CN212507305U - High-altitude operation platform applied to large-span factory building - Google Patents

High-altitude operation platform applied to large-span factory building Download PDF

Info

Publication number
CN212507305U
CN212507305U CN202020675808.0U CN202020675808U CN212507305U CN 212507305 U CN212507305 U CN 212507305U CN 202020675808 U CN202020675808 U CN 202020675808U CN 212507305 U CN212507305 U CN 212507305U
Authority
CN
China
Prior art keywords
operation platform
factory building
vertical
support surface
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020675808.0U
Other languages
Chinese (zh)
Inventor
王建
骆金科
罗正权
杨云鹏
官忠臣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Aerospace Construction Engineering Co ltd
Original Assignee
Guizhou Aerospace Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Aerospace Construction Engineering Co ltd filed Critical Guizhou Aerospace Construction Engineering Co ltd
Priority to CN202020675808.0U priority Critical patent/CN212507305U/en
Application granted granted Critical
Publication of CN212507305U publication Critical patent/CN212507305U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

应用于大跨度厂房的高空操作平台包括双梁行车及操作平台,所述操作平台包括操作平台底部支撑面、四周防护栏杆及操作面;沿行车梁长度方向横向铺设钢管形成操作平台底部支撑面,在所述操作平台底部支撑面上满铺多层板;所述四周防护栏杆包括立杆、横杆、斜向拉杆及挡脚板;在操作平台底部支撑面四周设立所述立杆,所述立杆高度方向设置水平横杆,所述立杆下部设置挡脚板,所述立杆之间设置有斜向拉杆;所述操作面采用脚手架钢管搭建于防护栏杆之间且操作面与操作平台底部支撑面之间搭设有上下人行安全通道。有益效果在于:所述移动式操作平台搭设简单,易于操作,节省施工成本;充分利用施工空间,提高了施工效率,降低了劳动强度。

Figure 202020675808

The high-altitude operation platform applied to the large-span workshop includes a double-beam driving and operation platform, and the operation platform includes the bottom support surface of the operation platform, the surrounding protective railings and the operation surface; steel pipes are laid horizontally along the length of the driving beam to form the bottom support surface of the operation platform. The supporting surface at the bottom of the operating platform is covered with multi-layer boards; the surrounding protective railings include vertical bars, cross bars, oblique pull bars and toe boards; the vertical bars are set up around the bottom supporting surface of the operating platform, and the vertical A horizontal cross bar is arranged in the height direction of the pole, a foot stop is arranged at the lower part of the vertical pole, and an oblique pull rod is arranged between the vertical poles; There are up and down pedestrian safety passages between the surfaces. The beneficial effects are as follows: the mobile operating platform is simple to set up, easy to operate, and saves construction costs; fully utilizes construction space, improves construction efficiency, and reduces labor intensity.

Figure 202020675808

Description

High-altitude operation platform applied to large-span factory building
Technical Field
The utility model belongs to engineering construction method, utensil relates to a be applied to the high altitude operation platform of large-span factory building.
Background
At present, when the steel structure factory building is constructed by the separate projects of roofing, decoration, water and electricity ventilation, fire fighting and the like, as the clearance height of most steel structure factory buildings is more than 5m, the conventional method is to erect a full hall scaffold or use a movable lifter for construction in the factory building, the erected full hall scaffold uses more materials and has long erection and disassembly time, a special scheme needs to be compiled for approval, and when the full hall scaffold is erected, a material ground transportation channel, a constructor upper and lower channel, the stacking position of the materials on a platform and the like need to be considered; when using portable lift, need solve the roughness and the ground strength problem on factory building ground in advance, need remove many times during the construction and solve the operation face problem.
The prior art has the problems of long construction period, high construction cost, inconsistent working procedures, increased safety risk factors and the like.
Disclosure of Invention
The utility model discloses to prior art's not enough, provided a be applied to high altitude operation platform construction method and operation platform of large-span factory building, this operation platform's application has solved the conventional construction of current large-span factory building and has had the technical defect that construction cycle is long and construction cost is high.
The high-altitude operation platform applied to the large-span factory building comprises a double-beam travelling crane and an operation platform, wherein the operation platform comprises an operation platform bottom supporting surface, peripheral protective railings and an operation surface;
transversely paving steel pipes along the length direction of the travelling crane beam to form an operation platform bottom supporting surface, and fully paving a multilayer board on the operation platform bottom supporting surface;
the peripheral guard rails comprise upright posts, cross rods, inclined pull rods and foot blocking plates; the vertical rods are arranged on the periphery of a supporting surface at the bottom of the operating platform, and the distance between the vertical rods is not more than 2 m; horizontal cross rods are arranged in the height direction of the vertical rods, and the interval between the horizontal cross rods is 0.6 m; a foot blocking plate is arranged at the lower part of the upright stanchion, and the height of the foot blocking plate from the bottom supporting surface of the operating platform is 10-30 cm; an oblique pull rod is arranged between the upright rods;
the operation surface is built between the protective handrails by scaffold steel pipes, and an upper pedestrian safety channel and a lower pedestrian safety channel are built between the operation surface and the bottom supporting surface of the operation platform.
Furthermore, a dense mesh type safety net is fully hung on the outer side of the guard rail;
further, the specification of the multilayer board is 1.2m multiplied by 2.4m, and the thickness is 12 mm.
Furthermore, the two ends of the steel pipe are not more than 1.5 m in overhanging.
Furthermore, the steel pipe adopts fastener and driving roof beam reciprocal anchorage.
Furthermore, the protective railing retracts to be not less than 20 centimeters at the two ends of the running beam.
Technical scheme's beneficial effect lies in: the mobile operation platform constructed by the technical scheme of the utility model is simple to erect, easy to operate, short in erection period, saved in construction cost, fully utilized in construction space, reduced in social resource waste, shortened in construction period, improved in construction efficiency and reduced in labor intensity; the safety risk factors during construction are effectively reduced, potential safety hazards are reduced, and construction is safer.
Drawings
FIG. 1 is a schematic view of the overall structure of the high-altitude operation platform applied to a large-span factory building;
in the figure, the device comprises a travelling crane support 1, a track 2, a double-beam travelling crane 3, a horizontal cross rod 4, a vertical rod 5 and an inclined pull rod 6.
Detailed Description
In order to make the technical solutions of the present invention better understood by those skilled in the art, the present invention will be further described in detail with reference to the following specific embodiments.
As shown in fig. 1, the high-altitude operation platform applied to a large-span factory building of the utility model comprises a double-beam crane 3 and an operation platform, wherein the operation platform 3 comprises an operation platform bottom supporting surface, peripheral protective railings and an operation surface;
the double-beam traveling crane 3 is arranged on the track 2 of the traveling crane support 1.
Transversely paving steel pipes along the length direction of the travelling crane beam to form an operation platform bottom supporting surface, and fully paving a multilayer board on the operation platform bottom supporting surface;
the peripheral guard rails comprise upright posts 5, cross rods 4, oblique pull rods 6 and foot blocking plates; the vertical rods 5 are arranged on the periphery of a supporting surface at the bottom of the operating platform, and the distance between the vertical rods 5 is not more than 2 m; horizontal cross rods 4 are arranged in the height direction of the upright rods 5, and the horizontal cross rods 4 are spaced by 0.6 meter; a foot baffle plate is arranged at the lower part of the upright rod 5, and the height of the foot baffle plate from the bottom supporting surface of the operating platform is 10-30 cm; an oblique pull rod 6 is arranged between the upright rods 5;
the operation surface is built between the protective handrails by scaffold steel pipes, and an upper pedestrian safety channel and a lower pedestrian safety channel are built between the operation surface and the bottom supporting surface of the operation platform.
The applicant needs to particularly state that: the high-altitude operation platform applied to the large-span factory building is built by scaffold steel pipes, and the joints of the steel pipes and the steel pipes are fixed by fasteners; the operation platform bottom supporting surface that technical scheme related to, all around prevent concrete putting up of railing and operation surface and all should accord with relevant regulation in steel pipe scaffold fastener GB 15831 supplyes 2006 and construction eminence operation safety technical specification JGJ 80-2016.
The utility model discloses the core technology point is the two roof beam driving in the make full use of large-span factory building, through buildding high altitude operation platform on the two roof beam driving to the removal through the two roof beam driving realizes the construction in different spaces. Technical scheme's application has solved traditional full hall scaffold frame or has used the various technical defect that portable lift construction exists, has realized the inside construction of high-efficient and low-cost large-span factory building.
The high-altitude operation platform is utilized to realize the following placement of the internal construction of a large-span plant:
the method comprises the following steps: a double-beam crane is arranged in the large-span plant;
step two: transversely paving steel pipes along the length direction of the double beams of the traveling crane to form a bottom supporting surface of the operating platform;
step three: fully paving a multilayer board on the bottom supporting surface of the operating platform;
step four: protective railing around building operation platform
The protective railing is built by scaffold steel pipes and fastened with each other by fasteners;
vertical rods are arranged around the bottom supporting surface of the operating platform, the distance between the vertical rods is not more than 2 meters, horizontal railings are arranged in the height direction of the vertical rods, the distance between the horizontal railings is 0.6 meter, foot blocking plates are arranged on the lower portions of the vertical rods, and the height of the foot blocking plates from the bottom supporting surface of the operating platform is 10-30 centimeters; an oblique pull rod is arranged between the upright rods;
the highest point of the protective barrier is 0.3 m lower than the roof girder;
a dense mesh type safety net is fully hung on the outer side of the protective railing;
step five: erecting an operation surface between the protective railings by using scaffold steel pipes, and erecting an upper and lower pedestrian safety channel between the operation surface and an operation platform bottom supporting surface;
step six: construction raw materials are manually or hoisted to an operation surface of an operation platform, professional constructors enter the site for construction, and construction of different positions is realized through traveling crane movement;
step seven: after the construction is finished, the high-altitude operation platform is gradually disassembled in a mode of firstly assembling from top to bottom and then disassembling.
In order to ensure the stability and the safety of the high-altitude operation platform, the two ends of the steel pipe are not more than 1.5 m in overhanging; the steel pipe is fixed with the crane beam by a fastener; the protective railing retracts to be not less than 20 centimeters at two ends of the running beam.
Through using in the large-span factory building technical scheme realizes roofing, decoration, water and electricity ventilation, fire control partition engineering construction back, finds through statistical analysis, utilizes the driving roof beam to set up operation platform and construct, has effectively reduced construction period and construction cost, has reduced the safe risk in the work progress, and the powerful smooth of having guaranteed the engineering goes on.
The cost required by construction is measured and calculated by the same construction project and different technical means, and the comparison is as follows:
Figure DEST_PATH_GDA0002767680330000041
as can be seen from the above table, the cost generated by adopting the technical scheme of the utility model is saved by 12000 yuan under the same condition compared with the cheaper mobile lifter; the total construction period is reduced by at least 12 days.
Portable operation platform sets up simply, easily operation, sets up the cycle weak point, saves construction cost, and make full use of construction space reduces the waste of social resource, has shortened the time limit for a project, improves the efficiency of construction, has reduced intensity of labour. And safety risk factors during construction are reduced, potential safety hazards are reduced, and construction is safer.
The above is a detailed description of the construction method and the operation platform of the high altitude operation platform applied to the large-span factory building provided by the utility model, and the embodiment is applied to explain the principle and the implementation mode of the application, and the description of the above embodiment is only used for helping to understand the method and the core idea of the application; meanwhile, for a person skilled in the art, according to the idea of the present application, there may be variations in the specific embodiments and the application scope, and in summary, the content of the present specification should not be construed as a limitation to the present application.

Claims (6)

1.应用于大跨度厂房的高空操作平台,其特征在于:所述高空操作平台包括双梁行车及操作平台,所述操作平台包括操作平台底部支撑面、四周防护栏杆及操作面;1. be applied to the aerial operation platform of large-span factory building, it is characterized in that: described aerial operation platform comprises double-beam driving and operation platform, and described operation platform comprises operation platform bottom support surface, surrounding guard railing and operation surface; 沿行车梁长度方向横向铺设钢管形成操作平台底部支撑面,在所述操作平台底部支撑面上满铺多层板;Lay steel pipes transversely along the length direction of the running beam to form the bottom support surface of the operation platform, and fully lay multi-layer boards on the bottom support surface of the operation platform; 所述四周防护栏杆包括立杆、横杆、斜向拉杆及挡脚板;在操作平台底部支撑面四周设立所述立杆,所述立杆间距不大于2米;所述立杆高度方向设置水平横杆,所述水平横杆间隔0.6米;所述立杆下部设置挡脚板,所述挡脚板离操作平台底部支撑面的高度为10至30厘米;所述立杆之间设置有斜向拉杆;The surrounding protective railings include vertical rods, cross rods, oblique pull rods and foot guards; the vertical rods are set up around the support surface at the bottom of the operating platform, and the distance between the vertical rods is not more than 2 meters; the vertical poles are set horizontally in the height direction The horizontal bar is 0.6 meters apart; the lower part of the vertical bar is provided with a foot plate, and the height of the foot plate from the bottom support surface of the operation platform is 10 to 30 cm; an oblique pull rod is arranged between the vertical bars ; 所述操作面采用脚手架钢管搭建于防护栏杆之间且操作面与操作平台底部支撑面之间搭设有上下人行安全通道。The operating surface is built between the protective railings by using scaffolding steel pipes, and an upper and lower pedestrian safety passage is set up between the operating surface and the bottom support surface of the operating platform. 2.如权利要求1所述的应用于大跨度厂房的高空操作平台,其特征在于:所述防护栏杆外侧满挂密目式安全网。2 . The high-altitude operation platform applied to a large-span factory building as claimed in claim 1 , wherein the outer side of the protective railing is fully hung with a dense mesh type safety net. 3 . 3.如权利要求1所述的应用于大跨度厂房的高空操作平台,其特征在于:所述多层板规格为1.2m×2.4m,厚度为12mm。3. The high-altitude operation platform applied to a large-span factory building according to claim 1, wherein the specification of the multi-layer board is 1.2m×2.4m, and the thickness is 12mm. 4.如权利要求1所述的应用于大跨度厂房的高空操作平台,其特征在于:所述钢管两端悬挑不大于1.5米。4. The aerial operation platform applied to a large-span factory building according to claim 1, wherein the two ends of the steel pipe cantilevered no more than 1.5 meters. 5.如权利要求1所述的应用于大跨度厂房的高空操作平台,其特征在于:所述钢管采用扣件与行车梁相互固定。5. The aerial operation platform applied to a large-span factory building according to claim 1, wherein the steel pipe is fixed to each other with a fastener and a traveling beam. 6.如权利要求1所述的应用于大跨度厂房的高空操作平台,其特征在于:所述防护栏杆在行车梁两端缩进不少于20厘米。6. The aerial operation platform applied to a large-span factory building according to claim 1, wherein the guardrail is indented by no less than 20 cm at both ends of the traveling beam.
CN202020675808.0U 2020-04-28 2020-04-28 High-altitude operation platform applied to large-span factory building Expired - Fee Related CN212507305U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020675808.0U CN212507305U (en) 2020-04-28 2020-04-28 High-altitude operation platform applied to large-span factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020675808.0U CN212507305U (en) 2020-04-28 2020-04-28 High-altitude operation platform applied to large-span factory building

Publications (1)

Publication Number Publication Date
CN212507305U true CN212507305U (en) 2021-02-09

Family

ID=74434791

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020675808.0U Expired - Fee Related CN212507305U (en) 2020-04-28 2020-04-28 High-altitude operation platform applied to large-span factory building

Country Status (1)

Country Link
CN (1) CN212507305U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636667A (en) * 2020-04-28 2020-09-08 贵州航天建设工程有限公司 Construction method and operating platform of high-altitude operating platform applied to large-span workshop

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636667A (en) * 2020-04-28 2020-09-08 贵州航天建设工程有限公司 Construction method and operating platform of high-altitude operating platform applied to large-span workshop

Similar Documents

Publication Publication Date Title
CN103635643B (en) Construction Method of Reinforced Concrete Cylinder in High-rise Steel Structure Building
CN106760529B (en) Roof steel truss sliding assembly construction platform and installation method
CN102322135A (en) Elevator shaft construction scaffolding device capable of being elevated along with construction layer of building main body structure and method for setting same
CN202324571U (en) Overhanging type double-row scaffold
CN104763109B (en) Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN115126233B (en) Construction method for using cantilever beam plate high formwork with complex outer vertical surface as outer wall scaffold
CN207749908U (en) A kind of enclosure wall of full assembly lightweight steel construction
CN104234447B (en) Deep foundation ditch tool-type hangs stair
CN202108242U (en) Elevator shaft construction scaffold device constructed and lifted together with a building main structure by layers
CN111636667A (en) Construction method and operating platform of high-altitude operating platform applied to large-span workshop
CN201635377U (en) Rigid hanging scaffolding for installation of long-span steel roof equipment piping
CN213268816U (en) Assembled shaped steel horizontal protection platform of encorbelmenting
CN206319610U (en) Roof system steel truss slipping and assembling construction platform structure
CN204876578U (en) Building construction system
CN205314242U (en) Job site ground many function combination formula protection canopy
CN105019657A (en) Building construction system
CN117090408A (en) Attached lifting protective shed and its installation and lifting methods
CN211621238U (en) Safety protection cage for steel bar operation in bridge pier column turning formwork construction
CN204876577U (en) Building construction system
CN209538639U (en) Make track movable Scaffold by oneself
CN209293510U (en) A water turbine maintenance platform
CN219449157U (en) ALC board installation construction system
CN220412695U (en) Device for transporting and installing ultra-long ALC (aluminum-control alloy) lath
CN204876575U (en) Building construction system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210209

CF01 Termination of patent right due to non-payment of annual fee