CN207110399U - A kind of construction site scaffold - Google Patents

A kind of construction site scaffold Download PDF

Info

Publication number
CN207110399U
CN207110399U CN201720886377.0U CN201720886377U CN207110399U CN 207110399 U CN207110399 U CN 207110399U CN 201720886377 U CN201720886377 U CN 201720886377U CN 207110399 U CN207110399 U CN 207110399U
Authority
CN
China
Prior art keywords
pole
connecting rod
frame
construction site
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720886377.0U
Other languages
Chinese (zh)
Inventor
刘斌
鲍玉萍
从占军
张相震
刘芝中
王边江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang Construction and Installation Group Co Ltd
Original Assignee
Heilongjiang Construction and Installation Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang Construction and Installation Group Co Ltd filed Critical Heilongjiang Construction and Installation Group Co Ltd
Priority to CN201720886377.0U priority Critical patent/CN207110399U/en
Application granted granted Critical
Publication of CN207110399U publication Critical patent/CN207110399U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of construction site scaffold, including pole, frame plate and staircase, the pole upper and lower ends are respectively installed with connecting tube, and connecting rod and connecting rod two are separately installed with for the both ends of pole by connecting tube, the frame plate is fixedly mounted corresponding to the connecting rod and connecting rod two on pole top on end face, fixed plate is installed with by connecting rod among the frame plate, the end of the staircase is fixedly connected with frame plate bottom, and it is fixedly connected by frame plate with connecting rod, the bottom of the staircase is fixedly connected with the connecting rod of installation below pole, the side of the pole respective link is provided with support frame, support frame as described above is fixedly connected by fixed pin shaft with pole.The construction site scaffold, simple in construction, installation easy to disassemble, stability is strong, effectively improves the security that worker uses scaffold.

Description

A kind of construction site scaffold
Technical field
It the utility model is related to Architectural Equipment technical field, more particularly to a kind of construction site scaffold.
Background technology
Scaffold refers to job site as operation and solves vertically and horizontally to transport the various supports set up.Architecture field Generic term, refer to and exterior wall, inside fitting or the higher place that can not directly construct of floor height be used on construction site.Mainly for Workmen works up and down or perimeter security net is gone along with sb. to guard him and high-altitude installation component etc., and some engineerings are also with scaffold when template makes With also being used extensively in departments such as advertising, municipal administration, traffic road and bridge, mines in addition.Many lack also be present in existing scaffold Fall into, the different parts of support body need to use the steel pipe of different size, cause scaffolding species more, and frame structure is answered It is miscellaneous, it is both needed to expend excessively artificial during assembling and dismounting, labor intensity is big for single workmen, therefore, It is necessary that the structure for being directed to existing building scaffold is further to be improved.
Utility model content
The purpose of this utility model is to solve shortcoming present in prior art, and a kind of construction site proposed is used Scaffold.
To achieve these goals, the utility model employs following technical scheme:
A kind of construction site scaffold, including pole, frame plate and staircase, the pole upper and lower ends are respectively installed with company Adapter, and connecting rod and connecting rod two are separately installed with for the both ends of pole by connecting tube, the frame plate is fixedly mounted on pole Corresponding to the connecting rod and connecting rod two in portion on end face, fixed plate is installed with by connecting rod among the frame plate, the staircase End is fixedly connected with frame plate bottom, and is fixedly connected by frame plate with connecting rod, and the bottom of the staircase below pole with installing Connecting rod be fixedly connected, the side of the pole respective link is provided with support frame, and support frame as described above passes through fixed pin shaft and branch Bar is fixedly connected.
Preferably, the connecting tube is four-way connecting tube, and the T-shaped setting of connecting tube, the respective link and connecting rod two Port in 90 degree be fixedly mounted.Connecting rod and connecting rod two are fixedly mounted in 90 by connecting tube for pole, make pole and connecting rod and Be square fixation between connecting rod two, there is provided the stability of strut support connecting rod and connecting rod two.
Preferably, the pole corresponds to and spacing collar is provided with below connecting tube, the spacing collar by set screw with Pole is fixedly connected.Spacing collar is fixed to pole by the position of connecting tube installing connecting rods and connecting rod two, will by set screw Spacing collar is tightly fixed on pole, improves the effect fixed to connecting tube position.
Preferably, the side of the frame plate respective link two is installed with gag lever post, the both ends difference of the gag lever post It is fixedly connected with the end face of fixed plate and connecting rod two.Fixed plate is fixed between pole, connecting rod and connecting rod two by gag lever post, Improve stability of the worker station in frame plate end face upper mounted plate.
Preferably, the side of the pole respective link two is provided with rhombic supporting frame, the rhombic supporting by frame plate Expansion bracket is provided with frame.Rhombic supporting frame improves and supports fixed fastness between pole and connecting rod two, and expansion bracket is to rhombus Support frame is fixed, it is ensured that the safety of frame plate support works worker.
Preferably, support frame as described above is provided with two groups, and cross-shaped be fixedly mounted on pole is corresponded between connecting tube Place.Support frame position fixation be connected to pole with connecting rod that interlocks limits, to ensure the stabilization of fixing support rack plate between pole Effect.
In the utility model, connecting rod and connecting rod two are fixedly mounted in 90 by connecting tube for pole, and support frame is staggeredly to branch Limitation is fixed in the position that bar is connected with connecting rod, and rhombic supporting frame improves and supports fixed fastness between pole and connecting rod two, stretches Contracting frame is fixed to rhombic supporting frame, and frame plate is fixedly mounted at connecting rod and connecting rod two that pole is connected with pole top, and and water chestnut The end of shape support frame is fixedly connected, and fixed plate is fixed between pole, connecting rod and connecting rod two by gag lever post, is improved worker station and is existed The stability of frame plate end face upper mounted plate, staircase is fixedly mounted on below frame plate, and is fixed with pole, is easy to worker to climb.Should Construction site scaffold, simple in construction, installation easy to disassemble, stability is strong, effectively improves the safety that worker uses scaffold Property.
Brief description of the drawings
Fig. 1 be the utility model proposes a kind of construction site scaffold structural representation;
Fig. 2 be the utility model proposes a kind of construction site scaffold top view;
Fig. 3 be the utility model proposes a kind of construction site scaffold side view.
In figure:1 pole;11 connecting tubes;12 connecting rods;13 connecting rods two;14 spacing collars;141 set screws;2 frame plates;21 fix Plate;22 gag lever posts;23 support frames;231 fixed pin shafts;24 rhombic supporting framves;241 expansion links;3 staircases.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.
Reference picture 1-3, a kind of construction site scaffold, including pole 1, frame plate 2 and staircase 3, the pole is two about 1 End is respectively installed with connecting tube 11, and is separately installed with connecting rod 12 and connecting rod 2 13 for the both ends of pole 1 by connecting tube 11, The connecting tube 11 is four-way connecting tube, and 11 T-shaped setting of connecting tube, the respective link 12 and the port of connecting rod 2 13 are in 90 degree of fixed installations.Connecting rod 12 and connecting rod 2 13 are fixedly mounted in 90 by connecting tube 11 for pole 1, make pole 1 and connecting rod 12 Be square fixation between connecting rod 2 13, there is provided the support link 12 of pole 1 and the stability of connecting rod 2 13.The correspondence of pole 1 The lower section of connecting tube 11 is provided with spacing collar 14, and the spacing collar 14 is fixedly connected by set screw 141 with pole 1.It is spacing 14 pairs of poles 1 of circle are fixed by the position of the installing connecting rods 12 of connecting tube 11 and connecting rod 2 13, by set screw 141 by spacing collar 14 are tightly fixed on pole 1, improve the effect fixed to the position of connecting tube 11.The top of pole 1 is fixedly mounted in the frame plate 2 Corresponding to connecting rod 12 and connecting rod 2 13 on end face, fixed plate 21, the frame are installed with by connecting rod 12 among the frame plate 2 The side of the respective link 2 13 of plate 2 is installed with gag lever post 22, and the both ends of the gag lever post 22 are respectively with fixed plate 21 and even The end face of bar 2 13 is fixedly connected.Fixed plate 21 is fixed between pole 1, connecting rod 12 and connecting rod 2 13 by gag lever post 22, Improve stability of the worker station in the end face upper mounted plate 21 of frame plate 2.The end of the staircase 3 is fixedly connected with the bottom of frame plate 2, and It is fixedly connected by frame plate 2 with connecting rod 12, the bottom of the staircase 3 is fixedly connected with the connecting rod 12 of the lower section of pole 1 installation, described The side of the respective link 12 of pole 1 is provided with support frame 23, and support frame as described above 23 is fixed by fixed pin shaft 231 and pole 1 to be connected Connect.The side of the respective link 2 13 of pole 1 is provided with rhombic supporting frame 24 by frame plate 2, in the rhombic supporting frame 24 It is provided with expansion bracket 241.Rhombic supporting frame 24 improves and supports fixed fastness, expansion bracket 241 between pole 1 and connecting rod 2 13 Rhombic supporting frame 24 is fixed, it is ensured that the safety of the support works worker of frame plate 2.
In the utility model, connecting rod 12 and connecting rod 2 13 are fixedly mounted in 90 by connecting tube 11 for pole 1, support frame 23 Limitation is fixed in the position being staggeredly connected to pole 1 with connecting rod 12 and connecting rod 2 13, and rhombic supporting frame 24 improves pole 1 and connecting rod two Fixed fastness is supported between 13, expansion bracket 241 is fixed to rhombic supporting frame 24, and frame plate 2 is fixedly mounted on pole 1 and pole At the connecting rod 12 and connecting rod 2 13 of the connection of 1 top, and it is fixedly connected with the end of rhombic supporting frame 24, gag lever post 22 is by fixed plate 21 are fixed between pole 1, connecting rod 12 and connecting rod 2 13, improve worker and stand in the stability of the end face upper mounted plate 21 of frame plate 2, help Ladder 3 is fixedly mounted on the lower section of frame plate 2, and is fixed with pole 1, is easy to worker to climb.
It is described above, the only preferable embodiment of the utility model, but the scope of protection of the utility model is not This is confined to, any one skilled in the art is in the technical scope that the utility model discloses, according to this practicality New technical scheme and its utility model design are subject to equivalent substitution or change, should all cover in protection model of the present utility model Within enclosing.

