CN208009863U - A kind of tool-type pier stud construction operation platform device - Google Patents

A kind of tool-type pier stud construction operation platform device Download PDF

Info

Publication number
CN208009863U
CN208009863U CN201820019075.8U CN201820019075U CN208009863U CN 208009863 U CN208009863 U CN 208009863U CN 201820019075 U CN201820019075 U CN 201820019075U CN 208009863 U CN208009863 U CN 208009863U
Authority
CN
China
Prior art keywords
operation platform
tool
link block
block
construction operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820019075.8U
Other languages
Chinese (zh)
Inventor
方新雷
伍志珍
潘志高
何昶
陈慧涛
缪仕健
付凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Construction Engineering Co Ltd
Original Assignee
Wuhan Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Construction Engineering Co Ltd filed Critical Wuhan Construction Engineering Co Ltd
Priority to CN201820019075.8U priority Critical patent/CN208009863U/en
Application granted granted Critical
Publication of CN208009863U publication Critical patent/CN208009863U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of tool-type pier stud construction operation platform devices, it includes single layer combination body, the first link block, cushion cap, which is characterized in that the first layer single layer combination body is fixed on by expansion bolt on the cushion cap for completion of having constructed;The single layer combination body is connected with single layer combination body by the first link block;The single layer combination body includes standard block, stairway unit, the first link block and the second link block, and the standard block is connected with standard block by the second link block;The standard block is connected with stairway unit by the second link block;The device construction safety, easily and fast, flexibly, it can disassembly and assembly anywhere or anytime, labour can effectively be saved by being used in the construction of municipal bridge pier column, accelerate material turnaround speed, it brought convenience to the construction of municipal road bridge pier column, improve working efficiency, and then reduce Construction Cost.

Description

一种工具式墩柱施工操作平台装置A tool type pier column construction operation platform device

技术领域technical field

本实用新型属于市政桥梁技术领域,涉及一种墩柱操作平台,尤其涉及一种工具式墩柱施工操作平台装置。本实用新型主要适用于市政桥梁工程的墩柱施工。The utility model belongs to the technical field of municipal bridges and relates to a pier column operation platform, in particular to a tool type pier column construction operation platform device. The utility model is mainly applicable to the construction of pier columns in municipal bridge engineering.

背景技术Background technique

目前,对于市政桥梁墩柱操作平台的施工方案基本都是采用钢管脚手架或碗口脚手架,对于墩柱数量众多的市政高架桥梁来说,由于钢管脚手架或碗口脚手架的的使用必须进行重复的搭设拆除工作,搭设及拆除操作平台的时间周期较长,需要的劳动力较多,且安全性不高。At present, the construction plan for the pier column operation platform of municipal bridges basically adopts steel pipe scaffolding or bowl-mouth scaffolding. For municipal viaducts with a large number of pier columns, the use of steel pipe scaffolding or bowl-mouth scaffolding must be erected The dismantling work, the time period of setting up and dismantling the operation platform is longer, requires more labor, and the safety is not high.

发明内容Contents of the invention

本实用新型的目的是克服上述不足,提供了一种工具式墩柱施工操作平台装置,该装置施工安全、方便、快速、灵活,可随时随地的拆卸和组装,运用在市政桥梁墩柱的施工上可以有效的节省劳动力,加快材料周转速度,给市政道桥梁墩柱施工带来方便、提高工作效率,进而降低工程施工成本。The purpose of this utility model is to overcome the above-mentioned shortcomings and provide a tool-type pier column construction operation platform device, which is safe, convenient, fast and flexible in construction, can be disassembled and assembled anytime and anywhere, and is used in the construction of municipal bridge pier columns It can effectively save labor, speed up material turnover, bring convenience to the construction of municipal road bridge piers, improve work efficiency, and reduce construction costs.

为了实现上述目的,本实用新型采用的技术方案是:In order to achieve the above object, the technical solution adopted by the utility model is:

一种工具式墩柱施工操作平台装置,它包括单层组合体、第一连接块、承台,其特征在于,所述的第一层单层组合体通过膨胀螺栓固定在已施工完成的承台上;所述的单层组合体和单层组合体通过第一连接块相连;第一层单层组合体在承台上;A tool-type pier column construction operation platform device, which includes a single-layer combination, a first connecting block, and a cap, and is characterized in that the first-layer single-layer combination is fixed on the completed bearing by expansion bolts. on the platform; the single-layer assembly and the single-layer assembly are connected through the first connecting block; the first layer of the single-layer assembly is on the platform;

所述的单层组合体包括标准单元、楼梯单元、第一连接块和第二连接块,所述的标准单元与标准单元通过第二连接块相连;所述的标准单元与楼梯单元通过第二连接块相连;The single-layer combination includes a standard unit, a staircase unit, a first connecting block and a second connecting block, and the standard unit is connected to the standard unit through the second connecting block; the standard unit and the staircase unit are connected through the second connecting block. connecting blocks;

所述的标准单元通过四根立杆、四根标准单元纵杆、5-8根横杆及四根钢管栏杆焊接而成,标准单元底部满焊2mm厚钢板,通过立杆、纵杆、横杆焊接成的骨架为整个标准单元的主要承重构件,供工作人员水平通行。The standard unit is welded by four vertical poles, four standard unit longitudinal poles, 5-8 horizontal bars and four steel pipe railings. The bottom of the standard unit is fully welded with 2mm thick steel plates. The welded skeleton is the main load-bearing member of the entire standard unit, which is used for staff to pass through horizontally.

所述的楼梯单元通过四根立杆、四根楼梯单元纵杆、八根横杆、一个楼梯及四根钢管栏杆焊接而成,通过立杆、纵杆、横杆焊接成的骨架为整个楼梯单元的主要承重构件,供工作人员上下通用。The staircase unit is welded by four vertical poles, four longitudinal poles of the staircase unit, eight crossbars, one staircase and four steel pipe railings, and the skeleton welded by the vertical poles, longitudinal poles and crossbars is the whole staircase unit The main load-bearing member is for the staff to use up and down.

优选的,所述的标准单元高度为2m,长度为3.5~5m(可依据实际情况调整长度尺寸),宽度为0.8m;Preferably, the standard unit has a height of 2m, a length of 3.5-5m (the length can be adjusted according to the actual situation), and a width of 0.8m;

优选的,楼梯单元高度为2m,长度为3.4m,宽度为0.8m,它的作用是供工作人员上下通行;Preferably, the height of the staircase unit is 2m, the length is 3.4m, and the width is 0.8m, and its function is for the staff to pass up and down;

优选的,所述的立杆、标准单元纵杆、横杆均为100mm×100mm方钢,厚度为5mm;所述的立杆的高度为2m,所述的标准单元纵杆长3.4-4.9m,所述的楼梯单元纵杆长3.4m,所述的横杆长0.6m;Preferably, the vertical rods, standard unit longitudinal rods, and horizontal rods are all 100mm×100mm square steel with a thickness of 5mm; the height of the vertical rods is 2m, and the length of the standard unit longitudinal rods is 3.4-4.9m , the longitudinal bar of the staircase unit is 3.4m long, and the horizontal bar is 0.6m long;

优选的,所述的钢管栏杆的直径为20mm,高度为1.2m,它的作用是作为工作人员的扶手;Preferably, the steel pipe railing has a diameter of 20mm and a height of 1.2m, and its function is as a handrail for staff;

优选的,所述钢板的厚度为2mm,它的作用是供工作人员环绕墩柱通行;Preferably, the thickness of the steel plate is 2mm, and its function is for staff to pass around the pier column;

优选的,所述第一连接块为10mm厚的方形钢板,钢板边长为150mm,第一连接块焊接在标准单元和楼梯单元四角的立杆上;Preferably, the first connecting block is a square steel plate with a thickness of 10 mm, the side length of the steel plate is 150 mm, and the first connecting block is welded on the poles at the four corners of the standard unit and the staircase unit;

优选的,所述第二连接块为10mm厚的角钢,角钢每侧宽100mm,长度为350mm,第二连接块焊接在标准单元和楼梯单元每个立杆的侧面;Preferably, the second connecting block is a 10mm thick angle steel, the angle steel is 100mm wide on each side, and the length is 350mm, and the second connecting block is welded on the side of each vertical bar of the standard unit and the staircase unit;

所述单层组合体由多个标准单元和一个楼梯单元通过第二连接块连接成的一个环形封闭的结构,通过楼梯单元7以实现工作人员的上下通行。The single-layer combination is a ring-shaped closed structure formed by connecting multiple standard units and a stair unit through the second connecting block, and the stair unit 7 is used to realize the up and down passage of staff.

依据墩柱设计高度,将多个单层组合体通过第一连接块连接固定成为一个完整的墩柱操作平台,当操作平台超过6m时在顶部四个角的位置设置揽风绳,揽风绳与地面夹角为45-60,揽风绳起到增加操作平台稳定性的作用。According to the design height of the pier column, multiple single-layer assemblies are connected and fixed through the first connecting block to form a complete pier column operation platform. When the operation platform exceeds 6m, wind ropes are installed at the four corners of the top. The angle with the ground is 45° . -60 . , The wind rope plays a role in increasing the stability of the operating platform.

本实用新型与现有技术相比,具有以下优点和效果:Compared with the prior art, the utility model has the following advantages and effects:

(1)该操作平台比现有技术搭设的钢管操作平台安全性更好,平台的制作可制作工厂化生产,操作平台的质量可以得到保障。(1) The operating platform is safer than the steel pipe operating platform built in the prior art, the platform can be manufactured in a factory, and the quality of the operating platform can be guaranteed.

(2)该装置现场组装以及拆卸方便,可多次重复利用,可加快施工进度,节省劳动力,降低工程造价。(2) The device is easy to assemble and disassemble on site, and can be reused many times, which can speed up the construction progress, save labor and reduce the project cost.

附图说明Description of drawings

图1为一种工具式墩柱施工操作平台装置的第一连接块示意图;Fig. 1 is a schematic diagram of the first connection block of a tool-type pier column construction operation platform device;

图2为一种工具式墩柱施工操作平台装置的第二连接块示意图;Fig. 2 is a schematic diagram of the second connection block of a tool-type pier column construction operation platform device;

图3为一种工具式墩柱施工操作平台装置的标准单元示意图;Fig. 3 is a schematic diagram of a standard unit of a tool-type pier column construction operation platform device;

图4为一种工具式墩柱施工操作平台装置的楼梯单元示意图;Fig. 4 is a schematic diagram of a stair unit of a tool-type pier column construction operation platform device;

图5为一种工具式墩柱施工操作平台装置的单层组合体示意图;Fig. 5 is a schematic diagram of a single-layer assembly of a tool-type pier column construction operation platform device;

图6为一种工具式墩柱施工操作平台装置示意图;Fig. 6 is a schematic diagram of a tool-type pier column construction operation platform device;

其中:1为立杆,2为钢管栏杆,3为钢板,4为楼梯,5为第一连接块,6为第二连接块,7为楼梯单元,8为标准单元,9为承台,10为墩柱,11为揽风绳,12为单层组合体,13为标准单元纵杆,14为横杆;15为楼梯单元纵杆。Among them: 1 is the vertical pole, 2 is the steel pipe railing, 3 is the steel plate, 4 is the staircase, 5 is the first connecting block, 6 is the second connecting block, 7 is the staircase unit, 8 is the standard unit, 9 is the cap, 10 11 is a wind rope, 12 is a single-layer assembly, 13 is a standard unit longitudinal bar, and 14 is a cross bar; 15 is a staircase unit longitudinal bar.

具体实施方式:Detailed ways:

下面结合具体实施方式对本实用新型作进一步详细介绍。Below in conjunction with specific embodiment, the utility model is described in further detail.

一种工具式墩柱施工操作平台装置,它包括单层组合体12、第一连接块5、承台9,其特征在于,所述的第一层单层组合体12通过膨胀螺栓固定在已施工完成的承台9上;所述的单层组合体12和单层组合体12通过第一连接块5相连;所述的单层组合体12包括五个标准单元8、一个楼梯单元7和第二连接块6,所述的标准单元8与标准单元8通过第二连接块6相连;所述的标准单元8与楼梯单元7通过第二连接块6相连;所述的标准单元8通过四根立杆1、四根标准单元纵杆13、5或6或7或8根横杆14及四根钢管栏杆2焊接而成,所述的立杆1、标准单元纵杆13、横杆14均为成品材料100×100mm的方钢,方钢壁厚为5mm,所述的立杆1的高度为2m,所述的标准单元纵杆13长3.4-4.9m,所述的横杆14长0.6m;所述的标准单元8高度为2m,长度为3.5~5m(可依据实际情况调整长度尺寸),宽度为0.8m,所述的标准单元8的两侧焊接直径为20mm的钢管栏杆2作为扶手栏杆,钢管栏杆2高度为1.2m,标准单元8底部满焊2mm厚的钢板3,钢板3供工作人员环绕墩柱通行;所述的楼梯单元7通过四根立杆1、四根楼梯单元纵杆15、八根横杆14、一个楼梯4及四根钢管栏杆2焊接而成,所述的立杆1、楼梯单元纵杆15、横杆14均成品材料100*100mm的方钢,方钢壁厚为5mm,所述的立杆1的高度为2m,所述的楼梯单元纵杆15长3.3m,所述的横杆14长0.6m;所述的楼梯单元7高度为2m,长度为3.4m,宽度为0.8m,所述的楼梯单元7两侧焊接直径为20mm的钢管栏杆2作为扶手栏杆,楼梯单元7供工作人员上下通行。A tool-type pier column construction operation platform device, which includes a single-layer assembly 12, a first connecting block 5, and a cap 9, and is characterized in that the first-layer single-layer assembly 12 is fixed on the existing On the cap platform 9 that the construction has been completed; the single-layer combination 12 and the single-layer combination 12 are connected through the first connecting block 5; the single-layer combination 12 includes five standard units 8, a staircase unit 7 and The second connection block 6, the standard unit 8 is connected with the standard unit 8 through the second connection block 6; the standard unit 8 is connected with the staircase unit 7 through the second connection block 6; the standard unit 8 is connected through four A vertical bar 1, four standard unit longitudinal bars 13, 5 or 6 or 7 or 8 horizontal bars 14 and four steel pipe railings 2 are welded together, and the described vertical bar 1, standard unit longitudinal bars 13, and horizontal bars 14 are all It is a square steel with a finished material of 100×100mm, the wall thickness of the square steel is 5mm, the height of the vertical bar 1 is 2m, the length of the standard unit longitudinal bar 13 is 3.4-4.9m, and the length of the horizontal bar 14 is 0.6m. m; the height of the standard unit 8 is 2m, the length is 3.5~5m (the length can be adjusted according to the actual situation), and the width is 0.8m, and the steel pipe railings 2 with a diameter of 20mm are welded on both sides of the standard unit 8 as Handrails, the steel pipe railing 2 is 1.2m in height, the bottom of the standard unit 8 is fully welded with a 2mm thick steel plate 3, and the steel plate 3 is for the staff to pass around the pier column; Bar 15, eight cross bars 14, a staircase 4 and four steel pipe railings 2 are welded together, and the vertical bar 1, staircase unit longitudinal bar 15, and cross bar 14 are all square steel of finished material 100*100mm, square steel Wall thickness is 5mm, and the height of described vertical bar 1 is 2m, and described stair unit longitudinal bar 15 is long 3.3m, and described cross bar 14 is long 0.6m; Described stair unit 7 height is 2m, and length is 3.4m and a width of 0.8m, steel pipe railings 2 with a diameter of 20mm welded on both sides of the stair unit 7 are used as handrails, and the stair unit 7 is for staff to pass up and down.

所述第一连接块5为10mm厚的方形钢板,钢板边长为150mm,第一连接块5焊接在标准单元8以及楼梯单元7四角的立杆1之上,用于单层组合体12之间的连接固定;The first connecting block 5 is a square steel plate with a thickness of 10 mm, and the side length of the steel plate is 150 mm. The first connecting block 5 is welded on the poles 1 at the four corners of the standard unit 8 and the staircase unit 7, and is used for the single-layer assembly 12. The connection between is fixed;

所述第二连接块6为10mm厚的角钢,角钢每侧宽100mm,长度为350mm,第二连接块6焊接在标准单元8和楼梯单元7的每个的立杆1侧面,用于标准单元8与标准单元8之间及标准单元8与楼梯单元7之间的连接固定;The second connecting block 6 is an angle steel with a thickness of 10 mm, the angle steel is 100 mm wide on each side, and the length is 350 mm. The second connecting block 6 is welded on the side of the vertical bar 1 of each of the standard unit 8 and the staircase unit 7, and is used for the standard unit The connections between 8 and standard unit 8 and between standard unit 8 and staircase unit 7 are fixed;

所述单层组合体12由五个标准单元8和一个楼梯单元7通过第二连接块6连接成的一个环形封闭的结构,通过楼梯单元7可以实现工作人员的上下通行。The single-layer composite body 12 is an annular closed structure formed by connecting five standard units 8 and one staircase unit 7 through the second connecting block 6 , through which the staff can pass up and down.

依据墩柱10设计高度,将多个单层组合体12通过第一连接块5连接固定成为一个完整的墩柱操作平台,当操作平台超过6m时在顶部四个角的位置设置揽风绳11,揽风绳11与地面夹角为45-60,揽风绳11起到增加操作平台稳定性的作用。According to the design height of the pier column 10, multiple single-layer assemblies 12 are connected and fixed through the first connecting block 5 to form a complete pier column operation platform. When the operation platform exceeds 6m, wind ropes 11 are installed at the four corners of the top , The included angle between the wind rope 11 and the ground is 45° . -60 . , The wind rope 11 plays the role of increasing the stability of the operating platform.

墩柱施工时,施工人员可以通过操作平台的第一层组合体进入操作架,通过操作平台中的楼梯单元7进行上下通行。整个装置为墩柱施工人员提供一个安全的操作平台及安全通道。该操作平台的所有单元及零部件均可以在工厂进行加工预制,运至现场进行组合,组装工艺简单,组装速度快,墩柱施工完成后,操作平台的拆除方便。此操作平台特别适用工期紧、墩柱数量众多的高架桥梁施工。During pier column construction, construction personnel can enter the operation frame through the first layer assembly of the operation platform, and pass up and down through the stair unit 7 in the operation platform. The whole device provides a safe operation platform and a safe passage for the pier construction personnel. All units and parts of the operation platform can be processed and prefabricated in the factory, transported to the site for assembly, the assembly process is simple, the assembly speed is fast, and the operation platform is easy to dismantle after the pier construction is completed. This operating platform is especially suitable for the construction of viaducts with tight construction schedules and a large number of piers.

以上所述仅为本实用新型最佳的实施方案,凡依本实用新型申请专利范围所作的均等变化与修饰,皆应属本实用新型专利的涵盖范围。The above is only the best embodiment of the utility model, and all equal changes and modifications made according to the scope of the patent application of the utility model should all belong to the scope of coverage of the utility model patent.

Claims (9)

1. a kind of tool-type pier stud construction operation platform device, it includes single layer combination body (12), the first link block (5), cushion cap (9), which is characterized in that the single layer combination body (12) is fixed on by expansion bolt on cushion cap (9);The single layer combination Body (12) is connected with single layer combination body (12) by the first link block (5);The single layer combination body (12) includes standard block (8), stairway unit (7), the first link block (5) and the second link block (6), the standard block (8) pass through the second link block (6) it is connected;The standard block (8) is connected with stairway unit (7) by the second link block (6).
2. a kind of tool-type pier stud construction operation platform device as described in claim 1, it is characterised in that:The standard list First (8) are welded by four upright bars (1), four standard block vertical poles (13), 5-8 roots cross bar (14) and four steel pipe railings (2), The steel plate (3) of standard block bottom full weld 2mm thickness.
3. a kind of tool-type pier stud construction operation platform device as described in claim 1, it is characterised in that:The stair list First (7) pass through four upright bars (1), four stairway unit vertical poles (15), eight cross bars (14), a stair (4) and four steel pipes Railing (2) welds.
4. a kind of tool-type pier stud construction operation platform device as claimed in claim 1 or 2, it is characterised in that:The mark Quasi- unit (8) is highly 2m, and length is 3.5~5m, width 0.8m.
5. a kind of tool-type pier stud construction operation platform device as described in claim 1 or 3, it is characterised in that:The building Terraced unit (7) is highly 2m, length 3.4m, width 0.8m.
6. a kind of tool-type pier stud construction operation platform device as claimed in claim 2 or claim 3, it is characterised in that:Described is vertical Bar (1), standard block vertical pole (13), cross bar (14) are 100mm × 100mm square steel, thickness 5mm;The upright bar (1) It is highly 2m, described standard block vertical pole (13) the long 3.4-4.9m, described stairway unit vertical pole (15) the long 3.3m, it is described Cross bar (14) long 0.6m;A diameter of 20mm of the steel pipe railing (2), is highly 1.2m.
7. a kind of tool-type pier stud construction operation platform device as described in claim 1, it is characterised in that:First connection Block (5) is the square plate of 10mm thickness, and the steel plate length of side is 150mm, and the first link block (5) is welded on standard block (8) and stair In the upright bar (1) of unit (7) quadrangle.
8. a kind of tool-type pier stud construction operation platform device as described in claim 1, it is characterised in that:Second connection Block (6) is the angle steel of 10mm thickness, and angle steel is per the wide 100mm in side, length 350mm, and the second link block (6) is welded on standard block (8) and the side of each upright bar (1) of stairway unit (7).
9. a kind of tool-type pier stud construction operation platform device as described in claim 1, it is characterised in that:The single layer group Fit (12) are connected and fixed by the first link block (5) as an operating platform, position of the operating platform at four angles in top Cable rope (11) is set, and cable rope (11) and ground angle are 45-60 degree.
CN201820019075.8U 2018-01-05 2018-01-05 A kind of tool-type pier stud construction operation platform device Expired - Fee Related CN208009863U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820019075.8U CN208009863U (en) 2018-01-05 2018-01-05 A kind of tool-type pier stud construction operation platform device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820019075.8U CN208009863U (en) 2018-01-05 2018-01-05 A kind of tool-type pier stud construction operation platform device

Publications (1)

Publication Number Publication Date
CN208009863U true CN208009863U (en) 2018-10-26

Family

ID=63882357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820019075.8U Expired - Fee Related CN208009863U (en) 2018-01-05 2018-01-05 A kind of tool-type pier stud construction operation platform device

Country Status (1)

Country Link
CN (1) CN208009863U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109487697A (en) * 2018-12-06 2019-03-19 广东腾盛模架科技有限公司 Construction safety assembled ladder cage module
CN109763427A (en) * 2018-12-29 2019-05-17 中交路桥华东工程有限公司 A kind of assembled operating platform of pier shaft reinforcing bar binding and its installation and method for dismounting
CN111677264A (en) * 2020-05-19 2020-09-18 中国铁建港航局集团有限公司 Method for constructing combined ladder cage with safety protection
CN111851976A (en) * 2020-06-29 2020-10-30 中天华南建设投资集团有限公司 Sizing operation platform used around internal climbing type movable arm tower crane and installation method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109487697A (en) * 2018-12-06 2019-03-19 广东腾盛模架科技有限公司 Construction safety assembled ladder cage module
CN109763427A (en) * 2018-12-29 2019-05-17 中交路桥华东工程有限公司 A kind of assembled operating platform of pier shaft reinforcing bar binding and its installation and method for dismounting
CN111677264A (en) * 2020-05-19 2020-09-18 中国铁建港航局集团有限公司 Method for constructing combined ladder cage with safety protection
CN111851976A (en) * 2020-06-29 2020-10-30 中天华南建设投资集团有限公司 Sizing operation platform used around internal climbing type movable arm tower crane and installation method thereof

Similar Documents

Publication Publication Date Title
CN208009863U (en) A kind of tool-type pier stud construction operation platform device
CN110387822B (en) Cast-in-situ bent cap assembly type steel pipe support and construction method thereof
CN102535845A (en) Construction method of bearing frame of corridor structure
CN103452311A (en) Method for erecting section steel cantilever structure support frame
CN102182303A (en) Oblique annular closed structural template supporting method
CN210507141U (en) Movable tensioning platform
CN206428595U (en) A kind of mobile platform suitable for the wet seam construction of section assembling box beam
CN106906756B (en) Can Fast Installation remove maintenance operation platform and its construction method
CN204876578U (en) Building construction system
CN204343642U (en) Builder's jack corner support frame
CN207244460U (en) A kind of reinforcing bar binding platform suitable for large size, thin walled hollow pier
CN203307733U (en) Construction platform system of concrete pier of viaduct
CN203475310U (en) Formwork for concrete slabs of composite steel-concrete box girders
CN111648229A (en) Assembled hoop platform for bent cap construction and mounting method thereof
CN204386135U (en) Portable Hanging Basket
CN207062787U (en) Can Fast Installation remove maintenance construction platform
CN107700363B (en) A bridge tower platform with self-contained lifting system and its construction method
CN207526141U (en) Small-section tower-shaped steel structure assembled operating platform
CN212507305U (en) High-altitude operation platform applied to large-span factory building
CN104195954B (en) Overhead column erection without scaffolding platform and erection method thereof
CN209760880U (en) Assembled steel structure stair
CN103556577B (en) Elevation adjusting device for steel truss and method for adjusting elevation of steel truss
CN206189594U (en) Shake to decrease and to replace steel beam structure
CN106320369B (en) Pipe rack column group is to the detachable movable platform of wafer type
CN111962850A (en) Construction method of overhanging scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181026

CF01 Termination of patent right due to non-payment of annual fee