CN105840211A - Pi-shaped plate and inverted arch combined tunnel bottom lining structure - Google Patents

Pi-shaped plate and inverted arch combined tunnel bottom lining structure Download PDF

Info

Publication number
CN105840211A
CN105840211A CN201610410042.1A CN201610410042A CN105840211A CN 105840211 A CN105840211 A CN 105840211A CN 201610410042 A CN201610410042 A CN 201610410042A CN 105840211 A CN105840211 A CN 105840211A
Authority
CN
China
Prior art keywords
inverted arch
arch
tunnel
lining
shape plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610410042.1A
Other languages
Chinese (zh)
Inventor
卿伟宸
张磊
高杨
郑伟
孟祥磊
林本涛
朱勇
陶伟明
钟昌桂
曾宏飞
黄华
王若晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201610410042.1A priority Critical patent/CN105840211A/en
Publication of CN105840211A publication Critical patent/CN105840211A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Abstract

The invention relates to a pi-shaped plate and inverted arch combined tunnel bottom lining structure. By transforming the traditional tunnel lining tunnel bottom structure style, the stress performance of a lining structure, especially a tunnel bottom structure, under the action of high water pressure or high ground stress is improved, and meanwhile, a drainage system in a tunnel is optimized, the drainage capacity of the tunnel is increased, and the water disaster risk of rainfall flood seasons during operation is reduced by combining the lining tunnel bottom structure. The pi-shaped plate and inverted arch combined tunnel bottom lining structure comprises an initial support structure, a secondary lining structure and a waterproofing and drainage system, wherein the secondary lining structure consists of a secondary lining arch wall segment and a secondary lining tunnel bottom structure, and the secondary lining tunnel bottom structure consists of an inverted arch and a pi-shaped plate arranged on the inverted arch; the pi-shaped plate consists of a top plate, a left-side vertical plate and a right-side vertical plate, and the upper ends of the left-side vertical plate and the right-side vertical plate and the top plate are fixedly combined together; the lower ends of the left-side vertical plate and the right-side vertical plate and the inverted arch are fixedly combined, and the two transversal ends of the top plate and the two ends of the inverted arch are fixedly combined; a corridor formed among the left-side vertical plate, the right-side vertical plate, the top plate and the secondary lining inverted arch can be used as a longitudinal drainage channel of the tunnel.

