CN209854576U - A trolley for the construction of slab culverts or passages - Google Patents

A trolley for the construction of slab culverts or passages Download PDF

Info

Publication number
CN209854576U
CN209854576U CN201920174277.4U CN201920174277U CN209854576U CN 209854576 U CN209854576 U CN 209854576U CN 201920174277 U CN201920174277 U CN 201920174277U CN 209854576 U CN209854576 U CN 209854576U
Authority
CN
China
Prior art keywords
pipe
longitudinal beam
steel
construction
trolley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920174277.4U
Other languages
Chinese (zh)
Inventor
林峰
贤良华
杨环荣
覃武
卢奕均
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Changxing Engineering Construction Co Ltd
Original Assignee
Guangxi Changxing Engineering Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Changxing Engineering Construction Co Ltd filed Critical Guangxi Changxing Engineering Construction Co Ltd
Priority to CN201920174277.4U priority Critical patent/CN209854576U/en
Application granted granted Critical
Publication of CN209854576U publication Critical patent/CN209854576U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a trolley for construction of an apron culvert or a channel, which belongs to the technical field of construction of the apron culvert or the channel, and comprises a left portal and a right portal with consistent structures, wherein the left portal and the right portal respectively comprise a plurality of steel pipe upright posts, a pipe top longitudinal beam, a pipe bottom longitudinal beam, a first inclined strut and an upright post steel cushion block; a second inclined support is arranged between the left portal frame and the right portal frame and is arranged on the steel pipe upright posts positioned on the outer sides of the left portal frame and the right portal frame; the pipe top longitudinal beam is characterized in that a combined steel template is arranged at the upper end of the pipe top longitudinal beam, transverse distribution beams transversely arranged are arranged between the combined steel template and the pipe top longitudinal beam and are longitudinally and uniformly distributed along the pipe top longitudinal beam, and distribution beam limiters are arranged on two sides of the transverse distribution beams, which are in contact with the pipe top longitudinal beam.

Description

一种用于盖板涵洞或通道施工的台车A trolley for the construction of slab culverts or passages

技术领域technical field

本实用新型涉及盖板涵洞或通道施工技术领域,特别是一种用于盖板涵洞或通道施工的台车。The utility model relates to the technical field of cover culvert or channel construction, in particular to a trolley used for cover culvert or channel construction.

背景技术Background technique

公路工程常规型涵洞或通道盖板施工中,为了支撑模板,一般采用满堂支架法进行盖板施工,在混凝土浇筑完毕拆模时,需要将支架全部拆除方可转入下一个施工区段,因此施工时模板及支架的一次性投入大,运转利用率低、人员工效低、可操作性繁琐。In the construction of conventional culvert or channel cover slabs in highway engineering, in order to support the formwork, the full-hole bracket method is generally used for cover slab construction. When the concrete is poured and the formwork is removed, all the brackets need to be removed before transferring to the next construction section. Therefore The one-time investment of formwork and support during construction is large, the operation utilization rate is low, the labor efficiency is low, and the operability is cumbersome.

专利号为201420255956的中国实用新型专利公开了一种用于支撑涵洞建筑模板的可移动支架,包括支架本体。其中,支架本体的底部设有可调节底托和承重滚动装置,承重滚动装置安装于所述底托上;支架本体的顶部设有高度可调节的顶托;顶托上部设有可拆卸支撑体。The Chinese Utility Model Patent No. 201420255956 discloses a movable support for supporting culvert building formwork, including a support body. Among them, the bottom of the bracket body is provided with an adjustable bottom support and a load-bearing rolling device, and the load-bearing rolling device is installed on the bottom support; the top of the support body is provided with a height-adjustable jack; the top of the jack is provided with a detachable support body .

上述实用新型专利通过在支架本体底部安装承重滚动装置解决了浇筑盖板顶板时支架重复拆装的问题,但是其结构复杂且施工过程中在其顶部需另外增加模板,上下搬运模板难度较大,需多人参与,结合实际情况,研发一种能够移动且可调整高度的台车,并在台车顶部预设模板,在施工应用中,可大幅降低施工的投入、节省工期及提高人员的工效。The above-mentioned utility model patent solves the problem of repeated disassembly and assembly of the support when pouring the top plate of the cover plate by installing a load-bearing rolling device at the bottom of the support body, but its structure is complex and additional formwork is required on the top during the construction process, and it is difficult to carry the formwork up and down. Multi-person participation is required, combined with the actual situation, a mobile and height-adjustable trolley is developed, and a template is preset on the top of the trolley. In construction applications, it can greatly reduce construction investment, save construction time and improve personnel efficiency. .

实用新型内容Utility model content

本实用新型的发明目的是,针对上述问题,提供了一种用于盖板涵洞或通道施工的台车,在施工应用中,可大幅降低施工的投入、节省工期及提高人员的工效。The purpose of the invention of the utility model is to provide a trolley for the construction of cover culverts or passages in view of the above problems, which can greatly reduce the construction investment, save the construction period and improve the work efficiency of personnel in the construction application.

为达到上述目的,本实用新型所采用的技术方案是:一种用于盖板涵洞或通道施工的台车,包括结构一致的左门架和右门架,所述左门架和所述右门架均包括若干根钢管立柱、管顶纵梁、管底纵梁、第一斜撑和立柱钢垫块;同一侧任意两根所述钢管立柱下端之间均纵向设置有所述管底纵梁;所述钢管立柱顶端开设有与所述管顶纵梁宽度相适应的凹口,所述管顶纵梁纵向架设在所述凹口中;同一侧所述任意两根钢管立柱中部之间均设置有所述第一斜撑;所述立柱钢垫块设置在所述钢管立柱底部;所述左门架和所述右门架之间设置有第二斜撑,所述第二斜撑设置于位于所述左门架和所述右门架外侧的钢管立柱上;所述管顶纵梁上端设置有组合钢模板,所述组合钢模板与所述管顶纵梁之间设置有横向设置的横分配梁,所述横分配梁沿所述管顶纵梁纵向均匀分布,所述横分配梁与所述管顶纵梁接触的两侧设置有分配梁限位器。In order to achieve the above purpose, the technical solution adopted by the utility model is: a trolley used for the construction of cover culverts or passages, including a left door frame and a right door frame with the same structure, the left door frame and the right door frame The gantry includes several steel pipe columns, pipe top longitudinal beams, pipe bottom longitudinal beams, first diagonal braces and column steel spacers; any two steel pipe column lower ends on the same side are longitudinally provided with the pipe bottom longitudinal beams. beam; the top of the steel pipe column is provided with a notch suitable for the width of the pipe top longitudinal beam, and the pipe top longitudinal beam is erected longitudinally in the notch; the middle parts of any two steel pipe columns on the same side are The first diagonal brace is provided; the column steel pad is arranged at the bottom of the steel pipe column; a second diagonal brace is provided between the left door frame and the right door frame, and the second diagonal brace is set On the steel pipe columns located outside the left door frame and the right door frame; the upper end of the pipe top longitudinal beam is provided with a combined steel formwork, and a horizontal arrangement is arranged between the combined steel formwork and the pipe top longitudinal beam The horizontal distribution beam is uniformly distributed longitudinally along the pipe top longitudinal beam, and the two sides of the horizontal distribution beam in contact with the pipe top longitudinal beam are provided with distribution beam stoppers.

进一步说明,所述钢管立柱的直径320mm,厚度为10mm,所述立柱钢垫块的规格为400*400*10mm。To further illustrate, the steel pipe column has a diameter of 320mm and a thickness of 10mm, and the specification of the column steel pad is 400*400*10mm.

进一步说明,所述管顶纵梁与所述管底纵梁均为I25工字钢。To further illustrate, both the pipe top longitudinal beam and the pipe bottom longitudinal beam are I25 I-beams.

进一步说明,所述第一斜撑和所述第二斜撑均为[10槽钢。To further illustrate, both the first diagonal brace and the second diagonal brace are [10 channel steel.

进一步说明,所述横分配梁采用I10工字钢,间距为25cm。To further illustrate, the horizontal distribution beam is made of I10 I-beam with a spacing of 25cm.

进一步说明,所述分配梁限位器的结构为[10槽钢,所述分配梁限位器焊接在所述横分配梁下端面,对所述横分配梁进行横向限位。To further illustrate, the structure of the distribution beam limiter is [10 channel steel, and the distribution beam limiter is welded on the lower end surface of the horizontal distribution beam to limit the horizontal distribution beam.

由于采用上述技术方案,本实用新型具有以下有益效果:本实用新型的技术方案制作的用于盖板涵洞或通道施工的台车,结构简单、拆装方便、操作灵活、安全可靠,可多个工地周转使用,可很好的适用于常规型涵洞或通道的盖板施工中;在任何常规型涵洞或通道盖板施工中,都可以自由移动、升降、停留,提高施工效率,降低施工成本。Due to the adoption of the above technical solution, the utility model has the following beneficial effects: the trolley used for the construction of cover culverts or channels made by the technical solution of the utility model has simple structure, convenient disassembly and assembly, flexible operation, safety and reliability, and can be used for multiple It is suitable for the construction of conventional culverts or channel cover plates; in the construction of any conventional culvert or channel cover plates, it can move, lift, and stay freely, improving construction efficiency and reducing construction costs.

将钢管立柱设计为直径320mm,厚度为10mm;将立柱钢垫块的规格设计为400*400*10mm;管顶纵梁与管底纵梁均采用I25工字钢;第一斜撑和所述第二斜撑均采用[10槽钢;横分配梁采用I10工字钢,间距为25cm;分配梁限位器的采用[10槽钢;以上设计是经过多次不同规格尺寸在实践中得出的最优组合,即在满足结构安全的同时又最大化节省钢材,将于盖板涵洞或通道施工的台车的制作成本控制到最低。The steel pipe column is designed to have a diameter of 320mm and a thickness of 10mm; the specification of the column steel pad is designed to be 400*400*10mm; both the pipe top longitudinal beam and the pipe bottom longitudinal beam are made of I25 I-beam; the first diagonal brace and the The second diagonal bracing adopts [10 channel steel; the horizontal distribution beam adopts I10 I-beam with a spacing of 25cm; the distribution beam limiter adopts [10 channel steel; the above design is obtained in practice after many different specifications and sizes. The optimal combination, that is, to maximize the saving of steel while satisfying the structural safety, will control the production cost of the trolley for the construction of the cover culvert or channel to the minimum.

附图说明Description of drawings

图1是本实用新型实施例用于盖板涵洞或通道施工的台车的立体图;Fig. 1 is the perspective view of the trolley used in the construction of cover culverts or passages in the embodiment of the present invention;

图2是本实用新型图1的门架图;Fig. 2 is the gantry diagram of Fig. 1 of the utility model;

图3是本实用新型图1的A处放大图。Fig. 3 is an enlarged view of A in Fig. 1 of the present utility model.

附图中,1-钢管立柱、2-管顶纵梁、3-管底纵梁、4-第一斜撑、5-立柱钢垫块、6-凹口、7-第二斜撑、8-组合钢模板、9-横分配梁、10-分配梁限位器。In the accompanying drawings, 1-steel pipe column, 2-pipe top longitudinal beam, 3-pipe bottom longitudinal beam, 4-first diagonal brace, 5-column steel pad, 6-notch, 7-second diagonal brace, 8 -Combined steel formwork, 9-horizontal distribution beam, 10-distribution beam limiter.

具体实施方式Detailed ways

以下结合附图对实用新型的具体实施进一步说明。The specific implementation of the utility model is further described below in conjunction with the accompanying drawings.

如图1-3所示,一种用于盖板涵洞或通道施工的台车,包括结构一致的左门架和右门架,左门架和右门架均包括三根钢管立柱1、管顶纵梁2、管底纵梁3、第一斜撑4和立柱钢垫块5;钢管立柱1的直径320mm,厚度为10mm,立柱钢垫块的规格为400*400*10mm,管顶纵梁2与管底纵梁3均为I25工字钢,同一侧任意两根钢管立柱1下端之间均设置有管底纵梁2;钢管立柱1顶端开设有与管顶纵梁2宽度相适应的凹口6,管顶纵梁2纵向架设在凹口6中;同一侧任意两根钢管立柱1中部之间均设置有第一斜撑4;立柱钢垫块5设置在钢管立柱1底部;左门架和右门架之间设置有第二斜撑7,第二斜撑7设置于位于左门架和右门架外侧的钢管立柱1上,第一斜撑4和第二斜撑7均为[10槽钢;管顶纵梁2上端设置有组合钢模板8,组合钢模板8与管顶纵梁2之间设置有横分配梁9,横分配梁9沿管顶纵梁2纵向均匀分布,横分配梁采用I10工字钢,间距为25cm,横分配梁9与管顶纵梁2接触的两侧设置有分配梁限位器10,分配梁限位器10的结构为[10槽钢,分配梁限位器10焊接在横分配梁9下端面,对横分配梁9进行横向限位。As shown in Figure 1-3, a trolley used for the construction of cover culverts or passages includes a left door frame and a right door frame with the same structure. Both the left door frame and the right door frame include three steel pipe columns 1. Pipe top Longitudinal beam 2, pipe bottom longitudinal beam 3, first diagonal brace 4 and column steel pad 5; steel pipe column 1 has a diameter of 320mm and a thickness of 10mm, and the specification of the column steel pad is 400*400*10mm. 2 and the pipe bottom longitudinal beam 3 are both I25 I-shaped steel, and there is a pipe bottom longitudinal beam 2 between the lower ends of any two steel pipe columns 1 on the same side; The notch 6, the vertical beam 2 on the top of the pipe is erected in the notch 6; the first diagonal brace 4 is arranged between the middle parts of any two steel pipe columns 1 on the same side; the column steel spacer 5 is arranged at the bottom of the steel pipe column 1; A second diagonal brace 7 is arranged between the mast and the right mast, and the second diagonal brace 7 is arranged on the steel pipe column 1 located outside the left mast and the right mast. The first diagonal brace 4 and the second diagonal brace 7 are both It is [10 channel steel; the upper end of the pipe top longitudinal beam 2 is provided with a combined steel formwork 8, and a horizontal distribution beam 9 is arranged between the combined steel formwork 8 and the pipe top longitudinal beam 2, and the horizontal distribution beam 9 is uniformly distributed along the vertical direction of the pipe top longitudinal beam 2. Distribution, the horizontal distribution beam adopts I10 I-beam, the spacing is 25cm, the two sides of the horizontal distribution beam 9 and the longitudinal beam 2 on the pipe top are provided with a distribution beam limiter 10, and the structure of the distribution beam limiter 10 is [10 grooves Steel, the distribution beam limiter 10 is welded on the lower end surface of the horizontal distribution beam 9, and the horizontal distribution beam 9 is laterally limited.

上述用于盖板涵洞或通道施工的台车实践应用于融水至河池高速公路三分部,起点位于罗城县四把镇大梧村,终点位于罗城县天河镇甫村附近,起止里程:K55+000~K69+700,全长14.7Km,主要由路基、桥梁、涵洞通道组成,其中桥梁共17座,涵洞共2073.76m/69道,通道共980.32m/27道。The above trolleys used for the construction of cover culverts or passages are actually applied to the third branch of Rongshui-Hechi Expressway. The starting point is located in Dawu Village, Siba Town, Luocheng County, and the end point is located near Fu Village, Tianhe Town, Luocheng County. : K55+000~K69+700, with a total length of 14.7Km, mainly composed of subgrades, bridges, and culvert passages, including 17 bridges, 2073.76m/69 culverts, and 980.32m/27 passages.

台车作为首件工程桩号K56+711为钢筋砼暗板涵通道中投入使用,涵长为32.0m,交角90°,净宽6m,净高4.5m,基础厚度1.2m,基础宽度2.25m,台身厚度1.15m,填土高度2.26m。The trolley as the first project stake number K56+711 is put into use in the reinforced concrete concealed culvert passage, the culvert length is 32.0m, the intersection angle is 90°, the net width is 6m, the net height is 4.5m, the foundation thickness is 1.2m, and the foundation width is 2.25m , the thickness of the table body is 1.15m, and the filling height is 2.26m.

为简化计算涵长均按照路基宽度26m进行计算,以下分别是采用台车施工和满堂支架施工的经济对比。In order to simplify the calculation, the culvert length is calculated according to the width of the subgrade of 26m. The following are the economic comparisons between the construction of the trolley and the construction of the full hall support.

采用台车施工的情况经济如下:The economical situation of using trolley construction is as follows:

(1)材料费(1) Material fee

按1个台车进行考虑。因台车由模板厂定制,材料主要为钢材,一个台车(6m)重量为8.6吨,4000元/吨×8.6吨=34400元。Consider it as 1 trolley. Because the trolley is customized by the template factory, the material is mainly steel, and the weight of a trolley (6m) is 8.6 tons, 4000 yuan/ton × 8.6 tons = 34400 yuan.

(2)人工费(2) Labor costs

采用台车施工时每道涵洞分6次安装,每次安装、调整及拆除投入人工0.4工日/人/次×6次×3人=9人工,9工日×150元/工日=1350元。When using trolley construction, each culvert is installed in 6 times, each installation, adjustment and dismantling requires 0.4 man-days/person/time×6 times×3 people=9 manpower, 9 man-days×150 yuan/man-day=1350 Yuan.

(3)机械费(3) Machinery fee

材料倒运及转场台车0.5工日,0.5工日×1200元/工日=600元.0.5 man-days for materials reversing and transfer trolleys, 0.5 man-days x 1200 yuan/man-day = 600 yuan.

采用满堂支架施工的情况经济如下:The economic situation of adopting the full hall bracket construction is as follows:

(1)材料费(1) Material fee

1)、碗扣支架1), Bowl buckle bracket

满堂支架施工时,按支架搭设施工1道进行考虑,支架立杆按照0.9m×1.2m进行布置,立杆直接立于方木上(方木不计),立杆上设置顶托进行调平,距基础30cm设置扫地杆,横杆层间距1m,剪刀撑按5m一道布置。During the construction of the whole hall support, it shall be considered according to the first step of the support erection construction. The support poles shall be arranged according to 0.9m×1.2m. Set up the sweeping pole 30cm away from the foundation, the distance between the horizontal poles is 1m, and the scissors are arranged in a row of 5m.

①钢管① steel pipe

立杆:3m×4排×24根/排=288mPole: 3m×4 rows×24/row=288m

横杆:26m×4层×4根/层+3.6m×4层×24根/层=1830mCross bar: 26m×4 layers×4 bars/layer+3.6m×4 layers×24 bars/layer=1830m

剪刀撑:6m/根×40根=240mScissors support: 6m/root x 40=240m

钢管租赁费0.018元/m/天,租赁费为:0.018元/m/天×(288+1830+240)m=42.444元/天。The steel pipe rental fee is 0.018 yuan/m/day, and the rental fee is: 0.018 yuan/m/day×(288+1830+240)m=42.444 yuan/day.

②顶托② jacking

顶托数量:4×24=96个。租赁费为:96×0.012元/个/天=1.152元/天。Jacking quantity: 4×24=96 pieces. The rental fee is: 96×0.012 yuan/piece/day=1.152 yuan/day.

③扣件③ Fasteners

扣件数量为:4×24×4+10×20=584个。租赁费为:96×0.008元/个/天=4.672元/天。The number of fasteners is: 4×24×4+10×20=584 pieces. The rental fee is: 96×0.008 yuan/piece/day=4.672 yuan/day.

以上合计租赁费为:48.3元/天。The above total rental fee is: 48.3 yuan / day.

2)、模板2), template

模板采用钢模板,面积为28×3.88=108.64m2,每平米重量88Kg,模板费用为108.64m2×88Kg/m2×4元/Kg=38241元。The formwork adopts steel formwork, the area is 28×3.88=108.64m2, the weight per square meter is 88Kg, and the formwork cost is 108.64m2×88Kg/m2×4 yuan/Kg=38241 yuan.

(2)人工费(2) Labor costs

满堂支架施工时,每道涵洞一次安装完成支架搭设、安装及调整底模、拆除底模需要投入人工4工日/人/次×1次×6人=24人工,24工日×150元/工日=3600元。During the construction of the support for the whole hall, 4 man-days/person/time × 1 time × 6 people = 24 manpower, 24 man-days × 150 yuan/ Working days = 3600 yuan.

(3)机械费(3) Machinery fee

满堂支架施工时模板安装需要吊车1工日,1工日×1200元/工日=1200元。During the construction of the full hall bracket, the formwork installation requires a crane for 1 working day, 1 working day × 1200 yuan / working day = 1200 yuan.

通过以上两种施工方式可以得出经济对比分析Through the above two construction methods, an economic comparative analysis can be drawn

通过以上两种施工方式可以得出经济对比分析Through the above two construction methods, an economic comparative analysis can be drawn

每道涵洞或通道台车施工时台车与满堂支架施工时长15天,施工时长基本一致,施工时安装6套台车及6套满堂支架同时施工33道涵洞计算。During the construction of each culvert or channel trolley, the construction time of the trolley and the full hall support is 15 days, and the construction time is basically the same. During the construction, 6 sets of trolleys and 6 sets of full hall supports are installed to construct 33 culverts at the same time.

1、材料费对比节省1. Compared with material cost saving

施工时安装6套台车及6套满堂支架,节省资金:(38241+48.3×15)×6-34400×6=27393元。Install 6 sets of trolleys and 6 sets of full hall supports during construction, saving money: (38241+48.3×15)×6-34400×6=27393 yuan.

2、人工费对比节省2. Compared with saving labor costs

每道涵洞或通道节省资金1950元,共计节省资金64350元。Each culvert or channel saves 1,950 yuan, totaling 64,350 yuan.

3、机械费对比节省3. Savings in comparison of mechanical costs

每道涵洞或通道节省资金2400元,共计节省资金79200元。Each culvert or channel saves 2,400 yuan, and a total of 79,200 yuan is saved.

综上所述,采用台车施工涵洞或盖板共可节省资金170943元,效益比较可观,实际施工因角度及明暗涵区别,涵长将加大,效益也将提高。To sum up, using trolleys to construct culverts or cover slabs can save a total of 170,943 yuan, and the benefits are considerable. Due to the difference in angle and light and dark culverts in actual construction, the culvert length will increase and the benefits will also increase.

上述说明是针对本实用新型较佳可行实施例的详细说明,但实施例并非用以限定本实用新型的专利申请范围,凡本实用新型所提示的技术精神下所完成的同等变化或修饰变更,均应属于本实用新型所涵盖专利范围。The above description is a detailed description of the preferred feasible embodiments of the present utility model, but the embodiments are not used to limit the scope of the patent application of the present utility model. All equivalent changes or modifications completed under the technical spirit suggested by the utility model, All should belong to the patent scope covered by the utility model.

Claims (6)

1.一种用于盖板涵洞或通道施工的台车,其特征在于:包括结构一致的左门架和右门架,所述左门架和所述右门架均包括若干根钢管立柱、管顶纵梁、管底纵梁、第一斜撑和立柱钢垫块;同一侧任意两根所述钢管立柱下端之间均纵向设置有所述管底纵梁;所述钢管立柱顶端开设有与所述管顶纵梁宽度相适应的凹口,所述管顶纵梁纵向架设在所述凹口中;同一侧所述任意两根钢管立柱中部之间均设置有所述第一斜撑;所述立柱钢垫块设置在所述钢管立柱底部;所述左门架和所述右门架之间设置有第二斜撑,所述第二斜撑设置于位于所述左门架和所述右门架外侧的钢管立柱上;所述管顶纵梁上端设置有组合钢模板,所述组合钢模板与所述管顶纵梁之间设置有横向设置的横分配梁,所述横分配梁沿所述管顶纵梁纵向均匀分布,所述横分配梁与所述管顶纵梁接触的两侧设置有分配梁限位器。1. A trolley for cover culvert or channel construction, characterized in that: it comprises a left door frame and a right door frame with the same structure, and the left door frame and the right door frame all include several steel pipe columns, The pipe top longitudinal beam, the pipe bottom longitudinal beam, the first diagonal brace and the column steel pad; the pipe bottom longitudinal beam is longitudinally arranged between the lower ends of any two steel pipe columns on the same side; the top of the steel pipe column is provided with A notch adapted to the width of the pipe top longitudinal beam, the pipe top longitudinal beam is vertically erected in the notch; the first diagonal brace is arranged between the middle parts of any two steel pipe columns on the same side; The column steel pad is arranged at the bottom of the steel pipe column; a second diagonal brace is arranged between the left door frame and the right door frame, and the second diagonal brace is arranged between the left door frame and the right door frame. On the steel pipe column on the outside of the right gantry; the upper end of the pipe roof longitudinal beam is provided with a combined steel formwork, and a horizontal distribution beam is arranged between the combined steel formwork and the pipe top longitudinal beam. Beams are evenly distributed longitudinally along the pipe top longitudinal beam, and distribution beam stoppers are provided on both sides of the horizontal distribution beam in contact with the pipe top longitudinal beam. 2.根据权利要求1所述的一种用于盖板涵洞或通道施工的台车,其特征在于:所述钢管立柱的直径320mm,厚度为10mm,所述立柱钢垫块的规格为400*400*10mm。2. A trolley for the construction of cover culverts or passages according to claim 1, characterized in that: the diameter of the steel pipe column is 320 mm, the thickness is 10 mm, and the specification of the steel pad for the column is 400* 400*10mm. 3.根据权利要求1所述的一种用于盖板涵洞或通道施工的台车,其特征在于:所述管顶纵梁与所述管底纵梁均为I25工字钢。3. A trolley for construction of cover culverts or passages according to claim 1, characterized in that: the longitudinal beam at the top of the pipe and the longitudinal beam at the bottom of the pipe are both I25 I-shaped steel. 4.根据权利要求1所述的一种用于盖板涵洞或通道施工的台车,其特征在于:所述第一斜撑和所述第二斜撑均为[10槽钢。4. A trolley for construction of cover culverts or passages according to claim 1, characterized in that: the first diagonal brace and the second diagonal brace are both [10 channel steel. 5.根据权利要求1所述的一种用于盖板涵洞或通道施工的台车,其特征在于:所述横分配梁采用I10工字钢,间距为25cm。5. A trolley for construction of cover culverts or passages according to claim 1, characterized in that: the horizontal distribution beam is made of I10 I-beam with a distance of 25cm. 6.根据权利要求1所述的一种用于盖板涵洞或通道施工的台车,其特征在于:所述分配梁限位器的结构为[10槽钢,所述分配梁限位器焊接在所述横分配梁下端面,对所述横分配梁进行横向限位。6. A kind of trolley for cover culvert or channel construction according to claim 1, characterized in that: the structure of the distribution beam limiter is [10 channel steel, and the distribution beam limiter is welded On the lower end surface of the horizontal distribution beam, the horizontal distribution beam is limited laterally.
CN201920174277.4U 2019-01-31 2019-01-31 A trolley for the construction of slab culverts or passages Expired - Fee Related CN209854576U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920174277.4U CN209854576U (en) 2019-01-31 2019-01-31 A trolley for the construction of slab culverts or passages

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920174277.4U CN209854576U (en) 2019-01-31 2019-01-31 A trolley for the construction of slab culverts or passages

Publications (1)

Publication Number Publication Date
CN209854576U true CN209854576U (en) 2019-12-27

Family

ID=68931372

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920174277.4U Expired - Fee Related CN209854576U (en) 2019-01-31 2019-01-31 A trolley for the construction of slab culverts or passages

Country Status (1)

Country Link
CN (1) CN209854576U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629465A (en) * 2019-01-31 2019-04-16 广西长兴工程建设有限公司 It is a kind of for cover board culvert or the trolley of passage construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629465A (en) * 2019-01-31 2019-04-16 广西长兴工程建设有限公司 It is a kind of for cover board culvert or the trolley of passage construction

Similar Documents

Publication Publication Date Title
CN108265885B (en) Construction method of high-large non-orthogonal large-inclination-angle special-shaped concrete inclined column
CN203021923U (en) Big cantilever bent cap steel truss construction platform
CN110820561A (en) Large cantilever prestress bent cap support device and construction method
CN112411391A (en) Single-column capping beam steel pipe column Bailey beam construction supporting system and construction method thereof
CN109267487A (en) A kind of long big section bent cap bracket system of overhanging
CN110886227B (en) Main tower cast-in-place lower cross beam support system and construction method
CN206942245U (en) Prefabricated case beam tie with reinforcing bar construction frame
CN102605717A (en) Pier-top longitudinal support scaffolding method
CN107435335A (en) Brick retaining wall steel bar girder hardened system and method on foundation pit enclosure top beam
CN110409624B (en) Reverse calculation and construction method for large equipment installation and main body structure
CN109778700B (en) Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road
CN209854576U (en) A trolley for the construction of slab culverts or passages
CN107386119A (en) A kind of variable cross-section beam sections type variable framework of steel reinforcement construction moulding bed device
CN213510645U (en) PBA secretly digs platform truck support template system that station side span was just propped up and is encircleed
CN207227958U (en) Variable cross-section beam sections type variable framework of steel reinforcement construction moulding bed device
CN210685373U (en) Trolley system suitable for concrete structure factory building construction
CN109629465A (en) It is a kind of for cover board culvert or the trolley of passage construction
CN117488647A (en) Combined beam suitable for upper and lower two-layer steel truss web rods of overhead in urban area and construction method
CN209538639U (en) Make track movable Scaffold by oneself
CN207244633U (en) Brick retaining wall steel bar girder hardened system on foundation pit enclosure top beam
CN207260605U (en) A kind of super plane structure construction material transport system
CN205617664U (en) Prefabricated pier stud locating rack for steel reinforcement cage
CN210256628U (en) Self-adaptive outer mold system for prefabricating concrete
CN110065145B (en) Self-adaptive external mold system for concrete prefabrication
CN206319260U (en) A kind of variable arc bridge floor stand device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191227