CN202787291U - Main pier steel cover box on-site two-abreast-machine hoisting construction structure - Google Patents

Main pier steel cover box on-site two-abreast-machine hoisting construction structure Download PDF

Info

Publication number
CN202787291U
CN202787291U CN 201220340272 CN201220340272U CN202787291U CN 202787291 U CN202787291 U CN 202787291U CN 201220340272 CN201220340272 CN 201220340272 CN 201220340272 U CN201220340272 U CN 201220340272U CN 202787291 U CN202787291 U CN 202787291U
Authority
CN
China
Prior art keywords
pier
crane barge
floating crane
main pier
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220340272
Other languages
Chinese (zh)
Inventor
孙鹏
李新形
潘中明
赵军科
田新平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHB First Engineering Co Ltd
Original Assignee
CCCC SHB First Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHB First Engineering Co Ltd filed Critical CCCC SHB First Engineering Co Ltd
Priority to CN 201220340272 priority Critical patent/CN202787291U/en
Application granted granted Critical
Publication of CN202787291U publication Critical patent/CN202787291U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a main pier steel cover box on-site two-abreast-machine hoisting construction structure which comprises a main pier, an auxiliary pier and a transition pier. A temporary pier is arranged between the main pier and the auxiliary pier, and the center axes of the main pier, the auxiliary pier, the transition pier and the temporary pier are the same line. A first floating crane and a second floating crane are symmetrically arranged on two sides of the temporary pier in parallel, and the first floating crane and the second floating crane are respectively provided with four mooring anchors. A first mooring anchor of the first floating crane and a second mooring anchor of the second floating crane are arranged in parallel corresponding to floating crane ship bodies. The floating crane ship bodies are fixedly arranged, and transport ships are arranged between the floating crane ship bodies and the main pier. The transport ships are fixedly connected with positioning ships. The main pier steel cover box on-site two-abreast-machine hoisting construction structure is simple in structure, novel in design, effectively solves the problems of bulk mass and large-tonnage installation of steel cover boxes on the condition of limited construction plants due to the fact that the steel cover boxes are moved forwards through two parallel crane machines, and is high in construction speed and installation accuracy, and has good economical benefit and social benefit.

Description

The on-the-spot two-shipper of a kind of main pier steel jacket box lifts constructing structure side by side
Technical field
The utility model relates to the bridge foundation construction technical field, refers to that particularly the on-the-spot two-shipper of a kind of main pier steel jacket box lifts constructing structure side by side.
Background technology
The basic crane barge integral hoisting method that adopts of most domestic offshore pile cap steel sleeve box lifting.Weight size according to steel jacket box adopts the lifting of suitable single crane hoisting and two-shipper.Construction area do not have other obstacles prerequisite under, above-mentioned two kinds of methods all can realize along bridge to or direction across bridge move, and then with the steel jacket box hoisted in position.But because construction environment tends to be provided with different obstacles, such as: in main channel, do not allow constructing operation, main pier steel jacket box can only be chosen in the auxiliary pier side and lift, and auxiliary pier lateral extent master pier has been provided with a steel pipe pile Temporary Piers nearby, lifting has formed barrier one to steel jacket box, the crane barge direction across bridge moves and can't realize, can only move along the bridge, and the steel jacket box construction hoisting is caused difficulty.
The utility model content
The purpose of this utility model is exactly for the deficiency of above-mentioned background technology, to provide the on-the-spot two-shipper of a kind of main pier steel jacket box to lift side by side constructing structure.
The technical solution of the utility model is: the on-the-spot two-shipper of a kind of main pier steel jacket box lifts constructing structure side by side, comprise main pier, auxiliary pier and transition pier, be provided with Temporary Piers between described main pier and the auxiliary pier, main pier, auxiliary pier, the central axis of transition pier and Temporary Piers is same straight line, parallel the first crane barge and the second crane barge of being provided with of described Temporary Piers bilateral symmetry, the first crane barge and the second crane barge are equipped with four mooring anchors, it is characterized in that: the first mooring anchor in the first crane barge and the second mooring anchor in the second crane barge respectively corresponding crane barge hull with the first crane barge and the second crane barge be arranged in parallel, described crane barge hull is fixedly installed, be provided with cargo ship between crane barge hull and the main pier, cargo ship is fixedly connected with station keeping ship.
The crane barge hull of described the first crane barge and the second crane barge is fixed by the wire rope colligation, avoids crane barge hull side shifting outside Temporary Piers.
Operating principle of the present utility model is:
Four mooring anchors that pass through of the first crane barge and the second crane barge realize that symmetrical parallel is arranged on the Temporary Piers both sides, then again the first mooring anchor in the first crane barge and the second mooring anchor in the second crane barge are weighed anchor and again cast anchor, make it corresponding parallel with the crane barge hull of the first crane barge and the second crane barge respectively.Drive the cargo ship that is fixedly connected with station keeping ship by the station keeping ship that is positioned at for the first time the arbitrary side in Temporary Piers both sides subsequently, realize cargo ship is fixedly installed between crane barge hull and the main pier.After erecting tools on the cargo ship installed, station keeping ship was dragged to cargo ship and withdraws the job site.After steel jacket box base plate height surpassed casing top certain altitude, the first crane barge and the second crane barge twisted the reach of anchor pine anchor simultaneously, slowly carry out when mobile, when moving to directly over the desired location, it is fixing that mooring anchor is cast anchor, and at this moment, can carry out the lifting construction of steel jacket box.
The utility model is simple in structure, modern design is installed steel jacket box by adopting two-shipper to lift side by side along bridge to reach, efficiently solves the installation of large volume under the confined condition of construction plant, large-tonnage steel casing, and speed of application is fast, installation accuracy is high, and good economic benefit and social benefit are arranged.
Description of drawings
Fig. 1 is overall structure schematic diagram before the utility model uses.
Overall structure schematic diagram when Fig. 2 is the utility model work.
The specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments, is convenient to be well understood to the utility model, but they do not consist of restriction to the utility model.
As shown in Figure 1, the on-the-spot two-shipper of a kind of main pier steel jacket box lifts constructing structure side by side, comprise main pier 1, auxiliary pier 2 and transition pier 3, be provided with Temporary Piers 4 between main pier 1 and the auxiliary pier 2, main pier 1, auxiliary pier 2, the central axis of transition pier 3 and Temporary Piers 4 is same straight line, parallel the first crane barge 5 and the second crane barge 6 of being provided with of Temporary Piers 4 bilateral symmetry, the first crane barge 5 and the second crane barge 6 are equipped with four mooring anchors, the first mooring anchor 5.1 in the first crane barge 5 and the second mooring anchor 6.1 in the second crane barge 6 respectively corresponding crane barge hull 5.2 and 6.2 with the first crane barge 5 and the second crane barge 6 be arranged in parallel, crane barge hull 5.2 and 6.2 is realized fixing by the wire rope colligation, can avoid like this crane barge hull 5.2 and 6.2 to Temporary Piers 4 outer side shiftings.Crane barge hull 5.2 and 6.2 and main pier 1 between be provided with cargo ship 7, cargo ship 7 is dragged to desired location by station keeping ship 8, and realizes fixing by station keeping ship 8.
The operating principle of present embodiment is:
Four mooring anchors that pass through of the first crane barge 5 and the second crane barge 6 realize that symmetrical parallel is arranged on the Temporary Piers both sides, then again the first mooring anchor 5.1 in the first crane barge 5 and the second mooring anchor 6.1 in the second crane barge 6 are weighed anchor and again cast anchor, make it corresponding parallel with the crane barge hull of the second crane barge 6 with the first crane barge 5 respectively.Drive the cargo ship 7 that is fixedly connected with station keeping ship 8 by the station keeping ship 8 that is positioned at for the first time the arbitrary side in Temporary Piers 4 both sides subsequently, realize cargo ship 7 is fixedly installed between crane barge hull and the main pier 1.After erecting tools on the cargo ship 7 installed, station keeping ship 8 was dragged to cargo ship 7 and withdraws job site (as shown in Figure 2).After steel jacket box base plate height surpassed casing top certain altitude, the first crane barge 5 and the second crane barge 6 twisted the reach of anchor pine anchor simultaneously, slowly carry out when mobile, when moving to directly over the desired location, it is fixing that mooring anchor is cast anchor, and at this moment, can carry out the lifting construction of steel jacket box.
Present embodiment is simple in structure, modern design is installed steel jacket box by adopting two-shipper to lift side by side along bridge to reach, efficiently solves the installation of large volume under the confined condition of construction plant, large-tonnage steel casing, and speed of application is fast, installation accuracy is high, and good economic benefit and social benefit are arranged.

Claims (2)

1. the on-the-spot two-shipper of main pier steel jacket box lifts constructing structure side by side, comprise main pier, auxiliary pier and transition pier, be provided with Temporary Piers between described main pier and the auxiliary pier, main pier, auxiliary pier, the central axis of transition pier and Temporary Piers is same straight line, parallel the first crane barge and the second crane barge of being provided with of described Temporary Piers bilateral symmetry, the first crane barge and the second crane barge are equipped with four mooring anchors, it is characterized in that: the first mooring anchor in the first crane barge and the second mooring anchor in the second crane barge respectively corresponding crane barge hull with the first crane barge and the second crane barge be arranged in parallel, described crane barge hull is fixedly installed, be provided with cargo ship between crane barge hull and the main pier, cargo ship is fixedly connected with station keeping ship.
2. the on-the-spot two-shipper of a kind of main pier steel jacket box according to claim 1 lifts constructing structure side by side, and it is characterized in that: the crane barge hull of described the first crane barge and the second crane barge is fixed by the wire rope colligation.
CN 201220340272 2012-07-13 2012-07-13 Main pier steel cover box on-site two-abreast-machine hoisting construction structure Expired - Fee Related CN202787291U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220340272 CN202787291U (en) 2012-07-13 2012-07-13 Main pier steel cover box on-site two-abreast-machine hoisting construction structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220340272 CN202787291U (en) 2012-07-13 2012-07-13 Main pier steel cover box on-site two-abreast-machine hoisting construction structure

Publications (1)

Publication Number Publication Date
CN202787291U true CN202787291U (en) 2013-03-13

Family

ID=47814573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220340272 Expired - Fee Related CN202787291U (en) 2012-07-13 2012-07-13 Main pier steel cover box on-site two-abreast-machine hoisting construction structure

Country Status (1)

Country Link
CN (1) CN202787291U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113508A (en) * 2015-09-11 2015-12-02 中交公路长大桥建设国家工程研究中心有限公司 Positioning, sinking and controlling system for large-scale bridge deepwater prefabricated foundation
CN105862896A (en) * 2016-03-31 2016-08-17 中交第三航务工程局有限公司江苏分公司 Mounting method of breakwater barrel type component
CN105862658A (en) * 2016-03-31 2016-08-17 中交第三航务工程局有限公司江苏分公司 Double-ship counter-pulling positioning method of breakwater barrel type component

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113508A (en) * 2015-09-11 2015-12-02 中交公路长大桥建设国家工程研究中心有限公司 Positioning, sinking and controlling system for large-scale bridge deepwater prefabricated foundation
CN105862896A (en) * 2016-03-31 2016-08-17 中交第三航务工程局有限公司江苏分公司 Mounting method of breakwater barrel type component
CN105862658A (en) * 2016-03-31 2016-08-17 中交第三航务工程局有限公司江苏分公司 Double-ship counter-pulling positioning method of breakwater barrel type component
CN105862896B (en) * 2016-03-31 2017-10-13 中交第三航务工程局有限公司江苏分公司 A kind of installation method of breakwater tub component
CN105862658B (en) * 2016-03-31 2018-04-17 中交第三航务工程局有限公司江苏分公司 A kind of double ships of breakwater tub component are to drawing localization method

Similar Documents

Publication Publication Date Title
CN102425167B (en) Pile sinking method for driving large-diameter steel pipe pile in intertidal zone
CN104631481B (en) A kind of open caisson mooring positioning device and construction method thereof
CN102767176A (en) Hoisting positioning construction method of pile foundation steel reinforcement cage
CN106218827A (en) Offshore wind farm O&M supports platform
CN202787291U (en) Main pier steel cover box on-site two-abreast-machine hoisting construction structure
CN101487233B (en) Mounting method for temporary pier top beam of large-span steel box girder stayed-cable bridge
CN104790400B (en) Water conservancy dam gate water surface transportation and installation device and application method thereof
CN201991011U (en) Hoisting and releasing system for construction of underwater pier bearing platform double-wall steel cofferdam
CN102826459B (en) Method for hoisting underwater structural part of ocean platform
CN202689016U (en) Cofferdam assembling and lifting platform for double-wall steel cofferdam construction of deep-water bridge pier
CN102852095A (en) Prefabricated bridge abutment multifunctional lifting system and construction procedure thereof
CN101806053A (en) Integral installation method of cantilever beams of self lifting type well drilling platform
CN204456106U (en) Waters pile sinking mobile guide station keeping ship
CN102206938A (en) Novel method for installing upper part block of offshore platform
CN103121627A (en) One-step type lifting system for wind power installation vessel and wind power installation vessel provided with same
CN102381438A (en) Wholly lifting mounting method for wholly built upstairs stem section of large-size semi-submerged ship
CN201971133U (en) Bottom-supported blower installation platform
CN102071652B (en) Method and device for dragging large-tonnage object ashore
CN202688882U (en) Cofferdam lowering positioning platform for double-wall steel cofferdam construction of deep-water bridge pier
CN202953142U (en) Steel cylinder transportation equipment
CN203682931U (en) Wharf building crane
CN105239572A (en) Offshore construction method for large-diameter single pile fan foundation structure
CN204224987U (en) A kind of continuous girder bridge multiple pipeline installation structure
CN105129632A (en) Grid-type steel sheet pile large cylinder main grid installation construction special-purpose crane ship
CN102877476B (en) Positioning and constructing method of steel cofferdam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130313

Termination date: 20180713

CF01 Termination of patent right due to non-payment of annual fee