Description

Lining structure at the bottom of π shape plate and inverted arch combination type tunnel
Technical field
The present invention relates to tunnel lining structure, grow or by seasonal effect particularly to a kind of subsoil water Greatly, tunnel bottom water pressure or crustal stress higher in the case of tunnel lining structure.
Background technology
Enter 21st century, railway construction in China high speed development, the above high standard of speed per hour 200km Quasi-double track railway is built more and more, especially in western mountainous areas, circuit show line is big by sweep, The restriction of the many factors such as shape complex geologic conditions, tunnel scale is increasing, karst of on the one hand growing up Rich water tunnel gets more and more, and on the other hand, high-ground stress tunnel gets more and more.
In recent years, there occurs some nothings during suitable ten thousand, Shanghai elder brother, the expensive Railway Tunnel operation such as extensively The water damage event such as the deformation of tiny fragments of stone, coal, etc. railway roadbed, inverted arch protuberance, lining cutting percolating water, cause Railway Design, construction, Build and the great attention of operation each side.
Tradition double track tunnel lining cutting typically uses the liner structure form of bent wall band inverted arch, such as Fig. 4 institute Show.Using Concrete Filled as railway roadbed basis on inverted arch, in construction, inverted arch is filled with inverted arch and is separately watered Build.Arranging Central drain+bilateral ditch in tunnel, Central drain is placed in the obturator on inverted arch. Underground water discharge path is: country rock → preliminary bracing → draining blind pipe → lateral sulcus → transverse drain → in Edema with the heart involved ditch, the i.e. water of tunnel structure periphery enter tunnel by preliminary bracing infiltration via draining blind pipe ejectment Central drain within road structural body, outside final discharge hole.The defect of conventional drainage systems maximum exists In: within Central drain is located at tunnel structure, main ejectment main ejectment arch wall scope circumferentially under Water, the hydrops below tunnel inverted arch cannot effectively ejectment.Especially in the close region of ground hydraulic connection, Under continuous rainfall or rainstorm weather, because of groundwater run off abruptly increase, traditional drainage system often cannot and Time ejectment in the gutter in tunnel structure body, thus cause level of ground water drastically to raise.At Gao Shui Under pressure effect, cause inverted arch at the bottom of tunnel or inverted arch to fill protuberance, thus destroy ballast bed structure.
Additionally, six being stained with, the rail segment high-ground stress tunnel such as Yun Gui, Cheng Lan is being built and was being runed Journey all occurs the disasters such as inverted arch protuberance cracking, in order to solve this problem, through frequently with circle in design On the one hand shape or subcircular liner structure (such as Fig. 5), cause that inverted arch difficulty of construction is big, excavated volume is big; On the other hand, on inverted arch, Concrete Filled amount is greatly increased, and causes waste.
Therefore, no matter for solving the high-pressure water-enriched problem in tunnel, karst area, or high-ground stress tunnel is faced upward Arch protuberance strain cracking problem, optimizes lining cutting tunnel bottom structure form, during reducing tunnel construction and operation Calamity source be instantly in the urgent need to.
Summary of the invention
The technical problem to be solved is to provide π shape plate and builds structure with inverted arch combination type tunnel end liner Make, by conventional tunnel lining cutting tunnel bottom structure form is transformed, improve at the bottom of the special tunnel of liner structure Structure stress performance under high hydraulic pressure or high-ground stress effect, in combination with constitution optimization at the bottom of lining cutting tunnel Hole inner water drainage system, increasing tunnel drainage ability, reduce rain flood water damage in season risk during operation.
The technical solution adopted for the present invention to solve the technical problems is as follows:
Lining structure at the bottom of the π shape plate of the present invention and inverted arch combination type tunnel, including preliminary bracing structure, two Secondary liner structure and waterproof and water drainage system, secondary liner structure is by secondary lining arch wall section, secondary lining tunnel Bottom structure is constituted, and it is characterized in that: described secondary lining tunnel bottom structure is by setting on inverted arch and inverted arch π shape plate is constituted, and described π shape plate is made up of top board, left side riser and right side riser, left side riser, Right side riser upper end and top board consolidation is integrated, lower end and inverted arch consolidation, the transverse ends of top board with face upward Arch two ends consolidation, the exterior feature formed between left side riser, right side riser, top board and secondary lining inverted arch Road can be as tunnel longitudinal drainage passage.
The invention has the beneficial effects as follows, use lining structure at the bottom of π shape plate and inverted arch combination type tunnel to replace and pass The circle used under system high-ground stress or high water pressures or subcircular lining cutting: first, at the bottom of tunnel, excavation is made Industry is more convenient, and earthwork reduces;Secondly, change the obturator on tradition inverted arch into π shape plate structure, Both saved concrete masonry, added again tunnel base space, pipe gallery can be set, for gutter, Cable ducts etc. are arranged;π shape plate and inverted arch combination type tunnel bottom structure, bending rigidity is greatly increased, significantly Increase tunnel bottom structure bearing capacity;Can realize liner structure " external draining ", arch wall secondary lining is behind Subsoil water does not introduce tunnel lateral sulcus, and is introduced directly into the collector drain between π shape plate and inverted arch, effectively keeps away Exempt from rain flood subsoil water in season excessive lateral sulcus drainability to pour in railway roadbed not;Simultaneously because gutter It is positioned under base plate, can guarantee that the smooth and easy excretion of subsoil water is avoided causing bottom slab crack to swell all the time.
Accompanying drawing explanation
This specification includes following five width accompanying drawings:
Fig. 1 is the section structure schematic diagram of lining structure at the bottom of π shape plate of the present invention and inverted arch combination type tunnel;
Fig. 2 is the enlarged drawing of A local in Fig. 1;
Fig. 3 is the enlarged drawing of B local in Fig. 1;
Fig. 4 is the bent wall band inverted arch liner structure schematic diagram of tradition;
Fig. 5 is subcircular liner structure schematic diagram under high-ground stress or high hydraulic pressure operating mode in traditional design.
Component shown in figure, toponym and corresponding labelling: wide road C;Preliminary bracing structure arch wall Section 10, arch wall shotcrete layer 10a, arch wall steelframe 10b, arch wall system anchor bolt 10c;Initial stage Supporting construction inverted arch section 11, inverted arch shotcrete layer 11a, inverted arch steelframe 11b;Waterproof and water drainage system 20, non-woven geotextile 20a, circle draining blind pipe 20b, splash guard 20c;Secondary lining arch wall section 30, inverted arch 31;Top board 40, left side riser 41, right side riser 42.
Detailed description of the invention
The present invention is further described with embodiment below in conjunction with the accompanying drawings.
With reference to lining structure at the bottom of Fig. 1, the π shape plate of the present invention and inverted arch combination type tunnel, including preliminary bracing Structure, secondary liner structure and waterproof and water drainage system 20, secondary liner structure is by secondary lining arch wall section 30, secondary lining tunnel bottom structure is constituted.Described secondary lining tunnel bottom structure is by inverted arch 31 and inverted arch 31 On arrange π shape plate constitute, described π shape plate is by top board 40, left side riser 41 and right side riser 42 are constituted, and left side riser 41, right side riser 42 upper end and top board 40 consolidation are integrated, lower end and Inverted arch 31 consolidates, and the transverse ends of top board 40 and inverted arch 31 two ends consolidate, left side riser 41, Right side riser 42, to form wide road C between top board 40 and inverted arch 31 be tunnel longitudinal drainage passage. Bearing of trend interval, described top board 40 ascender line road arranges the inspection well head communicated with wide road C.
With reference to Fig. 1, the present invention changes the obturator on tradition inverted arch into π shape plate structure, both saved Concrete masonry, adds again tunnel base space, can arrange pipe gallery, for gutter, cable duct Arrange.π shape plate and inverted arch combination type tunnel bottom structure, bending rigidity is greatly increased, and dramatically increases at the bottom of tunnel Structural-load-carrying capacity.Can realize liner structure " external draining ", arch wall secondary lining subsoil water behind is not Introduce tunnel lateral sulcus, and be introduced directly into the collector drain between π shape plate and inverted arch, be prevented effectively from rain flood season Joint subsoil water excessive lateral sulcus drainability pours in railway roadbed not.Owing to gutter is positioned under base plate, All the time can guarantee that the smooth and easy excretion of subsoil water is avoided causing bottom slab crack to swell.
With reference to 1 and Fig. 2, described waterproof and water drainage system 20 includes the non-woven geotextile that arch wall scope is laid The splash guard 20c that 20a and arch wall scope are laid, and it is laid in nonwoven along interval, tunnel excavation direction Circle draining blind pipe 20b between geotextiles 20a and splash guard 20c.Described circle draining blind pipe 20b Two ends be introduced directly into wide road C along top board 40 lower edge.
With reference to Fig. 1, described preliminary bracing structure includes preliminary bracing structure arch wall section 10, preliminary bracing Structure inverted arch section 11.With reference to Fig. 2, described arch wall preliminary bracing structure 10 includes covering arch wall country rock Arch wall shotcrete layer 10a and along the arch wall system anchor bolt 10c of arch wall quincuncial arrangement, arch wall Arch wall steelframe 10b is laid along interval, tunnel excavation direction in shotcrete layer 10a.Described arch wall sprays Bar-mat reinforcement is added in penetrating concrete layer 10a.With reference to Fig. 3, described inverted arch preliminary bracing structure 11 is wrapped The inverted arch shotcrete layer 11a, inverted arch shotcrete layer 11a that include covering inverted arch country rock are interior along tunnel Inverted arch steelframe 11b is laid at interval, excavation direction, road.
The above lining structure at the bottom of π shape plate of the present invention and inverted arch combination type tunnel that simply explains through diagrams Some principles, be not intended to be confined to the present invention shown in and described concrete structure and the scope of application In, therefore every corresponding amendment being likely utilized and equivalent, belong to the present invention and applied for The scope of the claims.

