CN105926782A - 混凝土后浇带施工方法 - Google Patents
混凝土后浇带施工方法 Download PDFInfo
- Publication number
- CN105926782A CN105926782A CN201610263941.3A CN201610263941A CN105926782A CN 105926782 A CN105926782 A CN 105926782A CN 201610263941 A CN201610263941 A CN 201610263941A CN 105926782 A CN105926782 A CN 105926782A
- Authority
- CN
- China
- Prior art keywords
- post
- space
- cast strip
- construction method
- pouring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
- E04B1/6801—Fillings therefor
Abstract
本发明涉及混凝土后浇带施工方法,包括步骤:搭建后浇带空间模板和后浇带两侧结构的模板,所述后浇带空间的侧模板为密目钢丝网形成;向后浇带空间中填入临时填充料,随后浇筑后浇带两侧结构的混凝土;后浇带两侧结构混凝土达到预设强度后,清除后浇带空间中的临时填充料;向后浇带空间中浇筑混凝土。本混凝土后浇带施工方法,采用密目钢丝网拼合成后浇带侧模板,在后浇带空间中填充粗砂之类的临时填充料,待两侧结构浇筑完成凝固后,再清除临时填充料,即可浇筑后浇带混凝土。后浇带空间中的临时填充料能有效避免浮浆渗入,大大减少浇筑前的清理工作量。
Description
技术领域
本发明涉及建筑施工领域,具体的是一种混凝土后浇带的施工方法。
背景技术
混凝土后浇带,是在建筑施工中为了防止现浇钢筋混凝土结构由于自身收缩不均或沉降不均匀产生有害裂缝,按照设计或施工规范要求,在底板及楼板相应位置留置的后浇筑的混凝土带。
施工时,需要用模板分隔出后浇带空间,对后浇带两侧结构先行浇筑,待两侧结构强度符合规范后,需拆除后浇带空间的侧模,对后浇带空间清理,然后浇筑形成后浇带,将两侧结构连成一体。
基于上述工程特点,进行后浇带空间模板设置是比较关键的工序,由于后浇带两侧结构的纵向钢筋会穿过后浇带空间,后浇带侧模版与纵筋接触位置存在间隙,而侧模版与底模板也难以保证完全密封,两侧结构浇筑时,不可避免有浆液渗入后浇带空间中,浆液粘接在纵向钢筋和模板表面后逐渐固化,使得侧模板拆除、钢筋、底模清理的作业量大大增加。
发明内容
本发明所要解决的技术问题是:提供一种混凝土后浇带施工方法,后浇带两侧结构浇筑时,能避免浆液渗入后浇带空间中,大大减少清理工作量。
本发明解决其技术问题所采用的技术方案是:
混凝土后浇带施工方法,包括顺序进行的以下步骤:
A、搭建后浇带空间模板和后浇带两侧结构的模板,所述后浇带空间的侧模板为密目钢丝网形成;
B、向后浇带空间中填入临时填充料,随后浇筑后浇带两侧结构的混凝土;
C、后浇带两侧结构混凝土达到预设强度后,清除后浇带空间中的临时填充料;
D、向后浇带空间中浇筑混凝土。
进一步的,所述步骤A中后浇带空间的底部模板设置有可拆卸的活动模板。
进一步的,所述步骤C中清除临时填充料的方法是,将活动模板抽出,清除活动模板上和后浇带空间中的临时填充料,再将活动模板装回。
进一步的,所述活动模板宽度为后浇带空间底部宽度的2/3。
进一步的,所述步骤A中,用密目钢丝网形成所述侧模板的方法是:在后浇带空间中的纵向钢筋上焊接或捆扎横向钢筋,将密目钢丝网捆扎在纵向钢筋或横向钢筋上,密目钢丝网拼接形成所述侧模板。
进一步的,所述步骤B中临时填充料为粗砂。
进一步的,所述后浇带空间宽度为≥800mm。
本发明的有益效果是:本混凝土后浇带施工方法,采用密目钢丝网拼合成后浇带侧模板,在后浇带空间中填充粗砂之类的临时填充料,待两侧结构浇筑完成凝固后,再清除临时填充料,即可浇筑后浇带混凝土。后浇带空间中的临时填充料能有效避免浮浆渗入,大大减少浇筑前的清理工作量。
附图说明
图1是采用本发明的后浇带施工方法进行模板设置的示意图;
图中附图标记为:梁1、楼板2、后浇带空间3、侧模板31、纵向钢筋4、常规模板51、活动模板52、脚手架9。
具体实施方式
下面结合附图和实施例对本发明进一步说明:
混凝土后浇带施工方法,包括顺序进行的以下步骤:
A、搭建后浇带空间3模板和后浇带两侧结构的模板,所述后浇带空间3的侧模板31为密目钢丝网形成;
B、向后浇带空间3中填入临时填充料,随后浇筑后浇带两侧结构的混凝土;
C、后浇带两侧结构混凝土达到预设强度后,清除后浇带空间3中的临时填充料;
D、向后浇带空间3中浇筑混凝土。
如图1所示:本施工方法,搭建后浇带空间3和后浇带两侧结构的模板时,后浇带空间3的侧模板31采用密目钢丝网形成,密目钢丝网是由密集细钢丝编织形成的网状,多块密目钢丝网拼接形成需要的后浇带空间3的侧模版31。
密目钢丝网的固定方式,优选的可以是捆扎在主钢筋上,例如在后浇带空间3中的纵向钢筋4上焊接或捆扎横向钢筋,将密目钢丝网捆扎在纵向钢筋4或横向钢筋上,密目钢丝网拼接形成所述侧模板31。
随后向后浇带空间3中填入临时填充料,临时填充料用于对后浇带空间3临时填充、支撑,优选的可以是采用粗砂,也可以是采用细沙,小石子等类似物料填充。
随后向后浇带两侧浇筑混凝土,由于临时填充料存在,混凝土浆液难以渗入后浇带空间3中,待后浇带两侧混凝土达到规定强度,则可以清除后浇带空间3中的临时填充料。清除方法可以是采用工具清扫,水冲洗等方式。最后向后浇带空间3中浇筑混凝土,凝固后形成后浇带与两侧结构连接成一体,密目钢丝网则保留在结构中。
采用本施工方法,临时填充料能最大可能的避免混凝土浆液渗入后浇带空间,几乎不需要清理凝固的浮浆,作业量大大减少。而密目钢丝网可以让混凝土表面形成不平整的结构,因此可以省去两侧结构的侧面二次凿毛工序,让后浇带与两侧结构结合紧密,且钢丝网的存在不会导致混凝土结构强渡降低。
为加快清理临时填充料的效率,优选的,可以是,所述步骤A中后浇带空间3的底部模板设置有可拆卸的活动模板52。
如图1所示实施例中,脚手架9上部采用常规模板51设置形成梁1、楼板2的底模板,用密目钢丝网形成的后浇带空间3的侧模版31,有纵向钢筋4穿过后浇带及其两侧结构。
其中后浇带空间3底部设置有活动模板52,活动模板52即是便于拆卸的模板,例如可以是活动模板直接拼合在相邻模板之间,而不设置螺栓连接,便于拆卸。
进一步的,采用活动模板52的优选实施方式时,步骤C中,工人可以将活动模板52抽出,快速清除活动模板52上和后浇带空间3中的临时填充料,再将活动模板52装回,随后进行后续步骤,可以大大提高清理临时填充料的作业效率。
活动模板52的宽度根据实际情况选择,优选的可以是所述活动模板52宽度为后浇带空间3底部宽度的2/3。抽出活动模板时,有利于维持后浇带空间3模板稳定性。
此外,后浇带空间3宽度优选的可以是≥800mm。
Claims (7)
1.混凝土后浇带施工方法,其特征在于,包括顺序进行的以下步骤:
A、搭建后浇带空间(3)模板和后浇带两侧结构的模板,所述后浇带空间(3)的侧模板(31)为密目钢丝网形成;
B、向后浇带空间(3)中填入临时填充料,随后浇筑后浇带两侧结构的混凝土;
C、后浇带两侧结构混凝土达到预设强度后,清除后浇带空间(3)中的临时填充料;
D、向后浇带空间(3)中浇筑混凝土。
2.如权利要求1所述的混凝土后浇带施工方法,其特征在于,所述步骤A中后浇带空间(3)的底部模板设置有可拆卸的活动模板(52)。
3.如权利要求2所述的混凝土后浇带施工方法,其特征在于,所述步骤C中清除临时填充料的方法是,将活动模板(52)抽出,清除活动模板(52)上和后浇带空间(3)中的临时填充料,再将活动模板(52)装回。
4.如权利要求2所述的混凝土后浇带施工方法,其特征在于,所述活动模板(52)宽度为后浇带空间(3)底部宽度的2/3。
5.如权利要求1所述的混凝土后浇带施工方法,其特征在于,所述步骤A中,用密目钢丝网形成所述侧模板(31)的方法是:在后浇带空间(3)中的纵向钢筋(4)上焊接或捆扎横向钢筋,将密目钢丝网捆扎在纵向钢筋(4)或横向钢筋上,密目钢丝网拼接形成所述侧模板(31)。
6.如权利要求1所述的混凝土后浇带施工方法,其特征在于,所述步骤B中临时填充料为粗砂。
7.如权利要求1所述的混凝土后浇带施工方法,其特征在于,所述后浇带空间(3)宽度为≥800mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610263941.3A CN105926782A (zh) | 2016-04-26 | 2016-04-26 | 混凝土后浇带施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610263941.3A CN105926782A (zh) | 2016-04-26 | 2016-04-26 | 混凝土后浇带施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105926782A true CN105926782A (zh) | 2016-09-07 |
Family
ID=56836229
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610263941.3A Pending CN105926782A (zh) | 2016-04-26 | 2016-04-26 | 混凝土后浇带施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105926782A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106759520A (zh) * | 2017-01-06 | 2017-05-31 | 安徽水利开发股份有限公司 | 后浇带的浇筑组件及浇筑后浇带的施工方法 |
CN112696008A (zh) * | 2020-12-22 | 2021-04-23 | 中国十九冶集团有限公司 | 楼面后浇带的施工方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09144146A (ja) * | 1995-11-28 | 1997-06-03 | Shin Etsu Polymer Co Ltd | 目地ガスケットと、これを用いた目地工法 |
CN101629423A (zh) * | 2009-07-17 | 2010-01-20 | 中冶实久建设有限公司 | 刚性封堵超长、超厚块体混凝土基础、板后浇带的方法 |
CN102277963A (zh) * | 2011-05-06 | 2011-12-14 | 江苏正威建设有限公司 | 防先浇砼溢入后浇带结构 |
CN202247961U (zh) * | 2011-08-12 | 2012-05-30 | 武汉建工股份有限公司 | 一种地下室后浇带装配式侧模装置 |
CN103195102A (zh) * | 2013-04-23 | 2013-07-10 | 中建七局第二建筑有限公司 | 地下防水剪力墙后浇带模板支撑结构与支撑方法 |
CN103485423A (zh) * | 2013-09-26 | 2014-01-01 | 中国华冶科工集团有限公司 | 后浇带留置的方法 |
CN204983178U (zh) * | 2015-08-06 | 2016-01-20 | 中国十七冶集团有限公司 | 一种后浇带浇筑封堵装置 |
-
2016
- 2016-04-26 CN CN201610263941.3A patent/CN105926782A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09144146A (ja) * | 1995-11-28 | 1997-06-03 | Shin Etsu Polymer Co Ltd | 目地ガスケットと、これを用いた目地工法 |
CN101629423A (zh) * | 2009-07-17 | 2010-01-20 | 中冶实久建设有限公司 | 刚性封堵超长、超厚块体混凝土基础、板后浇带的方法 |
CN102277963A (zh) * | 2011-05-06 | 2011-12-14 | 江苏正威建设有限公司 | 防先浇砼溢入后浇带结构 |
CN202247961U (zh) * | 2011-08-12 | 2012-05-30 | 武汉建工股份有限公司 | 一种地下室后浇带装配式侧模装置 |
CN103195102A (zh) * | 2013-04-23 | 2013-07-10 | 中建七局第二建筑有限公司 | 地下防水剪力墙后浇带模板支撑结构与支撑方法 |
CN103485423A (zh) * | 2013-09-26 | 2014-01-01 | 中国华冶科工集团有限公司 | 后浇带留置的方法 |
CN204983178U (zh) * | 2015-08-06 | 2016-01-20 | 中国十七冶集团有限公司 | 一种后浇带浇筑封堵装置 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106759520A (zh) * | 2017-01-06 | 2017-05-31 | 安徽水利开发股份有限公司 | 后浇带的浇筑组件及浇筑后浇带的施工方法 |
CN112696008A (zh) * | 2020-12-22 | 2021-04-23 | 中国十九冶集团有限公司 | 楼面后浇带的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105839850A (zh) | 地下室逆作法柱身后浇注预压施工方法 | |
CN205935650U (zh) | 一种后浇带支撑模板 | |
CN104594500B (zh) | 一体化梁板柱模板结构体系及施工方法 | |
CN105350559B (zh) | 一种适用于大型厂房的金刚砂结构地面的施工方法 | |
CN105275097A (zh) | 一种后浇带止水钢板和快易收口网安装方法 | |
CN109610263A (zh) | 一种装配式施工便道的施工方法 | |
CN106351180B (zh) | 渡槽全液压开启自行式模板系统 | |
CN105926782A (zh) | 混凝土后浇带施工方法 | |
CN209482709U (zh) | 一种现浇混凝土墙体沉降缝定型模板 | |
CN105064500B (zh) | 一种阳台梁板内侧填充墙体与主体结构整体浇筑施工方法 | |
CN209907616U (zh) | 一种现浇楼板施工缝侧挡结构 | |
CN203741792U (zh) | 一种混凝土齿槽消力池 | |
CN105927247A (zh) | 大断面全自动机械数控台车及其施工方法 | |
CN103741651B (zh) | 一种混凝土齿槽消力池及其施工方法 | |
CN211873040U (zh) | 用于狭窄空间台背回填的装置 | |
CN209907541U (zh) | 梯形排水沟整体浇筑模板体系 | |
CN109837924B (zh) | 基坑支护格构柱与主体结构交插部位的施工方法 | |
CN110130271A (zh) | 一种侧壁混凝土单面模板加固的施工方法 | |
CN206829155U (zh) | 一种能加强梁体与原状土粘结性能的锚杆框架梁模板 | |
CN206448272U (zh) | 路基边坡拱形骨架一次成型模具 | |
CN205444093U (zh) | 一种堤坝结构 | |
CN109295827A (zh) | 可拆装现浇筑式混凝土路面及建造方法 | |
CN211849445U (zh) | 一种河堤堤坝混凝土垫层的施工系统 | |
CN102912713A (zh) | 一种现浇路缘石用机具及其使用方法 | |
CN202849910U (zh) | 现浇路缘石用机具 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160907 |
|