 3) simultaneously.So, civil engineering smoke duct 4 area of three sections is designed as unequal, shield A section 7 He Shield C section 9 is designed (referring to Fig. 4) by required normal civil engineering smoke duct 4 area S, shield B section civil engineering smoke duct 4 Area is designed by about S/2.
4) selection of position is set about jet blower 1, in order to reduce shield section, 1 point three sections layouts of jet blower, cloth Seated position refers to Fig. 5 corresponding to shield B section 8() and two ends, the tunnel open cut secretly section of burying 10.Wherein it is positioned at the jet wind of shield B section 6 Machine 1 and shield A section 7 and shield C section 9 civil engineering smoke duct 4 transverse section project have overlapping.
It is respectively provided with jet blower 1, in shield A section 7 and shield C section 9 in shield B section 8 and shield tunnel 6 two ends open excavation section It is not provided with jet blower 1.Owing to the position civil engineering smoke duct 4 all with normal size that arranges of jet blower 1 arranges position phase Stagger mutually, decrease the dimensional requirement to shield section, can reach the mesh ground reducing shield diameter, reduce engineering construction difficulty And construction risk, save engineering-built cost.
This method of ventilation is applicable to the most two-tube municipal administration and highway shield tunnel, and two ends, tunnel exist the open cut secretly section of burying.
The local carried out the present invention in two-tube grow up shield tunnel ventilation form and details changes, without departing from this Bright claims limited range.
Above 1 embodiment of the present invention is described in detail, but content has been only presently preferred embodiments of the present invention, no The practical range for limiting the present invention can be considered.All impartial changes made according to the present patent application scope and improvement etc., all Within should still belonging to the patent covering scope of the present invention.

Claims (4)

1. the most two-tube municipal administration and highway are grown up the ventilating system of shield tunnel, it is characterised in that include shield tunnel, institute The top stating shield tunnel is provided with civil engineering smoke duct, and the two ends of described shield tunnel are provided with and civil engineering smoke duct phase Smoke evacuation ventilating shaft even, is provided with smoke exhaust fan and air-valve in described smoke evacuation ventilating shaft;The middle part of described shield tunnel is along tunnel longitudinally It is divided into shield A section, shield B section, shield C section, described shield A section, the civil engineering smoke duct area equation of shield C section, institute successively State the 2/5-3/5 that shield B section civil engineering smoke duct area is shield A section civil engineering smoke duct area, described shield B section and shield The open cut secretly section of burying in two ends, tunnel is respectively provided with jet blower.
The most two-tube a kind of municipal administration the most according to claim 1 and highway are grown up the ventilating system of shield tunnel, its feature Being, the more excellent area of described shield B section civil engineering smoke duct is the 1/2 of shield A section civil engineering smoke duct area.
The most two-tube a kind of municipal administration the most according to claim 1 and highway are grown up the ventilating system of shield tunnel, its feature Being, mutually stagger with civil engineering smoke duct position in the jet blower position being positioned at described shield B section, penetrating of described shield B section Have overlapping in flow fan and shield A section, the projection of shield C section civil engineering smoke duct transverse section.
4. the most two-tube municipal administration and highway are grown up a method of ventilation for shield tunnel, comprise the following steps:
(1) described shield tunnel is carried out longitudinal induced draught by arranging jet blower;
(2) by the civil engineering smoke duct being arranged in described shield tunnel, and the shield being connected with this civil engineering smoke duct The smoke evacuation of two ends, tunnel ventilating shaft, smoke exhaust fan, air-valve, carry out emphasis smoke evacuation during fire;
(3) the shield section longitudinal direction whole process of described shield tunnel is provided with separate civil engineering smoke duct, and longitudinally divides along tunnel Become three sections;The civil engineering smoke duct area of three sections is unequal, when shield A section or the section breaking out of fire of shield C, selects from burning things which may cause a fire disaster relatively Near jet blower carries out single-ended smoke evacuation;When the section breaking out of fire of shield B, the jet blower at shield tunnel two ends is arranged simultaneously Cigarette.
CN201610685662.6A 2016-08-19 2016-08-19 Underwater two-tube municipal administration and highway are grown up the ventilating system and method for ventilation of shield tunnel Active CN106121707B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610685662.6A CN106121707B (en) 2016-08-19 2016-08-19 Underwater two-tube municipal administration and highway are grown up the ventilating system and method for ventilation of shield tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610685662.6A CN106121707B (en) 2016-08-19 2016-08-19 Underwater two-tube municipal administration and highway are grown up the ventilating system and method for ventilation of shield tunnel

Publications (2)

Publication Number Publication Date
CN106121707A true CN106121707A (en) 2016-11-16
CN106121707B CN106121707B (en) 2019-04-19

Family

ID=57278790

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610685662.6A Active CN106121707B (en) 2016-08-19 2016-08-19 Underwater two-tube municipal administration and highway are grown up the ventilating system and method for ventilation of shield tunnel

Country Status (1)

Country Link
CN (1) CN106121707B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110714795A (en) * 2019-10-17 2020-01-21 聊城大学 Ventilation device for underwater suspension tunnel
CN111720151A (en) * 2020-06-10 2020-09-29 中铁第五勘察设计院集团有限公司 Tunnel structure with rectangular cross section
CN113530590A (en) * 2021-07-30 2021-10-22 中铁第四勘察设计院集团有限公司 Double-hole one-way long and large underwater highway tunnel ventilation system and ventilation method thereof

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1865662A (en) * 2006-06-20 2006-11-22 浙江省交通规划设计研究院 Smoke emission method in tunnel and tunnel ventilation system with separate smoke-emission device
DE102007040237A1 (en) * 2007-08-25 2009-02-26 Horst-Dieter Dipl.-Ing. Rector Air extraction system for active combating of fire in traffic tunnel creates oppositely-directed airflows from both directions after outbreak of fire and directs these to source of fire or smoke at calculated speed
CN101509392A (en) * 2009-03-13 2009-08-19 上海市隧道工程轨道交通设计研究院 Highway tunnel exhaust port opening method
CN202081896U (en) * 2011-06-01 2011-12-21 上海磁浮交通发展有限公司 Internal space arranging structure for magnetic levitation tunnel
CN202170803U (en) * 2011-08-01 2012-03-21 湖南省交通规划勘察设计院 Very long, deep-buried highway tunnel parallel adit ventilation operation system
CN102720519A (en) * 2012-06-21 2012-10-10 广州地铁设计研究院有限公司 Novel tunnel ventilation system for subway station
CN103939124A (en) * 2014-05-13 2014-07-23 武汉中交交通工程有限责任公司 Ventilation, smoke discharge and evacuation system for underwater single-tube double-layer shield traffic tunnel
CN104153805A (en) * 2014-07-31 2014-11-19 上海市城市建设设计研究总院 Intra-tunnel smoke discharge system and method
CN204002896U (en) * 2014-04-11 2014-12-10 中铁第四勘察设计院集团有限公司 One-tunnel one-track subway tunnel natural ventilating structure
CN104533498A (en) * 2014-12-18 2015-04-22 西南交通大学 Point exhaust type subway tunnel fire ventilation and smoke exhaust system
CN104675424A (en) * 2015-02-10 2015-06-03 招商局重庆交通科研设计院有限公司 Underwater tunnel ventilation system and ventilation method
CN204419226U (en) * 2014-12-18 2015-06-24 西南交通大学 Point row formula subway tunnel ventilation smoke extraction system
CN205895292U (en) * 2016-08-19 2017-01-18 中铁隧道勘测设计院有限公司 Double -barrelled municipal administration and highway shield tunnel's ventilation system that grows up under water

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1865662A (en) * 2006-06-20 2006-11-22 浙江省交通规划设计研究院 Smoke emission method in tunnel and tunnel ventilation system with separate smoke-emission device
DE102007040237A1 (en) * 2007-08-25 2009-02-26 Horst-Dieter Dipl.-Ing. Rector Air extraction system for active combating of fire in traffic tunnel creates oppositely-directed airflows from both directions after outbreak of fire and directs these to source of fire or smoke at calculated speed
CN101509392A (en) * 2009-03-13 2009-08-19 上海市隧道工程轨道交通设计研究院 Highway tunnel exhaust port opening method
CN202081896U (en) * 2011-06-01 2011-12-21 上海磁浮交通发展有限公司 Internal space arranging structure for magnetic levitation tunnel
CN202170803U (en) * 2011-08-01 2012-03-21 湖南省交通规划勘察设计院 Very long, deep-buried highway tunnel parallel adit ventilation operation system
CN102720519A (en) * 2012-06-21 2012-10-10 广州地铁设计研究院有限公司 Novel tunnel ventilation system for subway station
CN204002896U (en) * 2014-04-11 2014-12-10 中铁第四勘察设计院集团有限公司 One-tunnel one-track subway tunnel natural ventilating structure
CN103939124A (en) * 2014-05-13 2014-07-23 武汉中交交通工程有限责任公司 Ventilation, smoke discharge and evacuation system for underwater single-tube double-layer shield traffic tunnel
CN104153805A (en) * 2014-07-31 2014-11-19 上海市城市建设设计研究总院 Intra-tunnel smoke discharge system and method
CN104533498A (en) * 2014-12-18 2015-04-22 西南交通大学 Point exhaust type subway tunnel fire ventilation and smoke exhaust system
CN204419226U (en) * 2014-12-18 2015-06-24 西南交通大学 Point row formula subway tunnel ventilation smoke extraction system
CN104675424A (en) * 2015-02-10 2015-06-03 招商局重庆交通科研设计院有限公司 Underwater tunnel ventilation system and ventilation method
CN205895292U (en) * 2016-08-19 2017-01-18 中铁隧道勘测设计院有限公司 Double -barrelled municipal administration and highway shield tunnel's ventilation system that grows up under water

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110714795A (en) * 2019-10-17 2020-01-21 聊城大学 Ventilation device for underwater suspension tunnel
CN110714795B (en) * 2019-10-17 2021-02-26 聊城大学 Ventilation device for underwater suspension tunnel
CN111720151A (en) * 2020-06-10 2020-09-29 中铁第五勘察设计院集团有限公司 Tunnel structure with rectangular cross section
CN111720151B (en) * 2020-06-10 2021-10-22 中铁第五勘察设计院集团有限公司 Tunnel structure with rectangular cross section
CN113530590A (en) * 2021-07-30 2021-10-22 中铁第四勘察设计院集团有限公司 Double-hole one-way long and large underwater highway tunnel ventilation system and ventilation method thereof

Also Published As

Publication number Publication date
CN106121707B (en) 2019-04-19

Similar Documents

Publication Publication Date Title
CN103939124B (en) One single-tube double-layer shield traffic tunnel ventilation smoke exhaust and evacuating system under water
CN106121707A (en) The most two-tube municipal administration and highway are grown up the ventilating system of shield tunnel and method of ventilation
CN103306702B (en) A kind of tunnel ventilation construction air filling type spacer assembly
CN203452826U (en) Ventilating system used for city underground annular tunnel
CN205895292U (en) Double -barrelled municipal administration and highway shield tunnel's ventilation system that grows up under water
CN203347823U (en) Inflatable isolating device for tunnel ventilation construction
CN106168140A (en) Single tube levels municipal administration under water and highway are grown up shield tunnel ventilating system and method
CN205895293U (en) Lower floor's municipal administration and highway shield tunnel ventilation system that grows up is attend to single tube under water
CN108561169A (en) The combined type Ventilating Design Method in Urban Underground interchange tunnel
CN102425443B (en) Tunnel smoke control device for supplying air from parallel tunnels
CN108343459A (en) It is a kind of can be to the ventilation inclined shaft of double track tunnel supply and exhaust
CN107477827A (en) A kind of wall hanging purification fresh air shares the installation method in air conditioner ventilation hole
CN209042677U (en) A kind of fire-fighting evacuation stair pressurization ventilating shaft and new ventilating shaft Striping
KR101191592B1 (en) Selective point extraction ventilation method applied to active control
CN208546182U (en) Subway detour ventilating system with shield door
CN109707395A (en) Double-layer shield tunnel and smokejack setting method with upper and lower level smokejack
CN108756990A (en) Subway detour ventilating system with shield door and its operation method
CN210003320U (en) kinds of tunnel ventilation structure
CN207278289U (en) The ventilating system of city tunnel
CN205477703U (en) Tunnel ventilation structure
CN204783084U (en) Compound ground runner band corridor firebreak device
CN104929672B (en) Compound underground ring corridor fire prevention isolation device and method
CN208057144U (en) A kind of Long Traffic Tunnels region couples formula smoke control system
CN204984471U (en) Tunnel ventilation structure for highway
CN105041364B (en) Compound underground ring corridor fire separation device and method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190211

Address after: 300000 Tianjin Free Trade Test Zone (Airport Economic Zone) No. 36 West Central Road

Applicant after: CHINA RAILWAY LIUYUAN GROUP CO., LTD.

Address before: 300000 Hongqiao District, Tianjin City, Bridge South East Road

Applicant before: Zhongtie Tunnel Survey and Design Inst., Ltd.

GR01 Patent grant