CN106089244A - Frame props up arched tunnel lining structure - Google Patents
Frame props up arched tunnel lining structure Download PDFInfo
- Publication number
- CN106089244A CN106089244A CN201610410198.XA CN201610410198A CN106089244A CN 106089244 A CN106089244 A CN 106089244A CN 201610410198 A CN201610410198 A CN 201610410198A CN 106089244 A CN106089244 A CN 106089244A
- Authority
- CN
- China
- Prior art keywords
- frame
- tunnel
- props
- section
- abutment wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 42
- 239000004746 geotextile Substances 0.000 claims description 5
- 239000011435 rock Substances 0.000 claims description 5
- 239000000758 substrate Substances 0.000 claims description 5
- 239000011449 brick Substances 0.000 claims description 2
- 238000007596 consolidation process Methods 0.000 claims description 2
- 239000000463 material Substances 0.000 claims description 2
- 230000000694 effects Effects 0.000 abstract description 5
- 230000006378 damage Effects 0.000 abstract description 4
- 230000007812 deficiency Effects 0.000 abstract description 4
- 239000000126 substance Substances 0.000 abstract description 2
- 239000004567 concrete Substances 0.000 description 5
- 239000003673 groundwater Substances 0.000 description 4
- 239000011378 shotcrete Substances 0.000 description 4
- 206010030113 Oedema Diseases 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 241000521257 Hydrops Species 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000002146 bilateral effect Effects 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000008030 elimination Effects 0.000 description 1
- 238000003379 elimination reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 230000008595 infiltration Effects 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
- 238000002372 labelling Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/107—Reinforcing elements therefor; Holders for the reinforcing elements
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F16/00—Drainage
- E21F16/02—Drainage of tunnels
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Frame props up arched tunnel lining structure, with be prevented effectively from rain flood subsoil water in season increase severely but discharge capacity deficiency causes abutment wall structure crack to destroy, reduce the subsoil water effect to tunnel-liner polycrystalline substance that even eliminates, and then eliminate the rain flood subsoil water in the season destruction risk to liner structure.Including arch wall preliminary bracing structure, secondary liner structure be positioned at waterproof and water drainage system between the two, secondary liner structure includes crown section, abutment wall section and inverted arch section.Described abutment wall section is that abutment wall frame props up structure, as the carrying structure of crown section.Described inverted arch section is the tunnel bottom framework structure with internal cavities, and the end face of tunnel bottom framework structure lays base plate;The hoop port of described waterproof and water drainage system guides the internal cavities of tunnel bottom framework structure into.
Description
Technical field
The present invention relates to tunnel lining structure, the hard rock tunnel grown particularly to a kind of subsoil water or karst area tunnel
Road lining structure.
Background technology
Enter 21st century, along with railway construction in China high speed development, speed per hour 200km above high standard double track railway
Build more and more, the many factors such as especially in western mountainous areas, circuit show line is big by sweep, topographic and geologic complicated condition
Restriction, length of tunnel, scale increase sharply.Especially in karst area, grow due to karst and subsoil water and there is complexity, various
The feature such as property and irregularities, it is more and more higher that major long tunnel builds risk particularly operations risks.
In recent years, there occurs during suitable ten thousand, Shanghai elder brother, the expensive Railway Tunnel operation such as extensively some ballastless track bed deformation,
Inverted arch and fill the water damage event such as protuberance, lining side wall (generally abutment wall substrate to upwards two meters of scopes within) cracking, causes
Railway Design, construct, build and run the great attention of each side.
Tradition double track tunnel lining cutting typically uses the liner structure form of bent wall band inverted arch, and inverted arch uses Concrete Filled
As railway roadbed basis, in construction, inverted arch is filled with inverted arch and is separately poured.Central drain+bilateral ditch, middle edema with the heart involved are set in tunnel
Ditch is placed in the obturator on inverted arch.Underground water discharge path is: country rock → preliminary bracing → draining blind pipe → lateral sulcus → horizontal stroke
Tunnel is entered by preliminary bracing infiltration via draining blind pipe ejectment to drain pipe → Central drain, the i.e. water of tunnel structure periphery
Central drain within structural body, outside final discharge hole.The defect of conventional drainage systems maximum is: Central drain is located at tunnel
Within road structure, the periphery subsoil water of main ejectment main ejectment arch wall scope, the hydrops below tunnel inverted arch cannot effectively draw
Row.Especially in the close region of ground hydraulic connection, under continuous rainfall or rainstorm weather, because of groundwater run off abruptly increase, traditional
Drainage system often cannot ejectment in time in the gutter in tunnel structure body, thus cause level of ground water drastically to raise.?
