CN1763314A - Method for moving large-scale heavy member to launch and float on water, and member mounting method - Google Patents

Method for moving large-scale heavy member to launch and float on water, and member mounting method Download PDF

Info

Publication number
CN1763314A
CN1763314A CN 200510072038 CN200510072038A CN1763314A CN 1763314 A CN1763314 A CN 1763314A CN 200510072038 CN200510072038 CN 200510072038 CN 200510072038 A CN200510072038 A CN 200510072038A CN 1763314 A CN1763314 A CN 1763314A
Authority
CN
China
Prior art keywords
water
slope
air bag
under
floating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200510072038
Other languages
Chinese (zh)
Other versions
CN100419164C (en
Inventor
王炜
赵之顺
谭世森
郑维武
谢绍富
谭清宗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hangsheng Construction Group Co., Ltd.
Original Assignee
Guangdong Hangsheng Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Hangsheng Engineering Co Ltd filed Critical Guangdong Hangsheng Engineering Co Ltd
Priority to CNB2005100720380A priority Critical patent/CN100419164C/en
Publication of CN1763314A publication Critical patent/CN1763314A/en
Application granted granted Critical
Publication of CN100419164C publication Critical patent/CN100419164C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The invention provides a waterborne rafting and setting component through slope moving the large bulk weight component from land to water by gas cell, which comprises the following steps: (1) building the slope; (2) setting floating-auxiliary gas cell on the component; (3) putting, fixing and rolling the gas cell on the slope; (4) moving the large bulk weight component from land to water through slope and floating; (5) floating the waterborne component; (6) setting the waterborne component.

Description

The method that water, aquatic floating and transportation and member are installed under the movement large volume heavy component
Technical field
The present invention relates to a kind of large volume heavy component transportation and mounting method, specifically is to utilize air bag to pass through the method that water under the slope movement large volume heavy component, aquatic floating and transportation and member are installed.
Background technology
In port and pier and other (as rivers, Hu Hai etc.) waterborne civil engineering, because of the requirement of engineering construction project function of use, often design has large-scale component, as caisson, box culvert, large cylinder, cover plate, square, relieving slab etc.Construction to these large-scale components comprises transportation and the method that generally adopts prefabricated installation is installed, when this process of realization, the most frequently used construction technology method is with hanging ship prefabricated member to be hung on barge, with tugboat barge haul to predetermined infield, again with hanging ship the member installation of slinging.There are two shortcomings in this method:
1, need large-scale ship and the barge of hanging, and a large-scale student contributions pooled to pay for class activities of hanging ship and barge is very high, form higher engineering cost;
2, large-scale ship and the barge of hanging need take bigger satisfied waters of hanging ship and barge job requirements when construction operation, when existing construction waters hour, this hanging method will be restricted.
Also have in addition by the slope movement, adopt under water and do rail beam, lay the flatcar track on the rail beam, utilize flatcar the local floating of member movement to the enough depth of water.But do rail beam and track under water, the technical requirements height, engineering quantity is big, goes out the cost height of fortune.
Summary of the invention
Deficiency at the prior art existence, the objective of the invention is to put on the slope, fix and scroll airbag in order to solve under water, and water under the movement member, the problem of transportation by driving and installation component on the water then, what provide that a kind of cost is low, manufacture craft is simple and easy to operate utilizes air bag in the method that goes out fortune, installation component.
To achieve these goals, the technical solution used in the present invention specifically comprises the steps:
(1) build on the slope: the slope by land section and under water section forms, land section employing lay a good foundation upper berth, slope fill block stone is poured into a mould concrete method on the piece stone; Foundation trench dredging, fill block stone throwing, tamping block stone, leveling are adopted in slope section under water, and the flow and method of the piece stone surface layer that will flatten at last shop one deck steel plate or steel concrete cushion block builds the fortune slope;
(2) floating gasbag is being installed on the member:, determine the specification and the quantity of air bag according to member required size that helps buoyancy in water;
(3) put on the slope and fixation balloon: set and fixedly scoop out air bag on the slope by certain spacing;
(4) member is moved down in water by land on the slope: before member enters the slope,,, glided by the deadweight of member after member enters the slope to front haulage by hoist engine, hold member backward by hoist engine, make member slowly descend water until floating fully;
(5) member transportation by driving: the member gross buoyancy after floating gasbag is installed can not sink in water greater than deadweight, therefore only needs a tugboat traction to get final product, under the situation that stormy waves or trend are arranged, for safety, little tugboat of traction behind member is so that the direction of control member transportation by driving;
(6) member is installed: member is hauled to the predetermined area, promptly on the hoist engine around heaving pile on the member is connected to, so that adjust member position in the plane by the folding and unfolding of hoist engine, after member position in the plane reaches accuracy requirement, promptly pass through air bag deflation, the total buoyancy of member reduces, and when gross buoyancy during less than deadweight, member promptly sinks and is installed to the precalculated position.
The present invention can realize on concrete details like this, in step (1), and the pre-buried fixing draw ring of air bag under water on the steel plate of section or the steel concrete cushion block under water on the slope; In step (3), adopt the reservation draw ring to fix air bag under water with the rope made of hemp; In step (4), member down slides into air bag top under water by deadweight, holds member with the method for post-tensioning hoist engine earlier, and after again airbag aeration under water being made its rope made of hemp that rises broken reach predetermined pressure to prop up member, the wire rope that unclamps hoist engine makes member continuation downslide.
Compared with prior art, the present invention has following beneficial effect:
(1) with tradition transportation and mounting method ratio, the characteristics of utilizing air bag itself to have rolling, buoyancy and can carrying out the buoyancy adjustment, thereby operation is very easy, and reduce construction cost greatly.
(2) hanging ship with employing compares with barge: it is few to drop into main equipment, reduces cost greatly.
(3) hanging ship with employing compares with barge: less demanding, applied widely to the construction waters.
(4) hanging ship with employing compares with barge: flexibility is strong, and the duration is short.
(5) compare with adopting rail beam: air bag requires low to the slope construction, engineering quantity is little, and the duration is short, and cost is low.
Description of drawings
Fig. 1 is an operational flowchart of the present invention;
Air bag scheme of installation when Fig. 2 has cavity for member;
Air bag scheme of installation when Fig. 3 does not have cavity for member;
Fig. 4 is preclival schematic diagram for member moves to;
Fig. 5 moves to the schematic diagram on land section of slope for member;
Fig. 6 moves to the slope schematic diagram of section under water for member;
The schematic diagram that Fig. 7 floats in the water for member moves to;
Fig. 8 is an A portion enlarged diagram among Fig. 6;
Fig. 9 is a B portion enlarged diagram among Fig. 6;
Figure 10 is a member mounting plane schematic diagram.
The specific embodiment
Below in conjunction with accompanying drawing the present invention is further described but does not constitute any limitation of the invention:
, the invention discloses a kind of air bag that utilizes and pass through water under the slope movement large volume heavy component to shown in Figure 10 as Fig. 1, the method for transportation by driving and installation component on the water comprises the steps: then
(1) build on the slope, as shown in Figure 4, the slope by land section and under water section forms, land section 1 employing lay a good foundation upper berth, slope fill block stone is poured into a mould concrete method on the piece stone; The slope is section 2 general employing foundation trench dredging, fill block stone throwing, tamping block stone, leveling under water, the flow and method of the piece stone surface layer that will flatten at last shop one deck steel plate or concrete pad builds the fortune slope, and on steel plate or steel concrete cushion block the pre-buried fixing draw ring 3 of air bag under water.
(2) floating gasbag is being installed on the member:, determine the specification and the quantity of air bag 9 according to member 6 required size that helps buoyancy in water; Before the water, install floating gasbag in advance under the object, and the gas of substituting the bad for the good, so that under member, have enough buoyancy during water.
The specification size and the quantity of floating gasbag are decided by calculating.If the deadweight of member is G, the buoyancy of self is F Member, then help buoyancy F Air bag=G-F Member, because the proportion of water is 1.0, so the cumulative volume V=F of required floating gasbag Air bag/ g=(G-F Member)/g according to the volume of every air bag, can calculate required air bag quantity.The size of air bag is decided according to the size and the shape of member.
As shown in Figure 2, during (or about) runs through before and after member 6 has cavity, can be installed in air bag 9 in the member cavities, such as box culvert;
As shown in Figure 3, when the unmatched back of member (about) cavity that runs through or during for real chamber, can be contained in both sides, member front and back (or about) to floating gasbag 9 usefulness bundling belts 10, such as caisson, square, relieving slab, large cylinder etc., for ease of haul, generally be installed in the left and right sides of member.
(3) put on the slope and scoop out air bag: as shown in Figure 4, scoop out air bag 4 by land the setting of design attitude.For the air bag that scoops out under water,, must adopt fixing method in order to prevent the drift of air bag under current, wave and air bag self buoyancy.One of method is as Fig. 8,9, with the rope made of hemp 5 fixing air bags 4 under water, and when sliding under water the air bag top under the member, the airbag aeration rope made of hemp 5 (as Fig. 9) that rises brokenly under water, air bag promptly can roll downwards with member;
(4) member on the slope by land to moving down in the water: shown in Fig. 5,6,7, before member 6 enters the slope, by hoist engine 7 to front haulage, after member 6 enters the slope, deadweight by member is glided, and holds member backward by hoist engine 7, makes member slowly descend water until floating fully;
(5) member transportation by driving: member 6 gross buoyancies after floating gasbag 9 is installed can not sink in water greater than deadweight, therefore have only the tugboat traction of need to get final product, and need not large-scale ship and the barge of hanging.Under the situation that stormy waves or trend are arranged, for safety, little tugboat of traction behind member is so that the direction of control member transportation by driving.
Tugboat determines that by calculating traction power traction power is pressed following calculating:
F=K·A·r w·V 2/2g
In the formula: A=B (T+ δ)
B---member width (m);
T---member drinking water (m);
δ---water burst height (m) during transportation by driving;
r w=10.25KN/m 3
K is the dash form coefficient, and rectangle is got k=1.0.
(6) member is installed: member is hauled to the predetermined area, promptly on the hoist engine around heaving pile on the member 6 is connected to, as shown in figure 10, so that adjust member 6 position in the plane by hoist engine 11 folding and unfoldings, the placement position of hoist engine and specification quantity are decided on physical condition.The principle that the hoist engine plan-position is determined is to make member front and back move left and right on the plan-position, makes its plan-position meet predetermined requirement.Hoist engine specification and quantity are decided on the size of member, and specification is generally 3 ~ 10 tons, and quantity is generally 5 ~ 8, are distributed in member all directions all around.
(comprising the reliable structure that is higher than the water surface) can be utilized if there is land-based area the erecting bed, and hoist engine is arranged in land-based area as far as possible so, with handled easily.Can not utilize if there is land-based area, then berth in the precalculated position, hoist engine aboard ship is installed can be served the same role yet, reach identical purpose with barge 12.
In such mounting method used barge with hang the ship mounting method and be essentially different with used barge.The used barge of this installation method only is that required tonnage is little for installation hoist engine usefulness.And hang the used barge of ship mounting method is to load member usefulness, and required tonnage is big, so, even do not count, be separately the barge that loads member hanging ship, its student contributions pooled to pay for class activities are also quite high.This also is the advantage place of this job practices.
After member position in the plane reached accuracy requirement, promptly by air bag deflation, the total buoyancy of member reduced, and when gross buoyancy during less than deadweight, member promptly sinks, and in the sinking process, out of position whether observation component.If depart from, then adjust by the hoist engine folding and unfolding.After sinking to finishing, whether observation position is accurate once more, if do not reach designing requirement, then airbag aeration, member come-up are adjusted behind the position sinking again.Member is installed on the preposition.The member sinking is all exitted the air bag on the member to the precalculated position, and releasing is got off.Each hoist engine unties the mooring rope simultaneously, has promptly finished the installation work of member.
Adopt technical scheme of the present invention, build the fairly simple slope of based process, adopt draw ring and the fixing air bag under water of the rope made of hemp reserved on the slope, by the hoist engine post-tensioning member of slope movement is under water become the movement method similar to land level land translation member again and solve on the slope under water the problem of water under the movement member, the present invention can reduce cost and the technical requirements that builds the fortune ramp greatly.
Simultaneously, the present invention has utilized air bag itself to have the characteristics of buoyancy, after being installed in air bag on the member, tug on the water and transport and on preposition, install, slowly to air bag deflation, make member slowly sink and control the process of installation that it is very convenient to operate during installation with hoist engine, method than traditional water transportation and installation reduces construction cost greatly.

Claims (4)

1, the method that water, aquatic floating and transportation and member are installed under a kind of movement large volume heavy component, its feature comprises the steps:
(1) build on the slope: the slope by land section and under water section forms, land section employing lay a good foundation upper berth, slope fill block stone is poured into a mould concrete method on the piece stone; Foundation trench dredging, fill block stone throwing, tamping block stone, leveling are adopted in slope section under water, build the fortune slope at the piece stone surface layer shop one deck steel plate of leveling or the flow and method of steel concrete cushion block at last;
(2) floating gasbag is being installed on the member:, determine the specification and the quantity of air bag according to member required size that helps buoyancy in water;
(3) put on the slope and fixation balloon: put on the slope and fix by certain spacing and scoop out air bag;
(4) member is moved down in water by land on the slope: before member enters the slope,,, glided by the deadweight of member after member enters the slope to front haulage by hoist engine, hold member backward by hoist engine, make member slowly descend water until floating fully;
(5) member transportation by driving: the member gross buoyancy after floating gasbag is installed can not sink in water greater than deadweight, therefore only needs a tugboat traction to get final product, under the situation that stormy waves or trend are arranged, for safety, little tugboat of traction behind member is so that the direction of control member transportation by driving; Member continue under water to roll forward and reach after the draft automatically floating or reach preposition after by hanging the ship lifting;
(6) member is installed: member is hauled to the predetermined area, promptly on the hoist engine around heaving pile on the member is connected to, so that adjust member position in the plane by the folding and unfolding of hoist engine, after member position in the plane reaches accuracy requirement, promptly pass through air bag deflation, the total buoyancy of member reduces, and when gross buoyancy during less than deadweight, member promptly sinks and is installed to the precalculated position.
2, water under the movement large volume heavy component according to claim 1, aquatic floating and transportation and the member method of installing is characterized in that: in step (1), and the pre-buried fixing draw ring of air bag under water on the steel plate of section or the steel concrete cushion block under water on the slope; In step (3), adopt the reservation draw ring to fix air bag under water with the rope made of hemp; In step (4), by sliding into air bag top under water under the deadweight of member, hold member with the method for post-tensioning hoist engine earlier, after again airbag aeration under water being made its rope made of hemp that rises broken reach predetermined pressure to prop up member, the wire rope that unclamps hoist engine makes member continue downslide.
3, the method that water, aquatic floating and transportation and member are installed under the movement large volume heavy component according to claim 1, it is characterized in that: the large volume heavy component in step (2) be front and back or about run through cavity the time, can be installed in air bag in the member cavities.
4, according to claim 1ly utilize that air bag transports on the water, the method for installation component, it is characterized in that: when the member in step (2) is solid, can be installed in air bag before and after the member or the left and right sides, and preferably be installed in the left and right sides of member.
CNB2005100720380A 2005-05-26 2005-05-26 Method for moving large-scale heavy member to launch and float on water, and member mounting method Expired - Fee Related CN100419164C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100720380A CN100419164C (en) 2005-05-26 2005-05-26 Method for moving large-scale heavy member to launch and float on water, and member mounting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100720380A CN100419164C (en) 2005-05-26 2005-05-26 Method for moving large-scale heavy member to launch and float on water, and member mounting method

Publications (2)

Publication Number Publication Date
CN1763314A true CN1763314A (en) 2006-04-26
CN100419164C CN100419164C (en) 2008-09-17

Family

ID=36747616

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100720380A Expired - Fee Related CN100419164C (en) 2005-05-26 2005-05-26 Method for moving large-scale heavy member to launch and float on water, and member mounting method

Country Status (1)

Country Link
CN (1) CN100419164C (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100465389C (en) * 2007-03-23 2009-03-04 中铁大桥局集团第二工程有限公司 Bridge heavy steel cofferdam gasbag watering method
CN101282028B (en) * 2008-05-29 2010-06-09 国网武汉高压研究院 Method and apparatus for laying subaqueous cable
CN101476282B (en) * 2008-12-30 2010-11-17 中铁大桥局集团第一工程有限公司 Construction method for long, large and heavy component in river
CN101537875B (en) * 2008-05-05 2012-07-04 中交一航局第二工程有限公司 Process for shipping and launching wharfboat by floating same on vertical quay wall with assistance of airbag
CN102582799A (en) * 2012-04-11 2012-07-18 广新海事重工股份有限公司 Buoyancy tank and afloat buoyancy tank joining process
CN102992242A (en) * 2012-12-07 2013-03-27 中铁十局集团济南铁路工程有限公司 Steering method used when carrying large heavy by rolling air bags
CN104746525A (en) * 2015-01-22 2015-07-01 中交二航局第三工程有限公司 Lifting platform system for placing large caisson in water
CN107882332A (en) * 2017-11-09 2018-04-06 浙江恒盛建设集团有限公司 The building construction method of integrated casting
CN108202847A (en) * 2016-12-19 2018-06-26 龙口中集来福士海洋工程有限公司 Small floating thing launching method
CN108252328A (en) * 2018-02-01 2018-07-06 中交第航务工程局有限公司 The lower water transportation by driving of assembled pipe gallery and underwater assembling process
CN108583811A (en) * 2018-05-29 2018-09-28 湖北海洋工程装备研究院有限公司 A kind of floating and transportation method
CN109083011A (en) * 2018-07-31 2018-12-25 中交二航局第二工程有限公司 The installation method of steel drawn bridge when lifting equipment scarce capacity
CN111101515A (en) * 2019-12-31 2020-05-05 中交三航(上海)新能源工程有限公司 Large-diameter single-pile floating transportation construction method
CN112644655A (en) * 2020-11-26 2021-04-13 海洋石油工程股份有限公司 Method for abandoning jacket dragging ashore
CN113071611A (en) * 2021-04-07 2021-07-06 长江重庆航道工程局 Caisson transportation construction method in restricted channel

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1093583C (en) * 1996-07-01 2002-10-30 交通部第一航务工程局 Launching method for laud region prefabricated sinking caisson
JP3790984B2 (en) * 2001-02-28 2006-06-28 五洋建設株式会社 Underwater installation method and apparatus for sheet-like material

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100465389C (en) * 2007-03-23 2009-03-04 中铁大桥局集团第二工程有限公司 Bridge heavy steel cofferdam gasbag watering method
CN101537875B (en) * 2008-05-05 2012-07-04 中交一航局第二工程有限公司 Process for shipping and launching wharfboat by floating same on vertical quay wall with assistance of airbag
CN101282028B (en) * 2008-05-29 2010-06-09 国网武汉高压研究院 Method and apparatus for laying subaqueous cable
CN101476282B (en) * 2008-12-30 2010-11-17 中铁大桥局集团第一工程有限公司 Construction method for long, large and heavy component in river
CN102582799A (en) * 2012-04-11 2012-07-18 广新海事重工股份有限公司 Buoyancy tank and afloat buoyancy tank joining process
CN102992242A (en) * 2012-12-07 2013-03-27 中铁十局集团济南铁路工程有限公司 Steering method used when carrying large heavy by rolling air bags
CN102992242B (en) * 2012-12-07 2015-04-29 中铁十局集团济南铁路工程有限公司 Steering method used when carrying large heavy by rolling air bags
CN104746525A (en) * 2015-01-22 2015-07-01 中交二航局第三工程有限公司 Lifting platform system for placing large caisson in water
CN108202847A (en) * 2016-12-19 2018-06-26 龙口中集来福士海洋工程有限公司 Small floating thing launching method
CN107882332A (en) * 2017-11-09 2018-04-06 浙江恒盛建设集团有限公司 The building construction method of integrated casting
CN108252328A (en) * 2018-02-01 2018-07-06 中交第航务工程局有限公司 The lower water transportation by driving of assembled pipe gallery and underwater assembling process
CN108583811A (en) * 2018-05-29 2018-09-28 湖北海洋工程装备研究院有限公司 A kind of floating and transportation method
CN108583811B (en) * 2018-05-29 2019-09-03 湖北海洋工程装备研究院有限公司 A kind of floating and transportation method
CN109083011A (en) * 2018-07-31 2018-12-25 中交二航局第二工程有限公司 The installation method of steel drawn bridge when lifting equipment scarce capacity
CN111101515A (en) * 2019-12-31 2020-05-05 中交三航(上海)新能源工程有限公司 Large-diameter single-pile floating transportation construction method
CN112644655A (en) * 2020-11-26 2021-04-13 海洋石油工程股份有限公司 Method for abandoning jacket dragging ashore
CN113071611A (en) * 2021-04-07 2021-07-06 长江重庆航道工程局 Caisson transportation construction method in restricted channel

Also Published As

Publication number Publication date
CN100419164C (en) 2008-09-17

Similar Documents

Publication Publication Date Title
CN1763314A (en) Method for moving large-scale heavy member to launch and float on water, and member mounting method
CN100343454C (en) Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure
CN1240582C (en) Temporary floatation stabilization device and method
US3896628A (en) Marine structures
CN101774422B (en) Novel offshore installation construction resource-combined type pontoon barge
CN101837929B (en) Operation method for lifting fan for barge in shoal area
CN102322062B (en) Transportation and installation process of base barrel body of barrel type breakwater
CN103103972B (en) Prefabricate type nautical fixed platform and installing method
CN111980067B (en) Construction method for long-distance conveying of immersed tube by adopting refuting process
CN103806407A (en) Pile-bucket integrated wharf structure and construction method thereof
CN113668545A (en) Leveling method for semi-floating foundation bed of immersed tube submarine tunnel
CN112049641A (en) Energy-saving deep sea mining system based on buoyancy gravity difference vertical lifting device
CN103119222A (en) Surface-breaking re-usable submergeable template for installing one or more submerged columns/piles
CN101781887A (en) Overhang installation method for upper structure of offshore platform
CN104060592B (en) Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles
CN2687006Y (en) Submersible semi-submerged barge
CN1093583C (en) Launching method for laud region prefabricated sinking caisson
CN104973210B (en) Artificial structure's facility construction technology waterborne
TWI834746B (en) Work platform vessel equipped with crane and method of using the crane
US20130074758A1 (en) Anchoring apparatus for wave energy converters
CN209142332U (en) Boat equipment leans in vertical type system
CN101666102B (en) Movable prefabricated barrel-type gravity mixed foundation
CN216739456U (en) Wharf construction device
CN105648985B (en) Islands and reefs development & construction method
CN1312203A (en) Air and water lift platform with barrel-shaped footing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: HANG SHENG GUANGDONG CONSTRUCTION GROUP CO.

Free format text: FORMER NAME: HANGSHENG ENGINEERING CO., LTD., GUANGDONG PROV.

CP03 Change of name, title or address

Address after: Haizhuqu District Binjiang road Guangzhou city Guangdong province Yuanan Street No. 3 Lane

Patentee after: Guangdong Hangsheng Construction Group Co., Ltd.

Address before: Haizhuqu District Binjiang road Guangzhou city Guangdong province Yuanan Street No. 3 Lane

Patentee before: Hangsheng Engineering Co., Ltd., Guangdong Prov.

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080917

Termination date: 20130526