CN112211384B - Scaffold for building site - Google Patents

Scaffold for building site Download PDF

Info

Publication number
CN112211384B
CN112211384B CN202011045132.8A CN202011045132A CN112211384B CN 112211384 B CN112211384 B CN 112211384B CN 202011045132 A CN202011045132 A CN 202011045132A CN 112211384 B CN112211384 B CN 112211384B
Authority
CN
China
Prior art keywords
scaffold
limiting
vertical rod
wall
montant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011045132.8A
Other languages
Chinese (zh)
Other versions
CN112211384A (en
Inventor
吴长春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Changqing Building Products Co ltd
Original Assignee
Anhui Changqing Building Products Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Changqing Building Products Co ltd filed Critical Anhui Changqing Building Products Co ltd
Priority to CN202011045132.8A priority Critical patent/CN112211384B/en
Publication of CN112211384A publication Critical patent/CN112211384A/en
Application granted granted Critical
Publication of CN112211384B publication Critical patent/CN112211384B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/02Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means
    • E04G1/04Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section
    • E04G1/06Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section comprising members with rod-like or tubular portions fitting together end to end, with or without separate connecting pieces
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/20Stiff scaffolding clamps for connecting scaffold members of common shape for ends of members only, e.g. for connecting members in end-to-end relation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/22Stiff scaffolding clamps for connecting scaffold members of common shape for scaffold members in end-to-side relation

Abstract

The invention discloses a scaffold for a building site, and particularly relates to the technical field of scaffolds, which comprises a plurality of transverse rods and vertical rods, wherein the plurality of vertical rods are connected through connecting pipes, the plurality of transverse rods are positioned between the plurality of vertical rods, threaded pipes arranged on the connecting pipes are sleeved at two ends of the transverse rods, the plurality of vertical rods are fixedly connected, limiting grooves are formed in the outer walls of the vertical rods, first limiting strips matched with the limiting grooves are arranged on the inner walls of the connecting pipes, clamping concave parts and clamping convex parts used for positioning are arranged at the end parts of the vertical rods, a pipeline mechanism used for recovering the vertical rods is sleeved outside the vertical rods, and the height of the pipeline mechanism can be adjusted. When the scaffold is disassembled, the vertical rod parts of the scaffold do not need to throw the ground from high altitude, and equipment such as a tower crane does not need to be adopted to hoist the scaffold to the ground, so that the safety and convenience of the scaffold during the disassembly are improved, and the working efficiency is improved.

Description

Scaffold for building site
Technical Field
The invention relates to the technical field of scaffolds, in particular to a scaffold for a construction site.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is smoothly carried out. The scaffold is divided into an outer scaffold and an inner scaffold according to the erected positions; the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials; the scaffold is divided into a vertical rod type scaffold, a bridge type scaffold, a door type scaffold, a suspension type scaffold, a hanging type scaffold, a lifting type scaffold and a climbing type scaffold according to the structural form.
The scaffold easy to disassemble and assemble for the current building construction is more in types, such as a fastener type scaffold easy to disassemble and assemble, a socket type scaffold easy to disassemble and assemble, a bowl type scaffold easy to disassemble and assemble and the like. These scaffold dismantles and goes on from top to bottom successive layer usually, and rail and warning mark should be established to the ground of demolising the operation region, and the pipe of demolising can not directly be thrown to ground, and equipment handling such as tower crane is generally adopted to ground, and it is comparatively troublesome to operate, influences scaffold's dismantlement efficiency.
Disclosure of Invention
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides a scaffold frame for building site, includes a plurality of horizontal poles and montant, connects through the connecting pipe between a plurality of montants, and a plurality of horizontal poles are located between a plurality of montants, and the both ends cover of horizontal pole is equipped with the screwed pipe of locating on the connecting pipe, with a plurality of montant fixed connection, the spacing groove has been seted up on the outer wall of montant, be equipped with on the connecting pipe inner wall with spacing groove matched with first spacing, the tip of montant is provided with the joint that is used for the location sunken and the joint arch, the outside cover of montant is equipped with the pipeline mechanism that is used for retrieving the montant, pipeline mechanism's height-adjustable festival.
In a preferred embodiment, the pipeline mechanism comprises a limiting sleeve, a fixing screw and a recovery pipeline, the limiting sleeve is sleeved outside the vertical rod and can be movably adjusted up and down, the fixing screw is inserted into the limiting sleeve, the end of the fixing screw is attached to the outer wall of the vertical rod, and the recovery pipeline is fixed on the outer wall of the limiting sleeve.
In a preferred embodiment, a second limiting strip matched with the limiting groove is arranged on the inner wall of the limiting sleeve, and the recovery pipeline and the threaded pipe are not in the same straight line.
In a preferred embodiment, the limiting grooves on the plurality of vertical rods, the first limiting strips on the plurality of connecting pipes and the second limiting strips on the plurality of limiting sleeves are arranged in a collinear manner.
In a preferred embodiment, the clamping recess and the clamping protrusion are symmetrically arranged, the clamping recess of the lower vertical rod is in butt joint with the clamping protrusion of the upper vertical rod, and the clamping protrusion of the lower vertical rod is in butt joint with the clamping recess of the upper vertical rod.
In a preferred embodiment, the minimum distance between the inner wall of the recovery pipe and the outer wall of the vertical rod is larger than the difference between the inner diameter and the outer diameter of the connecting pipe.
The invention has the technical effects and advantages that:
1. when the scaffold is disassembled, the vertical rod parts of the scaffold do not need to throw the ground from high altitude, and equipment such as a tower crane does not need to be adopted to hoist the vertical rod parts to the ground, so that the safety and convenience of the scaffold during disassembling are improved, and the working efficiency is improved;
2. the invention has simple structure, adopts movable connection, is convenient and quick to disassemble and assemble, greatly improves the construction efficiency, can repeatedly utilize each component for many times, saves materials and greatly saves construction cost.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
FIG. 2 is a schematic view of a connection pipe according to the present invention.
FIG. 3 is a schematic cross-sectional view taken along line B-B of FIG. 1 according to the present invention.
FIG. 4 is a schematic cross-sectional view taken along line A-A of FIG. 1 according to the present invention.
The reference signs are: 1 montant, 2 horizontal poles, 3 connecting pipes, 4 screwed pipes, 5 spacing grooves, 6 first spacing, 7 joint sunken, 8 joint arch, 9 pipeline mechanism, 10 spacing sleeve pipes, 11 set screw, 12 recovery pipeline, 13 second spacing.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The scaffold for the construction site as shown in fig. 1-4 comprises a plurality of cross rods 2 and vertical rods 1, wherein the plurality of vertical rods 1 are connected through connecting pipes 3, the plurality of cross rods 2 are positioned between the plurality of vertical rods 1, threaded pipes 4 arranged on the connecting pipes 3 are sleeved at two ends of the cross rods 2, the plurality of vertical rods 1 are fixedly connected, the plurality of vertical rods 1 are connected and installed through the connecting pipes 3, and the installed vertical rods 1 are connected with the cross rods 2 through threaded rods to form a whole scaffold;
the connecting pipe is characterized in that a limiting groove 5 is formed in the outer wall of the vertical rod 1, a first limiting strip 6 matched with the limiting groove 5 is arranged on the inner wall of the connecting pipe 3, a clamping concave 7 and a clamping convex 8 for positioning are arranged at the end part of the vertical rod 1, the clamping concave 7 and the clamping convex 8 are symmetrically arranged, the clamping concave 7 of the lower vertical rod 1 is butted with the clamping convex 8 of the upper vertical rod 1, the clamping convex 8 of the lower vertical rod 1 is butted with the clamping concave 7 of the upper vertical rod 1, the clamping convex 8 and the clamping concave 7 are matched, and the first limiting strip 6 and the limiting groove 5 are matched at the same time, so that after the vertical rods 1 are connected, the directions and the positions of the vertical rods are fixed, and the limiting groove 5 on the upper vertical rod 1 and the limiting groove 5 on the lower vertical rod 1 are positioned on the same straight line;
a pipeline mechanism 9 for recovering the vertical rod 1 is sleeved outside the vertical rod 1, and the height of the pipeline mechanism 9 is adjustable;
the pipeline mechanism 9 comprises a limiting sleeve 10, a fixing screw 11 and a recovery pipeline 12, the limiting sleeve 10 is sleeved outside the vertical rod 1 and can be movably adjusted up and down, the fixing screw 11 is inserted into the limiting sleeve 10, the end part of the fixing screw is attached to the outer wall of the vertical rod 1, and a user adjusts the height and the position of the limiting sleeve 10 on the vertical rod 1 by adjusting the tightness degree of the fixing screw 11;
the recovery pipeline 12 is fixed on the outer wall of the limiting sleeve 10, the inner wall of the limiting sleeve 10 is provided with a second limiting strip 13 matched with the limiting groove 5, and the position of the recovery pipeline 12 relative to the vertical rod 1 is fixed by utilizing the matching use of the second limiting strip 13 and the limiting groove 5;
the recovery pipeline 12 and the threaded pipe 4 are not in the same straight line, so that the recovery pipeline 12 on the plurality of vertical rods 1 cannot conflict with the threaded pipe 4 in position during working;
the limiting grooves 5 on the plurality of vertical rods 1, the first limiting strips 6 on the plurality of connecting pipes 3 and the second limiting strips 13 on the plurality of limiting sleeves 10 are arranged in a collinear manner, and when a plurality of groups of vertical rods 1 are installed, the recovery pipelines 12 on the plurality of groups of vertical rods 1 can be positioned on the same straight line;
the minimum distance value between the inner wall of the recovery pipeline 12 and the outer wall of the vertical rod 1 is larger than the difference value of the inner diameter and the outer diameter of the connecting pipe 3, so that the vertical rod 1 passing through the interior of the recovery pipeline 12 cannot be collided by the pipe wall of the connecting pipe 3;
when the device is used, the limiting sleeve 10 is sleeved outside the vertical rod 1, the second limiting strip 13 in the limiting sleeve 10 is clamped in the limiting groove 5 on the outer wall of the vertical rod 1, then the vertical rods 1 are installed together through the connecting pipe 3, the first limiting strip 6 on the inner wall of the connecting pipe 3 is clamped in the limiting groove 5 on the outer wall of the vertical rod 1, the clamping recess 7 and the clamping protrusion 8 at the end part of the vertical rod 1 above are butted with the clamping recess 7 and the clamping protrusion 8 at the end part of the vertical rod 1 below, connection of the vertical rods 1 is completed, the recovery pipelines 12 on the vertical rods 1 after connection are on the same straight line, then the vertical rods 1 are fixedly connected through the transverse rods 2 and the threaded rods, the recovery pipelines 12 after installation are all located at the middle points of the vertical rods 1 where the recovery pipelines are installed, and the recovery pipeline 12 on the vertical rod 1 below is located at the bottom end of the vertical rod 1;
when dismantling, montant 1 with the top takes out from connecting pipe 3, then loosen set screw 11 on montant 1, tear pipeline mechanism 9 down, insert the montant 1 after the dismantlement in the recovery pipeline 12 of below, landing to subaerial from the top of scaffold along recovery pipeline 12, because the recovery pipeline 12 of below is located montant 1's bottom, consequently, the distance between the recovery pipeline 12 of below and the recovery pipeline 12 directly over it is greater than montant 1's length, when montant 1 falls to ground, can stack to subaerial, when dismantling scaffold, scaffold's montant 1 part need not throw ground from the high altitude, also need not to adopt equipment such as tower crane handling to ground, security and convenience when scaffold dismantlement have been improved, work efficiency has been improved.
The points to be finally explained are: first, in the description of the present application, it should be noted that, unless otherwise specified and limited, the terms "mounted," "connected," and "connected" should be understood broadly, and may be a mechanical connection or an electrical connection, or a communication between two elements, and may be a direct connection, and "upper," "lower," "left," and "right" are only used to indicate a relative positional relationship, and when the absolute position of the object to be described is changed, the relative positional relationship may be changed;
secondly, the method comprises the following steps: in the drawings of the disclosed embodiments of the invention, only the structures related to the disclosed embodiments are referred to, other structures can refer to common designs, and the same embodiment and different embodiments of the invention can be combined with each other without conflict;
and finally: the above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the present invention, and any modifications, equivalents, improvements and the like made within the spirit and principle of the present invention should be included in the scope of the present invention.

Claims (6)

1. The utility model provides a scaffold frame for building site, its characterized in that, includes a plurality of horizontal poles and montant, connects through the connecting pipe between a plurality of montants, and a plurality of horizontal poles are located between a plurality of montants, and the both ends cover of horizontal pole is equipped with the screwed pipe of locating on the connecting pipe, with a plurality of montant fixed connection, the spacing groove has been seted up on the outer wall of montant, be equipped with on the connecting pipe inner wall with spacing groove matched with first spacing, the tip of montant is provided with the joint that is used for the location sunken and the joint arch, the outside cover of montant is equipped with and is used for carrying out the pipeline mechanism who retrieves to the montant, pipeline mechanism's height-adjustable festival.
2. A scaffold for construction sites according to claim 1, wherein: the pipeline mechanism comprises a limiting sleeve, a fixing screw and a recovery pipeline, the limiting sleeve is sleeved outside the vertical rod and can be movably adjusted up and down, the fixing screw is inserted in the limiting sleeve and the end part of the fixing screw is attached to the outer wall of the vertical rod, and the recovery pipeline is fixed on the outer wall of the limiting sleeve.
3. A scaffold for construction sites according to claim 2, wherein: the inner wall of the limiting sleeve is provided with a second limiting strip matched with the limiting groove, and the recovery pipeline and the threaded pipe are not on the same straight line.
4. A scaffold for construction sites according to claim 3, wherein: the limiting device comprises a plurality of limiting grooves in the vertical rod, a plurality of first limiting strips on the connecting pipe and a plurality of second limiting strips on the limiting sleeve pipe, wherein the first limiting strips and the second limiting strips are arranged in a collinear mode.
5. A scaffolding for construction sites according to claim 4, wherein: the clamping recess and the clamping protrusion are symmetrically arranged, the clamping recess of the lower vertical rod is in butt joint with the clamping protrusion of the upper vertical rod, and the clamping protrusion of the lower vertical rod is in butt joint with the clamping recess of the upper vertical rod.
6. A scaffold for construction sites according to claim 2, wherein: the minimum distance value between the inner wall of the recovery pipeline and the outer wall of the vertical rod is larger than the difference value of the inner diameter and the outer diameter of the connecting pipe.
CN202011045132.8A 2020-09-28 2020-09-28 Scaffold for building site Active CN112211384B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011045132.8A CN112211384B (en) 2020-09-28 2020-09-28 Scaffold for building site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011045132.8A CN112211384B (en) 2020-09-28 2020-09-28 Scaffold for building site

Publications (2)

Publication Number Publication Date
CN112211384A CN112211384A (en) 2021-01-12
CN112211384B true CN112211384B (en) 2022-07-05

Family

ID=74051935

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011045132.8A Active CN112211384B (en) 2020-09-28 2020-09-28 Scaffold for building site

Country Status (1)

Country Link
CN (1) CN112211384B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115637839B (en) * 2022-11-04 2023-09-12 广西鲁板建筑设备制造有限公司 Quick assembly disassembly structure for building scaffold

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0657939A (en) * 1992-03-25 1994-03-01 Kawatetsu Kizai Kogyo Kk Folding scaffolding device
CN204174900U (en) * 2014-09-20 2015-02-25 邱垂亮 Building scaffold
CN207003968U (en) * 2017-07-26 2018-02-13 王晓明 A kind of dismountable scaffold of architectural engineering
CN108222491A (en) * 2018-02-01 2018-06-29 温州市东海建筑安装工程有限公司 A kind of civil engineering means for fastening scaffolding
CN109025240A (en) * 2018-08-17 2018-12-18 中建八局第二建设有限公司 A kind of safety scaffold disassembly siphunculus
CN209259614U (en) * 2018-12-11 2019-08-16 广东和益隆金属制品有限公司 Scaffold
CN110439243A (en) * 2019-07-03 2019-11-12 安徽长青建筑制品有限公司 A kind of Fast Installation formula metal scaffolding
CN210002847U (en) * 2019-04-22 2020-01-31 南京机电职业技术学院 scaffold easy to be assembled and disassembled

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0657939A (en) * 1992-03-25 1994-03-01 Kawatetsu Kizai Kogyo Kk Folding scaffolding device
CN204174900U (en) * 2014-09-20 2015-02-25 邱垂亮 Building scaffold
CN207003968U (en) * 2017-07-26 2018-02-13 王晓明 A kind of dismountable scaffold of architectural engineering
CN108222491A (en) * 2018-02-01 2018-06-29 温州市东海建筑安装工程有限公司 A kind of civil engineering means for fastening scaffolding
CN109025240A (en) * 2018-08-17 2018-12-18 中建八局第二建设有限公司 A kind of safety scaffold disassembly siphunculus
CN209259614U (en) * 2018-12-11 2019-08-16 广东和益隆金属制品有限公司 Scaffold
CN210002847U (en) * 2019-04-22 2020-01-31 南京机电职业技术学院 scaffold easy to be assembled and disassembled
CN110439243A (en) * 2019-07-03 2019-11-12 安徽长青建筑制品有限公司 A kind of Fast Installation formula metal scaffolding

Also Published As

Publication number Publication date
CN112211384A (en) 2021-01-12

Similar Documents

Publication Publication Date Title
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN112211384B (en) Scaffold for building site
CN207245149U (en) External scaffolding sets up auxiliary installation device
CN211689948U (en) Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN204040437U (en) Cantilever tripod and single protective frame system of encorbelmenting
CN204001802U (en) A kind of fence assembly and adopt this fence assembly and the construction protection railing that forms
CN206801072U (en) A kind of foundation ditch temporary guard rail
CN107059641B (en) Goods shelf type pier body outer scaffold
CN210084690U (en) Hoistway with elevator
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN210621500U (en) A basket is hung in construction that is used for municipal works and room to build engineering
CN204038917U (en) Dismountable external hanging service platform
CN207110399U (en) A kind of construction site scaffold
CN207080169U (en) A kind of wall attaching parts for bridge construction safety climbing ladder
CN207003968U (en) A kind of dismountable scaffold of architectural engineering
CN208686201U (en) It is a kind of for architectural engineering and the modular maintenance railing of road engineering
CN207104753U (en) Furred ceiling expansion bolt sleeve
CN107461029B (en) Lower hanging beam pouring forming device based on hydraulic climbing formwork system setting
CN212249076U (en) Large-scale space bending steel pipe truss aerial work operation platform
CN213654204U (en) Basket scaffold pre-buried sleeve fixing part
CN215717117U (en) Novel detachable external scaffolding is wall spare even
CN217998886U (en) Narrow space climbing platform
CN204418696U (en) Vertical reinforcement spreading lifting assistor
CN204530491U (en) A kind of high pier hydraulic climbing mould construction frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Scaffolding for construction sites

Effective date of registration: 20230328

Granted publication date: 20220705

Pledgee: Tianchang Science and Technology Financing Guarantee Co.,Ltd.

Pledgor: ANHUI CHANGQING BUILDING PRODUCTS Co.,Ltd.

Registration number: Y2023980036450