Under high hydraulic pressure effect, cause inverted arch at the bottom of tunnel or inverted arch to fill protuberance, thus destroy ballast bed structure.
Therefore, optimize liner structure and drainage system, it is ensured that draining is unobstructed, reduce even eliminate side wall lining behind and
Tunnel bottom water pressure, becomes reduction tunnel, karst area water damage risk, it is ensured that operation security in the urgent need to.
Summary of the invention
The technical problem to be solved is to provide a kind of frame and props up arched tunnel lining structure, to be prevented effectively from rain flood
Season subsoil water increase severely but discharge capacity deficiency causes abutment wall structure crack to destroy, reduce even elimination subsoil water to tunnel-liner
The effect of polycrystalline substance, and then eliminate the rain flood subsoil water in the season destruction risk to liner structure.
The technical solution adopted for the present invention to solve the technical problems is as follows:
Frame of the present invention props up arched tunnel lining structure, including arch wall preliminary bracing structure, secondary liner structure be positioned at two
Waterproof and water drainage system between person, secondary liner structure includes crown section, abutment wall section and inverted arch section, it is characterized in that: described abutment wall section
Structure is propped up, as the carrying structure of crown section for abutment wall frame;Described inverted arch section is the tunnel bottom framework structure with internal cavities, tunnel
The end face of bottom framework structure lays base plate;The hoop port of described waterproof and water drainage system guides the internal cavities of tunnel bottom framework structure into.
The invention has the beneficial effects as follows, use frame to prop up arch lining structure and replace tradition liner structure form, as arch
The carrying structure of secondary lining, substitutes abutment wall secondary lining form concrete in tradition lining cutting, can save concrete, the most favorably
In abutment wall ground water discharge behind;Under tunnel floor, frame structure system is set, can guarantee that at the bottom of tunnel, draining is unobstructed, subsoil water not with
Tunnel floor is directly had an effect, it is to avoid traditional lining cutting causes suitable due to spilled water hole impeded drainage at the bottom of abutment wall or drainability deficiency
Inverted arch hydraulic pressure is uprushed and is caused tunnel bottom structure to destroy;Realizing the external draining of liner structure, arch wall scope subsoil water is introduced directly into tunnel
In space under road base plate, it is prevented effectively from tradition lining cutting and pours in owing to rain flood subsoil water in season excessive lateral sulcus drainability is inadequate
In railway roadbed, it is ensured that the smooth and easy eliminating of subsoil water and avoid causing tunnel bottom structure cracking protuberance.
Accompanying drawing explanation
This specification includes following five width accompanying drawings:
Fig. 1 is the section structure schematic diagram that frame of the present invention props up arched tunnel lining structure;
Fig. 2 be Fig. 1 be A local enlarged drawing;
Fig. 3 is the profile of I-I line along Fig. 1;
Fig. 4 is the profile of II-II line along Fig. 1;
Fig. 5 is the profile of III-III line along Fig. 1;
Component shown in figure, toponym and corresponding labelling: arch wall preliminary bracing structure 10, arch wall shotcrete layer
10a, arch wall steelframe 10b, arch wall system anchor bolt 10c, confining bed 11;Waterproof and water drainage system 20, non-woven geotextile 20a, circle draining
Blind pipe 20b, splash guard 20c, spilled water hole 21;Crown section 30, filling wall 31, base plate 32;Abutment wall frame props up structure, frame props up foundation beam
41, frame Zhi Zhizhu 42, frame Zhi Dingliang 42;Tunnel bottom framework structure, foundation beam 51, crossbeam 52, short column 53;
Detailed description of the invention
The present invention is further described with embodiment below in conjunction with the accompanying drawings.
With reference to Fig. 1, the frame of the present invention props up arched tunnel lining structure, including arch wall preliminary bracing structure 10, secondary lining
Structure and be positioned at waterproof and water drainage system between the two, secondary liner structure includes crown section 30, abutment wall section and inverted arch section.Described limit
Wall section is that abutment wall frame props up structure, as the carrying structure of crown section 30, substitutes abutment wall secondary lining mould in tradition lining cutting and builds coagulation
Soil, can save the ground water discharge behind of concrete, the most beneficially abutment wall.Described inverted arch section is to have the tunnel underframe of internal cavities
Shelf structure, the end face laying base plate 32 of tunnel bottom framework structure, base plate 32 underframe internal cavities leads to as the longitudinal drainage in tunnel
Road, can guarantee that at the bottom of tunnel, draining is unobstructed, subsoil water is not directly had an effect with tunnel floor, it is to avoid traditional lining cutting is at the bottom of due to abutment wall
Spilled water hole impeded drainage or drainability deficiency cause suitable inverted arch hydraulic pressure and uprush and cause tunnel bottom structure to destroy.Described waterproof and water drainage system
Hoop port guide the interior longitudinal drainage passage of tunnel bottom framework structure into, base plate 32 can be along tunnel center line longitudinally on base plate 32
Portion's spaced openings, as longitudinal drainage CHCK well head.
The hoop port of described waterproof and water drainage system guides the internal cavities of tunnel bottom framework structure into, it is achieved the external row of liner structure
Water, arch wall scope subsoil water is introduced directly in the space under tunnel floor, is prevented effectively from tradition lining cutting due to rain flood underground in season
Water excessive lateral sulcus drainability not pours in railway roadbed, it is ensured that the smooth and easy eliminating of subsoil water and avoid causing tunnel bottom structure to ftracture
Protuberance.、
With reference to Fig. 2, arch wall shotcrete layer 10a that described arch wall preliminary bracing structure 10 includes covering arch wall country rock and
Arch wall system anchor bolt 10c along arch wall quincuncial arrangement.Cloth can be spaced along tunnel excavation direction in arch wall shotcrete layer 10a
If arch wall steelframe 10b.Bar-mat reinforcement is added in arch wall shotcrete layer 10a.
With reference to Fig. 3, described abutment wall frame props up structure and is propped up foundation beam 41, frame Zhi Zhizhu 42 and frame Zhi Dingliang 42 by frame and constitute.Frame
Foundation beam 41 is embedded in tunnel base plinth along tunnel longitudinal extension, and frame Zhi Dingliang 42 is along tunnel longitudinal extension, frame Zhi Zhizhu 42
The longitudinally spaced setting along tunnel, foundation beam 41 is propped up respectively in its upper and lower two ends with frame, frame Zhi Dingliang 42 consolidates.Described abutment wall frame props up knot
The filling wall 31 built by laying bricks or stones by the light block material is set in the sash of structure.
With reference to Fig. 4 and Fig. 5, described tunnel bottom framework structure longitudinally spaced laying along tunnel, by laying longitudinally spaced along tunnel
Foundation beam 51, crossbeam 52 and upper and lower side respectively with foundation beam 51, crossbeam 52 consolidation short column 53 constitute, foundation beam 51 embed ground
In base.Substrate close layer 11 is set between described foundation beam 51 for closing exposed country rock surface, prevents current scour and sapping
Foundation.Foundation beam 51 end face flushes with substrate close layer 11 surface.
Seeing figures.1.and.2, described waterproof and water drainage system 20 includes non-woven geotextile 20a that arch wall segment limit lays and waterproof
Plate 20c, and the longitudinally spaced circle draining blind pipe 20b being laid between non-woven geotextile 20a and splash guard 20c along tunnel.Institute
The bottom stating filling wall 31 arranges spilled water hole 21, and the two ends of circle draining blind pipe 20b are directed directly at spilled water hole 21.
The above frame of the present invention that simply explains through diagrams props up some principles of arched tunnel lining structure, be not intended to by
Shown in the present invention is confined to and in described concrete structure and the scope of application, thus every corresponding amendment being likely utilized with
And equivalent, belong to the apllied the scope of the claims of the present invention.
Claims (7)
1. frame props up arched tunnel lining structure, including arch wall preliminary bracing structure (10), secondary liner structure and be positioned at both it
Between waterproof and water drainage system, secondary liner structure includes crown section (30), abutment wall section and inverted arch section, it is characterized in that: described abutment wall section
Structure is propped up, as the carrying structure of crown section (30) for abutment wall frame;Described inverted arch section is to have the tunnel bottom framework knot of internal cavities
Structure, end face laying base plate (32) of tunnel bottom framework structure, base plate (32) underframe internal cavities leads to as the longitudinal drainage in tunnel
Road, the hoop port of described waterproof and water drainage system guides the interior longitudinal drainage passage of tunnel bottom framework structure into.
2. frame as claimed in claim 1 props up arched tunnel lining structure, it is characterized in that: described abutment wall frame props up structure by frame fork group
Plinth beam (41), frame Zhi Zhizhu (42) and frame Zhi Dingliang (42) are constituted, and frame props up foundation beam (41) and is embedded in tunnel base plinth along tunnel
Longitudinal extension, frame Zhi Dingliang (42) is along tunnel longitudinal extension, frame Zhi Zhizhu (42) longitudinally spaced setting along tunnel, its upper and lower two ends
Foundation beam (41), frame Zhi Dingliang (42) consolidation is propped up respectively with frame.
3. frame as claimed in claim 2 props up arched tunnel lining structure, it is characterized in that: described abutment wall frame props up in the sash of structure
The filling wall (31) built by laying bricks or stones by the light block material is set.
4. frame as claimed in claim 1 props up arched tunnel lining structure, it is characterized in that: described tunnel bottom framework structure is vertical along tunnel
To interval lay, by the foundation beam (51) of laying longitudinally spaced along tunnel, crossbeam (52) and upper and lower side respectively with foundation beam (51),
The short column (53) that crossbeam (52) consolidates is constituted, and foundation beam (51) embeds in ground.
5. frame as claimed in claim 4 props up arched tunnel lining structure, it is characterized in that: described foundation beam arranges substrate between (51)
Confining bed (11) is for closing exposed country rock surface, and foundation beam (51) end face flushes with substrate close layer (11) surface.
6. frame as claimed in claim 1 props up arched tunnel lining structure, it is characterized in that: described waterproof and water drainage system (20) includes arch
Non-woven geotextile (20a) that wall segment limit is laid and splash guard (20c), and longitudinally spaced along tunnel it is laid in non-woven geotextile
(20a) the circle draining blind pipe (20b) and between splash guard (20c).
7. the frame as described in claim 2 or 6 props up arched tunnel lining structure, it is characterized in that: the bottom of described filling wall (31)
Arranging spilled water hole (21), the two ends of circle draining blind pipe (20b) are directed directly to spilled water hole (21) place.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610410198.XA CN106089244A (en) | 2016-06-12 | 2016-06-12 | Frame props up arched tunnel lining structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610410198.XA CN106089244A (en) | 2016-06-12 | 2016-06-12 | Frame props up arched tunnel lining structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106089244A true CN106089244A (en) | 2016-11-09 |
Family
ID=57228734
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610410198.XA Pending CN106089244A (en) | 2016-06-12 | 2016-06-12 | Frame props up arched tunnel lining structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106089244A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107524458A (en) * | 2017-08-30 | 2017-12-29 | 中铁二院工程集团有限责任公司 | A kind of tunnel lining structure with tunnel bottom deformation allowance |
CN107905809A (en) * | 2017-12-27 | 2018-04-13 | 中铁二院工程集团有限责任公司 | Diplopore hollow, rectangular section load bearing beam road cutting type protecting arched tunnel liner structure and separate type drainage system |
CN107905808A (en) * | 2017-12-27 | 2018-04-13 | 中铁二院工程集团有限责任公司 | The foundation carrying of falling groove-shaped longitudinal beam is without tunnel bottom structure arch lining cutting and its drainage system |
CN107905812A (en) * | 2017-12-27 | 2018-04-13 | 中铁二院工程集团有限责任公司 | The hollow compound arch tunnel-liner in type tunnel bottom and its drainage system construction of falling from power |
CN107965327A (en) * | 2017-12-27 | 2018-04-27 | 中铁二院工程集团有限责任公司 | Arcuately tunnel bottom liner structure and its drainage system |
CN108005688A (en) * | 2017-12-27 | 2018-05-08 | 中铁二院工程集团有限责任公司 | The external dewatering type lining cutting of buried lateral sulcus and its drainage system |
CN108222960A (en) * | 2017-12-27 | 2018-06-29 | 中铁二院工程集团有限责任公司 | The V-arrangement skewback floor type lining cutting of tunnel bottom setting drainage gallery and its drainage system construction |
CN108331593A (en) * | 2018-02-11 | 2018-07-27 | 中铁二院工程集团有限责任公司 | A kind of cavity type preventing mean and construction method for the deformation of non-fragment orbit tunnel bottom |
CN108457696A (en) * | 2017-02-20 | 2018-08-28 | 辛德刚 | Empty wall drains anti-water tunnel |
CN108590697A (en) * | 2017-12-27 | 2018-09-28 | 中铁二院工程集团有限责任公司 | Box pedestal detaches bearing type liner structure and its drainage system with bridge-type tunnel bottom structure sound |
CN108757027A (en) * | 2018-05-23 | 2018-11-06 | 中铁二院工程集团有限责任公司 | Multi-functional lobby water system in a kind of tunnel |
CN109519192A (en) * | 2019-01-23 | 2019-03-26 | 四川省交通运输厅公路规划勘察设计研究院 | Store up drainage pressure-reducing construction and the tunnel structure across soft rock section in tunnel |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1306150A (en) * | 2000-06-11 | 2001-08-01 | 郭兰波 | Reinforcing bar netted chock and netted-shell bolting and shotcrete support |
KR101065555B1 (en) * | 2008-12-16 | 2011-09-19 | 한국건설기술연구원 | System preventing non-woven from mortar particles filled up the back space of PCL Precasting Concrete Lining and method constructing the non-woven to PCL |
CN202914107U (en) * | 2012-11-15 | 2013-05-01 | 华北科技学院 | Roadway support truss |
CN203130090U (en) * | 2013-01-16 | 2013-08-14 | 中铁二院工程集团有限责任公司 | Railway tunnel groove structure |
CN105089680A (en) * | 2015-04-14 | 2015-11-25 | 山东科技大学 | Gob-side entry retaining light-weight high-strength concrete block wall and construction technology thereof |
CN105545355A (en) * | 2016-01-19 | 2016-05-04 | 西南交通大学 | Drainage structure suitable for tunnel bottom in water-rich rock stratum |
CN206220972U (en) * | 2016-06-12 | 2017-06-06 | 中铁二院工程集团有限责任公司 | Frame branch arched tunnel lining structure |
-
2016
- 2016-06-12 CN CN201610410198.XA patent/CN106089244A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1306150A (en) * | 2000-06-11 | 2001-08-01 | 郭兰波 | Reinforcing bar netted chock and netted-shell bolting and shotcrete support |
KR101065555B1 (en) * | 2008-12-16 | 2011-09-19 | 한국건설기술연구원 | System preventing non-woven from mortar particles filled up the back space of PCL Precasting Concrete Lining and method constructing the non-woven to PCL |
CN202914107U (en) * | 2012-11-15 | 2013-05-01 | 华北科技学院 | Roadway support truss |
CN203130090U (en) * | 2013-01-16 | 2013-08-14 | 中铁二院工程集团有限责任公司 | Railway tunnel groove structure |
CN105089680A (en) * | 2015-04-14 | 2015-11-25 | 山东科技大学 | Gob-side entry retaining light-weight high-strength concrete block wall and construction technology thereof |
CN105545355A (en) * | 2016-01-19 | 2016-05-04 | 西南交通大学 | Drainage structure suitable for tunnel bottom in water-rich rock stratum |
CN206220972U (en) * | 2016-06-12 | 2017-06-06 | 中铁二院工程集团有限责任公司 | Frame branch arched tunnel lining structure |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108457696A (en) * | 2017-02-20 | 2018-08-28 | 辛德刚 | Empty wall drains anti-water tunnel |
CN107524458A (en) * | 2017-08-30 | 2017-12-29 | 中铁二院工程集团有限责任公司 | A kind of tunnel lining structure with tunnel bottom deformation allowance |
CN107524458B (en) * | 2017-08-30 | 2023-09-22 | 中铁二院工程集团有限责任公司 | Tunnel lining structure with tunnel bottom reserved deformation |
CN107965327A (en) * | 2017-12-27 | 2018-04-27 | 中铁二院工程集团有限责任公司 | Arcuately tunnel bottom liner structure and its drainage system |
CN107905809A (en) * | 2017-12-27 | 2018-04-13 | 中铁二院工程集团有限责任公司 | Diplopore hollow, rectangular section load bearing beam road cutting type protecting arched tunnel liner structure and separate type drainage system |
CN108005688A (en) * | 2017-12-27 | 2018-05-08 | 中铁二院工程集团有限责任公司 | The external dewatering type lining cutting of buried lateral sulcus and its drainage system |
CN108222960A (en) * | 2017-12-27 | 2018-06-29 | 中铁二院工程集团有限责任公司 | The V-arrangement skewback floor type lining cutting of tunnel bottom setting drainage gallery and its drainage system construction |
CN107905812A (en) * | 2017-12-27 | 2018-04-13 | 中铁二院工程集团有限责任公司 | The hollow compound arch tunnel-liner in type tunnel bottom and its drainage system construction of falling from power |
CN107905808A (en) * | 2017-12-27 | 2018-04-13 | 中铁二院工程集团有限责任公司 | The foundation carrying of falling groove-shaped longitudinal beam is without tunnel bottom structure arch lining cutting and its drainage system |
CN108590697A (en) * | 2017-12-27 | 2018-09-28 | 中铁二院工程集团有限责任公司 | Box pedestal detaches bearing type liner structure and its drainage system with bridge-type tunnel bottom structure sound |
CN107905808B (en) * | 2017-12-27 | 2024-01-23 | 中铁二院工程集团有限责任公司 | Arch lining system of basement inverted groove type longitudinal beam bearing tunnel-free bottom structure |
CN107905809B (en) * | 2017-12-27 | 2024-01-19 | 中铁二院工程集团有限责任公司 | Double-hole hollow rectangular section beam bearing cutting type arched tunnel lining structure |
CN108331593A (en) * | 2018-02-11 | 2018-07-27 | 中铁二院工程集团有限责任公司 | A kind of cavity type preventing mean and construction method for the deformation of non-fragment orbit tunnel bottom |
CN108331593B (en) * | 2018-02-11 | 2019-11-05 | 中铁二院工程集团有限责任公司 | A kind of construction method of the cavity type preventing mean for the deformation of non-fragment orbit tunnel bottom |
CN108757027B (en) * | 2018-05-23 | 2023-11-21 | 中铁二院工程集团有限责任公司 | Multifunctional drainage system in tunnel |
CN108757027A (en) * | 2018-05-23 | 2018-11-06 | 中铁二院工程集团有限责任公司 | Multi-functional lobby water system in a kind of tunnel |
CN109519192B (en) * | 2019-01-23 | 2023-10-10 | 四川省公路规划勘察设计研究院有限公司 | Tunnel stores up drainage decompression structure and stride across tunnel structure in soft rock district |
CN109519192A (en) * | 2019-01-23 | 2019-03-26 | 四川省交通运输厅公路规划勘察设计研究院 | Store up drainage pressure-reducing construction and the tunnel structure across soft rock section in tunnel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106089244A (en) | Frame props up arched tunnel lining structure | |
CN105863671B (en) | Frame-type subdrain system tunnel lining structure | |
CN206220972U (en) | Frame branch arched tunnel lining structure | |
CN105927272B (en) | Bottom plate anchors restricted type tunnel lining structure | |
CN106437748B (en) | A kind of separate type can repair tunnel lining structure | |
CN105840210B (en) | The compound arch tunnel lining structure in box tunnel bottom with hydrophobic function | |
CN102071607B (en) | Railroad bed repair method without affecting existing running conditions | |
CN203403426U (en) | Supporting structure of expensive earth road cutting side slope | |
CN205677631U (en) | It is combined arch tunnel lining structure at the bottom of the box tunnel with hydrophobic function | |
CN105840211A (en) | Pi-shaped plate and inverted arch combined tunnel bottom lining structure | |
CN103410159A (en) | Expansive soil cut slope support structure and construction method thereof | |
CN102926304A (en) | Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation | |
CN106437726A (en) | Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation | |
CN106640096A (en) | Construction method for penetrating through tunnel of backfilling soil section and transition section | |
CN109930613A (en) | A kind of construction method and structure of the roadbed slope drainage system that seeps water | |
CN107905811A (en) | The hollow longeron of foundation carries domes without the lining cutting of inverted arch type and its drainage system | |
CN107965327A (en) | Arcuately tunnel bottom liner structure and its drainage system | |
CN206016853U (en) | Base plate anchors restricted type tunnel lining structure | |
CN205936632U (en) | Tunnel lining structure can be maintained to disconnect -type | |
CN107245989A (en) | Bear the tunnel structure and its construction technology of external water pressure in height | |
CN106703053A (en) | Construction method for reinforced soil drainage composite revetment structure | |
CN206016821U (en) | Frame-type subdrain system tunnel lining structure | |
CN205035768U (en) | Enrockment concrete permeable dike | |
CN206016823U (en) | π shapes plate and inverted arch combined type tunnel bottom lining structure | |
CN102425175B (en) | Reinforcement protective structure of large spoil disposal area in mountainous area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161109 |