Claims (7)

1. lining structure at the bottom of π shape plate and inverted arch combination type tunnel, including preliminary bracing structure, secondary lining Building structure and waterproof and water drainage system (20), secondary liner structure is by secondary lining arch wall section (30), secondary Lining cutting tunnel bottom structure is constituted, and it is characterized in that: described secondary lining tunnel bottom structure by inverted arch (31) and is faced upward The π shape plate arranged on arch (31) is constituted, and described π shape plate is by top board (40), left side riser (41) Constitute with right side riser (42), left side riser (41), right side riser (42) upper end and top board (40) Consolidation is integrated, and lower end consolidates with inverted arch (31), the transverse ends of top board (40) and inverted arch (31) Two ends consolidate, at left side riser (41), right side riser (42), top board (40) and inverted arch (31) Between to form wide road (C) be tunnel longitudinal drainage passage.
2. lining structure at the bottom of π shape plate as claimed in claim 1 and inverted arch combination type tunnel, its feature It is: bearing of trend interval in described top board (40) ascender line road arranges the inspection communicated with wide road (C) Well head.
3. lining structure at the bottom of π shape plate as claimed in claim 1 and inverted arch combination type tunnel, its feature It is: described waterproof and water drainage system (20) includes non-woven geotextile (20a) and the arch that arch wall scope lays The splash guard (20c) that wall scope is laid, and it is laid in non-woven geotextile along interval, tunnel excavation direction (20a) the circle draining blind pipe 20b and between splash guard (20c).
4. lining structure at the bottom of π shape plate as claimed in claim 3 and inverted arch combination type tunnel, its feature It is: the two ends of described circle draining blind pipe (20b) are introduced directly into wide road (C) along top board (40) lower edge.
5. lining structure at the bottom of π shape plate as claimed in claim 1 and inverted arch combination type tunnel, its feature It is: described preliminary bracing structure includes that preliminary bracing structure arch wall section (10), preliminary bracing structure are faced upward Arch section (11);Described arch wall preliminary bracing structure (10) includes the arch wall injection covering arch wall country rock Concrete layer (10a) and the arch wall system anchor bolt (10c) along arch wall quincuncial arrangement, arch wall sprays Arch wall steelframe (10b) is laid along interval, tunnel excavation direction in concrete layer (10a).
6. lining structure at the bottom of π shape plate as claimed in claim 5 and inverted arch combination type tunnel, its feature It is: in described arch wall shotcrete layer (10a), add bar-mat reinforcement.
7. lining structure at the bottom of π shape plate as claimed in claim 5 and inverted arch combination type tunnel, its feature It is: described inverted arch preliminary bracing structure (11) includes covering the inverted arch shotcrete layer of inverted arch country rock (11a), inverted arch steelframe is laid along interval, tunnel excavation direction in inverted arch shotcrete layer (11a) (11b)。
CN201610410042.1A 2016-06-12 2016-06-12 Pi-shaped plate and inverted arch combined tunnel bottom lining structure Pending CN105840211A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610410042.1A CN105840211A (en) 2016-06-12 2016-06-12 Pi-shaped plate and inverted arch combined tunnel bottom lining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610410042.1A CN105840211A (en) 2016-06-12 2016-06-12 Pi-shaped plate and inverted arch combined tunnel bottom lining structure

Publications (1)

Publication Number Publication Date
CN105840211A true CN105840211A (en) 2016-08-10

Family

ID=56575798

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610410042.1A Pending CN105840211A (en) 2016-06-12 2016-06-12 Pi-shaped plate and inverted arch combined tunnel bottom lining structure

Country Status (1)

Country Link
CN (1) CN105840211A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106968712A (en) * 2017-05-12 2017-07-21 西南交通大学 Water rich strata tunnel bottom discharge structure and its construction method
CN107387117A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom and its construction method
CN107387119A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 Prefabricated assembled tunnel inverted arch, tunnel structure and its construction method
CN107524458A (en) * 2017-08-30 2017-12-29 中铁二院工程集团有限责任公司 A kind of tunnel lining structure with tunnel bottom deformation allowance
CN108222960A (en) * 2017-12-27 2018-06-29 中铁二院工程集团有限责任公司 The V-arrangement skewback floor type lining cutting of tunnel bottom setting drainage gallery and its drainage system construction
CN108222963A (en) * 2017-12-27 2018-06-29 中铁二院工程集团有限责任公司 The not contour longeron carrying stalk floor type lining cutting of tunnel bottom setting longitudinal direction collection drainage gallery and its drainage system construction
CN108316943A (en) * 2018-02-11 2018-07-24 中铁二院工程集团有限责任公司 A kind of device and its construction method preventing the deformation of non-fragment orbit tunnel bottom
CN109057826A (en) * 2018-08-08 2018-12-21 中铁二院工程集团有限责任公司 A kind of truss-like tunnel inverted arch liner structure
CN109763838A (en) * 2019-03-13 2019-05-17 中铁第一勘察设计院集团有限公司 Assembled inverted arch structure and its assembling method suitable for drill+blast tunnel

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201412160Y (en) * 2009-06-02 2010-02-24 中铁第四勘察设计院集团有限公司 Single-cave and double-line subway tunnel
JP4715571B2 (en) * 2006-03-14 2011-07-06 鹿島建設株式会社 Construction method inside tunnel
KR101144900B1 (en) * 2009-10-14 2012-05-14 강릉건설 주식회사 The bottom segment and shield tunnel process thereof
CN103306683A (en) * 2013-06-18 2013-09-18 中铁隧道集团有限公司 Construction method for comprehensive precipitation in hole in deep-buried tunnel excavation process
CN204357485U (en) * 2014-12-11 2015-05-27 中铁十一局集团第五工程有限公司 The drainage system of anti-tunnel double-lining behind ponding crossfire
CN104879164A (en) * 2015-03-12 2015-09-02 西南交通大学 Tunnel annular drain structure
CN204662651U (en) * 2015-04-29 2015-09-23 中铁工程设计咨询集团有限公司 A kind of cleaning plant of tunnel drainage blind pipe
CN204879051U (en) * 2015-08-19 2015-12-16 中交第一公路勘察设计研究院有限公司 Tunnel drain pipe fixing device
CN206016823U (en) * 2016-06-12 2017-03-15 中铁二院工程集团有限责任公司 π shapes plate and inverted arch combined type tunnel bottom lining structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4715571B2 (en) * 2006-03-14 2011-07-06 鹿島建設株式会社 Construction method inside tunnel
CN201412160Y (en) * 2009-06-02 2010-02-24 中铁第四勘察设计院集团有限公司 Single-cave and double-line subway tunnel
KR101144900B1 (en) * 2009-10-14 2012-05-14 강릉건설 주식회사 The bottom segment and shield tunnel process thereof
CN103306683A (en) * 2013-06-18 2013-09-18 中铁隧道集团有限公司 Construction method for comprehensive precipitation in hole in deep-buried tunnel excavation process
CN204357485U (en) * 2014-12-11 2015-05-27 中铁十一局集团第五工程有限公司 The drainage system of anti-tunnel double-lining behind ponding crossfire
CN104879164A (en) * 2015-03-12 2015-09-02 西南交通大学 Tunnel annular drain structure
CN204662651U (en) * 2015-04-29 2015-09-23 中铁工程设计咨询集团有限公司 A kind of cleaning plant of tunnel drainage blind pipe
CN204879051U (en) * 2015-08-19 2015-12-16 中交第一公路勘察设计研究院有限公司 Tunnel drain pipe fixing device
CN206016823U (en) * 2016-06-12 2017-03-15 中铁二院工程集团有限责任公司 π shapes plate and inverted arch combined type tunnel bottom lining structure

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106968712A (en) * 2017-05-12 2017-07-21 西南交通大学 Water rich strata tunnel bottom discharge structure and its construction method
CN107387117A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom and its construction method
CN107387119A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 Prefabricated assembled tunnel inverted arch, tunnel structure and its construction method
CN107387117B (en) * 2017-07-07 2023-12-19 中国铁道科学研究院铁道建筑研究所 Prefabricated tunnel structure with tunnel bottom and construction method thereof
CN107524458B (en) * 2017-08-30 2023-09-22 中铁二院工程集团有限责任公司 Tunnel lining structure with tunnel bottom reserved deformation
CN107524458A (en) * 2017-08-30 2017-12-29 中铁二院工程集团有限责任公司 A kind of tunnel lining structure with tunnel bottom deformation allowance
CN108222960A (en) * 2017-12-27 2018-06-29 中铁二院工程集团有限责任公司 The V-arrangement skewback floor type lining cutting of tunnel bottom setting drainage gallery and its drainage system construction
CN108222963A (en) * 2017-12-27 2018-06-29 中铁二院工程集团有限责任公司 The not contour longeron carrying stalk floor type lining cutting of tunnel bottom setting longitudinal direction collection drainage gallery and its drainage system construction
CN108316943A (en) * 2018-02-11 2018-07-24 中铁二院工程集团有限责任公司 A kind of device and its construction method preventing the deformation of non-fragment orbit tunnel bottom
CN108316943B (en) * 2018-02-11 2019-07-26 中铁二院工程集团有限责任公司 A kind of construction method for the device preventing the deformation of non-fragment orbit tunnel bottom
CN109057826A (en) * 2018-08-08 2018-12-21 中铁二院工程集团有限责任公司 A kind of truss-like tunnel inverted arch liner structure
CN109763838B (en) * 2019-03-13 2023-09-15 中铁第一勘察设计院集团有限公司 Assembled inverted arch structure suitable for tunnel by drilling and blasting method and assembling method thereof
CN109763838A (en) * 2019-03-13 2019-05-17 中铁第一勘察设计院集团有限公司 Assembled inverted arch structure and its assembling method suitable for drill+blast tunnel

Similar Documents

Publication Publication Date Title
CN105840211A (en) Pi-shaped plate and inverted arch combined tunnel bottom lining structure
CN105927272B (en) Bottom plate anchors restricted type tunnel lining structure
CN105863671B (en) Frame-type subdrain system tunnel lining structure
CN106437748B (en) A kind of separate type can repair tunnel lining structure
CN105840210B (en) The compound arch tunnel lining structure in box tunnel bottom with hydrophobic function
CN103256052B (en) Construction method for integral straight middle wall type double-arch tunnel
CN205677631U (en) It is combined arch tunnel lining structure at the bottom of the box tunnel with hydrophobic function
CN106089244A (en) Frame props up arched tunnel lining structure
CN102434175A (en) Tunnel lining self waterproof drainage system
CN206220972U (en) Frame branch arched tunnel lining structure
CN202483588U (en) Self water-proof drainage system of tunnel lining
CN107905811B (en) Inverted arch-free lining of foundation hollow longitudinal beam bearing arch structure
CN207673371U (en) A kind of novel tunnel drainage system construction
CN106640096A (en) Construction method for penetrating through tunnel of backfilling soil section and transition section
CN206016853U (en) Base plate anchors restricted type tunnel lining structure
CN206016823U (en) π shapes plate and inverted arch combined type tunnel bottom lining structure
CN107965327A (en) Arcuately tunnel bottom liner structure and its drainage system
CN205936632U (en) Tunnel lining structure can be maintained to disconnect -type
CN207568626U (en) A kind of tunnel structure for expansive stratum
CN206016821U (en) Frame-type subdrain system tunnel lining structure
CN107905810A (en) Boot last pedestal combed tunnel bottom liner structure and its drainage system
CN108005677B (en) Frame type integral tunnel bottom arch lining and drainage system thereof
CN208073501U (en) Foundation base type is without inverted arch type tunnel lining structure and its drainage system
CN107975378A (en) The U-shaped wall base with architecture separates bearing type liner structure with bottom plate sound
CN208073500U (en) Both sides setting has both the liner structure of the L-shaped pedestal of draining, carrying and supporting and retaining system function

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160810