CN105862896B - A kind of installation method of breakwater tub component - Google Patents

A kind of installation method of breakwater tub component Download PDF

Info

Publication number
CN105862896B
CN105862896B CN201610197611.9A CN201610197611A CN105862896B CN 105862896 B CN105862896 B CN 105862896B CN 201610197611 A CN201610197611 A CN 201610197611A CN 105862896 B CN105862896 B CN 105862896B
Authority
CN
China
Prior art keywords
tub component
ship
tub
component
hawser
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610197611.9A
Other languages
Chinese (zh)
Other versions
CN105862896A (en
Inventor
秦丹
范旭征博
杜厚新
曹鑫
刘鹏
张跃辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Branch Of Cccc Shanghai Port Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd filed Critical JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co Ltd
Priority to CN201610197611.9A priority Critical patent/CN105862896B/en
Publication of CN105862896A publication Critical patent/CN105862896A/en
Application granted granted Critical
Publication of CN105862896B publication Critical patent/CN105862896B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/02Caissons able to be floated on water and to be lowered into water in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • E02D23/10Caissons filled with compressed air
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0084Production methods for working underwater using pneumatical means
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Abstract

A kind of installation method of breakwater tub component, four draw rings are reserved in the root of tub component, it is symmetrically arranged at the front and rear part of tub component, partly latent connects two hawsers between refuting the anterior and draw ring at tub component rear portion, partly latent connects two hawsers between refuting the draw ring at rear portion and tub component rear portion, and connection intersects hawser between the anterior draw ring of tub component and main dragging ship;After after tub component air supporting in place, by draining pump and air bleeding valve, centralized management draining, exhaust adjust the switch of each pump at any time, after the balance for ensuring tub component, continue synchronous draining, negative pressure is sunk, until bucket enters the 3.0m of mud 2.0, each draining pump is closed, sinking operation is completed.The present invention is pulled by hawser, is coordinated the huge tonnage of tub component, is realized leveling of the tub component in air supporting and installation process, and balance can be not only grasped in time, improves delivery and installation effectiveness, moreover it is possible to constructed under severe weather conditions.

Description

A kind of installation method of breakwater tub component
Technical field
The present invention relates to a kind of harbour protection works, more particularly to a kind of installation method of breakwater tub component.
Background technology
The tub component of existing breakwater is the new anti-ripple that the materials such as a kind of use concrete, reinforcing bar, steel construction make Embankment structure form, the class formation bottomless is made up of by one the basic tub component of lid and two anti-ripple tub components.Will so Large-scale tub component be transported to from prefabricated place pre- buried, and it is a problem to be accurately positioned and install.
It is marine that a kind of Patent No. CN 1730842A, entitled soft-foundation box-cylinder type infrastructure are disclosed in the prior art Air supporting delivery and positioning sinking mounting method, by inflating or vacuumizing into cylinder, realize the air supporting or sinking to cylinder, though Right this method does not need large-scale lifting and ships that transport, and equipment is simple, and subsidence velocity is fast.Meanwhile, Chinese another patent CN The carrying for the basic tub component of tub breakwater that 102322062 B are disclosed and installation method, basic tub component pass through half Latent refute is conveyed to job site with transportation by driving air bag, and the floating of basic tub component and installation were positioned by transportation by driving air bag Journey can be effectively controlled, and keep basic tub component to be in poised state, because transportation by driving air bag has certain elasticity in itself, Indirectly act on basic tub component, the holdup time can be produced, it is impossible to basic tub component is carried out in time, accurately to control System.
The content of the invention
The technical problems to be solved by the invention are that there is provided a kind of reasonable in design, user in view of the shortcomings of the prior art Just the installation method of breakwater tub component.
The technical problems to be solved by the invention are realized by following technical scheme, and the present invention is a kind of anti-ripple The installation method of dike tub component, described tub component has the Long Circle staving of lid and is located on Long Circle staving including bottomless Two anti-ripple stavings of side, short-axis direction arrangement of the anti-ripple staving along Long Circle staving, the Long Circle staving is vertical by twice Cross wall, which separates to have, is equipped with steam vent and osculum at the top of 9 separations, each separation, two anti-ripple staving restockings are provided with behaviour Make on platform, GPS data collection device of four angles provided with the motion of collection staving and discrepancy in elevation data of operating platform, operating platform Provided with the one-to-one air bleeding valve of steam vent at the top of separation, steam vent connected by discharge duct with air bleeding valve, and operation is flat The osculum that the both sides of platform are respectively provided with the top of several rows of water pump, separation is connected by drainage pipeline with draining pump, is characterized in, its Step is,
(1) preparation of construction:
1.1 partly latents refute positioning:The marine site of tub component is being installed, when the sea water advanced partly latent that can not meet refutes dive to tub When component swims, the dive hole that dive is refuted for partly latent is dug, partly latent is refuted to be positioned in dive hole towards installation site, has been positioned Into defining partly latent and refute outlet port and refute front portion with tub component for partly latent;
1.2 auxiliary ship stations are in place:Tail ship, 1 station keeping ship, 3 anchor ships, 3 Liners are adjusted including 1 main dragging ship, 1 Oceangoing ship, 1 inflation ship;
The main ship that pulls is the crane ship not less than 100t, and beam requirement is in more than 20m, at least 6 windlass;
It is self-propulsion type ship to adjust tail ship, it is desirable to is refuted for flat board, there is 5 windlass;
Station keeping ship is refuted for flat board, at least 6 windlass;
Inflation ship is connected by gas ducting with the steam vent on Long Circle staving each separation;
1.3 reserve four draw rings in the root of tub component, are symmetrically arranged at the front and rear part of Long Circle staving, partly latent refutes front portion Two hawsers in left and right are connected between the draw ring at tub component rear portion, partly latent is refuted between the draw ring at rear portion and tub component rear portion Two hawsers in left and right are connected with, connection two intersects hawser between the anterior draw ring of tub component and main dragging ship;
(2) partly latent refutes dive:While partly latent refutes dive, the air bleeding valve on start-up operation platform, dive to tub component 0.8m is absorbed water, drinking water height is vented height for tub component air supporting stability Calculation, and control errors are treated in tub component in ± 5cm After gas is drained, air bleeding valve is closed;After exhaust valve closure, partly latent refutes continuation dive, and 7m is absorbed water in dive to tub component, now, Atmospheric pressure in Long Circle staving is the air gauge on 1.38 atmospheric pressure, inspection operation platform, checks whether air pressure is normal, Observation have no change within 8-12 minute, normally after, partly latent refutes continuation dive, and dive to tub component is swum, and treats that a barrel bottom is refuted from partly latent Clamping plate face when being 0.8-1.2m, check tub component whether there is inclinations, using inflation ship leveling tub component, tub component is floating After trip is stable, freeboard region is 0m-1.5m, then by inflating the freeboard of ship and exhaust valve regulation tub component extremely 0.8m;
(3) tub component undocks:After tub component swims stabilization, tub component is connected to by main dragging ship synchronous Intersection hawser, synchronous partly latent of releasing refutes hawser between rear portion and tub component rear portion, tub component slowly pulled out into partly latent Refute, during pull-out pass through adjust pull hawser tightness, it is ensured that tub component it is steady;
(4) tub component is drawn to foundation trench:After tub component hauling-out partly latent is refuted, continue to shrink tub component and main dragging ship Between intersection hawser to both apart from 40-60m, meanwhile, tense partly latent and refute hawser between anterior and tub component rear portion, solution Open tub component rear portion and partly latent refute hawser between rear portion, main dragging ship by windlass receive anchor hawser it is slow by tub component bring to In foundation trench, connection tub component and 2 hawsers between tail ship are adjusted, untie partly latent and refute hawser between tub component;
(5) pulled in tub component foundation trench:During high tide level, tub component is drawn in foundation trench, it is anterior to be pulled by main Ship receives anchor hawser, and rear portion is slowly moved to away from installation site 90-110m by adjusting tail ship stable, and along foundation trench, reconnects tub structure 2 between part rear portion and station keeping ship middle part intersect hawser, and the two ends of station keeping ship are connected with positioning anchor by intersecting hawser, passed through It is main pull between ship and tub component, the posture for intersecting hawser adjustment tub component between station keeping ship and tub component, make length The long axis direction of circular staving is vertical with foundation trench, unties tub component and adjusts the hawser between tail ship, and by tub component along base Groove is slowly pulled to away from installation site 40-60m;
(6) positioned at the beginning of tub component:At away from installation site 40-60m, tub component is kept posture, wait ebb, When the bottom of tub component is away from mud face 1.3-1.7m, main dragging ship and station keeping ship drive tub component to installation site, tense It is main to pull between ship and tub component, intersect hawser between station keeping ship and tub component, now, tub component and station keeping ship, Point-blank, not timing monitoring tub member position deviation passes through the cross lines on the ship of folding and unfolding two at the main center for pulling ship Tub component is pulled to normotopia by rope, waits ebb;
(7) it is accurately positioned, is vented sinking:Tidal level declines, when the bottom of tub component is away from mud face 0.5-0.8m, starts It is accurately positioned, according to the position deviation of tub component, is adjusted by the hawser that intersects between two ships and tub component, in essence It is determined that while position, the air bleeding valve on opening operation platform, tub component starts to sink under Gravitative Loads, is noted in sinking watching The balance of meaning tub component, observes GPS readings, when the elevation difference of tub component everywhere is more than 15cm, passes through the row of control Tolerance is carried out after leveling, balance, resynchronisation exhaust;
(8) tub component drainage sink:Exhaust sinks down into tub component and touched after mud, closes air bleeding valve, unties main dragging ship The intersection hawser on tub component is connected to station keeping ship, draining pump is opened, it is ensured that the draining pump in each cabin all normal works, Continue to observe GPS readings during drainage sink, when absolute altitude differs 15cm, leveling is carried out by controlling displacement, is balanced Afterwards, continue synchronous draining, negative pressure is sunk, until bucket enters mud 2.0-3.0m, close each draining pump, sinking operation is completed.
The technical problems to be solved by the invention can also further be realized by following technical scheme, the hawser Front section connect nylon cable.
The technical problems to be solved by the invention can also further be realized by following technical scheme, station keeping ship two The span that end intersects the positioning anchor on hawser is more than 200m.
The present invention coordinates the Pang of tub component by being pulled between tub component and auxiliary ship station by hawser Large-tonnage, realizes leveling of the tub component in air supporting and installation process;By double ships to drawing, rationally control on every station keeping ship Windlass, improve tub component positioning sinking precision, by intersect hawser intersection folding and unfolding act on, tub component can be made steady Ground carries out position adjustment, realizes precise positioning;In addition, by the GPS data collection device on four angles of operating platform, obtaining tub The motion conditions of component, pass through draining pump and air bleeding valve, centralized management draining, exhaust, under the air supporting for fully meeting tub component Heavy operation requires that operating personnel can be achieved with exhaust outlet on the operational platform, and monitoring cost is low, additionally it is possible to adapt to pipeline The actual conditions such as many, circuit is miscellaneous.Compared with prior art, its is reasonable in design, simple in construction, not only can in time, accurately grasp Balance, improves delivery and installation effectiveness, moreover it is possible to constructed under severe weather conditions.
Brief description of the drawings
Fig. 1 is the structural representation of tub component;
Fig. 2 is Fig. 1 front view;
Fig. 3 is step(5)The middle main operating diagram for pulling ship and station keeping ship.
Embodiment
The concrete technical scheme of the present invention is further described, in order to which those skilled in the art is further understood that this hair It is bright, without constituting the limitation to its right.
A kind of reference picture 1-3, installation method of breakwater tub component, described tub component includes the bottomless length for having a lid Circular staving 1 and two anti-ripple stavings 9 for being located at the top of Long Circle staving 1, short axle side of the anti-ripple staving 9 along Long Circle staving 1 To arrangement, by twice, the separation of partition wall 2 has 9 separations 3 to the Long Circle staving 1 in length and breadth, and the top of each separation 3 is equipped with row Stomata 4 and osculum 6, two anti-restockings of ripple staving 9 are provided with operating platform 10, and four angles of operating platform 10 are provided with collection bucket Body motion and the GPS data collection device 8 of discrepancy in elevation data, operating platform 10 is provided with to be corresponded with the steam vent 4 at the top of separation 3 Air bleeding valve 12, steam vent 4 connected by discharge duct 5 with air bleeding valve 12, and the both sides of operating platform 10 are respectively provided with several rows of water Pump 11, the osculum 6 at the top of separation 3 is connected by drainage pipeline 7 with draining pump 11, and its step is,
(1) preparation of construction:
1.1 partly latents refute positioning:The marine site of tub component is being installed, when the sea water advanced partly latent that can not meet refutes dive to tub When component swims, the dive hole that dive is refuted for partly latent is dug, partly latent is refuted to be positioned in dive hole towards installation site, has been positioned Into defining partly latent and refute outlet port and refute front portion with tub component for partly latent;
1.2 auxiliary ship stations are in place:Tail ship, 1 station keeping ship, 3 anchor ships, 3 Liners are adjusted including 1 main dragging ship, 1 Oceangoing ship, 1 inflation ship;
The main ship that pulls is the crane ship not less than 100t, and beam requirement is in more than 20m, at least 6 windlass 14;
It is self-propulsion type ship to adjust tail ship, it is desirable to is refuted for flat board, there is 5 windlass;
Station keeping ship is refuted for flat board, at least 6 windlass 14;
Inflation ship is connected by gas ducting with the steam vent on Long Circle staving each separation;
1.3 reserve four draw rings in the root of tub component, the front and rear part of Long Circle staving are symmetrically arranged at, before partly latent is refuted Be connected with two hawsers in left and right between the draw ring at portion and tub component rear portion, partly latent refute rear portion and tub component rear portion draw ring it Between be connected with two hawsers in left and right, connection two intersects hawser between the anterior draw ring of tub component and main dragging ship;
(2) partly latent refutes dive:While partly latent refutes dive, the air bleeding valve on start-up operation platform, dive to tub component 0.8m is absorbed water, drinking water height is vented height for tub component air supporting stability Calculation, and control errors are treated in tub component in ± 5cm After gas is drained, air bleeding valve is closed;After exhaust valve closure, partly latent refutes continuation dive, and 7m is absorbed water in dive to tub component, now, Atmospheric pressure in Long Circle staving is the air gauge on 1.38 atmospheric pressure, inspection operation platform, checks whether air pressure is normal, Observation have no change within 8-12 minute, normally after, partly latent refutes continuation dive, and dive to tub component is swum, and treats that a barrel bottom is refuted from partly latent Clamping plate face when being 0.8-1.2m, check tub component whether there is inclinations, using inflation ship leveling tub component, tub component is floating After trip is stable, freeboard region is 0m-1.5m, then by inflating the freeboard of ship and exhaust valve regulation tub component extremely 0.8m;
(3) tub component undocks:After tub component swims stabilization, tub component is connected to by main dragging ship synchronous Intersection hawser, synchronous partly latent of releasing refutes hawser between rear portion and tub component rear portion, tub component slowly pulled out into partly latent Refute, during pull-out pass through adjust pull hawser tightness, it is ensured that tub component it is steady;
(4) tub component is drawn to foundation trench:After tub component hauling-out partly latent is refuted, continue to shrink tub component and main dragging ship Between intersection hawser to both apart from 40-60m, meanwhile, tense partly latent and refute hawser between anterior and tub component rear portion, solution Open tub component rear portion and partly latent refute hawser between rear portion, main dragging ship by windlass receive anchor hawser it is slow by tub component bring to In foundation trench, connection tub component and 2 hawsers between tail ship are adjusted, untie partly latent and refute hawser between tub component;
(5) pulled in tub component foundation trench:During high tide level, tub component is drawn in foundation trench, it is anterior to be pulled by main Ship receives anchor hawser, and rear portion is slowly moved to away from installation site 90-110m by adjusting tail ship stable, and along foundation trench, reconnects tub structure 2 between part rear portion and the middle part of station keeping ship 13 intersect hawser, and the two ends of station keeping ship 13 are connected with positioning anchor by intersecting hawser, Pass through the appearance for intersecting hawser adjustment tub component between main dragging ship 15 and tub component, between station keeping ship 13 and tub component State, makes the long axis direction of Long Circle staving vertical with foundation trench, unties tub component and adjusts the hawser between tail ship, and by tub structure Part is slowly pulled to away from installation site 40-60m along foundation trench;
(6) positioned at the beginning of tub component:At away from installation site 40-60m, tub component is kept posture, wait ebb, when When the bottom of tub component is away from mud face 1.3-1.7m, main dragging ship 15 and station keeping ship 13 drive tub component to installation site, draw It is tight it is main pull between ship 15 and tub component, intersect hawser between station keeping ship 13 and tub component, now, tub component with it is fixed Point-blank, not timing monitors tub member position deviation, by the ship of folding and unfolding two for position ship 13, the main center for pulling ship 15 Intersection hawser tub component is pulled to normotopia, wait ebb;
(7) it is accurately positioned, is vented sinking:Tidal level declines, when the bottom of tub component is away from mud face 0.5-0.8m, starts essence It is determined that position, according to the position deviation of tub component, is adjusted, accurate by the hawser that intersects between two ships and tub component While positioning, the air bleeding valve on opening operation platform, tub component starts to sink under Gravitative Loads, notes in sinking watching The balance of tub component, observes GPS readings, when the elevation difference of tub component everywhere is more than 15cm, by controlling to be vented Measure to carry out after leveling, balance, resynchronisation exhaust;
(8) tub component drainage sink:Exhaust sinks down into tub component and touched after mud, closes air bleeding valve, unties main dragging ship The intersection hawser on tub component is connected to station keeping ship, draining pump is opened, it is ensured that the draining pump in each cabin all normal works, Continue to observe GPS readings during drainage sink, when tub component absolute altitude everywhere differs 15cm, by control displacement come Carry out after leveling, balance, continue synchronous draining, negative pressure is sunk, until bucket enters mud 2.0-3.0m, close each draining pump, sink to making Industry is completed.
The front section of the hawser connects nylon cable, and the span that station keeping ship two ends intersect between the positioning anchor on hawser is more than 200m。

Claims (3)

1. a kind of installation method of breakwater tub component, described tub component has the Long Circle staving of lid and set including bottomless Two anti-ripple stavings above Long Circle staving, short-axis direction arrangement of the anti-ripple staving along Long Circle staving, the Long Circle By twice, partition wall separates and has steam vent and osculum are equipped with the top of 9 separations, each separation staving in length and breadth, two anti-ripples Staving restocking is provided with operating platform, and gps data of four angles provided with the motion of collection staving and discrepancy in elevation data of operating platform is received Storage, operating platform is provided with passes through discharge duct and row with the one-to-one air bleeding valve of steam vent at the top of separation, steam vent Air valve connects, and the osculum that the both sides of operating platform are respectively provided with the top of several rows of water pump, separation passes through drainage pipeline and draining pump Connect, it is characterised in that:Its step is,
(1)Preparation of construction:
1.1 partly latents refute positioning:The marine site of tub component is being installed, when the sea water advanced partly latent that can not meet refutes dive to tub component When swimming, the dive hole that dive is refuted for partly latent is dug, partly latent is refuted to be positioned in dive hole towards installation site, and positioning is completed, Define partly latent and refute outlet port and refute front portion with tub component for partly latent;
1.2 auxiliary ship stations are in place:Tail ship, 1 station keeping ship, 3 anchor ships, 3 band cable ships, 1 are adjusted including 1 main dragging ship, 1 Bar inflates ship;
The main ship that pulls is the crane ship not less than 100t, and beam requirement is in more than 20m, at least 6 windlass;
It is self-propulsion type ship to adjust tail ship, it is desirable to is refuted for flat board, there is 5 windlass;
Station keeping ship is refuted for flat board, at least 6 windlass;
Inflation ship is connected by gas ducting with the steam vent on Long Circle staving each separation;
1.3 reserve four draw rings in the root of tub component, are symmetrically arranged at the front and rear part of Long Circle staving, and partly latent refutes anterior and bucket Two hawsers in left and right are connected between the draw ring at formula component rear portion, partly latent is connected between refuting the draw ring at rear portion and tub component rear portion There are two hawsers in left and right, connection two intersects hawser between the anterior draw ring of tub component and main dragging ship;
(2) partly latent refutes dive:While partly latent refutes dive, the air bleeding valve on start-up operation platform, dive to tub component is absorbed water 0.8m, drinking water height is vented height for tub component air supporting stability Calculation, and control errors treat gas in tub component in ± 5cm After drained, air bleeding valve is closed;After exhaust valve closure, partly latent refutes continuation dive, and 7m is absorbed water in dive to tub component, now, oval Atmospheric pressure in shape staving is the air gauge on 1.38 atmospheric pressure, inspection operation platform, checks whether air pressure is normal, is observed Have no change within 8-12 minutes, it is normal after, partly latent refutes continuation dive, and dive to tub component is swum, and treats barrel bottom from the folder that partly latent is refuted When plate face is 0.8-1.2m, check tub component whether there is inclination, using inflation ship leveling tub component, tub component swims surely After fixed, freeboard region is 0m-1.5m, then by inflating the freeboard of ship and exhaust valve regulation tub component extremely 0.8m;
(3) tub component undocks:After tub component swims stabilization, the friendship of tub component is connected to by main dragging ship synchronous Hawser is pitched, synchronous releasing partly latent refutes the hawser between rear portion and tub component rear portion, tub component is slowly pulled out into partly latent and refuted, is drawn When going out pass through adjust pull hawser tightness, it is ensured that tub component it is steady;
(4) tub component is drawn to foundation trench:After tub component hauling-out partly latent is refuted, continue to shrink between tub component and main dragging ship Intersection hawser to both apart from 40-60m, meanwhile, tense partly latent and refute hawser between anterior and tub component rear portion, untie bucket Formula component rear portion and partly latent refute the hawser between rear portion, and main dragging ship slowly brings tub component to foundation trench by windlass receipts anchor hawser It is interior, connection tub component and 2 hawsers between tail ship are adjusted, untie partly latent and refute hawser between tub component;
(5) pulled in tub component foundation trench:During high tide level, tub component is drawn in foundation trench, it is anterior to be received by main dragging ship Anchor hawser, rear portion is slowly moved to away from installation site 90-110m by adjusting tail ship stable, and along foundation trench, is reconnected after tub component 2 between portion and station keeping ship middle part intersect hawser, and the two ends of station keeping ship are connected with positioning anchor by intersecting hawser, are dragged by master Drag between ship and tub component, intersect the posture that hawser adjusts tub component between station keeping ship and tub component, make Long Circle The long axis direction of staving is vertical with foundation trench, unties tub component and adjusts the hawser between tail ship, and tub component is delayed along foundation trench Slowly it is pulled to away from installation site 40-60m;
(6) positioned at the beginning of tub component:At away from installation site 40-60m, tub component is kept posture, wait ebb, work as tub When the bottom of component is away from mud face 1.3-1.7m, main dragging ship and station keeping ship drive tub component to installation site, tense main pull Intersect hawser between ship and tub component, between station keeping ship and tub component, now, tub component and station keeping ship, main dragging The center of ship point-blank, not timing monitoring tub member position deviation, by the intersection hawser on the ship of folding and unfolding two by bucket Formula component is pulled to normotopia, waits ebb;
(7) it is accurately positioned, is vented sinking:Tidal level declines, when the bottom of tub component is away from mud face 0.5-0.8m, and it is accurate fixed to start Position, according to the position deviation of tub component, is adjusted by the hawser that intersects between two ships and tub component, is being accurately positioned While, the air bleeding valve on opening operation platform, tub component starts to sink under Gravitative Loads, and tub is noted in sinking watching The balance of component, observe GPS readings, when the elevation difference of tub component everywhere be more than 15cm when, by control capacity come Carry out after leveling, balance, resynchronisation exhaust;
(8) tub component drainage sink:Exhaust sinks down into tub component and touched after mud, closes air bleeding valve, unties main dragging ship and fixed Position ship is connected to the intersection hawser on tub component, opens draining pump, it is ensured that the draining pump in each cabin all normal works, draining Continue to observe GPS readings in sinking watching, when absolute altitude differs 15cm, carried out by controlling displacement after leveling, balance, after Continuous synchronization draining, negative pressure is sunk, until bucket enters mud 2.0-3.0m, closes each draining pump, sinking operation is completed.
2. the installation method of breakwater tub component according to claim 1, it is characterised in that:The leading portion portion of the hawser Tap nylon cable.
3. the installation method of breakwater tub component according to claim 1, it is characterised in that:Station keeping ship two ends cross lines The span between positioning anchor on rope is more than 200m.
CN201610197611.9A 2016-03-31 2016-03-31 A kind of installation method of breakwater tub component Active CN105862896B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610197611.9A CN105862896B (en) 2016-03-31 2016-03-31 A kind of installation method of breakwater tub component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610197611.9A CN105862896B (en) 2016-03-31 2016-03-31 A kind of installation method of breakwater tub component

Publications (2)

Publication Number Publication Date
CN105862896A CN105862896A (en) 2016-08-17
CN105862896B true CN105862896B (en) 2017-10-13

Family

ID=56626674

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610197611.9A Active CN105862896B (en) 2016-03-31 2016-03-31 A kind of installation method of breakwater tub component

Country Status (1)

Country Link
CN (1) CN105862896B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112814002A (en) * 2020-12-25 2021-05-18 中交第三航务工程局有限公司江苏分公司 Open caisson and negative pressure sinking construction process thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10299020A (en) * 1997-04-22 1998-11-10 Penta Ocean Constr Co Ltd Installation and sinking method for underwater structure and its equipment
CN1730842A (en) * 2005-09-07 2006-02-08 天津大学 Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure
CN102322062A (en) * 2011-06-17 2012-01-18 中交第三航务工程局有限公司 Transportation and installation process of base barrel body of barrel type breakwater
CN202139570U (en) * 2011-04-25 2012-02-08 中交第三航务工程勘察设计院有限公司 Seawall structure with adsorption type thin-wall reinforced concrete oval barrel type foundation up-right cap-shaped continuous wall
CN202577229U (en) * 2012-05-02 2012-12-05 中交第三航务工程勘察设计院有限公司 Foundation bulkhead wall structure
CN202787291U (en) * 2012-07-13 2013-03-13 中交二公局第一工程有限公司 Main pier steel cover box on-site two-abreast-machine hoisting construction structure
CN103334442A (en) * 2013-07-10 2013-10-02 中交路桥华南工程有限公司 Method and structure for connecting cofferdams in vertically rotating mode
CN103382713A (en) * 2012-05-02 2013-11-06 中交第三航务工程勘察设计院有限公司 Foundation quay wall structure and construction method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10299020A (en) * 1997-04-22 1998-11-10 Penta Ocean Constr Co Ltd Installation and sinking method for underwater structure and its equipment
CN1730842A (en) * 2005-09-07 2006-02-08 天津大学 Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure
CN202139570U (en) * 2011-04-25 2012-02-08 中交第三航务工程勘察设计院有限公司 Seawall structure with adsorption type thin-wall reinforced concrete oval barrel type foundation up-right cap-shaped continuous wall
CN102322062A (en) * 2011-06-17 2012-01-18 中交第三航务工程局有限公司 Transportation and installation process of base barrel body of barrel type breakwater
CN202577229U (en) * 2012-05-02 2012-12-05 中交第三航务工程勘察设计院有限公司 Foundation bulkhead wall structure
CN103382713A (en) * 2012-05-02 2013-11-06 中交第三航务工程勘察设计院有限公司 Foundation quay wall structure and construction method thereof
CN202787291U (en) * 2012-07-13 2013-03-13 中交二公局第一工程有限公司 Main pier steel cover box on-site two-abreast-machine hoisting construction structure
CN103334442A (en) * 2013-07-10 2013-10-02 中交路桥华南工程有限公司 Method and structure for connecting cofferdams in vertically rotating mode

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
桶式结构定位下沉施工及监控;夏俊桥 等;《中国港湾建设》;20160325;第36卷(第3期);第73-77页 *
桶式结构运输出运工艺;秦丹 等;《中国港湾建设》;20160325;第36卷(第3期);第69-72页 *

Also Published As

Publication number Publication date
CN105862896A (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN102322062B (en) Transportation and installation process of base barrel body of barrel type breakwater
DE69938294T2 (en) SEA BUILDING
CN101920766B (en) Shipbuilding method
US6539888B1 (en) Working ship
CN102251530B (en) Construction process of double-wall steel cofferdam for construction of pier bearing platform in main river water of Yellow River
CN101920771B (en) Method for undock ballasting in ship building
CN204527563U (en) Middle deep water semi-submersible drilling platform
CN106573665A (en) Floating structure and method of installing same
CN106687368A (en) Floating substructure for a wind generator and method of installing same
CN105000137B (en) Covering of the fan revolution single point mooring transfusion system
CN105151236A (en) Platform device for submerging, surfacing, moving and carrying floating piers and towers and working method thereof
CN106801431B (en) A kind of three rise gantry type wind power foundation structure and its construction method certainly
CN109403365A (en) Unmanned caisson goes out safely fortune system and goes out fortune technique
CN105003232B (en) A kind of ultra-deep sea marine oil and gas dry type production system and its installation evacuation method
CN105253270B (en) One kind combination floating box type maritime platform launching gear and maritime platform launching method
CN105862896B (en) A kind of installation method of breakwater tub component
CN108755644A (en) Transfer platform and its installation method for intertidal zone land cable drawing
CN207392285U (en) A kind of grid type gas disturbs river mouth mud scum dredger
CN103374905B (en) Movable self-installation platform
EP3147408A1 (en) Marine foundation and construction method thereof
CN104060592B (en) Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles
CN105862658B (en) A kind of double ships of breakwater tub component are to drawing localization method
CN109403422A (en) A kind of cruise-type cultivation work ship cold water mass water intake system
CN206218146U (en) Offshore operation at sea platform
CN106939613B (en) A kind of four rise gantry type wind power foundation structure and its construction method certainly

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230927

Address after: No. 147, Zhongshan Middle Road, Lianyun District, Lianyungang City, Jiangsu Province

Patentee after: JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co.,Ltd.

Patentee after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Address before: No. 147, Zhongshan Middle Road, Lianyun District, Lianyungang City, Jiangsu Province

Patentee before: JIANGSU BRANCH OF CCCC SHANGHAI PORT ENGINEERING Co.,Ltd.

TR01 Transfer of patent right