CN206053269U - Bamboo and iron mixed scaffolding for construction - Google Patents

Bamboo and iron mixed scaffolding for construction Download PDF

Info

Publication number
CN206053269U
CN206053269U CN201620883484.3U CN201620883484U CN206053269U CN 206053269 U CN206053269 U CN 206053269U CN 201620883484 U CN201620883484 U CN 201620883484U CN 206053269 U CN206053269 U CN 206053269U
Authority
CN
China
Prior art keywords
steel pipe
outrigger
horizontal
bamboo
outer frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620883484.3U
Other languages
Chinese (zh)
Inventor
苏汝恒
苏汝培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
World Pacific Scaffolding Systems Ltd
Original Assignee
World Pacific Scaffolding Systems Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by World Pacific Scaffolding Systems Ltd filed Critical World Pacific Scaffolding Systems Ltd
Priority to CN201620883484.3U priority Critical patent/CN206053269U/en
Application granted granted Critical
Publication of CN206053269U publication Critical patent/CN206053269U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A bamboo-iron mixed shed frame for buildings comprises an outer frame body, an inner frame body, a workbench, a connecting piece, a wall connecting device and a supporting piece; the outer frame body comprises more than two outer frame transverse steel pipes, outer frame vertical steel pipes, outer frame inclined steel pipes and connecting pieces with the same number as the number of the crossing parts of the steel pipes. The inner frame body comprises more than two inner frame transverse steel pipes, inner frame vertical steel pipes and connecting pieces with the same number as the number of the crossing parts of the steel pipes. The outer frame body is towards the one side of wall body, corresponds and is provided with interior frame body, and both connect through horizontal connecting pipe. The utility model discloses rational in infrastructure, the high use cost of intensity is low.

Description

建筑用竹铁混合棚架Bamboo and iron mixed scaffolding for construction

技术领域technical field

本技术涉及建筑设备技术领域,特别涉及一种建筑用竹铁混合棚架。The technology relates to the technical field of construction equipment, in particular to a bamboo-iron mixed scaffold for construction.

背景技术Background technique

建筑棚架早已有之,主要为金属架体,是用钢管为横、竖杆材,通过连接件连接成建筑用棚架;这些钢管棚架强度很够,但存在有成本高、运输强度大的不足。也有用竹子为材料的建筑用棚架,虽然解决了成本问题,但其强度及使用年限都存在问题。也有用钢管及竹杆为材料的混合棚架,如专利号为:“200610073535.7”,名称为:“脚手架”等的在先技术。但现有技术存在有钢管与竹杆搭配设计不合理的缺陷。Building scaffolds have existed for a long time, mainly metal frames, which use steel pipes as horizontal and vertical rods, and connect them to form building scaffolds through connectors; these steel pipe scaffolds are strong enough, but they have the disadvantages of high cost and high transportation intensity. lack of. Also useful bamboo is the construction scaffolding of material, though solved cost problem, all there is problem in its intensity and service life. Also useful steel pipe and bamboo pole are the mixed scaffolding of material, as patent number is: " 200610073535.7 ", and name is called: the prior art of " scaffolding " etc. But there is the unreasonable defective of steel pipe and bamboo pole collocation design in prior art.

发明内容Contents of the invention

本实用新型目的是针对以上现有技术的不足,设计一种结构合理、强度高的建筑用竹铁混合棚架。The purpose of the utility model is to design a bamboo-iron hybrid scaffold for buildings with reasonable structure and high strength for the above deficiencies in the prior art.

本实用新型目的可以通过以下技术方案实现,一种建筑用竹铁混合棚架,包括外架体、内架体、工作台、连接件、连墙器及承托件,其中:The purpose of this utility model can be achieved through the following technical solutions. A bamboo-iron mixed scaffold for construction includes an outer frame body, an inner frame body, a workbench, a connector, a wall connector and a supporting member, wherein:

外架体:包括两根以上的外架横钢管、外架竖钢管、外架斜钢管及与上述钢管的交叉处同样个数的连接件组成;每根外架竖钢管的底部设有承托件或棚架建于地面,承托件固定在墙体上;等间距设置的外架横钢管、外架竖钢管及间隔一根外架竖钢管和间隔两根外架横钢管对角所设的外架斜钢管的相互交叉处均由连接件相互连接;在每两根外架竖钢管之间设有两根以上外架竖竹管,在每两根外架横钢管之间设有两根以上外架横竹管,外架竖钢管、外架横钢管、外架竖竹管及外架横竹管的相互交叉处均设有使其连接的捆扎件;Outer frame body: It consists of more than two outer frame horizontal steel pipes, outer frame vertical steel pipes, outer frame oblique steel pipes and the same number of connectors as the intersection of the above steel pipes; the bottom of each outer frame vertical steel pipe is provided with a support The frame or scaffolding is built on the ground, and the supporting parts are fixed on the wall; the horizontal steel pipes of the outer frame, the vertical steel pipes of the outer frame, the vertical steel pipes of the outer frame, and the vertical steel pipes of the outer frame and the horizontal steel pipes of the outer frame are arranged at the opposite corners. The intersecting parts of the oblique steel pipes of the outer frame are connected with each other by connectors; more than two vertical bamboo pipes are arranged between every two vertical steel pipes of the outer frame, and two vertical bamboo pipes are arranged between every two horizontal steel pipes of the outer frame. The outer frame horizontal bamboo tubes above the root, the outer frame vertical steel tubes, the outer frame horizontal steel tubes, the outer frame vertical bamboo tubes and the outer frame horizontal bamboo tubes are all provided with binding pieces to connect them;

内架体:包括两根以上的内架横钢管、内架竖钢管及与上述钢管的交叉处同样个数的连接件组成;每根内架竖钢管的间距与外架竖钢管的间距相同,其底部设在承托外架竖钢管的承托件上;或棚架建于地上;每根内架横钢管的间距与外架横钢管的间距及高度相同;等间距设置的内架横钢管及内架竖钢管相互交叉处均由连接件相互连接;在每两根内架竖钢管之间设有一根以上内架竖竹管,内架竖竹管与内架横钢管的相互交叉处均设有使其连接的捆扎件;Inner frame body: It consists of more than two inner frame horizontal steel pipes, inner frame vertical steel pipes and the same number of connectors as the intersection of the above steel pipes; the distance between each inner frame vertical steel pipe is the same as that of the outer frame vertical steel pipe, The bottom is set on the supporting piece supporting the vertical steel pipes of the outer frame; or the scaffolding is built on the ground; the distance between each horizontal steel pipe of the inner frame is the same as the distance and height of the horizontal steel pipes of the outer frame; the horizontal steel pipes of the inner frame are arranged at equal intervals The intersections of the vertical steel pipes of the inner frame and the vertical steel pipes of the inner frame are connected by connecting pieces; more than one vertical bamboo pipe of the inner frame is arranged between every two vertical steel pipes of the inner frame, and the intersections of the vertical bamboo pipes of the inner frame and the horizontal steel pipes of the inner frame are all be provided with bindings to connect it;

外架体朝向墙体的一面,对应设置有内架体,在外架横钢管与外架竖钢管的交叉处,内架横钢管与内架竖钢管的交叉处设有连接外架体及内架体的水平连接钢管,相互之间通过连接件连接,外架体与内架体之间的距离为600 mm以上;The side of the outer frame facing the wall is correspondingly equipped with an inner frame. At the intersection of the horizontal steel pipe of the outer frame and the vertical steel pipe of the outer frame, the intersection of the horizontal steel pipe of the inner frame and the vertical steel pipe of the inner frame is provided with a connecting outer frame and an inner frame. The horizontally connected steel pipes of the body are connected to each other through connectors, and the distance between the outer frame body and the inner frame body is more than 600 mm;

在外架横钢管与内架横钢管之间钢管的顶部设有供工作人员工作的工作台;On the top of the steel pipe between the horizontal steel pipe of the outer frame and the horizontal steel pipe of the inner frame, there is a workbench for the staff to work on;

从最底的外架横钢管起,每隔一个外架横钢管与每个外架竖钢管的交叉处,设有一个将外架横钢管与外架竖钢管与墙体固定的连墙器。From the lowest outer frame horizontal steel pipe, every other intersection of the outer frame horizontal steel pipe and each outer frame vertical steel pipe is provided with a wall connector that fixes the outer frame horizontal steel pipe and the outer frame vertical steel pipe to the wall.

所述的建筑用竹铁混合棚架,其外架横钢管之间的距离及内墙横钢管之间的距离为2000mm, 外架竖钢管之间的距离及内墙竖钢管之间的距离为3100 mm。Described bamboo-iron hybrid scaffold for construction, the distance between the horizontal steel pipes of its outer frame and the distance between the horizontal steel pipes of the inner wall is 2000mm, the distance between the vertical steel pipes of the outer frame and the vertical steel pipes of the inner wall is 3100 mm.

所述的建筑用竹铁混合棚架,其设在外架横钢管与内架横钢管之间钢管顶部的工作台木桥板,在木桥板的底部,外架横钢管与内架横钢管之间设有起加强作用的内外横杆连接竹杆,相互之间的连接是通过绑扎实现。The bamboo-iron mixed scaffolding for construction is arranged on the workbench wooden bridge board on the top of the steel pipe between the outer frame horizontal steel pipe and the inner frame horizontal steel pipe, and at the bottom of the wooden bridge board, between the outer frame horizontal steel pipe and the inner frame horizontal steel pipe. There are internal and external horizontal bars connecting the bamboo bars for reinforcement, and the connection between them is realized by binding.

所述的建筑用竹铁混合棚架,其工作台的侧边设有向上突出的踢脚挡板。In the bamboo-iron mixed scaffolding for construction, the side of the workbench is provided with kicking baffles protruding upwards.

所述的建筑用竹铁混合棚架,其最底层起的两个外架横钢管之间,设有可防止人员及物料跌落的向外延伸的竹斜杆,在最端头的两根外架竖钢管之间的竹斜杠之间设有防护网。The bamboo-iron composite scaffolding for construction, between the two outer frame horizontal steel pipes from the bottom, is provided with outwardly extending bamboo slanting rods that can prevent people and materials from falling. A protective net is arranged between the bamboo slashes between the vertical steel pipes.

本实用新型与现有技术相比,结构合理,强度高,成本低。Compared with the prior art, the utility model has the advantages of reasonable structure, high strength and low cost.

附图说明Description of drawings

图1为本实用新型的外架体结构示意图;Fig. 1 is the outer frame structure schematic diagram of the present utility model;

图2为本实用新型的内架体结构示意图;Fig. 2 is a schematic diagram of the structure of the inner frame of the utility model;

图3为本实用新型的侧面局部结构示意图;Fig. 3 is the side partial structure schematic diagram of the utility model;

图4为本实用新型的侧面结构示意图;Fig. 4 is the side structure schematic diagram of the utility model;

图5为本实用新型的实施例结构示意图。Fig. 5 is a structural schematic diagram of an embodiment of the utility model.

具体实施方式detailed description

如图1、图2、图3、图4所示,建筑用竹铁混合棚架,包括外架体1、内架体2、工作台3、连接件4、捆扎带40、连墙器5及承托件6组成,其中:As shown in Fig. 1, Fig. 2, Fig. 3, and Fig. 4, the bamboo-iron hybrid scaffold for construction includes an outer frame body 1, an inner frame body 2, a workbench 3, a connecting piece 4, a binding strap 40, and a wall connector 5 and supporting parts 6, in which:

外架体1:包括两根以上的外架横钢管10、外架竖钢管11、外架斜钢管12及与上述钢管的交叉处同样个数的连接件4组成。每根外架竖钢管11的底部设有承托件6或建于地上,承托件6通过膨胀螺栓60固定在墙体8上。等间距设置的外架横钢管10、外架竖钢管11及间隔一根外架竖钢管10和间隔两根外架横钢管11对角所设的外架斜钢管12的相互交叉处均由连接件4相互连接。在每两根外架竖钢管11之间设有两根以上外架竖竹管13,在每两根外架横钢管10之间设有两根以上外架横竹管14;外架竖钢管11、外架横钢管10、外架竖竹管13及外架横竹管14的相互交叉处均设有使其连接的捆扎件40。Outer frame body 1: comprises more than two outer frame horizontal steel pipes 10, outer frame vertical steel pipes 11, outer frame oblique steel pipes 12 and the same number of connectors 4 as the intersections of the above steel pipes. The bottom of each outer frame vertical steel pipe 11 is provided with a supporting member 6 or built on the ground, and the supporting member 6 is fixed on the wall body 8 by expansion bolts 60 . The outer frame horizontal steel pipes 10 arranged at equal intervals, the outer frame vertical steel pipes 11 and the outer frame inclined steel pipes 12 arranged at the opposite corners of one outer frame vertical steel pipe 10 and two outer frame horizontal steel pipes 11 diagonally are all connected by The pieces 4 are connected to each other. Between every two outer frame vertical steel pipes 11, be provided with more than two outer frame vertical bamboo pipes 13, between every two outer frame horizontal steel pipes 10, be provided with more than two outer frame horizontal bamboo pipes 14; outer frame vertical steel pipes 11 , the outer frame horizontal steel pipe 10, the outer frame vertical bamboo tube 13 and the outer frame horizontal bamboo tube 14 are all provided with binding parts 40 connecting them.

内架体2:包括两根以上的内架横钢管20、内架竖钢管21及与上述钢管的交叉处同样个数的连接件4组成。每根内架竖钢管20的间距与外架竖钢管11的间距位置相同,其底部设在承托外架竖钢管的承托件6上。每根内架横钢管20的间距与外架横钢管10的间距及高度相同;等间距设置的内架横钢管20及内架竖钢管21相互交叉处均由连接件4相互连接。在每两根内架竖钢管21之间设有一根以上内架竖竹管22,内架竖竹管22与内架横钢管20的相互交叉处均设有使其连接的捆扎件40。Inner frame body 2: composed of more than two inner frame horizontal steel pipes 20, inner frame vertical steel pipes 21 and the same number of connectors 4 as the intersections of the above steel pipes. The spacing of the vertical steel pipes 20 of each inner frame is the same as that of the vertical steel pipes 11 of the outer frame, and its bottom is located on the support member 6 supporting the vertical steel pipes of the outer frame. The spacing of each inner frame horizontal steel pipe 20 is the same as the spacing and height of the outer frame horizontal steel pipe 10; Between every two inner frame vertical steel pipes 21, be provided with more than one inner frame vertical bamboo pipe 22, and the mutual intersections of the inner frame vertical bamboo pipe 22 and the inner frame horizontal steel pipe 20 are all provided with binding parts 40 connecting them.

外架体1朝向墙体的一面,对应设置有内架体2,在外架横钢管10与外架竖钢管11的交叉处,内架横钢管20与内架竖钢管21的交叉处设有连接外架体及内架体的水平连接竹管7,相互之间通过连接件4连接,外架体1与内架体2之间的距离为60CM以上。The outer frame body 1 faces one side of the wall body, and the inner frame body 2 is correspondingly arranged. At the intersection of the outer frame horizontal steel pipe 10 and the outer frame vertical steel pipe 11, the intersection of the inner frame horizontal steel pipe 20 and the inner frame vertical steel pipe 21 is provided with a connection The horizontal connecting bamboo tubes 7 of the outer frame body and the inner frame body are connected with each other through the connector 4, and the distance between the outer frame body 1 and the inner frame body 2 is more than 60 cm.

在外架横钢管10与内架横钢管20之间钢管的顶部设有供工作人员工作的工作台3;所述工作台的侧边设有向上突出的踢脚挡板30,用于防止物件或工作人员滑落。The top of the steel pipe between the outer frame horizontal steel pipe 10 and the inner frame horizontal steel pipe 20 is provided with a workbench 3 for the staff to work; the side of the workbench is provided with an upwardly protruding skirt 30 for preventing objects The staff slipped.

从最底的外架横钢管10起,每隔一个外架横钢管10与每个外架竖钢管11的交叉处,设有一个将外架横钢管10与外架竖钢管11与墙体8固定的连墙器5。From the bottom outer frame horizontal steel pipe 10, every other intersection of the outer frame horizontal steel pipe 10 and each outer frame vertical steel pipe 11 is provided with an outer frame horizontal steel pipe 10 and the outer frame vertical steel pipe 11 and the wall 8 Fixed wall connector 5.

如图5实施例所述,建筑用竹铁混合棚架,其外架横钢管10之间的距离及内墙横钢管20之间的距离为2000 m m, 外架竖钢管11之间的距离及内墙竖钢管21之间的距离为3100 m m;其外架竖竹管13之间的距离为775 mm、外架横竹管14之间的距离为650m m、内架竖竹管22介于两根外架竖钢管11之间外架竖钢管11及内墙竖钢管21位置应互相对应装置内外横杆水平连接竹杆70及内架体的水平连接竹管7。As described in Figure 5, the bamboo-iron hybrid scaffold for construction, the distance between the outer frame horizontal steel pipes 10 and the distance between the inner wall horizontal steel pipes 20 is 2000 mm, the distance between the outer frame vertical steel pipes 11 and The distance between the vertical steel tubes 21 of the inner wall is 3100 mm; the distance between the vertical bamboo tubes 13 of the outer frame is 775 mm, the distance between the horizontal bamboo tubes 14 of the outer frame is 650 mm, and the vertical bamboo tubes 22 of the inner frame are between two Between the vertical steel pipes 11 of the outer frame, the vertical steel pipes 11 of the outer frame and the vertical steel pipes 21 positions of the inner wall should correspond to each other and connect the bamboo pipes 7 of the horizontal bar 70 and the inner frame body of the horizontal bar inside and outside the device.

所述的建筑用竹铁混合棚架,其设在外架横钢管10与内架横钢管20之间钢管顶部的工作台3为木桥板,在木桥板的底部,外架横钢管10与内架横钢管20之间设有起加强作用的内外横杆水平连接竹杆70,相互之间的连接是通过绑扎40实现,外架横钢管10与内架横钢管20高度相同及装设内外横杆水平连接竹杆70及内架体的水平连接竹管7。The bamboo-iron mixed scaffolding for construction, it is arranged on the workbench 3 at the top of the steel pipe between the outer frame horizontal steel pipe 10 and the inner frame horizontal steel pipe 20 is a wooden bridge board, at the bottom of the wooden bridge board, the outer frame horizontal steel pipe 10 and the inner frame horizontal steel pipe 20 Between the inner frame horizontal steel pipes 20, there are internal and external cross bars horizontally connecting the bamboo bars 70 that play a reinforcing role. The mutual connection is realized by binding 40. The horizontal bar connects the bamboo bar 70 and the horizontal connection bamboo tube 7 of the inner frame body.

所述的建筑用竹铁混合棚架,其最底层起的两个外架横钢管10之间,设有可防止人员及物料跌落的向外延伸的竹斜杆9,在最端头的两根外架竖钢管21之间的竹斜杠9之间设有防护网。The bamboo-iron composite scaffolding for construction has an outwardly extending bamboo slanting rod 9 that can prevent people and materials from falling between the two outer frame horizontal steel pipes 10 at the bottom. A protective net is provided between the bamboo slashes 9 between the vertical steel pipes 21 of the outer frame.

Claims (5)

1. a kind of bamboo ferrum mixing frame for building, it is characterised in which includes outer frame body, inner frame body, workbench, connector, company Wall device and supporting parts, wherein:
Outer frame body:Infall including the horizontal steel pipe of the outriggers of more than two, outrigger perpendicular steel pipe, the oblique steel pipe of outrigger and with above-mentioned steel pipe The connector composition of same number;The bottom of the perpendicular steel pipe of every outrigger is provided with supporting parts or is erected at ground, and supporting parts are fixed on On body of wall;The perpendicular steel pipe of the horizontal steel pipe of outrigger of spaced set, outrigger and the perpendicular steel pipe of one, interval outrigger and the two outrigger horizontal strokes in interval The place of intersecting of the diagonal set oblique steel pipe of outrigger of steel pipe is connected with each other by connector;Erecting between steel pipe per two outriggers The perpendicular bamboo trunk of more than two outriggers is provided with, the horizontal bamboo trunk of more than two outriggers between horizontal steel pipe, is being provided with per two outriggers, outrigger erects steel The place of intersecting of pipe, the perpendicular bamboo trunk of the horizontal steel pipe of outrigger, outrigger and the horizontal bamboo trunk of outrigger is equipped with the binding piece for connecting which;
Inner frame body:Including the horizontal steel pipe of the internal frames of more than two, the perpendicular steel pipe of internal frame and the same number with the infall of above-mentioned steel pipe Connector is constituted;The spacing of the perpendicular steel pipe of every internal frame is identical with the spacing of the perpendicular steel pipe of outrigger, and its bottom is located at support outrigger and erects steel The supporting parts of pipe set up on the ground;The horizontal spacing of steel pipe of every internal frame and the spacing of the horizontal steel pipe of outrigger and highly identical;Deng The perpendicular steel pipe place of intersecting of the horizontal steel pipe of internal frame and internal frame that spacing is arranged is connected with each other by connector;Steel is being erected per two internal frames More than one internal frame is provided between pipe and erects bamboo trunk, the perpendicular bamboo trunk of internal frame is equipped with the place of intersecting of the horizontal steel pipe of internal frame and is connected which Binding piece;
Outer frame body is correspondingly arranged on inner frame body towards the one side of body of wall, and the infall of steel pipe is erected with outrigger in the horizontal steel pipe of outrigger, interior The horizontal steel pipe of frame is provided with the level connection joint bamboo trunk for being connected outer frame body and inner frame body with the infall of the perpendicular steel pipe of internal frame, passes through each other Connector connects, and the distance between outer frame body and inner frame body are more than 60 m m;
The workbench for staff's work is provided between the horizontal steel pipe of outrigger and the horizontal steel pipe of internal frame at the top of steel pipe;
From the horizontal steel pipe of the outrigger at most bottom, every a horizontal steel pipe of outrigger and the infall of the perpendicular steel pipe of each outrigger, one is provided with Company's wall device that outrigger horizontal steel pipe and outrigger perpendicular steel pipe is fixed with body of wall.
2. bamboo ferrum mixing frame for building according to claim 1, it is characterised in that between the horizontal steel pipe of the outrigger away from From and the distance between the horizontal steel pipe of interior wall be 2000mm, the distance between perpendicular steel pipe of outrigger and the distance between perpendicular steel pipe of interior wall For 3100m.
3. bamboo ferrum mixing frame for building according to claim 1 and 2, it is characterised in that described to be located at the horizontal steel pipe of outrigger The workbench wooden bridge plate of steel pipe top between the horizontal steel pipe of internal frame, in the bottom of wooden bridge plate, the horizontal steel pipe of outrigger and the horizontal steel pipe of internal frame Between be provided with the inside and outside cross bar connection bamboo stem of booster action, connection each other is realized by colligation.
4. bamboo ferrum mixing frame for building according to claim 1 and 2, it is characterised in that the side of the workbench sets There is the skirt baffle plate for projecting upwards.
5. bamboo ferrum mixing frame for building according to claim 1 and 2, it is characterised in that rise two of the bottom Between the horizontal steel pipe of outrigger, the bamboo brace for stretching out that can prevent personnel and material from falling is provided with, in two outriggers of most termination Protection network is provided between bamboo slash between perpendicular steel pipe.
CN201620883484.3U 2016-08-15 2016-08-15 Bamboo and iron mixed scaffolding for construction Active CN206053269U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620883484.3U CN206053269U (en) 2016-08-15 2016-08-15 Bamboo and iron mixed scaffolding for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620883484.3U CN206053269U (en) 2016-08-15 2016-08-15 Bamboo and iron mixed scaffolding for construction

Publications (1)

Publication Number Publication Date
CN206053269U true CN206053269U (en) 2017-03-29

Family

ID=58380904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620883484.3U Active CN206053269U (en) 2016-08-15 2016-08-15 Bamboo and iron mixed scaffolding for construction

Country Status (1)

Country Link
CN (1) CN206053269U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110735525A (en) * 2019-10-22 2020-01-31 武汉建工集团股份有限公司 A prefabricated self-supporting steel pipe scaffolding system
CN110735526A (en) * 2019-10-22 2020-01-31 武汉建工集团股份有限公司 assembling self-standing scaffold system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110735525A (en) * 2019-10-22 2020-01-31 武汉建工集团股份有限公司 A prefabricated self-supporting steel pipe scaffolding system
CN110735526A (en) * 2019-10-22 2020-01-31 武汉建工集团股份有限公司 assembling self-standing scaffold system
CN110735525B (en) * 2019-10-22 2021-06-01 武汉建工集团股份有限公司 Prefabricated assembled self-supporting steel pipe scaffold system

Similar Documents

Publication Publication Date Title
CN204126230U (en) Assembly scaffold unit
CN209799400U (en) A multi-functional pier column steel bar binding tire frame
CN206053269U (en) Bamboo and iron mixed scaffolding for construction
CN206625134U (en) A kind of side form frock for cast-in-situ box girder
CN103774838B (en) A kind of construction of lift well assembling safe operation platform and using method
CN206053279U (en) Tool type scaffold unit and tool type scaffold
CN204492133U (en) A kind of easy insulated column construction tool frame
CN104164889B (en) Demountable tower crane foundation
CN207582933U (en) Super High large span outrigger drawknot structure
CN206267562U (en) Detachable platform frame
CN210738053U (en) A turnable operating platform suitable for elevator counterweight installation
CN201148726Y (en) Independent climbing frame super large operating platform
CN219826024U (en) Scaffold structure easy to build
CN206971808U (en) Modular support device
CN206279783U (en) Assembled construction safety channel
CN206376514U (en) Tool climbing scaffold
CN204691201U (en) A kind of Liftable hanging formula scaffold system
CN205669326U (en) Combined protective shed for constructional engineering
CN104948004B (en) A kind of site safety manages revolving enclosure wall
CN206591747U (en) A kind of standard knot formula building site banister that can be recycled
CN203807949U (en) Assembly type overwater pier body construction support
CN116591468A (en) Temporary support device and construction method for a concrete cantilever structure
CN107476200B (en) Full-hall support staggered overlapping structure and method
CN205591506U (en) Scaffold
CN208088850U (en) A kind of steel structure column welding panel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant