CN105863236A - Construction method of wall connecting device for industrial factory building outer wall scaffold - Google Patents

Construction method of wall connecting device for industrial factory building outer wall scaffold Download PDF

Info

Publication number
CN105863236A
CN105863236A CN201610175091.1A CN201610175091A CN105863236A CN 105863236 A CN105863236 A CN 105863236A CN 201610175091 A CN201610175091 A CN 201610175091A CN 105863236 A CN105863236 A CN 105863236A
Authority
CN
China
Prior art keywords
wall
scaffold
steel column
support body
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610175091.1A
Other languages
Chinese (zh)
Other versions
CN105863236B (en
Inventor
孙颖
黄先文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
Shanghai Mcc No13 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mcc No13 Construction Co Ltd filed Critical Shanghai Mcc No13 Construction Co Ltd
Priority to CN201610175091.1A priority Critical patent/CN105863236B/en
Publication of CN105863236A publication Critical patent/CN105863236A/en
Application granted granted Critical
Publication of CN105863236B publication Critical patent/CN105863236B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/007Devices and methods for erecting scaffolds, e.g. automatic scaffold erectors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to the field of outer wall scaffold construction in building operations, in particular to a construction method of a wall connecting device for an industrial factory building outer wall scaffold. The construction method is characterized by comprising a step 1, a plurality of steel upright columns are arranged and connected to a plurality of factory building structure columns by pulling and connecting scaffold tubes to combine a temporary stress frame body; a step 2, the steel upright columns are vertically connected by connecting bolts in an extension way; and a step 3, according to a wall connecting piece setting requirement, an outer scaffold body is pulled and connected to the temporary stress frame body in the step 1 by wall connecting scaffold tubes to reach a wall connecting effect. The wall connecting device is easy to manufacture, convenient to install, flexible to disassemble and assemble, and simple to operate; the construction efficiency can be improved, and circulation use is realized; safety is guaranteed; and economic benefits are favorably improved.

Description

Construction method for the wall attaching parts of industrial premises exterior wall scaffold
Technical field
The exterior wall scaffold that the present invention relates in construction builds field, the construction method of a kind of wall attaching parts for industrial premises exterior wall scaffold.
Background technology
During structure and decoration construction, generally use external scaffolding to provide operation side, it is ensured that the safety of operating personnel.Code requirement double-pole scaffold above for height 24m, should use rigid connecting tube to be connected with building, and the connected mode of wall-connecting piece generally uses and agent structure drawknot.But, in some industrial premises design, for meeting the requirement of production technology, the more situation occurring that post net design size is relatively big, structure headroom is higher, cause enough and reliably not connecting wall point in the structure construction stage and can carry out drawknot with external scaffolding support body, if arranging less wall-connecting piece, will be unable to meet code requirement, causing huge potential safety hazard.
Summary of the invention
It is an object of the invention to, it is provided that a kind of making is easily, easy for installation, can dismount flexibly, simple to operate, can improve efficiency of construction and can have enough to meet the need use, it is ensured that the construction method of the wall attaching parts of the exterior wall scaffold of safety.
In order to achieve the above object, the present invention is achieved in that
A kind of construction method of the wall attaching parts for industrial premises exterior wall scaffold, including
Step 1, some steel columns and mill construction post are set it are combined into interim stress support body by drawknot scaffold tubes;Each joint steel column vertical extension is connected by step 2, employing connecting bolt;
Step 3, arranging requirement according to wall-connecting piece, by external scaffolding support body, interim stress support body carries out drawknot by even wall scaffold tubes with described in step 1, reaches even wall effect.
The construction method of the described wall attaching parts for industrial premises exterior wall scaffold, interim stress support body is formed by multiple tracks drawknot scaffold tubes combination drawknot with mill construction post by some steel columns, wherein, steel column is by upper sealing plate, steel pipe, lower shrouding and the welding of some horizontal steel bands are formed, upper sealing plate, lower shrouding is respectively provided with bolt connecting hole, vertical extension is carried out for being fixed with structure floor by steel column and being connected each joint steel column, some horizontal steel bands are used to be welded and fixed with steel pipe in steel column facade surrounding, the specification of steel pipe is identical with out-mould scaffold support body steel pipe specification, it is beneficial to carry out even wall drawknot with external scaffolding support body.
The construction method of the described wall attaching parts for industrial premises exterior wall scaffold, when pouring floorslab concrete, level interval design attitude according to exterior wall scaffold wall-connecting piece, determine the position of required steel column, and pre-embedded bolt, the lower shrouding of steel column is fastenedly connected with pre-embedded bolt, vertical line space design according to wall-connecting piece, determine the height of steel column, use connecting bolt that each joint steel column is carried out vertical extension, steel column and peripheral structure post are connected into interim stress support body by multiple tracks drawknot scaffold tubes, exterior wall scaffold support body is linked by right-angle coupler by the company's of employing wall scaffold tubes with the steel pipe in steel column, reach rigidity and connect the purpose of wall.
The present invention makes easily, easy for installation, can dismount flexibly, simple to operate, can improve efficiency of construction and can have enough to meet the need use, it is ensured that safety, being conducive to increasing economic efficiency.
Accompanying drawing explanation
Fig. 1 steel column organigram.
Fig. 2 be in Fig. 1 A-A to sectional view.
Fig. 3 is external scaffolding support body and interim stress support body wall attaching parts schematic diagram.
Detailed description of the invention
The present invention is further illustrated below by way of specific embodiment.
A kind of construction method of the wall attaching parts for industrial premises exterior wall scaffold, including
Step 1, some steel columns and mill construction post are set it are combined into interim stress support body by drawknot scaffold tubes;Each joint steel column vertical extension is connected by step 2, employing connecting bolt;
Step 3, arranging requirement according to wall-connecting piece, by external scaffolding support body, interim stress support body carries out drawknot by even wall scaffold tubes with described in step 1, reaches even wall effect.
As shown in Figure 1, steel column is welded to form by upper sealing plate 1, steel pipe 3, lower shrouding 2 and some horizontal steel bands 4, upper sealing plate 1, lower shrouding 2 are respectively provided with bolt connecting hole 5, vertical extension is carried out for being fixed with structure floor by steel column and being connected each joint steel column, some horizontal steel bands 4 are used to be welded and fixed with steel pipe 3 in steel column facade surrounding, the specification of steel pipe 3 is identical with out-mould scaffold support body steel pipe specification, is beneficial to carry out even wall drawknot with external scaffolding support body 6..
Fig. 2 external scaffolding support body and interim stress support body wall attaching parts schematic diagram: when pouring floorslab concrete, level interval design attitude according to exterior wall scaffold wall-connecting piece, determine the position of required steel column, and pre-embedded bolt, the lower shrouding 2 of steel column is fastenedly connected with pre-embedded bolt, vertical line space design according to wall-connecting piece, determine the height of steel column, each joint steel column is carried out vertical extension by mode with bolts, steel column is connected into interim stress support body with peripheral structure post 9 by multiple tracks drawknot scaffold tubes 7, exterior wall scaffold support body 6 is linked by right-angle coupler by the company's of employing wall scaffold tubes 8 with the steel pipe 3 in steel column, reach rigidity and connect the purpose of wall.
This wall attaching parts construction method solves in the Construction of Multi-Storey Industrial Buildings of, structure free height big at colum network size, can carry out the difficult problem of drawknot with external scaffolding support body without enough and reliably connecting wall point.

Claims (3)

1. it is used for a construction method for the wall attaching parts of industrial premises exterior wall scaffold, it is characterized in that, including
Step 1, some steel columns and mill construction post are set it are combined into interim stress support body by drawknot scaffold tubes;Each joint steel column vertical extension is connected by step 2, employing connecting bolt,
Step 3, arranging requirement according to wall-connecting piece, by external scaffolding support body, interim stress support body carries out drawknot by even wall scaffold tubes with described in step 1, reaches even wall effect.
It is used for the construction method of the wall attaching parts of industrial premises exterior wall scaffold the most according to claim 1, it is characterized in that: interim stress support body is formed by multiple tracks drawknot scaffold tubes combination drawknot with mill construction post by some steel columns, wherein, steel column is by upper sealing plate, steel pipe, lower shrouding and the welding of some horizontal steel bands are formed, upper sealing plate, lower shrouding is respectively provided with bolt connecting hole, vertical extension is carried out for being fixed with structure floor by steel column and being connected each joint steel column, some horizontal steel bands are used to be welded and fixed with steel pipe in steel column facade surrounding, the specification of steel pipe is identical with out-mould scaffold support body steel pipe specification, it is beneficial to carry out even wall drawknot with external scaffolding support body.
It is used for the construction method of the wall attaching parts of industrial premises exterior wall scaffold the most according to claim 2, it is characterized in that: when pouring floorslab concrete, level interval design attitude according to exterior wall scaffold wall-connecting piece, determine the position of required steel column, and pre-embedded bolt, the lower shrouding of steel column is fastenedly connected with pre-embedded bolt, vertical line space design according to wall-connecting piece, determine the height of steel column, use connecting bolt that each joint steel column is carried out vertical extension, steel column and peripheral structure post are connected into interim stress support body by multiple tracks drawknot scaffold tubes, exterior wall scaffold support body is linked by right-angle coupler by the company's of employing wall scaffold tubes with the steel pipe in steel column, reach rigidity and connect the purpose of wall.
CN201610175091.1A 2016-03-25 2016-03-25 For the construction method of the wall attaching parts of industrial premises exterior wall scaffold Active CN105863236B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610175091.1A CN105863236B (en) 2016-03-25 2016-03-25 For the construction method of the wall attaching parts of industrial premises exterior wall scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610175091.1A CN105863236B (en) 2016-03-25 2016-03-25 For the construction method of the wall attaching parts of industrial premises exterior wall scaffold

Publications (2)

Publication Number Publication Date
CN105863236A true CN105863236A (en) 2016-08-17
CN105863236B CN105863236B (en) 2018-06-29

Family

ID=56624890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610175091.1A Active CN105863236B (en) 2016-03-25 2016-03-25 For the construction method of the wall attaching parts of industrial premises exterior wall scaffold

Country Status (1)

Country Link
CN (1) CN105863236B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107675871A (en) * 2017-07-25 2018-02-09 浙江省建工集团有限责任公司 One kind is building rise long-span outrigger wall-connecting piece construction method
CN113107178A (en) * 2021-04-26 2021-07-13 中国五冶集团有限公司 Outer frame for construction of outer wall enclosure wall of industrial factory building
CN113550560A (en) * 2021-06-07 2021-10-26 中国五冶集团有限公司 Construction method of wall connecting system for forming large-size hole frame structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203939226U (en) * 2014-04-17 2014-11-12 中冶天工上海十三冶建设有限公司 A kind of wall-connecting piece device for scaffold

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203939226U (en) * 2014-04-17 2014-11-12 中冶天工上海十三冶建设有限公司 A kind of wall-connecting piece device for scaffold

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
何勇: ""多层建筑落地式双排扣件式钢管脚手架连墙件的设置探讨"", 《建筑安全》 *
何树东: ""浅谈建筑施工扣件式钢管脚手架连墙件的设置"", 《科技信息(科学教研)》 *
杨峰: ""扣件式脚手架施工方案易忽视的三个问题之探讨"", 《建筑安全》 *
梁耀峰: ""扣件式钢管脚手架伤亡事故案例分析及预防"", 《建筑安全》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107675871A (en) * 2017-07-25 2018-02-09 浙江省建工集团有限责任公司 One kind is building rise long-span outrigger wall-connecting piece construction method
CN113107178A (en) * 2021-04-26 2021-07-13 中国五冶集团有限公司 Outer frame for construction of outer wall enclosure wall of industrial factory building
CN113550560A (en) * 2021-06-07 2021-10-26 中国五冶集团有限公司 Construction method of wall connecting system for forming large-size hole frame structure

Also Published As

Publication number Publication date
CN105863236B (en) 2018-06-29

Similar Documents

Publication Publication Date Title
CN203867216U (en) Detachable steel frame supporting structure for ultra-high-rise building cantilevered plate
CN206513004U (en) A kind of movable hanger for being easy to roof inner slab to install
CN204266609U (en) Assembled architecture faces limit horizontal protective and chooses net system
CN105863236A (en) Construction method of wall connecting device for industrial factory building outer wall scaffold
JP2012132145A (en) Lifting device for building
CN203834926U (en) Formwork erecting structure for bare concrete basement exterior wall
CN201794286U (en) Hanging combined external scaffold and triangular supporting device thereof
CN202866261U (en) Operation hanging rack for civil construction
CN201915638U (en) Hyperbolic steel funnel construction equipment
CN103615103A (en) Hanging type assembled movable platform
CN201377167Y (en) High-altitude assembly platform for segmented factory-building pillars
CN103967178A (en) Curtain wall corner structure with no upright posts
CN204435833U (en) Operation platform wall-attached supporting seat
CN203451012U (en) Double-cage elevator safety protective door spindle device
CN204059671U (en) A kind of assembling factory building wallboard and upright post connection structure
CN103397779B (en) A kind of method for supporting of large height shear wall formwork
CN208718346U (en) Building engineering outer scaffold wall connector
CN202787956U (en) Multifunctional outer wall large panel
CN204418696U (en) Vertical reinforcement spreading lifting assistor
CN204357090U (en) A kind of horizontal support framework of attached lift scaffold
CN104234189A (en) Four-pipe truss structure of prefabricated house
CN205242981U (en) Concrete construction operation platform
CN216380480U (en) Integral movable operation frame
CN103114712B (en) Buckle steel platform support system and construction method thereof
CN220285383U (en) Novel protection canopy

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190814

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Co-patentee after: CHINA MCC20 GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469