CN216380480U - Integral movable operation frame - Google Patents
Integral movable operation frame Download PDFInfo
- Publication number
- CN216380480U CN216380480U CN202121595140.XU CN202121595140U CN216380480U CN 216380480 U CN216380480 U CN 216380480U CN 202121595140 U CN202121595140 U CN 202121595140U CN 216380480 U CN216380480 U CN 216380480U
- Authority
- CN
- China
- Prior art keywords
- layer
- rods
- operating
- platform
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model relates to an integral movable operation frame which is provided with a plurality of layers of operation platforms, wherein horizontal rods are continuously arranged inside and outside each layer of operation platform, a safety vertical net is additionally arranged on each layer of operation platform, a quadrilateral operation platform surrounding a structural column is formed, the operation platforms of each layer are connected together through vertical rods, and inclined rods are additionally arranged on the side surfaces of the operation platforms; each layer of operating platform is provided with a shaping walkway plate, and the side surface of each layer of operating platform is provided with a protective railing and a shaping fence; and a lifting ring is arranged at the top of the integral movable operating frame. The integral movable operation frame provided by the utility model has sufficient strength, rigidity and stability, is simple and convenient to operate, high in cost performance, easy to disassemble, reusable, clean and environment-friendly, is suitable for large-scale construction sites with more structural columns, can effectively save the construction period and cost of the column construction, can ensure the safety and stability of the construction, and is convenient for workers to work up and down.
Description
Technical Field
The utility model relates to an operation frame for a construction site, which is used for construction of a subsection engineering column with higher floor height and larger section and exceeding a certain scale, can save the time for assembling and disassembling a column bent frame, and belongs to the technical field of building construction.
Background
In the existing column construction, when a large-section column of projects such as large-scale factory buildings, subway parking lots and the like is constructed, the elevation difference between the column and a beam is higher, and the column is arranged with strength, so that the column is constructed firstly and then the beam slab construction is carried out. At this moment, generally, scaffolds need to be erected around the columns, and workers can perform operations such as reinforcement binding and template laying through scaffold plates at various heights.
The tradition adopts fastener steel-pipe type or dish knot formula scaffold frame, and the construction can just begin after the scaffold frame is all need set up in every post construction to after this post construction is accomplished, need demolish again and transport and continue to set up by next root column. The process of taking apart when the layer height is high wastes time and energy and the material loss is great, need spend more cost on setting up and demolising this two processes of scaffold frame. In projects such as large-scale factory buildings and subway parking lots, the number of common structural columns is large, the floor height is high, the section of each column is large, and the cost of expenditure on column scaffold projects is not high.
Therefore, the operation scaffold of the column needs to be made into a whole, the working procedures of erecting and dismantling the scaffold are omitted, and finally the section steel and the section steel bolts are connected with each other through various summary and discussion to form an integral movable operation frame.
Disclosure of Invention
The utility model aims to solve the technical problem of ensuring the safety, stability and efficiency during the construction of the column, saving the construction period and cost of the scaffold engineering, and providing an integral movable operation frame which is used for replacing the column scaffold adopted in the prior art and omitting the process of erecting and disassembling the scaffold.
In order to solve the technical problems, the utility model adopts the technical scheme that: an integral movable operation frame is provided with a plurality of layers of operation platforms, horizontal rods are continuously arranged inside and outside each layer of operation platform, a safety vertical net is additionally arranged on each layer of operation platform, a quadrilateral operation platform surrounding a structural column is formed, the operation platforms of each layer are connected together through vertical rods, and inclined rods are additionally arranged on the side surfaces of the operation platforms; each layer of operating platform is provided with a shaping walkway plate, and the side surface of each layer of operating platform is provided with a protective railing and a shaping fence; and a lifting ring is arranged at the top of the integral movable operating frame.
Furthermore, one side of the integral movable operation frame is provided with an up-down stair, an up-down stair channel and a rest platform.
Furthermore, the vertical rods and the horizontal rods, the longitudinal horizontal rods and the transverse horizontal rods are fixed by bolts, and the operation platforms are detached or additionally installed by the bolts to adjust the height, so that the vertical and horizontal combined column is suitable for a 3-14m structural column.
Furthermore, the safety vertical net is sleeved on the hook welded on the side surface of the vertical rod through the upper sleeve of the safety vertical net.
Furthermore, the vertical rods and the horizontal rods adopt square tubes with 60 × 60 mm.
Further, the bolt is an M12 hexagon bolt.
The utility model has the beneficial effects that:
the integral movable operation frame provided by the utility model has sufficient strength, rigidity and stability, is simple and convenient to operate, high in cost performance, easy to disassemble, reusable, clean and environment-friendly, is suitable for large-scale construction sites with more structural columns, can effectively save the construction period and cost of the column construction, can ensure the safety and stability of the construction, and is convenient for workers to work up and down.
Drawings
FIG. 1 is a front view of an integral mobile handling frame;
FIG. 2 is a top view of an integral movable handling frame;
FIG. 3 is a diagram of a square tube bolted joint;
fig. 4 is a diagram of a connecting node between a safety vertical net and a square pipe vertical rod.
Detailed Description
The utility model is further described with reference to the following figures and examples.
As shown in fig. 1 and 2, the integral movable handling frame of the utility model comprises a horizontal rod 1, a vertical rod 2, an inclined rod 3, a guard rail 4, a fence 5, a walkway plate 6, an up-down stair 7, a rest platform 8, an up-down stair channel 9, a safety vertical net and the like.
Integral portable handling frame is equipped with multilayer operation platform, all sets up horizon bar 1 inside and outside in succession on each layer operation platform, installs safe upright net additional to constitute the quadrangle operation platform around structural column 11, link together through pole setting 2 between each layer operation platform, the side installs down tube 3 additional for strengthen joint strength and rigidity between the pole setting 2. And a shaping walkway plate 6 is arranged on each layer of operating platform, and a protective railing 4 and a shaping fence 5 are arranged on the side surface of each layer of operating platform. The top of the integral movable operation frame is provided with a hanging ring 10. One side of the integral movable operation frame is provided with an up-down stair 7, an up-down stair channel 9 and a rest platform 8.
As shown in fig. 3, the vertical rod 2 and the horizontal rod 1, and the longitudinal and transverse horizontal rods 1 are fixed by bolts 12. The operation platform is disassembled or additionally installed through the bolts 12, the height is adjusted, and the device is suitable for the structural column 11 of 3-14 m.
As shown in fig. 4, the safety vertical net is sleeved on the hook welded on the side surface of the vertical rod through the upper sleeve of the safety vertical net.
Preferably, the vertical rods and the horizontal rods adopt 60-60 mm square tubes.
Preferably, the bolt is an M12 hexagon bolt.
The utility model realizes one-time erection and repeated use, and can effectively save the cost of manpower, materials and machinery. The operation frame can ensure the operation safety of workers. The utility model is assembled, can be disassembled and recycled, and is clean and environment-friendly. The utility model adopts the materials such as bolts, section steel and the like, and has low cost. Accessible hoisting equipment removes in the construction place, and the number of times of can having enough to meet the need is many, can realize economic benefits maximize.
Claims (6)
1. An integral portable handling frame which characterized in that: the device is provided with a plurality of layers of operating platforms, horizontal rods are continuously arranged inside and outside each layer of operating platform, a safety vertical net is additionally arranged, a quadrilateral operating platform surrounding a structural column is formed, the operating platforms of all layers are connected together through vertical rods, and inclined rods are additionally arranged on the side surfaces of the operating platforms; each layer of operating platform is provided with a shaping walkway plate, and the side surface of each layer of operating platform is provided with a protective railing and a shaping fence; and a lifting ring is arranged at the top of the integral movable operating frame.
2. The unitary moveable operator stand of claim 1 wherein: one side of the integral movable operation frame is provided with an up-down stair, an up-down stair channel and a rest platform.
3. The unitary moveable operator stand of claim 1 wherein: the vertical rods and the horizontal rods and the longitudinal horizontal rods and the transverse horizontal rods are fixed by bolts, and the operation platforms are detached or additionally installed by the bolts, so that the height is adjusted, and the device is suitable for 3-14m structural columns.
4. The unitary moveable operator stand of claim 1 wherein: the safety vertical net is sleeved on the hook welded on the side surface of the vertical rod through the upper sleeve of the safety vertical net.
5. The unitary moveable operator stand of claim 1 wherein: the vertical rods and the horizontal rods adopt square tubes with 60-60 mm.
6. The integral movable carrier of claim 3, wherein: the bolt is an M12 hexagon bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121595140.XU CN216380480U (en) | 2021-07-14 | 2021-07-14 | Integral movable operation frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121595140.XU CN216380480U (en) | 2021-07-14 | 2021-07-14 | Integral movable operation frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216380480U true CN216380480U (en) | 2022-04-26 |
Family
ID=81216945
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121595140.XU Active CN216380480U (en) | 2021-07-14 | 2021-07-14 | Integral movable operation frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216380480U (en) |
-
2021
- 2021-07-14 CN CN202121595140.XU patent/CN216380480U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201158933Y (en) | High-rise maintaining scaffold device with extruding structure | |
CN103485574B (en) | A kind of granulation tower tower top structure of reinforced concrete method | |
CN206873307U (en) | Movable type bridge justifies pier stud work high above the ground operating platform | |
CN114059758A (en) | Assembled double-layer integral elevator shaft platform | |
CN203834926U (en) | Formwork erecting structure for bare concrete basement exterior wall | |
CN216476193U (en) | Portable steel member installation operation platform of modularization | |
CN212866793U (en) | Assembled construction elevator stops layer platform | |
CN213418433U (en) | Stair combined type operation platform | |
CN210828394U (en) | High-rise building demolishs device | |
CN103352570B (en) | Assembled construction gateway | |
CN210857934U (en) | Cage type scaffold | |
CN109944164B (en) | Self-elevating hollow thin-wall pier roller die system and construction method thereof | |
CN216380480U (en) | Integral movable operation frame | |
CN115162772B (en) | Demolishing process for high-rise building | |
CN104164889A (en) | Demountable tower crane foundation | |
CN215978575U (en) | Safety protection system for dismantling reinforced concrete water tower in limited space | |
CN112343359A (en) | High-rise building demolishs device | |
CN213204913U (en) | Modular prefabricated staircase operation platform | |
CN209874434U (en) | Simple and easy scaffold frame of encorbelmenting of building high latitude | |
CN112502475B (en) | Supporting bearing capacity conversion device and using method thereof | |
CN210563531U (en) | Steel structure support for building protection | |
CN204603635U (en) | For the moulding bed of Node In Large-span Pipe Truss modularization making | |
CN213898077U (en) | High-rise building construction operation elevator shaft and lighting well operation platform | |
CN220978730U (en) | Lantern frame device for upright post construction | |
CN213297074U (en) | Portable outer wall handling frame of encorbelmenting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |