CN208545734U - Transfer platform for intertidal zone land cable drawing - Google Patents
Transfer platform for intertidal zone land cable drawing Download PDFInfo
- Publication number
- CN208545734U CN208545734U CN201821055141.3U CN201821055141U CN208545734U CN 208545734 U CN208545734 U CN 208545734U CN 201821055141 U CN201821055141 U CN 201821055141U CN 208545734 U CN208545734 U CN 208545734U
- Authority
- CN
- China
- Prior art keywords
- buoyancy tank
- transfer platform
- cable
- intertidal zone
- dragger
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model relates to bottom cable laying technical fields, it is related to a kind of transfer platform for intertidal zone land cable drawing, including for pull cable end be twisted machine, for relay drawing cable outer wall dragger and to be twisted machine, dragger the generator of power supply is provided, it is twisted machine, dragger and generator to be arranged on the same buoyancy tank, and is equipped with the piling bar and cable drawing channel-attached of fixed buoyancy tank.When installation, transport crane barge, land hoist engine and transfer platform the design installation site of transfer platform buoyancy tank point-blank, machine is twisted by land when flood slack and crane barge hoist engine combines transfer platform buoyancy tank being pulled to design installation site, adjusts to carry and sits beach, piling is fixed when low edd slack.Compared with the conventional method debugged from the transport of land single-piece, on-site assembly, field device installation procedure is simplified, equipment installation period is shortened, reduces installation cost;Reduce the influence to natural wetland simultaneously.
Description
Technical field
The utility model relates to bottom cable laying technical fields, lead in particular to for intertidal zone land cable
The transfer platform of drawing.
Background technique
Submarine cable is the important power transmission being connected between Offshore Units and land facility and signal transmission facilities.According to
Environmental condition where bottom cable laying construction is different, and submarine cable is usually divided into coastal waters section and logs in section.Each section of difference
Using different targeted technical equipments and construction method.The cable laying of coastal waters section carries out deposited buried construction by paving cable ship;
The cable laying for logging in section generallys use drawing mode: paving cable ship approaches debarkation point anchoring;The submarine cable on cable ship will be spread
End is pulled to land facility terminal along design routing;Then carry out logging in the deposited buried operation of section cable.Log in a section cable laying
After completion, paving cable ship carries out coastal waters section cable laying.
A section cable drawing is logged in order to realize, needs logging in a section cable routing ascender line setting cable drawing channel, and
Inflection point is routed in cable and other necessary position setting several groups pull power-equipment.For logging in characterized by dykes and dams
Section, for section apart from short, one group of drawing power-equipment is arranged in the land of no water logging risk between tide.For being with natural beach
Feature logs in section, and intertidal zone distance needs to arrange several groups drawing power-equipment in intertidal zone, therefore has water logging risk.
In order to avoid water logging equipment, and make cable drawing channel plane absolute altitude when pulling construction period peak level
More than the water surface, need to set up scaffold temporary operating platform and scaffold access.The cable drawing channel of intertidal zone is usually by foot
Fixed V-type support roller and H-type support roller composition on channel that hand cradle is set up, the steel plate and steel plate being laid with thereon.The drawing of intertidal zone
Power-equipment generally includes to be twisted machine, dragger and generator, dispersion or that concentrates be arranged in scaffold building, upper laying steel
On the temporary operating platform of plate.
The monomer weight for being twisted machine, dragger and generator as drawing power-equipment is larger, and handling installation needs
Biggish haulage vehicle and crane is wanted to cooperate.Since natural beach is with a varied topography and muddy, it usually needs on the way pad soil pave the way to
Installation site is designed, the needs of the transport of drawing power-equipment and lifting installation are just able to satisfy.It is this to transport and pacify from land direction
The usual way of dress, construction earth volume is big, and by tidal effect, the effective time is short, long in time limit, economic cost and time
It is at high cost;In-site installation, contraposition and the debugging for pulling power-equipment simultaneously have also accordingly increased duration and cost;In addition a large amount of
Earthwork the ecology of natural wetland can be caused to seriously affect, again repair be also required to sizable time cost and economy
Cost.Further, since be limited to drauht, can not will drawing power-equipment from marine direction transport to design installation site into
Row installation.
Therefore it provides a kind of intertidal zone logs in a section cable pulling apparatus solution, becomes those skilled in the art and wanted
The important technological problems of solution.
Utility model content
The utility model proposes the transfer platforms pulled for intertidal zone land cable, including for pulling cable end
Be twisted machine, for relay drawing cable outer wall dragger and to be twisted machine, dragger the generator of power supply is provided, be twisted machine,
Dragger and generator are arranged on the same buoyancy tank, and are equipped with the piling bar and cable drawing channel-attached of fixed buoyancy tank.
The inside configuration of the buoyancy tank is divided into interconnected cabin, and setting no less than makes buoyancy tank have load of setting the tone for one
The immersible pump of function;
Two topsides of the buoyancy tank are each to be symmetrical arranged a no less than pile protection cylinder;
Four are arranged symmetrically on the deck of the buoyancy tank for connecting the lifting lifting lug of Current Collector Sleave;
The bow stern both ends of the buoyancy tank are each to be symmetrical arranged two for connecting the drawing lifting lug of drawing rigging;
The piling bar is temporarily fixed on the deck of buoyancy tank, identical as pile protection cylinder quantity;After transfer platform is in place, piling bar is inserted
Enter in pile protection cylinder;
Cable drawing channel-attached includes being arranged in buoyancy tank bow stern each one to ensure that cable smoothly passes in and out buoyancy tank side
The cable of edge, which enters sink, several V-type support rollers lifted cable and play drag reduction and several limitation direction of draw and plays drag reduction, to be made
H-type support roller, is each attached on pontoon deck;
The cable enters the center line of sink, V-type support roller, H-type support roller, and the center line with dragger is in same straight line
On, and arranged along the length direction of buoyancy tank;
The utility model proposes the installation methods of the transfer platform pulled for intertidal zone land cable, including following step
It is rapid:
(1) before climax, crane barge transport transfer platform buoyancy tank approaches the anchoring of seashore Its Adjacent Waters, and is made by warping the berth
Crane barge, land are twisted machine and transfer platform design installation site on same straight line;
(2) traction rope for being twisted machine from land is drawn on crane barge, and is connected to two, transfer platform buoyancy tank bow end
The drawing rigging of drawing lifting lug is connected with shackle;
(3) traction rope of hoist engine on crane barge is connect with the drawing rigging at transfer platform buoyancy tank stern end with shackle;
(4) enter water with crane barge lifting transfer platform buoyancy tank, transfer platform buoyancy tank is swum on the water surface, and passes through starting buoyancy tank
Interior immersible pump carries out tune load, the depth of water when drinking water of transfer platform buoyancy tank being made to be less than installation site flood slack;
(5) when closing on high tide level, land is twisted machine recycling traction rope, and crane barge hoist engine discharges traction rope at the same time,
Transfer platform buoyancy tank designs installation site movement to it;
(6) when flood slack, when transfer platform buoyancy tank is drawn near design installation site, the traction rope of crane barge hoist engine
It draws over to one's side, is allowed to slightly band power, under the folding and unfolding cable cooperation that land is twisted machine and crane barge hoist engine, transfer platform buoyancy tank is pulled to
Design installation site;
(7) start the immersible pump in buoyancy tank, so that transfer platform buoyancy tank is sat beach by adjusting to carry, free land and be twisted machine and crane barge
The connection of traction rope and transfer platform buoyancy tank bow stern the drawing rigging of hoist engine;
(8) when low edd slack, piling bar is successively hung in each pile protection cylinder of transfer platform buoyancy tank by Amphibious digging machine admission respectively
Interior, piling bar reentries mud certainly;
(9) vibration hammer is lifted into piling bar upper end by Amphibious digging machine, starts vibration hammer, piling bar is squeezed into mud face or less and is designed
Depth;
(10) piling bar and pile protection cylinder are welded together with connecting plate, is installed;
(11) it after transfer platform use, needs to withdraw recycling, withdraws the inverse process that recycling transfer platform is its installation.
The beneficial effects of the utility model are: solving intertidal zone logs in a section installation question for cable pulling apparatus, with from
The conventional method that the transport of land single-piece, on-site assembly are debugged is compared, and field device installation procedure is simplified, and shortens equipment installation
Duration reduces installation cost;Reduce the influence to natural wetland simultaneously.
Detailed description of the invention
It is described in further detail below in conjunction with the drawings and the specific embodiments.
Fig. 1 is the floor plan of utility model;
Fig. 2 is the front elevation view after being installed of utility model;
Fig. 3 is the buoyancy tank subdivision schematic diagram of utility model;
Fig. 4 is arrangement schematic diagram when utility model is installed.
Wherein: 1- buoyancy tank;2- piling bar;3- pile protection cylinder;4- is twisted machine;5- dragger;6- generator;7- cable
Enter sink;8-V type support roller;9-H type support roller;10- pulls lifting lug;11- lifts lifting lug;12- immersible pump;13- crane barge;
The land 14- is twisted machine;15- hoist engine;16- installation site.
Specific embodiment
As shown in Figure 1, Figure 2, the utility model includes buoyancy tank 1, piling bar 2 and is arranged in drawing power-equipment on pontoon deck and leads
Draw channel-attached.
Such as Fig. 3, the inside configuration of the buoyancy tank 1 is divided into interconnected cabin, and two immersible pumps 12 of optimal setting make to float
Case 1 has certain tune and carries function;
As shown in Figure 1, Figure 2, buoyancy tank 1 is in each two pile protection cylinders 3 arranged symmetrically of two topsides;It leads at each two arranged symmetrically of bow stern both ends
Draw lifting lug 10;Four lifting lifting lugs 11 are arranged symmetrically on deck.
Such as Fig. 1, piling bar 2 is fixed temporarily on 1 deck of buoyancy tank.
As shown in Figure 1, Figure 2, drawing power-equipment includes the dragger 5 for being twisted machine 4, relay drawing cable for pulling cable
With to be twisted machine 4, dragger 5 generator 6 of power supply is provided, be each attached on 1 deck of buoyancy tank.
As shown in Figure 1, Figure 2, drawing channel-attached includes that two cables enter the H-type support roller 9 of V-type support roller 8, three of sink 7, two,
It is each attached on 1 deck of buoyancy tank.Two cables enter sink 7 and are separately positioned on 1 bow stern both ends of buoyancy tank, it is ensured that cable smoothly passes in and out floating
1 edge of case.Two V-type support rollers 8, which serve, lifts cable, drag reduction.Three H-type support rollers 9 can limit the direction of draw of cable and rise
Drag reduction effect.
Such as Fig. 1, the center line that the H-type support roller 9 of V-type support roller 8, three of dragger 5, two and two cables enter sink 7 exists
It is arranged on same straight line along 1 length direction of buoyancy tank.
1 outer dimension of buoyancy tank is true from redesign according to the design installation site high tide level depth of water and equipment gross weight, ship type buoyancy tank
Fixed, the drinking water of buoyancy tank must be less than the design installation site high tide level depth of water, determine the length and width of buoyancy tank 1 according to this.
Such as: design installation site high tide level depth of water 1.2m, equipment gross weight 30t, it is assumed that the length 14.5m and width of buoyancy tank 1
8.5m, moldeed depth 1.5m are spent, empirically estimates the self weight 20t of buoyancy tank and attachment;The drinking water that transfer platform buoyancy tank 1 is calculated is
0.41m < 1.2m has biggish tune to carry operating space.Conclusion: meet construction requirement, it is assumed that data fit requirement;Otherwise it needs
Again it to check.
Such as Fig. 4, the utility model proposes the transfer platform for intertidal zone land cable drawing installation method, including
Following steps:
(1) before climax, crane barge transport transfer platform buoyancy tank 1 approaches the anchoring of seashore Its Adjacent Waters, and passes through warping the berth
Crane barge 13, land is set to be twisted machine 14 and transfer platform design installation site 16 substantially on same straight line;
(2) it will be drawn on crane barge 13 from the traction rope that land is twisted machine 14, and be connected to 1 bow end of transfer platform buoyancy tank
The drawing rigging of two drawing lifting lugs 10 is connected with shackle;
(3) traction rope of hoist engine 15 on crane barge 13 is connect with the drawing rigging at 1 stern end of transfer platform buoyancy tank with shackle;
(4) transfer platform being lifted with crane barge 13 and entering water, transfer platform buoyancy tank 1 is swum on the water surface, and passes through starting diving
Pump 12 carries out tune load, the depth of water when drinking water of transfer platform buoyancy tank 1 being made to be less than installation site flood slack;
(5) when closing on high tide level, land is twisted machine 14 and recycles traction rope, and crane barge hoist engine 15 discharges traction at the same time
Rope, transfer platform buoyancy tank 1 design installation site movement to it;
(6) when flood slack, when transfer platform buoyancy tank 1 is drawn near design installation site 16, hoist engine on crane barge 13
15 traction rope is drawn over to one's side, and slightly band power is allowed to, in the case where land is twisted the folding and unfolding cable cooperation of machine 14 and 13 hoist engine 15 of crane barge, will in
Turn platform buoyancy tank 1 and is pulled to 16 positions of design installation;
(7) start immersible pump 12, so that transfer platform buoyancy tank 1 is sat beach by adjusting to carry, free land and be twisted machine 14 and crane barge 13
The connection of traction rope and 1 bow stern of transfer platform buoyancy tank the drawing rigging of hoist engine 15;
(8) when low edd slack, Amphibious digging machine admission successively hangs in piling bar 2 in each pile protection cylinder 3 of transfer platform respectively,
Piling bar 2 reentries mud certainly;
(9) vibration hammer is lifted into piling bar upper end by Amphibious digging machine, starts vibration hammer, piling bar 2 is squeezed into mud face to divide into
Count depth;
(10) piling bar 2 and pile protection cylinder 3 are welded together with connecting plate, is installed;
(11) after transfer platform use, need to withdraw recycling;Withdraw the inverse process that recycling transfer platform is its installation.
Claims (8)
1. for the transfer platform of intertidal zone land cable drawing, including being twisted machine, for relay for pull cable end
Pull cable outer wall dragger and to be twisted machine, dragger the generator of power supply is provided, which is characterized in that be twisted machine, traction
Machine and generator are arranged on the same buoyancy tank, and are equipped with the piling bar and cable drawing channel-attached of fixed buoyancy tank.
2. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that: the buoyancy tank
Inside configuration be divided into interconnected cabin, setting no less than one makes buoyancy tank have to set the tone and carry the immersible pump of function.
3. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that: the buoyancy tank
Two topsides it is each be symmetrical arranged no less than a pile protection cylinder.
4. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that: the buoyancy tank
Deck on be arranged symmetrically four for connecting the lifting lifting lugs of Current Collector Sleave.
5. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that: the buoyancy tank
Bow stern both ends it is each be symmetrical arranged two for connect pull rigging drawing lifting lugs.
6. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that: the piling bar
It is temporarily fixed on the deck of buoyancy tank, it is identical as pile protection cylinder quantity;After transfer platform is in place, piling bar is inserted into pile protection cylinder.
7. the transfer platform according to claim 1 for intertidal zone land cable drawing, it is characterised in that: the cable
If drawing channel-attached include be arranged in buoyancy tank bow stern each one ensure cable smoothly pass in and out buoyancy tank edge cable enter sink,
Dry care lifts cable and plays the V-type support roller and several H-type support rollers for limiting direction of draw and playing drag reduction of drag reduction, fixed
On pontoon deck.
8. the transfer platform according to claim 7 for intertidal zone land cable drawing, it is characterised in that: the cable
The center line for entering sink, V-type support roller, H-type support roller, is on the same straight line with the center line of dragger, and along the length of buoyancy tank
Direction arrangement.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821055141.3U CN208545734U (en) | 2018-07-04 | 2018-07-04 | Transfer platform for intertidal zone land cable drawing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821055141.3U CN208545734U (en) | 2018-07-04 | 2018-07-04 | Transfer platform for intertidal zone land cable drawing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208545734U true CN208545734U (en) | 2019-02-26 |
Family
ID=65422603
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821055141.3U Active CN208545734U (en) | 2018-07-04 | 2018-07-04 | Transfer platform for intertidal zone land cable drawing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208545734U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108755644A (en) * | 2018-07-04 | 2018-11-06 | 天津立海兴海洋工程有限公司 | Transfer platform and its installation method for intertidal zone land cable drawing |
-
2018
- 2018-07-04 CN CN201821055141.3U patent/CN208545734U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108755644A (en) * | 2018-07-04 | 2018-11-06 | 天津立海兴海洋工程有限公司 | Transfer platform and its installation method for intertidal zone land cable drawing |
CN108755644B (en) * | 2018-07-04 | 2024-01-26 | 天津海瑞兴能源科技有限公司 | Transfer platform for cable traction in intertidal zone login and installation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108755644A (en) | Transfer platform and its installation method for intertidal zone land cable drawing | |
CN101774422B (en) | Novel offshore installation construction resource-combined type pontoon barge | |
CN111661273B (en) | Installation and construction method of deep and open sea semi-submersible fan | |
CN101837929B (en) | Operation method for lifting fan for barge in shoal area | |
CN102322062A (en) | Transportation and installation process of base barrel body of barrel type breakwater | |
CN107600326A (en) | A kind of releasable formula gravity anchor system for deep ocean buoy | |
CN106015736B (en) | Submarine pipeline suspended span processing method | |
CN216834193U (en) | Floating body and floating type offshore transformer substation | |
CN208545734U (en) | Transfer platform for intertidal zone land cable drawing | |
CN114455017A (en) | Floating body, floating type offshore transformer substation and installation method thereof | |
CN103195038A (en) | Method for forming self-elevating artificial island through connection of platform units | |
CN102359122A (en) | Method for installing buttress under assistance of buoyant boxes | |
CN102206938A (en) | Novel method for installing upper part block of offshore platform | |
CN109178225B (en) | Pull rod type undocking method for semi-submersible type ocean engineering platform | |
CN207143999U (en) | A kind of underwater immersed tube and the device for setting up underwater immersed tube | |
CN211618030U (en) | Ship floating device on water | |
CN106379488B (en) | The method for quickly carrying out marine floating support mounting platform | |
CN212715000U (en) | Steel cofferdam positioning system in deep water | |
CN105648996A (en) | Lifting ballasting barge applicable to installation of simple wellhead platform and mounting method thereof | |
CN108454793A (en) | A kind of novel shallow draft, low clearance, high-environmental open body barge | |
JPH1121866A (en) | Oil fence | |
TWI702327B (en) | Harbour plant and method for mooring a floating body in a harbour plant | |
CN111764418A (en) | Steel cofferdam positioning system in deep water | |
EP3532678B1 (en) | Harbour plant and method for mooring a floating body in a harbour plant | |
JPS59145688A (en) | Launching/grounding system for vessel and ocean structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20190520 Address after: 102600 Beijing Daxing District Qingxiang South Road 29 Courtyard 9 Floor 2 Unit 916 Patentee after: Beijing Hai Xing Energy Technology Co., Ltd. Address before: 300 000 Tianjin Binhai New Area Tianjin Free Trade Test Area (East Xinjiang Bonded Port Area) No. 1069 Shaanxi Road, Tianjin Port First Agricultural Food Office Building, 2nd Floor 203 Patentee before: Tianjin Hairuixing Energy Technology Co., Ltd. |
|
TR01 | Transfer of patent right |