Claims (6)

1. a kind of construction site scaffold, including pole (1), frame plate (2) and staircase (3), it is characterised in that the pole (1) upper and lower ends are respectively installed with connecting tube (11), and are separately installed with company by both ends of the connecting tube (11) for pole (1) Bar (12) and connecting rod two (13), the frame plate (2) are fixedly mounted corresponding to the connecting rod (12) and connecting rod two (13) on pole (1) top On end face, fixed plate (21), the end of the staircase (3) and frame are installed with by connecting rod (12) among the frame plate (2) Plate (2) bottom is fixedly connected, and is fixedly connected by frame plate (2) with connecting rod (12), bottom and the pole (1) of the staircase (3) The connecting rod (12) of lower section installation is fixedly connected, and the side of pole (1) respective link (12) is provided with support frame (23), described Support frame (23) is fixedly connected by fixed pin shaft (231) with pole (1).
2. a kind of construction site scaffold according to claim 1, it is characterised in that the connecting tube (11) is four-way The port of connecting tube, and connecting tube (11) T-shaped setting, the respective link (12) and connecting rod two (13) is fixed in 90 degree pacifies Dress.
3. a kind of construction site scaffold according to claim 1, it is characterised in that the pole (1) is corresponding to be connected Spacing collar (14) is provided with below pipe (11), the spacing collar (14) connects by the way that set screw (141) and pole (1) are fixed Connect.
4. a kind of construction site scaffold according to claim 1, it is characterised in that the fixed plate (21) is corresponding to be connected The side of bar two (13) is installed with gag lever post (22), the both ends of the gag lever post (22) respectively with fixed plate (21) and connecting rod The end face of two (13) is fixedly connected.
A kind of 5. construction site scaffold according to claim 1, it is characterised in that pole (1) respective link The side of two (13) is provided with rhombic supporting frame (24) by frame plate (2), and expansion bracket is provided with the rhombic supporting frame (24) (241)。
6. a kind of construction site scaffold according to claim 1, it is characterised in that support frame as described above (23) is provided with Two groups, and it is cross-shaped be fixedly mounted on pole (1) to correspond to locate between connecting tube (11).
CN201720886377.0U 2017-07-19 2017-07-19 A kind of construction site scaffold Active CN207110399U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720886377.0U CN207110399U (en) 2017-07-19 2017-07-19 A kind of construction site scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720886377.0U CN207110399U (en) 2017-07-19 2017-07-19 A kind of construction site scaffold

Publications (1)

Publication Number Publication Date
CN207110399U true CN207110399U (en) 2018-03-16

Family

ID=61584780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720886377.0U Active CN207110399U (en) 2017-07-19 2017-07-19 A kind of construction site scaffold

Country Status (1)

Country Link
CN (1) CN207110399U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523490A (en) * 2020-11-23 2021-03-19 滁州市德诺新材料科技有限公司 Reverse-jacking scaffold convenient to assemble for building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523490A (en) * 2020-11-23 2021-03-19 滁州市德诺新材料科技有限公司 Reverse-jacking scaffold convenient to assemble for building

Similar Documents

Publication Publication Date Title
CN109235861B (en) Be applied to small high-rise building's assembled scaffold frame
CN107902545B (en) Horse way air pipe hoisting construction device and construction method
CN206016226U (en) Tool type scaffold interlayer guard system
CN105649314A (en) Suspension platform for high and long-span corridor construction
CN103422663A (en) Adhesive lifting scaffold
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN112681714A (en) Construction method of steel wire rope lengthened rear support type hanging basket
CN205502551U (en) Platform is suspended in midair in high altitude large -span vestibule construction
CN207110399U (en) A kind of construction site scaffold
CN204752026U (en) Tower crane escape way
CN201635377U (en) Rigid suspended type scaffold provided with large-span steel roof equipment pipeline
CN206753009U (en) One kind building fabricated scaffold
CN103628692B (en) A kind of floor beam mounting bracket and use it to install the method for floor beam
CN109653484B (en) Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering
CN204038917U (en) Dismountable external hanging service platform
CN112211384B (en) Scaffold for building site
CN213952912U (en) Overhanging type scaffold
CN115807532A (en) Device for attaching suspension bracket and construction method
CN215212255U (en) Suspension type frame combined high-altitude operation platform
CN213868835U (en) Scaffold frame for interior decoration convenient to height-adjusting
CN108756194B (en) Telescopic scaffold for installing elevator shaft frame and method thereof
CN205000618U (en) Novel scaffold
CN202990386U (en) Externally-suspended scaffold
CN210067401U (en) Positioning and adjusting device for climbing scaffold
CN207526085U (en) A kind of attachment type raise scaffold structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant