CN205242981U CN201521104836.2U CN201521104836U CN205242981U CN 205242981 U CN205242981 U CN 205242981U CN 201521104836 U CN201521104836 U CN 201521104836U CN 205242981 U CN205242981 U CN 205242981U
Authority
CN
China
Prior art keywords
rod
vertical connecting
connecting rod
concrete construction
operation platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201521104836.2U
Other languages
Chinese (zh)
Inventor
张永初
覃郁芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 8 Co Ltd
Original Assignee
Sinohydro Bureau 8 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 8 Co Ltd filed Critical Sinohydro Bureau 8 Co Ltd
Priority to CN201521104836.2U priority Critical patent/CN205242981U/en
Application granted granted Critical
Publication of CN205242981U publication Critical patent/CN205242981U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

本实用新型公开了一种混凝土施工操作平台,包括踏板,还包括至少两个支撑角架,所述支撑角架包括竖直连接杆、水平承重杆、斜拉杆和模板钢管,所述竖直连接杆与模板钢管固定连接,所述水平承重杆与所述竖直连接杆的下端固定连接,所述斜拉杆固设于所述水平承重杆和竖直连接杆之间,所述踏板搭设于所述水平承重杆上。本实用新型的混凝土施工操作平台具有结构简单、安全可靠、应用范围广等优点。

The utility model discloses a concrete construction operation platform, which includes a pedal and at least two supporting angle frames, the supporting angle frames include a vertical connecting rod, a horizontal load-bearing rod, a diagonal tie rod and a formwork steel pipe, and the vertical connecting rod The rod is fixedly connected with the template steel pipe, the horizontal load-bearing rod is fixedly connected with the lower end of the vertical connecting rod, the diagonal stay rod is fixed between the horizontal load-bearing rod and the vertical connecting rod, and the pedal is set on the above the horizontal load-bearing rod. The concrete construction operation platform of the utility model has the advantages of simple structure, safety and reliability, wide application range and the like.

Description

混凝土施工操作平台Concrete construction operation platform

技术领域technical field

本实用新型涉及建筑施工设备,尤其涉及一种混凝土施工操作平台。The utility model relates to building construction equipment, in particular to a concrete construction operation platform.

背景技术Background technique

近年来,随着建筑物高度的增加,钢筋混凝土结构因其良好的力学性能和经济性,逐渐被应用于高层建筑结构尤其是有特殊外型的高层建筑结构中,混凝土施工在立模、支架方面已经比较成熟。在采用钢筋混凝土结构建设高层建筑时,配套的高空作业施工措施存在安全隐患。比较常见的是混凝土施工人员自行搭设的简陋竹木踏板或没有操作架而直接行走在模板间进行施工,发生安全事故频率较高,亟需一种混凝土施工时统一可行的施工操作平台。In recent years, with the increase of building height, reinforced concrete structures have been gradually applied to high-rise building structures, especially those with special shapes, because of their good mechanical properties and economical efficiency. has become relatively mature. When building high-rise buildings with reinforced concrete structures, there are potential safety hazards in the supporting high-altitude construction measures. It is more common for concrete construction workers to build simple bamboo and wood pedals or walk directly between the formworks without an operating frame for construction. The frequency of safety accidents is high, and there is an urgent need for a unified and feasible construction operation platform during concrete construction.

实用新型内容Utility model content

本实用新型要解决的技术问题是克服现有技术的不足,提供一种结构简单、安全可靠、应用范围广的混凝土施工操作平台。The technical problem to be solved by the utility model is to overcome the deficiencies of the prior art and provide a concrete construction operation platform with simple structure, safety and reliability, and wide application range.

为解决上述技术问题,本实用新型采用以下技术方案:In order to solve the above technical problems, the utility model adopts the following technical solutions:

一种混凝土施工操作平台,包括踏板,还包括至少两个支撑角架,所述支撑角架包括竖直连接杆、水平承重杆、斜拉杆和模板钢管,所述竖直连接杆与模板钢管固定连接,所述水平承重杆与所述竖直连接杆的下端固定连接,所述斜拉杆固设于所述水平承重杆和竖直连接杆之间,所述踏板搭设于所述水平承重杆上。A concrete construction operation platform, including pedals, and at least two supporting angle frames, the supporting angle frames include vertical connecting rods, horizontal load-bearing rods, diagonal stay rods and formwork steel pipes, and the vertical connecting rods are fixed to the formwork steel pipes connection, the horizontal load-bearing rod is fixedly connected to the lower end of the vertical connecting rod, the diagonal stay rod is fixed between the horizontal load-bearing rod and the vertical connecting rod, and the pedal is set on the horizontal load-bearing rod .

作为上述技术方案的进一步改进:As a further improvement of the above technical solution:

所述竖直连接杆的上端设置有钩状部,所述钩状部挂设于所述模板钢管上。The upper end of the vertical connecting rod is provided with a hook portion, and the hook portion is hung on the template steel pipe.

所述模板钢管上设有螺纹孔,所述竖直连接杆通过设于所述螺纹孔内的螺栓固定在模板钢管上。The template steel pipe is provided with a threaded hole, and the vertical connecting rod is fixed on the template steel pipe through a bolt provided in the threaded hole.

所述踏板上固设有护栏,所述护栏沿踏板长度方向设置,护栏上部与所述竖直连接杆之间固设有护栏拉杆。A guardrail is fixed on the pedal, and the guardrail is arranged along the length direction of the pedal, and a guardrail pull rod is fixed between the upper part of the guardrail and the vertical connecting rod.

与现有技术相比,本实用新型的优点在于:本实用新型的混凝土施工操作平台利用建筑物模板系统中已有的模板钢管作为支撑,设置竖直连接杆与模板钢管固定连接,竖直连接杆下端设置水平承重杆用以安装踏板,水平承重杆与竖直连接杆之间设置斜拉杆,整体结构简单、可靠,有效提高了混凝土施工时的安全性。Compared with the prior art, the utility model has the advantages that: the concrete construction operation platform of the utility model uses the existing template steel pipes in the building formwork system as a support, and the vertical connecting rods are fixedly connected with the template steel pipes, and the vertical connection A horizontal load-bearing rod is arranged at the lower end of the rod to install the pedal, and a diagonal tie rod is arranged between the horizontal load-bearing rod and the vertical connecting rod. The overall structure is simple and reliable, and the safety during concrete construction is effectively improved.

进一步地,竖直连接杆上端设置钩状部,利用钩状部挂设于模板钢管上,结构简单、便于拆装,且安装后具有较高的可靠性,适用于传统的加工比较随意的木模板系统。Furthermore, the upper end of the vertical connecting rod is provided with a hook-shaped part, which is used to hang on the formwork steel pipe. The structure is simple, easy to disassemble, and has high reliability after installation. It is suitable for traditional wooden Templating system.

进一步地,在模板钢管上设置螺纹孔,利用螺栓将竖直连接杆固定于模板钢管上,结构简单可靠,竖直连接杆与模板钢管连接后可与钢模板系统一起吊装使用,同步实现建筑物模板系统和混凝土施工操作平台的拼装,非常方便,适用于钢模板系统。Further, threaded holes are set on the formwork steel pipes, and the vertical connecting rods are fixed on the formwork steel pipes by bolts. The structure is simple and reliable. After the vertical connecting rods are connected with the formwork steel pipes, they can be hoisted and used together with the steel formwork system, simultaneously realizing building The assembly of the formwork system and the concrete construction operation platform is very convenient, and it is suitable for the steel formwork system.

附图说明Description of drawings

图1为本实用新型混凝土施工操作平台实施例1的结构示意图;Fig. 1 is the structural representation of embodiment 1 of concrete construction operation platform of the present invention;

图2为本实用新型混凝土施工操作平台实施例1的侧视图;Fig. 2 is the side view of Embodiment 1 of the concrete construction operation platform of the present invention;

图3为本实用新型混凝土施工操作平台实施例2的结构示意图;Fig. 3 is the structural representation of embodiment 2 of the concrete construction operation platform of the present invention;

图4为本实用新型混凝土施工操作平台实施例2的侧视图。Fig. 4 is a side view of Embodiment 2 of the concrete construction operation platform of the present invention.

图中各标号表示:1、模板钢管;2、竖直连接杆;3、水平承重杆;4、斜拉杆;5、踏板;6、钩状部;7、螺栓;8、护栏;9、护栏拉杆。Each label in the figure indicates: 1. Formwork steel pipe; 2. Vertical connecting rod; 3. Horizontal load-bearing rod; 4. Diagonal stay rod; 5. Pedal; tie rod.

具体实施方式detailed description

以下结合说明书附图和具体实施例对本实用新型作进一步描述。The utility model will be further described below in conjunction with the accompanying drawings and specific embodiments of the description.

实施例1Example 1

如图1所示,本实施例的混凝土施工操作平台,包括踏板5,还包括至少两个支撑角架,支撑角架包括竖直连接杆2、水平承重杆3、斜拉杆4和模板钢管1,竖直连接杆2与模板钢管1固定连接,水平承重杆3与竖直连接杆2的下端固定连接,斜拉杆4固设于水平承重杆3和竖直连接杆2之间,踏板5搭设于水平承重杆3上,其中水平承重杆3与竖直连接杆2之间,斜拉杆4与水平承重杆3、竖直连接杆2之间均采用螺纹紧固件实现固定连接,在其他实施例也可采用焊接、铆接等。该混凝土施工操作平台利用建筑物模板系统中已有的模板钢管1作为支撑,设置竖直连接杆2与模板钢管1固定连接,竖直连接杆2下端设置水平承重杆3用以安装踏板5,水平承重杆3与竖直连接杆2之间设置斜拉杆4,整体结构简单、可靠,有效提高了混凝土施工时的安全性。As shown in Figure 1, the concrete construction operation platform of this embodiment includes a pedal 5, and also includes at least two support angle frames, and the support angle frames include vertical connecting rods 2, horizontal load-bearing rods 3, diagonal stay rods 4 and template steel pipes 1 , the vertical connecting rod 2 is fixedly connected with the template steel pipe 1, the horizontal load-bearing rod 3 is fixedly connected with the lower end of the vertical connecting rod 2, the diagonal tie rod 4 is fixed between the horizontal load-bearing rod 3 and the vertical connecting rod 2, and the pedal 5 is erected On the horizontal load-bearing rod 3, between the horizontal load-bearing rod 3 and the vertical connecting rod 2, between the diagonal stay rod 4 and the horizontal load-bearing rod 3, and the vertical connecting rod 2, threaded fasteners are used to realize fixed connection. For example, welding, riveting, etc. can also be used. The concrete construction operation platform utilizes the existing template steel pipe 1 in the building formwork system as a support, and a vertical connecting rod 2 is fixedly connected to the template steel pipe 1, and a horizontal load-bearing rod 3 is arranged at the lower end of the vertical connecting rod 2 to install a pedal 5, A diagonal tie rod 4 is arranged between the horizontal load-bearing rod 3 and the vertical connecting rod 2, the overall structure is simple and reliable, and the safety during concrete construction is effectively improved.

如图2所示,本实施例中,竖直连接杆2的上端设置有钩状部6,钩状部6挂设于模板钢管1上,结构简单、便于拆装,且安装后具有较高的可靠性,适用于传统的加工比较随意的木模板系统。As shown in Figure 2, in this embodiment, the upper end of the vertical connecting rod 2 is provided with a hook-shaped part 6, which is hung on the formwork steel pipe 1. The structure is simple, easy to disassemble, and has a high It is suitable for the traditional wooden formwork system with relatively random processing.

实施例2Example 2

如图3和图4所示,本实施例的混凝土施工操作平台的结构与实施例1大致相同,不同之处在于,模板钢管1上设有螺纹孔,竖直连接杆2通过设于螺纹孔内的螺栓7固定在模板钢管1上,该混凝土施工操作平台结构简单可靠,竖直连接杆2与模板钢管1连接后可与钢模板系统一起吊装使用,同步实现建筑物模板系统和混凝土施工操作平台的拼装,非常方便,适用于钢模板系统。As shown in Figure 3 and Figure 4, the structure of the concrete construction operation platform of this embodiment is roughly the same as that of Embodiment 1, the difference is that the formwork steel pipe 1 is provided with threaded holes, and the vertical connecting rod 2 passes through the threaded holes. The bolts 7 inside are fixed on the formwork steel pipe 1. The structure of the concrete construction operation platform is simple and reliable. After the vertical connecting rod 2 is connected to the formwork steel pipe 1, it can be hoisted together with the steel formwork system, and the building formwork system and concrete construction operations can be realized simultaneously. The assembly of the platform is very convenient and suitable for the steel formwork system.

本实施例中,踏板5上固设有护栏8,护栏8沿踏板5长度方向设置,可进一步提高操作平台的安全性,护栏8上部与竖直连接杆2之间固设有护栏拉杆9,提高了护栏8的安装强度、可靠性。In this embodiment, a guardrail 8 is fixed on the pedal 5, and the guardrail 8 is arranged along the length direction of the pedal 5, which can further improve the safety of the operating platform. A guardrail pull bar 9 is fixed between the upper part of the guardrail 8 and the vertical connecting rod 2, The installation strength and reliability of the guardrail 8 are improved.

虽然本实用新型已以较佳实施例揭露如上,然而并非用以限定本实用新型。任何熟悉本领域的技术人员,在不脱离本实用新型技术方案范围的情况下,都可利用上述揭示的技术内容对本实用新型技术方案做出许多可能的变动和修饰,或修改为等同变化的等效实施例。因此,凡是未脱离本实用新型技术方案的内容,依据本实用新型技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均应落在本实用新型技术方案保护的范围内。Although the present invention has been disclosed above with preferred embodiments, it is not intended to limit the present invention. Any person familiar with the art, without departing from the scope of the technical solution of the present utility model, can use the technical content disclosed above to make many possible changes and modifications to the technical solution of the utility model, or modify it into an equivalent change, etc. effective example. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention shall fall within the protection scope of the technical proposal of the present invention.

Claims (4)

1.一种混凝土施工操作平台,包括踏板(5),其特征在于:还包括至少两个支撑角架,所述支撑角架包括竖直连接杆(2)、水平承重杆(3)、斜拉杆(4)和模板钢管(1),所述竖直连接杆(2)与模板钢管(1)固定连接,所述水平承重杆(3)与所述竖直连接杆(2)的下端固定连接,所述斜拉杆(4)固设于所述水平承重杆(3)和竖直连接杆(2)之间,所述踏板(5)搭设于所述水平承重杆(3)上。1. A concrete construction operation platform, including a pedal (5), characterized in that: it also includes at least two supporting angle frames, and the supporting angle frames include vertical connecting rods (2), horizontal load-bearing rods (3), oblique The tie rod (4) and the template steel pipe (1), the vertical connecting rod (2) is fixedly connected to the template steel pipe (1), and the horizontal load-bearing rod (3) is fixed to the lower end of the vertical connecting rod (2) connected, the diagonal stay rod (4) is fixed between the horizontal load-bearing rod (3) and the vertical connecting rod (2), and the pedal (5) is erected on the horizontal load-bearing rod (3). 2.根据权利要求1所述的混凝土施工操作平台,其特征在于,所述竖直连接杆(2)的上端设置有钩状部(6),所述钩状部(6)挂设于所述模板钢管(1)上。2. The concrete construction operation platform according to claim 1, characterized in that, the upper end of the vertical connecting rod (2) is provided with a hook portion (6), and the hook portion (6) is hung on the above the template steel pipe (1). 3.根据权利要求1所述的混凝土施工操作平台,其特征在于,所述模板钢管(1)上设有螺纹孔,所述竖直连接杆(2)通过设于所述螺纹孔内的螺栓(7)固定在模板钢管(1)上。3. The concrete construction operation platform according to claim 1, characterized in that, the formwork steel pipe (1) is provided with a threaded hole, and the vertical connecting rod (2) passes through the bolt provided in the threaded hole (7) Fix it on the template steel pipe (1). 4.根据权利要求3所述的混凝土施工操作平台,其特征在于,所述踏板(5)上固设有护栏(8),所述护栏(8)沿踏板(5)长度方向设置,护栏(8)上部与所述竖直连接杆(2)之间固设有护栏拉杆(9)。4. The concrete construction operation platform according to claim 3, characterized in that a guardrail (8) is fixed on the pedal (5), and the guardrail (8) is arranged along the length direction of the pedal (5), and the guardrail ( 8) A guardrail rod (9) is fixed between the upper part and the vertical connecting rod (2).
CN201521104836.2U 2015-12-28 2015-12-28 Concrete construction operation platform Expired - Lifetime CN205242981U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521104836.2U CN205242981U (en) 2015-12-28 2015-12-28 Concrete construction operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521104836.2U CN205242981U (en) 2015-12-28 2015-12-28 Concrete construction operation platform

Publications (1)

Publication Number Publication Date
CN205242981U true CN205242981U (en) 2016-05-18

Family

ID=55942061

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521104836.2U Expired - Lifetime CN205242981U (en) 2015-12-28 2015-12-28 Concrete construction operation platform

Country Status (1)

Country Link
CN (1) CN205242981U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610510A (en) * 2018-12-12 2019-04-12 中铁局集团厦门建设工程有限公司 Self-assembled mobile formwork for the partition wall in the main structure of the subway station and the half-cover excavation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610510A (en) * 2018-12-12 2019-04-12 中铁局集团厦门建设工程有限公司 Self-assembled mobile formwork for the partition wall in the main structure of the subway station and the half-cover excavation method

Similar Documents

Publication Publication Date Title
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN203808484U (en) Integrated cantilevered and attached external scaffolding
CN103291066B (en) A kind of construction elevator wall-attached frame servicing unit reinforcement means
WO2023240812A1 (en) Overall construction platform structure and method for adding core tube wall body in air
CN205527156U (en) Elevator well frame structure infinitely continues convenient to on -site Assembly and installation
CN102454292A (en) Supporting steel frame of high altitude large-span cantilever structure mold frame
CN204343642U (en) Builder's jack corner support frame
CN102061810B (en) Construction method of safe flat net positioned on periphery of building
CN205242981U (en) Concrete construction operation platform
CN207686280U (en) A kind of aluminum alloy mould plate early dismantling head device that assortable full hall scaffold uses
CN103615103A (en) Hanging type assembled movable platform
CN201943350U (en) Supporting steel frame for die holder of high-altitude large span overhanging structure
CN205688778U (en) A kind of elevating scaffold special over sling structure
CN206636157U (en) A steel structure suitable for construction site assembly
CN202324585U (en) Connecting tube of holistic inserted lift scaffold with steel frame structure for high-rise buildings
CN205617772U (en) Gallows structure under lifting foot hand rack special use
CN204343647U (en) A kind of the shaped steel suspension scaffolding bracing frame
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform
CN203545501U (en) Auxiliary lifting device of inner crawl type tower crane in small space
CN203361596U (en) Auxiliary support of integrated lifting operation platform
CN211229455U (en) Support type external overhanging scaffold
CN202324586U (en) Integral attached device attached with lifting scaffold
CN207453448U (en) A kind of bar type wall-attached frame
CN219219401U (en) Temporary protection device for deformation joint in staggered floor construction of tower
CN203783107U (en) Climbing frame with connector reinforcing device for construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20160518