CN108755644A - Transfer platform and its installation method for intertidal zone land cable drawing - Google Patents

Transfer platform and its installation method for intertidal zone land cable drawing Download PDF

Info

Publication number
CN108755644A
CN108755644A CN201810742114.1A CN201810742114A CN108755644A CN 108755644 A CN108755644 A CN 108755644A CN 201810742114 A CN201810742114 A CN 201810742114A CN 108755644 A CN108755644 A CN 108755644A
Authority
CN
China
Prior art keywords
buoyancy tank
transfer platform
cable
land
machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810742114.1A
Other languages
Chinese (zh)
Other versions
CN108755644B (en
Inventor
董立军
柴宝亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Haixing Ocean Engineering Co Ltd
Original Assignee
Tianjin Haixing Ocean Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Haixing Ocean Engineering Co Ltd filed Critical Tianjin Haixing Ocean Engineering Co Ltd
Priority to CN201810742114.1A priority Critical patent/CN108755644B/en
Publication of CN108755644A publication Critical patent/CN108755644A/en
Application granted granted Critical
Publication of CN108755644B publication Critical patent/CN108755644B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/10Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle in or under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)
  • Ship Loading And Unloading (AREA)

Abstract

The present invention relates to bottom cable laying technical fields, disclose a kind of transfer platform and its installation method for intertidal zone land cable drawing, include for pull cable end be twisted machine, the dragger of cable outer wall is pulled for relay and to be twisted machine, dragger the generator of power supply is provided, it is twisted machine, dragger and generator to be arranged on the same buoyancy tank, and is equipped with the piling bar and cable drawing channel-attached of fixed buoyancy tank.When installation, transport crane barge, land hoist engine and transfer platform the design installation site of transfer platform buoyancy tank point-blank, machine is twisted by land when flood slack and crane barge hoist engine combines transfer platform buoyancy tank being pulled to design installation site, adjusts to carry and sits beach, when low edd slack piling fix.Compared with the conventional method debugged from the transport of land single-piece, Assembling, field device installation procedure is simplified, equipment installation period is shortened, reduces installation cost;Reduce the influence to natural wetland simultaneously.

Description

Transfer platform and its installation method for intertidal zone land cable drawing
Technical field
The present invention relates to bottom cable laying technical fields, in particular to what is pulled for intertidal zone land cable Transfer platform and its installation method.
Background technology
Submarine cable is the important power transmission being connected between Offshore Units and land facility and signal transmission facility.According to Environmental condition where bottom cable laying construction is different, and submarine cable is usually divided into coastal waters section and logs in section.Each section of difference Using different targetedly technical equipments and construction method.The cable laying of coastal waters section carries out deposited buried construction by paving cable ship; Log in the cable laying generally use drawing mode of section:Paving cable ship approaches debarkation point anchoring;The submarine cable on cable ship will be spread End is pulled to land facility terminal along design routing;Then carry out logging in the deposited buried operation of section cable.Log in a section cable laying After completion, paving cable ship carries out coastal waters section cable laying.
A section cable drawing is logged in order to realize, needs logging in a section cable routing ascender line setting cable drawing channel, and It route inflection point in cable and other necessary position setting several groups pull power-equipment.For logging in characterized by dykes and dams Section, segment distance is short between tide, and one group of drawing power-equipment is arranged in the land of no water logging risk.For being with natural beach Feature logs in section, and intertidal zone distance needs to pull power-equipment in intertidal zone arrangement several groups, therefore has water logging risk. In order to avoid water logging equipment, and make cable drawing channel plane absolute altitude when pulling construction period peak level It more than the water surface, needs to set up scaffold temporary operating platform and scaffold access.The cable of intertidal zone pulls channel usually by foot Fixed V-type support roller and H-type support roller composition on channel that hand cradle is set up, the steel plate and steel plate being laid with thereon.The drawing of intertidal zone Power-equipment generally includes to be twisted machine, dragger and generator, dispersion or that concentrates be arranged in scaffold building, upper laying steel On the temporary operating platform of plate.
The monomer weight for being twisted machine, dragger and generator as drawing power-equipment is larger, and handling installation needs Want larger haulage vehicle and crane cooperation.Since natural beach is with a varied topography and muddy, it usually needs on the way pad soil pave the way to Installation site is designed, the needs of the transport of drawing power-equipment and lifting installation could be met.It is this to transport and pacify from land direction The usual way of dress, construction earth volume is big, and by tidal effect, the effective time is short, long in time limit, economic cost and time It is of high cost;In-site installation, contraposition and the debugging for pulling power-equipment simultaneously have also accordingly increased duration and cost;In addition a large amount of Earthwork the ecology of natural wetland can be caused to seriously affect, again repair be also required to sizable time cost and economy Cost.Further, since be limited to drauht, can not will drawing power-equipment from marine direction transport to design installation site into Row installation.
Therefore it provides a kind of intertidal zone logs in a section solution for cable pulling apparatus, become those skilled in the art institute The important technological problems to be solved.
Invention content
The present invention proposes the transfer platform for intertidal zone land cable drawing, and proposes to be used for intertidal zone based on this Land cable pulls the installation method of transfer platform.
As in a first aspect, the present invention proposes, for the transfer platform of intertidal zone land cable drawing, including to be used to pull Cable end be twisted machine, the dragger of cable outer wall is pulled for relay and to be twisted machine, dragger the power generation of power supply is provided Machine is twisted machine, dragger and generator and is arranged on the same buoyancy tank, and be equipped with fixed buoyancy tank piling bar and cable drawing it is logical Road attachment.
The inside configuration of the buoyancy tank is divided into interconnected cabin, and setting no less than makes buoyancy tank have load of setting the tone for one The immersible pump of function;
Two topsides of the buoyancy tank are each to be symmetrical arranged a no less than pile protection cylinder;
Four lifting lifting lugs for connecting Current Collector Sleave are arranged symmetrically on the deck of the buoyancy tank;
The bow stern both ends of the buoyancy tank are each to be symmetrical arranged two drawing lifting lugs for connecting drawing rigging;
The piling bar is temporarily fixed on the deck of buoyancy tank, identical as pile protection cylinder quantity;After transfer platform is in place, piling bar is inserted Enter in pile protection cylinder;
Cable drawing channel-attached include be arranged in each one of buoyancy tank bow stern ensure cable smooth-going disengaging buoyancy tank side The cable of edge, which enters sink, several V-type support rollers lifted cable and play drag reduction and several limitation direction of draw and plays drag reduction, to be made H-type support roller, is each attached on pontoon deck;
The cable enters the center line of sink, V-type support roller, H-type support roller, and the center line with dragger is in same straight line On, and arranged along the length direction of buoyancy tank;
As second aspect, the present invention proposes the installation method of the transfer platform for intertidal zone land cable drawing, packet Include following steps:
(1) before climax, crane barge transport transfer platform buoyancy tank approaches the anchoring of seashore Its Adjacent Waters, and is made by warping the berth Crane barge, land are twisted machine and transfer platform designs installation site on same straight line;
(2) traction rope for being twisted machine from land is drawn on crane barge, and is connected to two, transfer platform buoyancy tank bow end The drawing rigging of drawing lifting lug is connected with shackle;
(3) traction rope of hoist engine on crane barge is connect with the drawing rigging at transfer platform buoyancy tank stern end with shackle;
(4) enter water with crane barge lifting transfer platform buoyancy tank, transfer platform buoyancy tank is swum on the water surface, and by starting buoyancy tank Interior immersible pump carries out tune load, the depth of water when drinking water of transfer platform buoyancy tank being made to be less than installation site flood slack;
(5) when closing on high tide level, land is twisted machine recycling traction rope, and at the same time crane barge hoist engine discharges traction rope, Transfer platform buoyancy tank designs installation site movement to it;
(6) when flood slack, when transfer platform buoyancy tank is drawn near design installation site, the traction rope of crane barge hoist engine It draws over to one's side, is allowed to slightly band power, in the case where land is twisted folding and unfolding cable cooperation of the machine with crane barge hoist engine, transfer platform buoyancy tank is pulled to Design installation site;
(7) start the immersible pump in buoyancy tank, so that transfer platform buoyancy tank is sat beach by adjusting to carry, free land and be twisted machine and crane barge The connection of the traction rope of hoist engine and transfer platform buoyancy tank bow stern drawing rigging;
(8) when low edd slack, piling bar is hung in each pile protection cylinder of transfer platform buoyancy tank by Amphibious digging machine admission respectively successively Interior, piling bar reentries mud certainly;
(9) vibration hammer is lifted into piling bar upper end by Amphibious digging machine, and piling bar is squeezed into mud face or less and designed by Vibration on Start-up hammer Depth;
(10) piling bar and pile protection cylinder are welded together with connecting plate, installation is complete;
(11) it after transfer platform use, needs to withdraw recycling, withdraws the inverse process that recycling transfer platform is its installation.
The beneficial effects of the invention are as follows:It solves intertidal zone and logs in a section installation question for cable pulling apparatus, and from land The conventional method that single-piece transport, Assembling are debugged is compared, and is simplified field device installation procedure, is shortened equipment erector Phase reduces installation cost;Reduce the influence to natural wetland simultaneously.
Description of the drawings
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, in being described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, other drawings may also be obtained based on these drawings.
It is described in further detail below in conjunction with the drawings and the specific embodiments.
Fig. 1 is the floor plan of the present invention;
Fig. 2 is front elevation view of the present invention after installation is complete;
Fig. 3 is the buoyancy tank subdivision schematic diagram of the present invention;
Arrangement schematic diagram when Fig. 4 is present invention drawing installation.
Wherein:1- buoyancy tanks;2- piling bars;3- pile protection cylinders;4- is twisted machine;5- draggers;6- generators;7- cables Enter sink;8-V type support rollers;9-H type support rollers;10- pulls lifting lug;11- lifts lifting lug;12- immersible pumps;13- crane barges; The land 14- is twisted machine;15- hoist engines;16- installation sites.
Specific implementation mode
As Figure 1-Figure 4:
As shown in Figure 1, Figure 2, the present invention includes buoyancy tank 1, piling bar 2 and is arranged in drawing power-equipment on pontoon deck and pulls logical Road attachment.
If the inside configuration of Fig. 3, the buoyancy tank 1 are divided into interconnected cabin, two immersible pumps 12 of optimal design-aside make to float Case 1 has certain tune and carries function;
As shown in Figure 1, Figure 2, buoyancy tank 1 is in each two pile protection cylinders 3 arranged symmetrically of two topsides;It leads at each two arranged symmetrically of bow stern both ends Draw lifting lug 10;Four lifting lifting lugs 11 are arranged symmetrically on deck.
Such as Fig. 1, piling bar 2 is fixed temporarily on 1 deck of buoyancy tank.
As shown in Figure 1, Figure 2, drawing power-equipment includes the dragger 5 for being twisted machine 4, relay drawing cable for pulling cable With to be twisted machine 4, dragger 5 generator 6 of power supply is provided, be each attached on 1 deck of buoyancy tank.
As shown in Figure 1, Figure 2, drawing channel-attached enters the H-type support roller 9 of V-type support roller 8, three of sink 7, two including two cables, It is each attached on 1 deck of buoyancy tank.Two cables enter sink 7 and are separately positioned on 1 bow stern both ends of buoyancy tank, it is ensured that cable smooth-going disengaging is floating 1 edge of case.Two V-type support rollers 8, which serve, lifts cable, drag reduction.Three H-type support rollers 9 can limit the direction of draw of cable and rise Drag reduction acts on.
Such as Fig. 1, the center line that the H-type support roller 9 of V-type support roller 8, three of dragger 5, two and two cables enter sink 7 exists Same 1 length direction of straight line upper edge buoyancy tank arrangement.
1 appearance and size of buoyancy tank is true from redesign according to the design installation site high tide level depth of water and equipment gross weight, ship type buoyancy tank Fixed, the drinking water of buoyancy tank must be less than the design installation site high tide level depth of water, determine the length and width of buoyancy tank 1 according to this.
Such as:Design installation site high tide level depth of water 1.2m, equipment gross weight 30t, it is assumed that the length 14.5m and width of buoyancy tank 1 8.5m, moldeed depth 1.5m are spent, empirically estimates the dead weight 20t of buoyancy tank and attachment;The drinking water that transfer platform buoyancy tank 1 is calculated is 0.41m < 1.2m have larger tune to carry operating space.Conclusion:Meet construction requirement, it is assumed that data fit requirement;Otherwise it needs Again it to check.
Such as Fig. 4, as second aspect, the present invention proposes a kind of peace of the transfer platform for intertidal zone land cable drawing Dress method, includes the following steps:
(1) before climax, crane barge transport transfer platform buoyancy tank 1 approaches the anchoring of seashore Its Adjacent Waters, and passes through warping the berth So that crane barge 13, land is twisted machine 14 and designs installation site 16 substantially on same straight line with transfer platform;
(2) traction rope for being twisted machine 14 from land is drawn on crane barge 13, and is connected to 1 bow end of transfer platform buoyancy tank The drawing rigging of two drawing lifting lugs 10 is connected with shackle;
(3) traction rope of hoist engine 15 on crane barge 13 is connect with the drawing rigging at 1 stern end of transfer platform buoyancy tank with shackle;
(4) it lifts transfer platform with crane barge 13 and enters water, transfer platform buoyancy tank 1 is swum on the water surface, and is dived under water by starting Pump 12 carries out tune load, the depth of water when drinking water of transfer platform buoyancy tank 1 being made to be less than installation site flood slack;
(5) when closing on high tide level, land is twisted machine 14 and recycles traction rope, and at the same time crane barge hoist engine 15 discharges traction Rope, transfer platform buoyancy tank 1 design installation site movement to it;
(6) when flood slack, when transfer platform buoyancy tank 1 is drawn near design installation site 16, hoist engine on crane barge 13 15 traction rope is drawn over to one's side, and slightly band power is allowed to, in the case where land is twisted the folding and unfolding cable cooperation of machine 14 and 13 hoist engine 15 of crane barge, will in Turn platform buoyancy tank 1 and is pulled to 16 positions of design installation;
(7) start immersible pump 12, so that transfer platform buoyancy tank 1 is sat beach by adjusting to carry, free land and be twisted machine 14 and crane barge 13 The connection of the traction rope of hoist engine 15 and 1 bow stern of transfer platform buoyancy tank drawing rigging;
(8) when low edd slack, Amphibious digging machine admission successively hangs in piling bar 2 in each pile protection cylinder of transfer platform 3 respectively, Piling bar 2 reentries mud certainly;
(9) vibration hammer is lifted into piling bar upper end by Amphibious digging machine, and piling bar 2 is squeezed into mud face to divide by Vibration on Start-up hammer Count depth;
(10) piling bar 2 and pile protection cylinder 3 are welded together with connecting plate, installation is complete;
(11) it after transfer platform use, needs to withdraw recycling;Withdraw the inverse process that recycling transfer platform is its installation.

Claims (9)

1. for intertidal zone land cable drawing transfer platform, include for pull cable end be twisted machine, be used for relay Pull the dragger of cable outer wall and to be twisted machine, dragger the generator of power supply is provided, which is characterized in that be twisted machine, traction Machine and generator are arranged on the same buoyancy tank, and are equipped with the piling bar and cable drawing channel-attached of fixed buoyancy tank.
2. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that:The buoyancy tank Inside configuration be divided into interconnected cabin, setting no less than one makes buoyancy tank have to set the tone and carry the immersible pump of function.
3. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that:The buoyancy tank Two topsides it is each be symmetrical arranged no less than a pile protection cylinder.
4. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that:The buoyancy tank Deck on be arranged symmetrically four for connecting the lifting lifting lugs of Current Collector Sleave.
5. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that:The buoyancy tank Bow stern both ends it is each be symmetrical arranged two for connect pull rigging drawing lifting lugs.
6. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that:The piling bar It is temporarily fixed on the deck of buoyancy tank, it is identical as pile protection cylinder quantity;After transfer platform is in place, piling bar is inserted into pile protection cylinder.
7. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that:The cable If drawing channel-attached include be arranged in each one of buoyancy tank bow stern ensure the cable at cable smooth-going disengaging buoyancy tank edge enter sink, Dry care lifts cable and plays the V-type support roller of drag reduction and several H-type support rollers for limiting direction of draw and playing drag reduction, fixed On pontoon deck.
8. the transfer platform according to claim 7 for intertidal zone land cable drawing, it is characterised in that:The cable The center line for entering sink, V-type support roller, H-type support roller, is on the same straight line with the center line of dragger, and along the length of buoyancy tank Direction is arranged.
9. the installation method of the transfer platform for intertidal zone land cable drawing according to claims 1 to 8, feature It is:Include the following steps:
(1) before climax, crane barge transport transfer platform buoyancy tank approaches the anchoring of seashore Its Adjacent Waters, and makes to float by warping the berth It hangs, land is twisted machine and the design installation site of transfer platform buoyancy tank is on same straight line;
(2) traction rope for being twisted machine from land is drawn on crane barge, is pulled with two, transfer platform buoyancy tank bow end is connected to The drawing rigging of lifting lug is connected with shackle;
(3) traction rope of hoist engine on crane barge is connect with the drawing rigging at transfer platform buoyancy tank stern end with shackle;
(4) enter water with crane barge lifting transfer platform, transfer platform buoyancy tank is swum on the water surface, and by starting the diving in buoyancy tank Pump carries out tune load, the depth of water when drinking water of transfer platform buoyancy tank being made to be less than installation site flood slack;
(5) when closing on high tide level, land is twisted machine recycling traction rope, and at the same time crane barge hoist engine discharges traction rope, transfer Platform buoyancy tank designs installation site movement to it;
(6) when flood slack, when transfer platform buoyancy tank is drawn near design installation site, the traction rope of crane barge hoist engine is received It pulls, is allowed to slightly band power, in the case where land is twisted folding and unfolding cable cooperation of the machine with crane barge hoist engine, transfer platform buoyancy tank is pulled to and is set Count installation site;
(7) start the immersible pump in buoyancy tank, so that transfer platform buoyancy tank is sat beach by adjusting to carry, free land and be twisted machine and crane barge elevator The connection of the traction rope of machine and transfer platform buoyancy tank bow stern drawing rigging;
(8) when low edd slack, Amphibious digging machine admission successively hangs in piling bar in each pile protection cylinder of transfer platform buoyancy tank, steel respectively Mud is reentried in stake certainly;
(9) vibration hammer is lifted into piling bar upper end by Amphibious digging machine, and it is deep to be squeezed into mud face or less design by Vibration on Start-up hammer for piling bar Degree;
(10) piling bar and pile protection cylinder are welded together with connecting plate, installation is complete;
(11) it after transfer platform use, needs to withdraw recycling, withdraws the inverse process that recycling transfer platform is its installation.
CN201810742114.1A 2018-07-04 2018-07-04 Transfer platform for cable traction in intertidal zone login and installation method thereof Active CN108755644B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810742114.1A CN108755644B (en) 2018-07-04 2018-07-04 Transfer platform for cable traction in intertidal zone login and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810742114.1A CN108755644B (en) 2018-07-04 2018-07-04 Transfer platform for cable traction in intertidal zone login and installation method thereof

Publications (2)

Publication Number Publication Date
CN108755644A true CN108755644A (en) 2018-11-06
CN108755644B CN108755644B (en) 2024-01-26

Family

ID=63972642

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810742114.1A Active CN108755644B (en) 2018-07-04 2018-07-04 Transfer platform for cable traction in intertidal zone login and installation method thereof

Country Status (1)

Country Link
CN (1) CN108755644B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110474259A (en) * 2019-08-30 2019-11-19 北京海瑞兴能源科技有限责任公司 Log in section cable laying system and a laying method
CN110539853A (en) * 2019-09-11 2019-12-06 北京海瑞兴能源科技有限责任公司 Cable laying ship deck arrangement and construction method for laying long-distance sand shores and submarine cables
CN112744326A (en) * 2021-02-24 2021-05-04 博雅工道(北京)机器人科技有限公司 Traction assembly and splicing platform with same
CN112832325A (en) * 2021-02-24 2021-05-25 河南省水利勘测设计研究有限公司 Floating dock pump station trusteeship floating dock underwater bearing platform structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102412533A (en) * 2011-11-28 2012-04-11 江苏海上龙源风力发电有限公司 Intertidal belt submarine cable paving method
EP3098916A1 (en) * 2015-05-27 2016-11-30 Bohlen & Doyen GmbH Device for introducing an object, in particular a cable, in the bottom of a body of water
CN106786193A (en) * 2016-12-26 2017-05-31 浙江舟山启明电力集团公司海缆工程公司 Long range intertidal zone submarine cable logs in cable laying operation operational method and system
CN206308681U (en) * 2016-11-14 2017-07-07 中交天航南方交通建设有限公司 A kind of positioning combined operation at sea floats platform
CN208545734U (en) * 2018-07-04 2019-02-26 天津海瑞兴能源科技有限公司 Transfer platform for intertidal zone land cable drawing

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102412533A (en) * 2011-11-28 2012-04-11 江苏海上龙源风力发电有限公司 Intertidal belt submarine cable paving method
EP3098916A1 (en) * 2015-05-27 2016-11-30 Bohlen & Doyen GmbH Device for introducing an object, in particular a cable, in the bottom of a body of water
CN206308681U (en) * 2016-11-14 2017-07-07 中交天航南方交通建设有限公司 A kind of positioning combined operation at sea floats platform
CN106786193A (en) * 2016-12-26 2017-05-31 浙江舟山启明电力集团公司海缆工程公司 Long range intertidal zone submarine cable logs in cable laying operation operational method and system
CN208545734U (en) * 2018-07-04 2019-02-26 天津海瑞兴能源科技有限公司 Transfer platform for intertidal zone land cable drawing

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110474259A (en) * 2019-08-30 2019-11-19 北京海瑞兴能源科技有限责任公司 Log in section cable laying system and a laying method
CN110539853A (en) * 2019-09-11 2019-12-06 北京海瑞兴能源科技有限责任公司 Cable laying ship deck arrangement and construction method for laying long-distance sand shores and submarine cables
CN112744326A (en) * 2021-02-24 2021-05-04 博雅工道(北京)机器人科技有限公司 Traction assembly and splicing platform with same
CN112832325A (en) * 2021-02-24 2021-05-25 河南省水利勘测设计研究有限公司 Floating dock pump station trusteeship floating dock underwater bearing platform structure and construction method thereof

Also Published As

Publication number Publication date
CN108755644B (en) 2024-01-26

Similar Documents

Publication Publication Date Title
CN108755644A (en) Transfer platform and its installation method for intertidal zone land cable drawing
CN101774422B (en) Novel offshore installation construction resource-combined type pontoon barge
CN111661273B (en) Installation and construction method of deep and open sea semi-submersible fan
CN102322062B (en) Transportation and installation process of base barrel body of barrel type breakwater
CN205044921U (en) Multi -functional marine construction is from peaceful platform
CN101837929B (en) Operation method for lifting fan for barge in shoal area
CN106522275B (en) Self-propulsion type semi-submerged ship goes out the large-scale Immersed tunnel technique of fortune
CN107600326A (en) A kind of releasable formula gravity anchor system for deep ocean buoy
CN216834193U (en) Floating body and floating type offshore transformer substation
CN208545734U (en) Transfer platform for intertidal zone land cable drawing
CN106759340A (en) Steel-pipe pile pile-pulling construction method and device in low spatial water
CN103195039B (en) Artificial island construction method for self-elevating straight-through deck platform
CN108222069A (en) A kind of underwater immersed tube, the device and construction method for setting up underwater immersed tube
CN207143999U (en) A kind of underwater immersed tube and the device for setting up underwater immersed tube
CN106379488B (en) The method for quickly carrying out marine floating support mounting platform
CN211618030U (en) Ship floating device on water
CN108454793A (en) A kind of novel shallow draft, low clearance, high-environmental open body barge
CN105648996A (en) Lifting ballasting barge applicable to installation of simple wellhead platform and mounting method thereof
CN212715000U (en) Steel cofferdam positioning system in deep water
KR100305219B1 (en) fabricated barge
CN214272150U (en) Ocean current retaining wall
CN205259216U (en) Adopt steel truss to add concrete structure of back cover under water of muscle
CN111764418A (en) Steel cofferdam positioning system in deep water
CN211107892U (en) Amphibious L NG tank container reloading ship
CN102700686B (en) A kind of box pontoon for tunnel driving crossing underneath river and construction technology thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 300 000 Tianjin Tianjin Free Trade Test Area (East Xinjiang Bonded Port Area) No. 1069 Shaanxi Road, Tianjin Port First Agricultural Food Office Building, 2nd Floor 203

Applicant after: TIANJIN HAIRUIXING ENERGY TECHNOLOGY Co.,Ltd.

Address before: Room 320, Building 1, Science and Technology Park, No. 3 Hongri South Road, Nankai District, Tianjin

Applicant before: TIANJIN LIHAIXING MARINE ENGINEERING CO.,LTD.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant