CN110439243A - A kind of Fast Installation formula metal scaffolding - Google Patents

A kind of Fast Installation formula metal scaffolding Download PDF

Info

Publication number
CN110439243A
CN110439243A CN201910594577.2A CN201910594577A CN110439243A CN 110439243 A CN110439243 A CN 110439243A CN 201910594577 A CN201910594577 A CN 201910594577A CN 110439243 A CN110439243 A CN 110439243A
Authority
CN
China
Prior art keywords
scaffold
ontology
connection ring
connection
scaffold ontology
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910594577.2A
Other languages
Chinese (zh)
Inventor
吴长春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Changqing Construction Products Co Ltd
Original Assignee
Anhui Changqing Construction Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Changqing Construction Products Co Ltd filed Critical Anhui Changqing Construction Products Co Ltd
Priority to CN201910594577.2A priority Critical patent/CN110439243A/en
Publication of CN110439243A publication Critical patent/CN110439243A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/02Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means
    • E04G1/04Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section
    • E04G1/06Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section comprising members with rod-like or tubular portions fitting together end to end, with or without separate connecting pieces
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/20Stiff scaffolding clamps for connecting scaffold members of common shape for ends of members only, e.g. for connecting members in end-to-end relation

Abstract

The invention discloses a kind of Fast Installation formula metal scaffoldings, are related to Construction Formwork & Scaffold Technology field.Including scaffold ontology, the connection sleeve for connecting two scaffold ontologies, the connection sleeve the outer peripheral sidewall socket of the scaffold ontology be arranged the connection sleeve include for connecting the first part of the scaffold ontology, the second part for connecting another scaffold ontology.The present invention be able to solve the dismounting of existing scaffold need to consume a large amount of time, dismounting large labor intensity the problem of.

Description

A kind of Fast Installation formula metal scaffolding
Technical field
The present invention relates to Construction Formwork & Scaffold Technology fields, and in particular to a kind of Fast Installation formula metal scaffolding.
Background technique
In municipal field, municipal bridge is common one of urban operating mechanism, in municipal bridge construction and the mistake of maintenance Cheng Zhong, steel structure scaffold are essential auxiliary equipment.
Steel structure scaffold in the prior art needs to install a large amount of screw completion and is fastenedly connected when building, therefore every Secondary dismounting requires to consume a large amount of time and removes dismounting screw, and screw quantity is more, it is easy to lose, increase worker to zero Management intensity on part increases the labor intensity dismounted every time.
Moreover, in use, screw is easy to produce loosening, therefore current steel structure scaffold is there are more deficiency, There is also very big security risks, while can reduce the construction efficiency to municipal bridge.
Summary of the invention
In view of the deficiencies of the prior art, the present invention discloses a kind of Fast Installation formula metal scaffolding, is able to solve existing foot Hand cradle dismounting need to consume a large amount of time, dismounting large labor intensity the problem of.
In order to achieve the above object, the present invention is achieved by the following technical programs:
A kind of Fast Installation formula metal scaffolding,
Including scaffold ontology, the connection sleeve for connecting two scaffold ontologies, the connection sleeve is in institute The outer peripheral sidewall socket setting of scaffold ontology is stated,
The connection sleeve includes for connecting the first part of the scaffold ontology, for connecting another foot hand The second part of frame ontology, the first part and the scaffold ontology are slidably connected, the first part and described second Partial turn connection,
It is equipped with the first connection ring towards one end of the second part in the first part, first connection ring is along institute The circumferentially extending for stating first part is equipped with the second connection ring towards one end of the first part in the second part, described Along the circumferentially extending of the second part, first connection ring and second connection ring are slidably connected, use second connection ring In guiding second part the circumferentially rotating along the scaffold ontology,
It is equipped with external screw thread in outer peripheral sidewall of the first part away from one end of the second part, at described second The inner circumferential side wall away from one end of the first part is divided to be equipped with internal screw thread, the external screw thread and internal screw thread engagement are to connect Two scaffold ontologies.
Preferably, the section of first connection ring is set as L-shaped, and the section of second connection ring is set as and institute State the L-shaped of the first connection ring cooperation, first connection ring and second connection ring link closely setting.
Preferably, it is equipped with sliding slot in the outer peripheral sidewall of the scaffold ontology, the sliding slot is along the scaffold ontology It is axially extending, to guide connection sleeve the sliding axially along the scaffold ontology,
It is equipped with sliding block in the inner circumferential side wall of the first part, the sliding block and the sliding slot are slidably connected, to guide Connection sleeve is stated to slide along the sliding slot.
Preferably, stop collar, the relatively described scaffold body peripheral of the stop collar are equipped in the end of the scaffold The height of side wall is set greater than the height of the relatively described scaffold body peripheral side wall of the sliding block, to prevent the connector sleeve Cylinder skids off the end of the scaffold ontology.
Preferably, it is equipped with first through hole in the first part, the first through hole is prolonged along the axial direction of the first part It stretches, the first through hole is passed through through the first part for the scaffold ontology.
Preferably, it is equipped with the second through-hole in the second part, second through-hole prolongs along the axial direction of the second part It stretches, second through-hole is connected to the first through hole through the second part and passes through for the scaffold ontology.
The present invention discloses a kind of Fast Installation formula metal scaffolding, has the advantage that
The connection sleeve of setting can be in the axial easy slide of scaffold ontology, convenient for changing the scaffold of connection sleeve The position of ontology, so that position, which is adjusted flexibly, connects another scaffold ontology at the both ends of scaffold ontology according to actual needs.
Connection sleeve is set as including first part and second part, and first part is slided with respect to scaffold ontology, and second Part is rotated relative to scaffold ontology, the internal screw thread engagement of the external screw thread and second part of first part, thus two feet of connection Hand cradle ontology, connection speed is fast, good connecting effect.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is the installation diagram of the embodiment of the present invention;
Fig. 2 is the main view of the embodiment of the present invention;
Fig. 3 is the partial sectional view of the embodiment of the present invention;
Fig. 4 is the main view that sleeve is connected in the embodiment of the present invention;
Fig. 5 is the cross-sectional view that sleeve is connected in the embodiment of the present invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
As shown in Figures 1 to 5, a kind of Fast Installation formula metal scaffolding described in the embodiment of the present invention,
Including scaffold ontology 1, the connection sleeve 2 for connecting two scaffold ontologies 1, the connection sleeve 2 Be socketed setting in the outer peripheral sidewall of the scaffold ontology 1, connection sleeve A2 on scaffold ontology A1 as shown in Figure 1 and Connection sleeve B2 connection on another scaffold ontology B2, to quickly fix scaffold ontology A1 and connection sleeve A2.
The connection sleeve 2 include for connecting the first part 21 of the scaffold ontology 1, it is another described for connecting The second part 22 of scaffold ontology 1, the first part 21 and the scaffold ontology 1 are slidably connected, the first part 21 and the second part 22 be rotatablely connected.
It is equipped with the first connection ring 212 towards one end of the second part 22 in the first part 21, described first connects Ring 212 is connect along the circumferentially extending of the first part 21, is set in one end of the second part 22 towards the first part 21 There are the second connection ring 222, circumferentially extending of second connection ring 222 along the second part 22, first connection ring 212 It is slidably connected with second connection ring 222, for guiding the second part 22 to turn along the circumferential direction of the scaffold ontology 1 It is dynamic.
The section of first connection ring 212 is set as L-shaped, and the section of second connection ring 222 is set as and institute State the L-shaped of the first connection ring 212 cooperation, first connection ring 212 and second connection ring 222 link closely setting, thus Guarantee that first part 21 and second part 22 will not fall off while guiding first part 21 and second part 22 relatively rotates, In order to reduce the friction between first part 21 and second part 22, it is equipped with oilhole 223 on second part 22, is used for first The contact surface of part 21 and second part 22 provides lubricating oil to reduce friction.
It is equipped with external screw thread 213 in outer peripheral sidewall of the first part 21 away from one end of the second part 22, in institute It states inner circumferential side wall of the second part 22 away from one end of the first part 21 and is equipped with internal screw thread 221, the external screw thread 213 and institute The engagement of internal screw thread 221 is stated to connect two scaffold ontologies 1.
Sliding slot 11, axis of the sliding slot 11 along the scaffold ontology 1 are equipped in the outer peripheral sidewall of the scaffold ontology 1 To extension, to guide connection the sliding axially in the inner circumferential side of the first part 21 along the scaffold ontology 1 of sleeve 2 Wall is equipped with sliding block 211, and the sliding block 211 and the sliding slot 11 are slidably connected, to guide the connection sleeve 2 along the sliding slot 11 Sliding.
Stop collar 12, relatively described 1 peripheral side of scaffold ontology of the stop collar 12 are equipped in the end of the scaffold The height of wall is set greater than the height of relatively described 1 outer peripheral sidewall of scaffold ontology of the sliding block 211, to prevent the connection Sleeve 2 skids off the end of the scaffold ontology 1.
First through hole 210, axial direction of the first through hole 210 along the first part 21 are equipped in the first part 21 Extend, the first through hole 210 is passed through through the first part 21 for the scaffold ontology 1.
The second through-hole 220, axial direction of second through-hole 220 along the second part 22 are equipped in the second part 22 Extend, second through-hole 220 is connected to the first through hole 210 through the second part 22 for the scaffold ontology 1 passes through.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.
Moreover, the terms "include", "comprise" or any other variant thereof is intended to cover non-exclusive inclusion, to make Obtaining the process, method, article or equipment including a series of elements not only includes those elements, but also including not arranging clearly Other element out, or further include for elements inherent to such a process, method, article, or device.Not more In the case where limitation, the element that is limited by sentence "including a ...", it is not excluded that including process, the side of the element There is also other identical elements in method, article or equipment.
The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although with reference to the foregoing embodiments Invention is explained in detail, those skilled in the art should understand that: it still can be to aforementioned each implementation Technical solution documented by example is modified or equivalent replacement of some of the technical features;And these modification or Replacement, the spirit and scope for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution.

Claims (6)

1. a kind of Fast Installation formula metal scaffolding, it is characterised in that:
Including scaffold ontology, the connection sleeve for connecting two scaffold ontologies, the connection sleeve is in the foot The outer peripheral sidewall of hand cradle ontology is socketed setting,
The connection sleeve includes for connecting the first part of the scaffold ontology, for connecting another scaffold sheet The second part of body, the first part and the scaffold ontology are slidably connected, the first part and the second part Rotation connection,
It is equipped with the first connection ring towards one end of the second part in the first part, first connection ring is along described the A part circumferentially extending, the second part towards one end of the first part be equipped with the second connection ring, described second Connection ring is along the circumferentially extending of the second part, and first connection ring and second connection ring are slidably connected, for drawing The second part circumferentially rotating along the scaffold ontology is led,
It is equipped with external screw thread in outer peripheral sidewall of the first part away from one end of the second part, is carried on the back in the second part The inner circumferential side wall of one end from the first part is equipped with internal screw thread, and the external screw thread and internal screw thread engagement are to connect two The scaffold ontology.
2. Fast Installation formula metal scaffolding as described in claim 1, it is characterised in that: the section of first connection ring is arranged For L-shaped, the section of second connection ring is set as the L-shaped cooperated with first connection ring, first connection ring It links closely setting with second connection ring.
3. Fast Installation formula metal scaffolding as described in claim 1, it is characterised in that:
It is equipped with sliding slot in the outer peripheral sidewall of the scaffold ontology, the sliding slot is axially extending along the scaffold ontology, with Connection sleeve the sliding axially along the scaffold ontology is guided,
It is equipped with sliding block in the inner circumferential side wall of the first part, the sliding block and the sliding slot are slidably connected, to guide the company Female connector cylinder is slided along the sliding slot.
4. Fast Installation formula metal scaffolding as claimed in claim 3, it is characterised in that: be equipped with limit in the end of the scaffold Position ring, the height of the relatively described scaffold body peripheral side wall of the stop collar are set greater than the relatively described foot hand of the sliding block The height of frame body peripheral side wall, to prevent the connection sleeve from skidding off the end of the scaffold ontology.
5. Fast Installation formula metal scaffolding as described in claim 1, it is characterised in that: it is logical to be equipped with first in the first part Hole, the first through hole is axially extending along the first part, and the first through hole is through the first part for described Scaffold ontology passes through.
6. Fast Installation formula metal scaffolding as claimed in claim 5, it is characterised in that: it is logical to be equipped with second in the second part Hole, second through-hole is along the axially extending of the second part, and second through-hole is through the second part and described the The connection of one through-hole is passed through for the scaffold ontology.
CN201910594577.2A 2019-07-03 2019-07-03 A kind of Fast Installation formula metal scaffolding Pending CN110439243A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910594577.2A CN110439243A (en) 2019-07-03 2019-07-03 A kind of Fast Installation formula metal scaffolding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910594577.2A CN110439243A (en) 2019-07-03 2019-07-03 A kind of Fast Installation formula metal scaffolding

Publications (1)

Publication Number Publication Date
CN110439243A true CN110439243A (en) 2019-11-12

Family

ID=68429347

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910594577.2A Pending CN110439243A (en) 2019-07-03 2019-07-03 A kind of Fast Installation formula metal scaffolding

Country Status (1)

Country Link
CN (1) CN110439243A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112211384A (en) * 2020-09-28 2021-01-12 安徽长青建筑制品有限公司 Scaffold for building site

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202012100091U1 (en) * 2012-01-11 2012-02-27 Goodwell Management Ltd. pipe connection
CN202531566U (en) * 2012-02-28 2012-11-14 江泽炼 Connector and combined sectional pipe
CN102877578A (en) * 2012-09-29 2013-01-16 冯文钦 Dry-hanging stone curtain wall mounting and maintaining method and sleeve
CN205036695U (en) * 2015-07-08 2016-02-17 林政德 Bushing spare
CN208072917U (en) * 2018-04-04 2018-11-09 中国建筑第二工程局有限公司 Carrying frame is built in a kind of room

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202012100091U1 (en) * 2012-01-11 2012-02-27 Goodwell Management Ltd. pipe connection
CN202531566U (en) * 2012-02-28 2012-11-14 江泽炼 Connector and combined sectional pipe
CN102877578A (en) * 2012-09-29 2013-01-16 冯文钦 Dry-hanging stone curtain wall mounting and maintaining method and sleeve
CN205036695U (en) * 2015-07-08 2016-02-17 林政德 Bushing spare
CN208072917U (en) * 2018-04-04 2018-11-09 中国建筑第二工程局有限公司 Carrying frame is built in a kind of room

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112211384A (en) * 2020-09-28 2021-01-12 安徽长青建筑制品有限公司 Scaffold for building site
CN112211384B (en) * 2020-09-28 2022-07-05 安徽长青建筑制品有限公司 Scaffold for building site

Similar Documents

Publication Publication Date Title
CN110439243A (en) A kind of Fast Installation formula metal scaffolding
CN203189389U (en) Fixing structure of hydraulic oil cylinder guide sleeves and baffle rings
CN202812592U (en) Sleeve and pipe quick connector
CN105065482B (en) It is capable of the yielding coupling of the impaired parts of quick-replaceable
CN205384959U (en) Plug -in strip operating means
CN209483448U (en) A kind of assembled camshaft structure of engine
CN205649458U (en) Jump ring formula quick detach hinge
CN206694432U (en) One kind extruding tightening covering device
CN206653325U (en) A kind of high-efficient automatic Screw driving machine
CN206998797U (en) A kind of piston ring installing/dismounting mechanism
CN205136255U (en) Nonrust steel pipe coupling assembling
CN216130882U (en) High-corrosion-resistance high-leakage-resistance tubing coupling
CN201330064Y (en) Novel hanger of screw conveyer
CN210739927U (en) Lubricating device for robot maintenance
CN204799356U (en) Low -speed low speed coal mill abrasionproof decreases screw shell
CN211737803U (en) Multistage combination formula profile of tooth spline housing
CN205533284U (en) Connect formula water pump soon
CN110153946B (en) Drawing device
CN108302114A (en) Hinging pin shaft
CN208450566U (en) Die casting machine pull rod scraping
CN204512157U (en) A kind of transmission shaft structure for car transmissions
CN208203781U (en) A kind of shifting fork type actuator pin shaft structure
CN203322685U (en) Automatic oiling device for steel billet fixture start and stop device
CN219365970U (en) Sucker rod elevator convenient to assembly
CN209067121U (en) Wear-and corrosion-resistant rod collar

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191112

RJ01 Rejection of invention patent application after publication