CN1730842A - Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure - Google Patents

Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure Download PDF

Info

Publication number
CN1730842A
CN1730842A CN 200510015014 CN200510015014A CN1730842A CN 1730842 A CN1730842 A CN 1730842A CN 200510015014 CN200510015014 CN 200510015014 CN 200510015014 A CN200510015014 A CN 200510015014A CN 1730842 A CN1730842 A CN 1730842A
Authority
CN
China
Prior art keywords
cylindrical shell
box
sinking
gas
type suction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200510015014
Other languages
Chinese (zh)
Other versions
CN100343454C (en
Inventor
别社安
齐越
贺立
苏永生
只红茹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CNB2005100150141A priority Critical patent/CN100343454C/en
Publication of CN1730842A publication Critical patent/CN1730842A/en
Application granted granted Critical
Publication of CN100343454C publication Critical patent/CN100343454C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention is the marine air floatation hauling and locating and depositing installation process of case and barrel shaped foundation structure for soft soil. The construction process includes inflating the case and barrel shaped foundation structure in water for it to float and hauling to the installation site; locating in the floating state; deflating for deposition via controlling the deflation speed and amount to control the deposition speed and inclination; pumping out air from the structure and applying pressure for further deposition; pumping out water from the structure for further deposition until pumping out all water inside the structure and completing the installation. The said process needs no large hoisting and transportation apparatus, and is simple, controllable and low in cost.

Description

Soft-foundation box-cylinder type infrastructure maritime air float hauling and positioning sinking mounting method
Technical field
The present invention relates to a kind of foundation structure that is inserted in the soft foundation---maritime air float hauling, location and the sinking mounting method of box-type suction foundation structure.Belong to the building structure construction method in coastal waters and the port works field.
Background technology
At the soft foundation in coastal waters and the port works, occurred a series of with the new construction of box-type suction foundation structure as architecture basics, as novel mole (removable cylinder foundation breakwater structure, the patent No.: 022531467; The upright arc diaphragm wall of removable steel reinforced concrete box-type suction foundation breakwater structure, 2004200294670), (mobile light casing basis retaining soil and water is every wave structure to enclose low bank between fields and shore protection the patent No.:, 012093904), seabed tunnel (box foundation seabed tunnel structure the patent No.:, 022090614), harbour (the bucket foundation gravitation-type deep-water dock structure on the soft foundation, the patent No.: 021213739) etc. the patent No.:.Box-type suction foundation structure in these new constructions is generally by the basic cylinder or the rectangular arrangement of polygon cylindrical shell of four top band lamina tectis, lower openings, and being rigidly connected by the side plate between top board and basic cylindrical shell forms.If such structure is made of steel, about 150 tons to 500 tons of weight, if use concrete for making, about 1000 tons to 3000 tons of weight.During use, the box-type suction foundation structure is inserted in the soft foundation of seabed basis as superstructure.
Use conventional methods these structures are installed, general earlier with prefabricated structure slippage or lift on the transport barge, be transported to the erecting bed with transport barge, hang with argosy then structure is hung onto mounting points location from transport barge, adopt the method that vacuumizes and add ballast that structure is sunk in the earth afterwards.This job practices needs large-scale ships that transport and ship to hang equipment on the one hand, and the use cost of these equipment is very high; Work progress complexity on the other hand, efficiency of construction is lower, and construction quality is difficult to guarantee, and when adding under the method for ballast sink structure as employing, the degree of skewness of structure is difficult to control, also needs to have bad luck a large amount of ballast block or Ballast Water.
Can pneumatically supported characteristics at the box-type suction foundation structure, can adopt a cover new method to come it is transported, locatees and sinks to installing, promptly adopt air floating method that it is hauled, in the air supporting state it is carried out installing and locating, the method that adopts venting, vacuumizes and draw water is to the degree of skewness of its sink installation and the installation of adjustment structure.
Summary of the invention
The objective of the invention is to propose a kind of safe, economic, practical haul, location and sinking mounting method at the box-type suction foundation structure that is inserted in the soft foundation.
For achieving the above object, the present invention is realized by following technical proposals: a kind of soft-foundation box-cylinder type infrastructure maritime air float hauling and positioning sinking mounting method, described box-type suction foundation structure is meant that it is the overall structure that uncovered cylinder or polygon cylindrical shell are regularly arranged into that a plurality of upper ends are provided with lamina tecti, lower end, wherein the lamina tecti of each cylindrical shell or upper end sidewall are provided with the ventilation and the suction eye of band pipe valve, the maritime air float hauling and the positioning sinking mounting method of such box-type suction foundation structure is characterized in that comprising following process:
(1) air float hauling: under the prefabricated box-type suction foundation structure behind the water, inflate in cylindrical shell by the air vent on each cylindrical shell, make structure float on the water surface, adjust the aeration quantity in the cylindrical shell, make the underwater penetration of each cylindrical shell reach the requirement of satisfying towage stability, just can haul afterwards it;
(2) air supporting location: box-type suction foundation structure air float hauling is to the infield, emit the portion gas in each cylindrical shell, at the bottom of structure is sunk down into tin and the distance between the mud face be 0~1.0m, under this air supporting state, with structure lentamente alongside by a location barge of having had good positioning, adjust the relative position of structure by hawser then, finish the air supporting location at the barge edge; Or arrange 4 to 8 anchorage hawsers in the box-type suction foundation structural perimeter, the air supporting location that utilizes the folding and unfolding of each anchorage hawser to finish the box-type suction foundation structure; Behind the structure air supporting location, continue to emit the gas in each cylindrical shell, structure is sunk, not with before the mud face contact, position observation, be offset, then stop the sinking of exitting, position again as stated above as fruit structure in the cylindrical shell bottom;
(3) going into mud sinks to installing: the mud sinking installation process of going into of box-type suction foundation structure comprises:
1) sink by dead load exhaust outlet and leveling: open ventilation and suction eye on each cylindrical shell, under the dead load effect, gas is discharged in the tube, and cylindrical shell is gone into mud, comes the subsidence velocity of control structure by the control exhaust velocity; The inclination situation of observation structure in the sinking process, when the structure run-off the straight, the gas that stops or reducing in the cylindrical shell of the big side of deflection is emitted, gas in the cylindrical shell of maintenance or the little side of increasing deflection is emitted, make the structure recovery level, continue balanced venting then and sink, until box-type suction foundation dead load and soil body resistance balance, till structure is no longer sunk; If dead load is bigger or the depth of water is bigger, after the gas in the cylindrical shell was discharged entirely, structure also continued to sink under the deadweight effect, and then the interior water body of tube can be discharged from ventilation and suction eye, until dead load and soil body resistance balance, till structure is no longer sunk;
2) leveling of exerting pressure by bleeding is sunk: structure if also have gas to exist in the tube, then utilizes jet vacuum pump from air vent or suction eye gas in the tube to be extracted out after stopping to sink by deadweight, structure continuation sinking; The inclination situation of observation structure in the sinking process, when the structure run-off the straight, the gas that stops or reducing in the cylindrical shell of the big side of deflection is extracted out, gas in the cylindrical shell of maintenance or the little side of increasing deflection is extracted out, make the structure recovery level,. continue the equilibrium sinking of bleeding then, till the gas in each cylindrical shell of box-type suction foundation structure is all extracted out;
3) leveling of exerting pressure by drawing water is sunk: after the gas in the box-type suction foundation structure cylindrical shell is all discharged, utilize proof submersible sand discharging pump or jet pump from suction eye water body in the tube to be extracted out, structure continues to sink; The inclination situation of observation structure in the sinking process, when the structure run-off the straight, the water body that stops or reducing in the cylindrical shell of the big side of deflection is extracted out, water body in the cylindrical shell of maintenance or the little side of increasing deflection is extracted out, make the structure recovery level, continue the equilibrium sinking of drawing water then, till the water body in each was all extracted out, the sinking of box-type suction foundation structure installed.
Superiority of the present invention is: the transportation of box-type suction foundation structure does not need the large transport ship oceangoing ship, the on-the-spot installation do not need large-scale lifting boats and ships and has bad luck a large amount of ballast block or Ballast Water, positioning sinking equipment is simple, easy construction, subsidence velocity is fast, degree of skewness is controlled easily, and the integrated construction expense is low.
Description of drawings
Below in conjunction with accompanying drawing the present invention is illustrated.
Fig. 1 is with the breakwater structure sectional schematic diagram of box-type suction foundation structure as the basis.
Fig. 2 is the bottom plan view of box-type suction foundation structure.
Fig. 3 is in the air supporting floating state for the box-type suction foundation structure.
Fig. 4 is in the air float hauling state for the box-type suction foundation structure.
Fig. 5 carries out air supporting location schematic diagram for the alongside of box-type suction foundation structure in barge side, location.
Fig. 6 utilizes the anchorage hawser for the box-type suction foundation structure and carries out air supporting location schematic diagram.
Fig. 7 is in by dead load exhaust sinking state for the box-type suction foundation structure.
Fig. 8 is in the sinking state of bleeding for the box-type suction foundation structure.
Fig. 9 is in the sinking state that draws water for the box-type suction foundation structure.
Figure 10 is the box-type suction foundation structure state that sinks to being in place.
1 is basic cylindrical shell among the figure, and 2 is the tube lamina tecti, and 3 is ventilation and the suction eye on the tube lamina tecti, and 4 is the structural upright cylinder mole of box-type suction foundation, and 5 is the junction plate between basic cylindrical shell, and 6 is the intermediate cylinder cabin that four basic cylindrical shells and junction plate surround,
7 for the air in the cylindrical shell of air supporting floating state basis is in pressured state,
8 is the towing cable rope of air float hauling,
9 for the air pressure in the cylindrical shell of air float hauling state front side is slightly larger than the interior air pressure of rear side cylindrical shell,
10 are the location barge, 11 anchorage hawsers for the location barge,
12 for the alongside of box-type suction foundation structure in location the cleating of barge,
13 is the air supporting location anchorage hawser of box-type suction foundation structure,
14 is air in the expelling tube,
15 for the air pressure in the exhaust sinking state cylindrical shell a little more than atmospheric pressure,
16 are an air in the extraction tube,
17 for the air pressure in the sinking state cylindrical shell of bleeding less than atmospheric pressure,
18 are a water body in the extraction tube,
19 for the water pressure in the sinking state cylindrical shell of drawing water less than tube outward with the water pressure at degree of depth place,
20 contact with the foundation soil face for box-type suction foundation structure basis, the back tube top board downside that sinks to putting in place.
The specific embodiment
One embodiment of the invention is as follows: box-type suction foundation breakwater structure as depicted in figs. 1 and 2, wherein 4 of the box-type suction foundation structure basic cylindrical shells are diameter 10.5m, high 8m, the concrete cylinder of wall thickness 0.25m, the barrel spacing 2.5m of adjacent two cylindrical shells, adjacent two cylindrical shells connect with the thick connection wall of 0.5m, it is identical with the cylindrical shell height to connect wall, the lamina tecti of four basis tubes is a square radius plate, thick 0.50m, it has girt strip, heavily about 1500 tons of this box-type suction foundation structure, the about 5~6m of the high water mark depth of water of infield.
After this box-type suction foundation structure is prefabricated on land, adopt slideway or diving barge that it is moved in water.Before the water, the air vent place on the lamina tecti in 4 basis tubes and intermediate cylinder cabin all is connected inflation and outlet valve and pipeline, on the lamina tecti of 4 basis tubes a proof submersible sand discharging pump is installed respectively under the structure.
In the water process, after basic barrel bottom is not had by water logging, in tube cabin, four bases and middle cylindrical shell, inflate under the box-type suction foundation structure.As the about 4.0m of basic barrel bottom entry, when each cylindrical shell internal gas pressure reached 35.0kPa, structure promptly may float in the water, shows as Fig. 3.
The floating slow traction of box-type suction foundation structure of inflation is left slideway or diving barge, emit the part air in each cylindrical shell, make the about 4.5~5.0m of basic barrel bottom entry, the about 1.0~1.5m of envelope air water post in each cylindrical shell, air in the cylindrical shell overflows when preventing that structure is waved in the haul process like this, make in addition air float hauling advance in air pressure in the cylindrical shell of front side basis greater than the air pressure in the cylindrical shell of rear side basis, like this so as in haul to be advanced structural entity maintenance level.Under this floading condition, can show as Fig. 4 with the structure air float hauling to the erecting bed.
When box-type suction foundation structure air float hauling behind the infield, the alongside of box-type suction foundation structure by the barge of location, is emitted portion gas in the tube, structure is sunk, the mud face is approached in the cylindrical shell bottom; Under the air supporting floating state, the plan-position by the hawser adjustment structure between box-type suction foundation structure and the location barge accurately is positioned structure for the infield, shows as Fig. 5.
Under suitable tide water level situation, evenly emit the air in each cylindrical shell of box-type suction foundation structure, structure is discharged with the air in each cylindrical shell under the deadweight effect and is slowly sunk, and shows as Fig. 7.In the sinking process of this moment, by adjusting the discharge quantity in each cylindrical shell, make structure maintenance level, when occurring tilting in the structure sinking process, the air that stops or reducing in the cylindrical shell of the big side of deflection is emitted, air in the cylindrical shell of maintenance or the little side of increasing deflection is emitted, and behind structure level, evenly emits the air in each cylindrical shell again.On softer ground, venting back structure basic barrel under the deadweight effect can sink to 4~5m in the foundation soil.
For the tide water level situation of this box-type suction foundation structure and corresponding infield, after stopping to sink by the deadweight exhaust, the air in each cylindrical shell is all discharged, and is full of water in the cylindrical shell.Close the venting valve on each top, open the suction pump on each cylindrical shell, the water in the cylindrical shell is extracted out, structure continues to sink, and shows as Fig. 9.In the sinking process of this moment, by adjusting the pump-out of each cylindrical shell, make structure maintenance level, when occurring tilting in the structure sinking process, the cylindrical shell that stops or reducing the big side of deflection draws water, the cylindrical shell of maintenance or the little side of increasing deflection draws water, and behind structure level, evenly extracts the water in each cylindrical shell again out, water in each cylindrical shell is extracted out fully, cylindrical shell top board downside with contact above the ground, then this box-type suction foundation structure is in place, and shows as Figure 10.If it is 60m that an efficient is installed on each tube top, basis 3The suction pump of/h then sank by the deadweight exhaust with 1 hour, drew water to sink structure is in place with 6~8 hours.
When the box-type suction foundation structure adopts the inventive method to transport with the positioning sinking installation, only need one 1500 horsepowers tugboat, a middle-size and small-size location barge, the proof submersible sand discharging pump of 4 7.5kW and corresponding electricity generation system, haul and positioning sinking equipment are simple, easy construction, and subsidence velocity is fast, degree of skewness is controlled easily, and the integrated construction expense is low.

Claims (1)

1. soft-foundation box-cylinder type infrastructure maritime air float hauling and positioning sinking mounting method, described box-type suction foundation structure is meant that it is the overall structure that uncovered cylinder or polygon cylindrical shell are regularly arranged into that a plurality of upper ends are provided with lamina tecti, lower end, wherein the lamina tecti of each cylindrical shell or upper end sidewall are provided with the ventilation and the suction eye of band pipe valve, the maritime air float hauling and the positioning sinking mounting method of such box-type suction foundation structure is characterized in that comprising following process:
(1) air float hauling: under the prefabricated box-type suction foundation structure behind the water, inflate in cylindrical shell by the air vent on each cylindrical shell, make structure float on the water surface, adjust the aeration quantity in the cylindrical shell, make the underwater penetration of each cylindrical shell reach the requirement of satisfying towage stability, just can haul afterwards it;
(2) air supporting location: box-type suction foundation structure air float hauling is to the infield, emit the portion gas in each cylindrical shell, at the bottom of structure is sunk down into tin and the distance between the mud face be 0~1.0m, under this air supporting state, with structure lentamente alongside by a location barge of having had good positioning, adjust the relative position of structure by hawser then, finish the air supporting location at the barge edge; Or arrange 4 to 8 anchorage hawsers in the box-type suction foundation structural perimeter, the air supporting location that utilizes the folding and unfolding of each anchorage hawser to finish the box-type suction foundation structure; Behind the structure air supporting location, continue to emit the gas in each cylindrical shell, structure is sunk, not with before the mud face contact, position observation, be offset, then stop the sinking of exitting, position again as stated above as fruit structure in the cylindrical shell bottom;
(3) going into mud sinks to installing: the mud sinking installation process of going into of box-type suction foundation structure comprises:
1) sink by dead load exhaust outlet and leveling: open ventilation and suction eye on each cylindrical shell, under the dead load effect, gas is discharged in the tube, and cylindrical shell is gone into mud, comes the subsidence velocity of control structure by the control exhaust velocity; The inclination situation of observation structure in the sinking process, when the structure run-off the straight, the gas that stops or reducing in the cylindrical shell of the big side of deflection is emitted, gas in the cylindrical shell of maintenance or the little side of increasing deflection is emitted, make the structure recovery level, continue balanced venting then and sink, until box-type suction foundation dead load and soil body resistance balance, till structure is no longer sunk; If dead load is bigger or the depth of water is bigger, after the gas in the cylindrical shell was discharged entirely, structure also continued to sink under the deadweight effect, and then the interior water body of tube can be discharged from ventilation and suction eye, until dead load and soil body resistance balance, till structure is no longer sunk;
2) leveling of exerting pressure by bleeding is sunk: structure if also have gas to exist in the tube, then utilizes jet vacuum pump from air vent or suction eye gas in the tube to be extracted out after stopping to sink by deadweight, structure continuation sinking; The inclination situation of observation structure in the sinking process, when the structure run-off the straight, the gas that stops or reducing in the cylindrical shell of the big side of deflection is extracted out, gas in the cylindrical shell of maintenance or the little side of increasing deflection is extracted out, make the structure recovery level, continue the equilibrium sinking of bleeding then, till the gas in each cylindrical shell of box-type suction foundation structure is all extracted out;
3) leveling of exerting pressure by drawing water is sunk: after the gas in the box-type suction foundation structure cylindrical shell is all discharged, utilize proof submersible sand discharging pump or jet pump from suction eye water body in the tube to be extracted out, structure continues to sink; The inclination situation of observation structure in the sinking process, when the structure run-off the straight, the water body that stops or reducing in the cylindrical shell of the big side of deflection is extracted out, water body in the cylindrical shell of maintenance or the little side of increasing deflection is extracted out, make the structure recovery level, continue the equilibrium sinking of drawing water then, till the water body in each was all extracted out, the sinking of box-type suction foundation structure installed.
CNB2005100150141A 2005-09-07 2005-09-07 Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure Expired - Fee Related CN100343454C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100150141A CN100343454C (en) 2005-09-07 2005-09-07 Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100150141A CN100343454C (en) 2005-09-07 2005-09-07 Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure

Publications (2)

Publication Number Publication Date
CN1730842A true CN1730842A (en) 2006-02-08
CN100343454C CN100343454C (en) 2007-10-17

Family

ID=35963257

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100150141A Expired - Fee Related CN100343454C (en) 2005-09-07 2005-09-07 Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure

Country Status (1)

Country Link
CN (1) CN100343454C (en)

Cited By (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101169663B (en) * 2007-11-02 2010-06-02 上海市基础工程有限公司 Pneumatic caisson air pressure automatic regulation system
CN101666099B (en) * 2009-09-28 2011-02-16 天津大学 Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology
CN101775812B (en) * 2010-01-21 2011-07-13 道达(上海)风电投资有限公司 Built-in buoy towing barrel-shaped foundation sinking method
CN102322062A (en) * 2011-06-17 2012-01-18 中交第三航务工程局有限公司 Transportation and installation process of base barrel body of barrel type breakwater
CN102926350A (en) * 2012-11-12 2013-02-13 天津大学 Floating transport and towing dock module and construction method thereof
CN101591918B (en) * 2009-06-24 2013-07-24 江苏道达海上风电工程科技有限公司 Foundation reinforcement method based on bucket foundation negative pressure technology
CN101718096B (en) * 2009-11-10 2013-10-30 江苏道达海上风电工程科技有限公司 Large wall thickness foundation sinking method by combining diversion and negative pressure technology
CN103669382A (en) * 2013-12-19 2014-03-26 天津港(集团)有限公司 Installing, leveling and firming method for box-cylinder foundation structure to subside into foundation soil
CN103669383A (en) * 2013-12-13 2014-03-26 中交第一航务工程局有限公司 Method for installing and leveling caisson on seabed ground
CN103981905A (en) * 2014-04-30 2014-08-13 天津大学 Real-time monitoring method for sinking attitude of composite bucket foundation for offshore wind turbine
CN104114771A (en) * 2012-02-10 2014-10-22 尤尼沃萨尔基础公司 Method of installing a foundation in the sea bed and such foundation
CN104164885A (en) * 2014-08-06 2014-11-26 中国海洋石油总公司 Caisson towing method
CN104775398A (en) * 2015-04-13 2015-07-15 天津大学 Box tube type basic siphon corridor water taking structure and application thereof
CN104831741A (en) * 2015-05-13 2015-08-12 天津大学 Box and bucket type foundation purifying water building structure and application thereof
CN105604083A (en) * 2016-03-17 2016-05-25 王燏斌 Bridge deep-water sunk well foundation construction method
CN105735337A (en) * 2016-03-17 2016-07-06 王燏斌 Bridge deep water open caisson foundation construction method
CN105735241A (en) * 2015-04-13 2016-07-06 天津大学 Application of siphon corridor water taking structure of box drum type foundation to soft foundation
CN105862658A (en) * 2016-03-31 2016-08-17 中交第三航务工程局有限公司江苏分公司 Double-ship counter-pulling positioning method of breakwater barrel type component
CN105862896A (en) * 2016-03-31 2016-08-17 中交第三航务工程局有限公司江苏分公司 Mounting method of breakwater barrel type component
CN106049526A (en) * 2015-04-02 2016-10-26 韩国海洋科学技术院 Suction foundation with improved self-weight sinking performance and construction method thereof
CN106759426A (en) * 2016-12-30 2017-05-31 中交第二航务工程局有限公司 Soft layer well sinking control method and device
CN106948355A (en) * 2017-03-20 2017-07-14 天津大学 A kind of pocketed caisson foundation sinking attitude presents control system
CN106988335A (en) * 2017-03-20 2017-07-28 天津大学 A kind of compound barrel-shaped foundation sinking posture feedback control system
CN108104148A (en) * 2017-12-12 2018-06-01 河海大学 A kind of thin-walled steel suction bucket basis with reinforced pipe and its installation method
CN109881663A (en) * 2019-04-09 2019-06-14 中交一航局第二工程有限公司 Concrete tubular pile and its pile-driving system and sea area pile sinking construction method
CN110172991A (en) * 2019-05-07 2019-08-27 天津大学 A kind of three blower foundations recycling construction method
CN110397093A (en) * 2019-07-08 2019-11-01 天津大学 A kind of negative pressure control apparatus and its application method of adjustable bucket foundation sinking rate
CN110924420A (en) * 2019-11-18 2020-03-27 清华大学 Composite foundation for treating underwater soft soil foundation based on rapid prepressing consolidation
CN111350191A (en) * 2020-03-04 2020-06-30 中交第三航务工程勘察设计院有限公司 Bucket type foundation structure pumping system and construction process thereof
CN111576428A (en) * 2020-05-20 2020-08-25 华电重工股份有限公司 Attitude feed control system and attitude feed control method for fan foundation sinking process
CN113266030A (en) * 2021-05-13 2021-08-17 武汉市市政建设集团有限公司 Underwater bottom sealing construction method for deep well
CN113914356A (en) * 2021-10-22 2022-01-11 中国地质大学(武汉) Deepwater installation device and method for cylindrical foundation
CN114182764A (en) * 2021-11-25 2022-03-15 上海勘测设计研究院有限公司 Foundation anti-scouring device and construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3387398B2 (en) * 1997-11-13 2003-03-17 株式会社大林組 How to penetrate caisson foundation
JP2001323480A (en) * 2000-05-16 2001-11-22 Ohbayashi Corp Method of constructing underwater foundation
CN2467578Y (en) * 2001-03-19 2001-12-26 天津大学 Removable light caisson foundation soil water earth-retaining and water retaining structure
CN2530980Y (en) * 2002-03-28 2003-01-15 天津大学 Box type base submarine tunnel structure
CN2567270Y (en) * 2002-08-28 2003-08-20 天津大学 Movable cylinder foundation breakwater structure

Cited By (47)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101169663B (en) * 2007-11-02 2010-06-02 上海市基础工程有限公司 Pneumatic caisson air pressure automatic regulation system
CN101591918B (en) * 2009-06-24 2013-07-24 江苏道达海上风电工程科技有限公司 Foundation reinforcement method based on bucket foundation negative pressure technology
CN101666099B (en) * 2009-09-28 2011-02-16 天津大学 Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology
CN101718096B (en) * 2009-11-10 2013-10-30 江苏道达海上风电工程科技有限公司 Large wall thickness foundation sinking method by combining diversion and negative pressure technology
CN101775812B (en) * 2010-01-21 2011-07-13 道达(上海)风电投资有限公司 Built-in buoy towing barrel-shaped foundation sinking method
CN102322062A (en) * 2011-06-17 2012-01-18 中交第三航务工程局有限公司 Transportation and installation process of base barrel body of barrel type breakwater
CN102322062B (en) * 2011-06-17 2013-04-10 中交第三航务工程局有限公司 Transportation and installation process of base barrel body of barrel type breakwater
CN104114771B (en) * 2012-02-10 2016-04-20 尤尼沃萨尔基础公司 The method of mounting foundation and this ground in sea bed
CN104114771A (en) * 2012-02-10 2014-10-22 尤尼沃萨尔基础公司 Method of installing a foundation in the sea bed and such foundation
US10113290B2 (en) 2012-02-10 2018-10-30 Universal Foundation A/S Method of installing a foundation in the sea bed and such foundation
CN102926350A (en) * 2012-11-12 2013-02-13 天津大学 Floating transport and towing dock module and construction method thereof
CN102926350B (en) * 2012-11-12 2015-08-19 天津大学 A kind of can the construction method of dock module of transportation by driving towage
CN103669383A (en) * 2013-12-13 2014-03-26 中交第一航务工程局有限公司 Method for installing and leveling caisson on seabed ground
CN103669383B (en) * 2013-12-13 2015-12-02 中交第一航务工程局有限公司 A kind of method of installation and leveling caisson on ground, seabed
CN103669382A (en) * 2013-12-19 2014-03-26 天津港(集团)有限公司 Installing, leveling and firming method for box-cylinder foundation structure to subside into foundation soil
CN103981905A (en) * 2014-04-30 2014-08-13 天津大学 Real-time monitoring method for sinking attitude of composite bucket foundation for offshore wind turbine
CN103981905B (en) * 2014-04-30 2016-02-24 天津大学 A kind of offshore wind turbine compound cartridge type foundation immersion attitude method of real-time
CN104164885A (en) * 2014-08-06 2014-11-26 中国海洋石油总公司 Caisson towing method
CN106049526B (en) * 2015-04-02 2019-01-01 韩国海洋科学技术院 Suction foundation with improved self-weight sinking performance and construction method thereof
CN106049526A (en) * 2015-04-02 2016-10-26 韩国海洋科学技术院 Suction foundation with improved self-weight sinking performance and construction method thereof
CN105735241A (en) * 2015-04-13 2016-07-06 天津大学 Application of siphon corridor water taking structure of box drum type foundation to soft foundation
CN104775398B (en) * 2015-04-13 2016-09-21 天津大学 A kind of box-type suction foundation siphon gallery water intaking structure
CN104775398A (en) * 2015-04-13 2015-07-15 天津大学 Box tube type basic siphon corridor water taking structure and application thereof
CN104831741A (en) * 2015-05-13 2015-08-12 天津大学 Box and bucket type foundation purifying water building structure and application thereof
CN105735337A (en) * 2016-03-17 2016-07-06 王燏斌 Bridge deep water open caisson foundation construction method
CN105604083A (en) * 2016-03-17 2016-05-25 王燏斌 Bridge deep-water sunk well foundation construction method
CN105862658B (en) * 2016-03-31 2018-04-17 中交第三航务工程局有限公司江苏分公司 A kind of double ships of breakwater tub component are to drawing localization method
CN105862658A (en) * 2016-03-31 2016-08-17 中交第三航务工程局有限公司江苏分公司 Double-ship counter-pulling positioning method of breakwater barrel type component
CN105862896A (en) * 2016-03-31 2016-08-17 中交第三航务工程局有限公司江苏分公司 Mounting method of breakwater barrel type component
CN105862896B (en) * 2016-03-31 2017-10-13 中交第三航务工程局有限公司江苏分公司 A kind of installation method of breakwater tub component
CN106759426A (en) * 2016-12-30 2017-05-31 中交第二航务工程局有限公司 Soft layer well sinking control method and device
CN106988335A (en) * 2017-03-20 2017-07-28 天津大学 A kind of compound barrel-shaped foundation sinking posture feedback control system
CN106948355A (en) * 2017-03-20 2017-07-14 天津大学 A kind of pocketed caisson foundation sinking attitude presents control system
CN106948355B (en) * 2017-03-20 2019-10-29 天津大学 A kind of pocketed caisson foundation sinking posture feedback control system
CN106988335B (en) * 2017-03-20 2019-10-29 天津大学 A kind of compound barrel-shaped foundation sinking posture feedback control system
CN108104148A (en) * 2017-12-12 2018-06-01 河海大学 A kind of thin-walled steel suction bucket basis with reinforced pipe and its installation method
CN109881663A (en) * 2019-04-09 2019-06-14 中交一航局第二工程有限公司 Concrete tubular pile and its pile-driving system and sea area pile sinking construction method
CN110172991B (en) * 2019-05-07 2021-06-04 天津大学 Construction method for recycling three-cylinder fan foundation
CN110172991A (en) * 2019-05-07 2019-08-27 天津大学 A kind of three blower foundations recycling construction method
CN110397093A (en) * 2019-07-08 2019-11-01 天津大学 A kind of negative pressure control apparatus and its application method of adjustable bucket foundation sinking rate
CN110924420A (en) * 2019-11-18 2020-03-27 清华大学 Composite foundation for treating underwater soft soil foundation based on rapid prepressing consolidation
CN111350191A (en) * 2020-03-04 2020-06-30 中交第三航务工程勘察设计院有限公司 Bucket type foundation structure pumping system and construction process thereof
CN111350191B (en) * 2020-03-04 2021-08-31 中交第三航务工程勘察设计院有限公司 Bucket type foundation structure pumping system and construction process thereof
CN111576428A (en) * 2020-05-20 2020-08-25 华电重工股份有限公司 Attitude feed control system and attitude feed control method for fan foundation sinking process
CN113266030A (en) * 2021-05-13 2021-08-17 武汉市市政建设集团有限公司 Underwater bottom sealing construction method for deep well
CN113914356A (en) * 2021-10-22 2022-01-11 中国地质大学(武汉) Deepwater installation device and method for cylindrical foundation
CN114182764A (en) * 2021-11-25 2022-03-15 上海勘测设计研究院有限公司 Foundation anti-scouring device and construction method

Also Published As

Publication number Publication date
CN100343454C (en) 2007-10-17

Similar Documents

Publication Publication Date Title
CN100343454C (en) Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure
CN107542101B (en) Construction method of offshore four-buoy-buoyancy tank combined foundation structure
US3896628A (en) Marine structures
CN1240940C (en) Method and system for installing and transporting an offshore wind power station at sea
CN107653895B (en) Combined offshore six-buoy buoyancy tank foundation structure and construction method thereof
CN107630461B (en) Combined offshore four-buoy buoyancy tank foundation structure and construction method thereof
CN102322062B (en) Transportation and installation process of base barrel body of barrel type breakwater
CN1763314A (en) Method for moving large-scale heavy member to launch and float on water, and member mounting method
CN1317160C (en) Self-installed suction anchor
US11891768B2 (en) Auxiliary structure for floating and sinking a whole offshore wind turbine with suction bucket foundation(s)
NL2004212C2 (en) Floating marine structure with suction piles and platform resting on a barge clamped between suction piles and platform.
CN100432343C (en) Cylindrical base sea embankment structure for tretching over and protecting suhmarine pipeline and its mounting method
CN106830381B (en) Seabed oxygenation device
CN113463679B (en) Offshore wind power multi-cylinder jacket foundation installation and recovery method
CN1613717A (en) Floating transported and sucking cylindered anchor device and its operating method
CN211032946U (en) Movable free-rising and sinking storm platform
CN111472377A (en) Offshore wind power integral installation device and method utilizing mat-buoyancy tank
CN2687006Y (en) Submersible semi-submerged barge
CN2752320Y (en) Iceproof self-mounting barrel-type basic wellhead platform
CN210562256U (en) Offshore wind power barrel type foundation construction structure
CN213062078U (en) Offshore wind power integral installation device utilizing mat and buoyancy tank
CN212506365U (en) High pile cap foundation installation system suitable for ultra-shallow water area
CN2545087Y (en) Entering-in-mud air float lifting platform for launching, etc.
CN217374826U (en) A tubular pile conveyer for rising move back tide mud flat
CN221589683U (en) Gravity reinforced concrete anchor foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20071017

Termination date: 20210907

CF01 Termination of patent right due to non-payment of annual fee