CN105970755A - Construction method for prevention and treatment for sidewise slippage of soft soil roadbed - Google Patents

Construction method for prevention and treatment for sidewise slippage of soft soil roadbed Download PDF

Info

Publication number
CN105970755A
CN105970755A CN201610369123.1A CN201610369123A CN105970755A CN 105970755 A CN105970755 A CN 105970755A CN 201610369123 A CN201610369123 A CN 201610369123A CN 105970755 A CN105970755 A CN 105970755A
Authority
CN
China
Prior art keywords
soft soil
roadbed
laterally
foundation
soil roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610369123.1A
Other languages
Chinese (zh)
Inventor
朱汉华
陈孟冲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Communications Planning Institute Co Ltd
Original Assignee
Ningbo Communications Planning Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Communications Planning Institute Co Ltd filed Critical Ningbo Communications Planning Institute Co Ltd
Priority to CN201610369123.1A priority Critical patent/CN105970755A/en
Publication of CN105970755A publication Critical patent/CN105970755A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a construction method for prevention and treatment for sidewise slippage of a soft soil roadbed. The core of the construction method is to control the integrity of the stressed deformation state of the roadbed and adopt transverse resistance piles. The key technology of the construction method is to control combination and integration of unevenly settled base plates or bars of the roadbed and transverse resistance pile foundations so as to establish a soft soil roadbed counterforce balance system. Compared with the prior art, the construction method for prevention and treatment for sidewise slippage of the soft soil roadbed has the main characteristics that the concept of establishing the soft soil roadbed counterforce balance system is proposed; the design on the soft soil roadbed is improved centering on control over the integrity of the stressed deformation state of the soft soil roadbed and establishing indexes including counter torque of the soft soil roadbed and the like; and the purpose of prevention and treatment for the sidewise slippage phenomenon of the soft soil roadbed is achieved.

Description

The soft soil roadbed lateral sliding construction method of a kind of preventing and treating
Technical field
The invention belongs to construction method field, be specifically related to the soft soil roadbed lateral sliding construction method of a kind of preventing and treating.
Background technology
Soft soil roadbed differential settlement phenomenon is more, particularly closes on the situation of waterside, limit, mountain soft soil foundation characteristic relative mistake, weak soil Roadbed generation lateral sliding problem is the most prominent.And existing soft soil roadbed method for processing foundation and the method for analysis are also a lot, but become The suitability of merit case is the most poor.Applicant studies discovery, and it is that two reasons easily ignored are at all: (1) roadbed is even Continuous body and the essential difference of discrete bodies: discrete bodies can bear pressure, but is substantially not subject to pulling force, can not bear moment; Continuum can bear pressure, pulling force and moment, and control roadbed force and deformation state globality can build opposing roadbed and laterally slide The counter-force equilibrium system substrate moved;(2) soft soil roadbed ground weak soil has the feature such as macrovoid ratio, high-compressibility, easily draws Feeling like jelly earth roadbed generation lateral sliding phenomenon, the countertorque building the anti-force balancing system of soft soil foundation is the most crucial.
The most existing soft soil roadbed lateral sliding analysis and processing method ignore the structure anti-force balancing system of soft soil foundation, particularly Closing on the situation of waterside, limit, mountain soft soil foundation characteristic relative mistake, soft soil roadbed generation lateral sliding problem as shown in Figure 1 is the most prominent It is not at all surprising to go out.
Summary of the invention
For solving the problems referred to above, the present invention proposes the soft soil roadbed lateral sliding construction method of a kind of preventing and treating.
The present invention is directed to two problems that existing soft soil roadbed analysis exists with processing method, the earth roadbed analysis theories of traditional soft is ignored The anti-force balancing system of structure soft soil foundation, controls roadbed force and deformation state globality the most simply and to build soft soil foundation anti- Moment, could resist soft soil roadbed lateral sliding.On the basis of summing up experience and thinking dialectically, around controlling soft soil roadbed being subject to The indexs such as force deformation state globality and structure soft soil foundation countertorque improve Soft Soil Subgrade Design.The theoretical basis of the present invention is as follows:
Globality or have base plate soft soil roadbed, its equilibrium system and counter-force equilibrium system equation are as follows:
FG=FM (1.1)
MF=FM*e (1.2)
In formula: FGFor soft soil roadbed weight;FMSoft soil foundation counter-force for section to be calculated;MFWeak soil for section to be calculated Subgrade reaction square;E be the soft soil foundation counter-force equilibrium system in section to be calculated theoretical counter-force away from.
Therefore, formula (1.1), (1.2) show to improve Soft Soil Subgrade Design method according to malformation control method for coordinating with Fig. 2, Controlling soft soil roadbed force and deformation state globality in design and laterally resist stake, its key technology is to control settlement of subgrade Base plate or sash and laterally resist the combination of pile foundation so that it is as an anti-force balancing system of unitary construction soft soil foundation, reach Prevent and treat the purpose of soft soil roadbed lateral sliding phenomenon.And in existing construction method, the most do not design this anti-force balancing system.
For achieving the above object, the present invention specifically adopts the following technical scheme that
Prevent and treat soft soil roadbed lateral sliding construction method, when roadbed be limit, newly-built mountain soft soil roadbed time, step is as follows:
Limit, S101: qualitative analysis mountain yet to be built is soft soil roadbed arranges the scope laterally resisting stake, determine simultaneously roadbed base plate or sash and Set the parameter laterally resisting pile foundation;
S102: manual sorting smooth soft soil foundation surface;
S103: lay the grains of sand or blotter on manual sorting smooth soft soil foundation surface;
S104: according to the qualitative analysis of S101, is set by design requirement in soft soil foundation and laterally resists pile foundation;
S105: cast-in-place or place prefabricated reinforced concrete base plate or frame above the grains of sand laid on soft soil foundation surface or blotter Lattice, as the key-course of soft soil roadbed force and deformation state globality, and are combined with pile foundation entirety, are used for resisting soft soil roadbed side To sliding;
When roadbed be newly-built waterside soft soil roadbed time, step is as follows:
S201: qualitative analysis waterside yet to be built is soft soil roadbed arranges the scope laterally resisting stake;Determine simultaneously roadbed base plate or sash and Set the parameter laterally resisting pile foundation;
S202: manual sorting smooth soft soil foundation surface;
S203: lay the grains of sand or blotter on manual sorting smooth soft soil foundation surface;
S204: according to the qualitative analysis of S201, is set by design requirement in soft soil foundation and laterally resists pile foundation;
S205: above the grains of sand laid on soft soil foundation surface or blotter cast-in-place or place prefabricated reinforced concrete base plate or Sash, as the key-course of soft soil roadbed force and deformation state globality, and is combined with pile foundation entirety, is used for resisting soft soil roadbed Lateral sliding.
As preferably, in described S101, qualitative analysis standard is: the soft soil foundation degree of depth residing for the left and right sides of target roadbed When differing by more than 1m, soft soil foundation moment of resistance is difficult to the lateral sliding caused more than soft soil roadbed left and right sides differential settlement Moment, this section of roadbed must be arranged laterally resists stake, otherwise laterally resists stake without arranging.
As preferably, in described S201, qualitative analysis standard is: the side, waterside of target roadbed far from waterside distance less than 1m time, Soft soil foundation moment of resistance is difficult to the lateral sliding moment caused more than soft soil roadbed left and right sides differential settlement, this section of roadbed palpus Arrange and laterally resist stake, otherwise laterally resist stake without arranging.
As preferably, in described S103 and S203, the thickness of the grains of sand or blotter is 50cm.
As preferably, in described S104, laterally opposing pile foundation isReinforced concrete pile, laterally longitudinal rectangle 2 × 10m arranges, pile foundation is punched Soft Soil Layer and entered supporting course.2 × 10m is disposed with beneficially standardized construction, and pile foundation enters supporting course energy Build the countertorque resisting soft soil roadbed lateral sliding reliably.
As preferably, in described S204, laterally opposing pile foundation isFoam concrete is filled out in single wall screw corrugated tube, its Technique is arranged for first filling foam concrete, quincunx 1.0 × 1.0m or 1.5 × 1.5m again with follow-up steel pipe press-in corrugated tube, stake Base length 6~10m, foam concrete match ratio is foam grain: husky: cement: water: additive=20.0:260:380:160: 8.8 (its comprcssive strength 1.5MPa, unit weight 8.3kN/m3Water capacity weight 10kN/m3).First fill out again with follow-up steel pipe press-in corrugated tube The technique building foam concrete can ensure that pile foundation construction quality, reduces foam concrete divergence loss;Foam concrete comprcssive strength 1.5MPa, unit weight 8.3kN/m3Water capacity weight 10kN/m3, the countertorque actively resisting soft soil roadbed lateral sliding can be built.
Compared with prior art, the present invention is mainly characterized by: propose to build the theory of the anti-force balancing system of soft soil foundation, around Control soft soil roadbed force and deformation state globality and build the index improvement Soft Soil Subgrade Designs such as soft soil foundation countertorque, by reinforcing bar Concrete floor or sash are combined with pile foundation entirety, are used for resisting soft soil roadbed lateral sliding, reach to prevent and treat soft soil roadbed generation side To the purpose of sliding phenomenon.
Accompanying drawing explanation
Fig. 1 is soft soil roadbed lateral sliding phenomenon schematic diagram;
Fig. 2 is the countertorque Disposal Measures force analysis figure building the anti-force balancing system of soft soil foundation;
Fig. 3 is the base plate controlling limit, mountain soft soil roadbed lateral sliding of the present invention or sash and the structure chart laterally resisting stake;
Fig. 4 is the base plate controlling waterside soft soil roadbed lateral sliding of the present invention or sash and the structure chart laterally resisting stake.
Detailed description of the invention
With detailed description of the invention the present invention it is further elaborated below in conjunction with the accompanying drawings and illustrates.Each embodiment in the present invention Technical characteristic, on the premise of not colliding with each other, all can carry out respective combination.
Prevent and treat soft soil roadbed lateral sliding construction method, the soft soil roadbed and soft soil roadbed employing in the waterside distinct methods for limit, newly-built mountain.
Limit, the most newly-built mountain is soft soil roadbed: (1) is according to the soft soil roadbed model arranging laterally opposing stake in limit, formula (1.2) qualitative analysis mountain Enclose.Qualitative analysis standard is: when the soft soil foundation degree of depth residing for the left and right sides of target roadbed differs by more than 1m, soft soil foundation Moment of resistance is difficult to more than soft soil roadbed lateral sliding moment, and this section of roadbed must be arranged laterally resists stake, otherwise without arranging laterally Opposing stake.Determine roadbed base plate or sash by Soft Soil Subgrade Design specification again and laterally resist pile foundations parameter with setting, build opposing soft The counter-force equilibrium system of earth roadbed lateral sliding;(2) manual sorting smooth soft soil foundation surface, notices that heavy-duty machinery arranges smooth The operation of soft soil foundation surface is easily destroyed soft ground surface layer duricrust, can run counter to desire on the contrary;(3) at the smooth weak soil of manual sorting Foundation surface lays the 50cm thickness grains of sand or blotter, as lower step procedures machinery bed course and soft soil foundation surface drainage layer; (4) result analyzed according to step (1), is needing to set the soft soil foundation section of pile foundation, is setting by the design requirement of related specifications Laterally resisting pile foundation, generally laterally opposing pile foundation isReinforced concrete pile, the most longitudinal rectangle 2 × 10m arranges, Pile foundation is punched Soft Soil Layer and is entered supporting course, not only reinforcing soft ground but also build the passive resistance forming countertorque;(5) at weak soil Foundation surface has been laid cast-in-place by the design requirement of related specifications above the 50cm thickness grains of sand or blotter or has placed precast reinforced mixed Solidifying soil base plate or sash longitudinally, as the key-course of soft soil roadbed force and deformation state globality, resist pile foundation fixed knot with horizontal Close the real counter-force equilibrium system being formed and resisting soft soil roadbed lateral sliding, reach to administer the purpose of soft soil roadbed lateral sliding phenomenon, Concrete setting is as shown in Figure 3.(6) filling roadbed and do road surface by specification.
The most newly-built waterside is soft soil roadbed: (1) is according to the soft soil roadbed model arranging laterally opposing stake in formula (1.2) qualitative analysis waterside Enclose;Qualitative analysis standard is: the side, waterside of the close water of target roadbed far from waterside distance less than 1m time, soft soil foundation resistance Square is difficult to more than soft soil roadbed lateral sliding moment, and this section of roadbed must be arranged laterally resists stake, otherwise laterally resists stake without arranging. Determine roadbed base plate or sash by Soft Soil Subgrade Design specification again and laterally resist pile foundation with setting, build and resist soft soil roadbed lateral cunning The counter-force equilibrium system moved;(2) manual sorting smooth soft soil foundation surface, notices that heavy-duty machinery arranges smooth soft soil foundation surface Operation is easily destroyed soft ground surface layer duricrust, can run counter to desire on the contrary;(3) lay on manual sorting smooth soft soil foundation surface The 50cm thickness grains of sand or blotter, as lower step procedures machinery bed course and soft soil foundation surface drainage layer;(4) according to step (1) needs, soft soil foundation is set by the design requirement of related specifications and laterally resists pile foundation, and generally laterally opposing pile foundation is Filling out foam concrete in single wall screw corrugated tube, its technique fills foam concrete again for being first pressed into corrugated tube with follow-up steel pipe, prunus mume (sieb.) sieb.et zucc. Flower-shape 1.0 × 1.0m or 1.5 × 1.5m arranges, pile foundation length 6~10m, and foam concrete match ratio is foam grain: husky: water Mud: water: additive=20.0:260:380:160:8.8 (its comprcssive strength 1.5MPa, unit weight 8.3kN/m3Water capacity weight 10kN/m3), not only reinforcing soft ground but also build the active resistance forming countertorque;(5) 50cm has been laid on soft soil foundation surface Or placement prefabricated reinforced concrete base plate cast-in-place by the design requirement of related specifications or sash above the thick grains of sand or blotter, as The key-course of soft soil roadbed force and deformation state globality, really forms the soft soil roadbed side of opposing with laterally opposing pile foundation secure bond To the counter-force equilibrium system of sliding, reaching to administer the purpose of soft soil roadbed lateral sliding phenomenon, concrete setting is as shown in Figure 4.(6) Filling roadbed and do road surface by specification.
Embodiment described above is the one preferably scheme of the present invention, and so it is not intended to limiting the invention.Relevant technology is led The those of ordinary skill in territory, without departing from the spirit and scope of the present invention, it is also possible to make a variety of changes and modification. The technical scheme that the most all modes taking equivalent or equivalent transformation are obtained, all falls within protection scope of the present invention.

Claims (6)

1. prevent and treat soft soil roadbed lateral sliding construction method for one kind, it is characterised in that:
When roadbed be limit, newly-built mountain soft soil roadbed time, step is as follows:
Limit, S101: qualitative analysis mountain yet to be built is soft soil roadbed arranges the scope laterally resisting stake, determine simultaneously roadbed base plate or sash and Set the parameter laterally resisting pile foundation;
S102: manual sorting smooth soft soil foundation surface;
S103: lay the grains of sand or blotter on manual sorting smooth soft soil foundation surface;
S104: according to the qualitative analysis of S101, is set by design requirement in soft soil foundation and laterally resists pile foundation;
S105: cast-in-place or place prefabricated reinforced concrete base plate or frame above the grains of sand laid on soft soil foundation surface or blotter Lattice, as the key-course of soft soil roadbed force and deformation state globality, and are combined with pile foundation entirety, are used for resisting soft soil roadbed side To sliding;
When roadbed be newly-built waterside soft soil roadbed time, step is as follows:
S201: qualitative analysis waterside yet to be built is soft soil roadbed arranges the scope laterally resisting stake;Determine simultaneously roadbed base plate or sash and Set the parameter laterally resisting pile foundation;
S202: manual sorting smooth soft soil foundation surface;
S203: lay the grains of sand or blotter on manual sorting smooth soft soil foundation surface;
S204: according to the qualitative analysis of S201, is set by design requirement in soft soil foundation and laterally resists pile foundation;
S205: above the grains of sand laid on soft soil foundation surface or blotter cast-in-place or place prefabricated reinforced concrete base plate or Sash longitudinally, as the key-course of soft soil roadbed force and deformation state globality, and is combined with pile foundation entirety, is used for resisting weak soil Roadbed lateral sliding.
2. the soft soil roadbed lateral sliding construction method of preventing and treating as claimed in claim 1, it is characterised in that: in described S101, Qualitative analysis standard is: when the soft soil foundation degree of depth residing for the left and right sides of target roadbed differs by more than 1m, and this section of roadbed must set Put and laterally resist stake, otherwise laterally resist stake without arranging.
3. the soft soil roadbed lateral sliding construction method of preventing and treating as claimed in claim 1, it is characterised in that: in described S201, Qualitative analysis standard is: the side, waterside of target roadbed far from waterside distance less than 1m time, this section of roadbed must be arranged laterally resists stake, Otherwise laterally resist stake without arranging.
4. the soft soil roadbed lateral sliding construction method of preventing and treating as claimed in claim 1, it is characterised in that: described S103 and S203 In, the thickness of the grains of sand or blotter is 50cm.
5. the soft soil roadbed lateral sliding construction method of preventing and treating as claimed in claim 1, it is characterised in that: in described S104, Laterally opposing pile foundation isReinforced concrete pile, the most longitudinal rectangle 2 × 10m arranges, pile foundation is punched Soft Soil Layer and entered Supporting course.
6. the soft soil roadbed lateral sliding construction method of preventing and treating as claimed in claim 1, it is characterised in that: in described S204, Laterally opposing pile foundation isFilling foam concrete in single wall screw corrugated tube, its technique is first with follow-up steel pipe press-in ripple Pipe fills foam concrete, quincunx 1.0 × 1.0m or 1.5 × 1.5m again and arranges, pile foundation length 6~10m, foam concrete Match ratio is foam grain: husky: cement: water: additive=20.0:260:380:160:8.8, and comprcssive strength 1.5Mpa is held Weight 8.3kN/m3
CN201610369123.1A 2016-05-27 2016-05-27 Construction method for prevention and treatment for sidewise slippage of soft soil roadbed Pending CN105970755A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610369123.1A CN105970755A (en) 2016-05-27 2016-05-27 Construction method for prevention and treatment for sidewise slippage of soft soil roadbed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610369123.1A CN105970755A (en) 2016-05-27 2016-05-27 Construction method for prevention and treatment for sidewise slippage of soft soil roadbed

Publications (1)

Publication Number Publication Date
CN105970755A true CN105970755A (en) 2016-09-28

Family

ID=57009801

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610369123.1A Pending CN105970755A (en) 2016-05-27 2016-05-27 Construction method for prevention and treatment for sidewise slippage of soft soil roadbed

Country Status (1)

Country Link
CN (1) CN105970755A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107805987A (en) * 2017-09-14 2018-03-16 中交第公路勘察设计研究院有限公司 The hassock layer Foam lightweight soil road structure and construction method in deep soft foundation section
CN117436183A (en) * 2023-12-21 2024-01-23 湖南大学 Synchronous construction method for bridge, municipal road and adjacent service area in deep soft soil area

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01131702A (en) * 1987-11-13 1989-05-24 Keisuke Yamakawa Method of construction completing foundation work after installation of body in construction of grade separation bridge and built-up type grade separation bridge divided into each block
JP2005290889A (en) * 2004-04-01 2005-10-20 Giken Seisakusho Co Ltd Structure of depressed road and its execution method
CN202227214U (en) * 2011-08-30 2012-05-23 中铁二院工程集团有限责任公司 Deep soft soil foundation embankment structure of high-speed railway
CN203346750U (en) * 2013-07-09 2013-12-18 中铁第四勘察设计院集团有限公司 Long-short pile raft structure roadbed of deep spongy soil region
CN203729174U (en) * 2013-12-30 2014-07-23 浙江大学城市学院 Pile-raft composite foundation structure
CN205116204U (en) * 2015-09-29 2016-03-30 中铁第四勘察设计院集团有限公司 Roadbed structure of crowded native bored concrete pile stake board of two -way spiral

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01131702A (en) * 1987-11-13 1989-05-24 Keisuke Yamakawa Method of construction completing foundation work after installation of body in construction of grade separation bridge and built-up type grade separation bridge divided into each block
JP2005290889A (en) * 2004-04-01 2005-10-20 Giken Seisakusho Co Ltd Structure of depressed road and its execution method
CN202227214U (en) * 2011-08-30 2012-05-23 中铁二院工程集团有限责任公司 Deep soft soil foundation embankment structure of high-speed railway
CN203346750U (en) * 2013-07-09 2013-12-18 中铁第四勘察设计院集团有限公司 Long-short pile raft structure roadbed of deep spongy soil region
CN203729174U (en) * 2013-12-30 2014-07-23 浙江大学城市学院 Pile-raft composite foundation structure
CN205116204U (en) * 2015-09-29 2016-03-30 中铁第四勘察设计院集团有限公司 Roadbed structure of crowded native bored concrete pile stake board of two -way spiral

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
周斌: "高速铁路载体桩复合地基沉降变形规律研究", 《中国优秀硕士学位论文全文数据库工程科技II辑》 *
王伟: "塑料排水板联合CFG桩在处理公路软基中的应用", 《北方交通》 *
郑俊杰等: "《地基处理技术》", 30 September 2009, 华中科技大学出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107805987A (en) * 2017-09-14 2018-03-16 中交第公路勘察设计研究院有限公司 The hassock layer Foam lightweight soil road structure and construction method in deep soft foundation section
CN117436183A (en) * 2023-12-21 2024-01-23 湖南大学 Synchronous construction method for bridge, municipal road and adjacent service area in deep soft soil area
CN117436183B (en) * 2023-12-21 2024-03-05 湖南大学 Synchronous construction method for bridge, municipal road and adjacent service area in deep soft soil area

Similar Documents

Publication Publication Date Title
CN202718084U (en) Composite foundation with flexible piles and drain boards combined
WO2021000444A1 (en) Foundation reinforcement structure and method for hoisting heavy equipment close to unclosed building
CN105332380B (en) Strut changing structure and method for underground building
CN103334357A (en) Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN107524159A (en) A kind of hybrid reinforced soil retaining wall
CN202969393U (en) Ribbing load reduction structure of road high hill culvert
CN109235159A (en) A kind of road structure and construction method for helping wide enlarging for runing high-speed railway
CN103938634A (en) Deep foundation pit supporting structure and construction method
CN204112305U (en) Existing railway line excavation section weak subgrade is reinforced and is used multi-functional lobby water system
CN105714678B (en) A kind of combined type gravity anchorage
CN105970755A (en) Construction method for prevention and treatment for sidewise slippage of soft soil roadbed
CN104818658B (en) Road widening method for collapsible yellow earth foundation layer
CN101418574B (en) Construction method for reinforcing grade beam
CN101215840B (en) Airplane-type foundation reinforcement given-force construction method
CN206902734U (en) A kind of earth construction of soft foundation zone
CN206359995U (en) Reinforced concrete cast-in-situ retaining wall
CN109024665A (en) A kind of building-brick type reinforced earth bulkhead and its construction method
CN108797636A (en) A kind of upper font retaining wall structure and its construction method
CN209307786U (en) A kind of road structure extended for runing high-speed railway side width
CN207846454U (en) Overhanging type unilateral side wall mixed reinforcement and replacing structure
CN103981880A (en) Treatment method of composite foundation using top-enlarged and bottom-enlarged CFG piles
CN216712980U (en) Deep soft soil foundation reinforcing and processing structure combining concrete lattice wall and discrete material piles
CN215977211U (en) Structure is handled to compound foundation of tubular pile combination cement mixing pile
CN105239581A (en) Lattice-shaped strengthening method for bottom of foundation pit in soft soil area
CN204753289U (en) System is widened to road on settlement by soaking loess foundation layer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160928

RJ01 Rejection of invention patent application after publication