CN104746525A - Lifting platform system for placing large caisson in water - Google Patents

Lifting platform system for placing large caisson in water Download PDF

Info

Publication number
CN104746525A
CN104746525A CN201510031048.3A CN201510031048A CN104746525A CN 104746525 A CN104746525 A CN 104746525A CN 201510031048 A CN201510031048 A CN 201510031048A CN 104746525 A CN104746525 A CN 104746525A
Authority
CN
China
Prior art keywords
platform
water
steel pipe
prefabricated
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510031048.3A
Other languages
Chinese (zh)
Inventor
刘忠友
叶跃平
茅兵海
姚平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No3 Engineering Co Ltd Of Cccc Second Harbor Engineering Co
Original Assignee
No3 Engineering Co Ltd Of Cccc Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No3 Engineering Co Ltd Of Cccc Second Harbor Engineering Co filed Critical No3 Engineering Co Ltd Of Cccc Second Harbor Engineering Co
Priority to CN201510031048.3A priority Critical patent/CN104746525A/en
Publication of CN104746525A publication Critical patent/CN104746525A/en
Pending legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

A lifting platform system for placing a large caisson in water comprises a plurality of prefabricated platforms and lifting platforms supported in water. One side of the lifting platform leans on the edges of the prefabricated platforms. The tops of the prefabricated platforms and the tops of the lifting platforms are the same in structure and each sequentially comprise a face plate and a truss beam of a mesh structure from top to bottom. The lower sides of the truss beams of the prefabricated platforms are supported by the top ends of steel pipe columns which are arrayed in a matrix mode. The lower ends of the steel pipe columns are hit into a water bottom mud field. The lower sides of the truss beams of the lifting platforms are hinged to the top ends of the lifting rods. The bottoms of the lifting rods with the lower ends extending in the steel pipe columns are supported by a prefabricated concrete foundation at the lower ends of the steel pipe columns through a plurality of supporting bases. Without renting a semi-submersible barge prefabricated and transported large caisson, the prefabricating and transporting cost of the large caisson is greatly reduced, and the transporting safety of the large caisson is improved. After a project ends, the prefabricating platforms and the lifting platforms can be repeatedly used after being detached, and the resource utilization rate is increased.

Description

Water lifting platform system under Large Caisson
Technical field
The present invention relates to a kind of lower water transport communication system of box concrete precast element for building large pier, embankment, particularly relating to a kind of large-sized concrete caisson and being transported to plateform system in water from land or pier, belonging to hydraulic engineering technical field.
Background technology
it is prefabricated that Large Caisson is typically chosen in land precasting yard, and then barge transport is dived to half and refuted, and adopts half to dive to refute Large Caisson is transported to waters, erecting bed installs.But some regional population is intensive, available land resources is less, does not have the prefabricated Large Caisson in place be applicable to, need floating afloat half dive refute prefabricated; Though also there are some engineerings can build land precasting yard, do not have large-scale half to dive and refute, even cannot leasing partly dives refutes and has influence on normally carrying out of engineering.Adopt concrete prefabricatedly form the closed box reaching more than 20 meter because caisson is one, can swim on the water surface, but because its thousands of tons of that weighs is to ton up to ten thousand, how heavy caisson descend water to be a great problem of construction hydraulic engineering project.Dive as long-term lease ton half and refute, not only will spend a huge sum of money, and half dives and refute as a raft, because its drinking water area is large, moldeed depth is dark, both sides wing wall is high, and thus wind, flowing water are half-and-half dived and refuted impact very greatly, and its rocking property can have influence on the prefabricated quality of caisson.Meanwhile, the wind in work progress, flowing water half-and-half dive to refute all larger impact, and half dives refutes traction and location of casting anchor in port and all there is larger danger, and running into strong wind needs to hide.Therefore, in the urgent need to research and develop a kind of Large Caisson precasting yard or pier prefabricated, directly descended the system of water by precasting yard harbour or pier, effectively solve the problem.
Summary of the invention
The object of this invention is to provide that a kind of structure is reliable, construction cost is lower and water lifting platform system under Large Caisson that is convenient transportation after lower water.
The present invention is achieved by the following technical programs:
Water lifting platform system under a kind of Large Caisson, comprise and be severally supported on prefabricated platform in water and lift platform, described several prefabricated platform is spliced into a platform harbour, and lift platform side leans against on platform quayside; Prefabricated platform is identical with lift platform top structure, be followed successively by the girder truss of panel, network from top to bottom, described girder truss comprises crisscross and is fixedly connected with many integral longerons and Duo Gen crossbeam, be supported on the downside of the girder truss of prefabricated platform on the many steel pipe pile tops becoming matrix arrangement, steel pipe pile lower end is squeezed in water-bed mud ground; The elevating lever top becoming matrix to arrange with many on the downside of the girder truss of lift platform is hinged, elevating lever lower end puts in steel pipe pile, bottom elevating lever by several seat supports on the precast concrete foundation of steel pipe pile lower end, wherein the steel pipe pile upper end end face of supporting elevation bar is concordant with water-bed mud face.
Object of the present invention can also be realized further by following technical measures.
Water lifting platform system under aforesaid Large Caisson, the two ends of wherein said lift platform side adjacent with prefabricated platform are also respectively equipped with lifting and guiding device, described lifting and guiding device comprises guide collar and junction plate, described guide collar and lift platform top surface being parallel, be enclosed within the steel pipe pile of the contiguous prefabricated platform lower with lift platform, vertically disposed junction plate upper end is fixedly connected with on the downside of girder truss, and junction plate lower end is fixedly connected with the extended end of guide collar.
Aforesaid Large Caisson lifting platform system waterborne, wherein two adjacent side of prefabricated platform and lift platform are all obliquely installed.
Aforesaid Large Caisson lifting platform system waterborne, wherein elevating lever is the lifting plunger cylinder of more piece plunger.
Aforesaid Large Caisson lifting platform system waterborne, the steel pipe pile internal diameter that elevating lever is wherein housed is greater than the maximum transverse size bottom elevating lever, is provided with the pole of several support cylinder cylinder body at steel pipe pile top mouth.
Water lifting platform system under aforesaid Large Caisson, wherein elevating lever stroke to be greater than under Large Caisson after water undersurface depth H 1 and lift platform end face apart from low water stage water surface distance H2 sum.
The Large Caisson that the present invention will be prefabricated on precasting yard or prefabricated platform, adopt air bag transport or other mode land transportations to on the lift platform end face of prefabricated platform either flush, along with the decline of many elevating levers of supporting elevation table top, the Large Caisson of lift platform carrying is slowly lowered to water thereupon, until Large Caisson is in floating state, finally haul to storage place or job site.Do not need to rent partly to dive and refute prefabricated and transport Large Caisson, greatly reduce the prefabricated of Large Caisson and cost of transportation, improve the safety of Large Caisson transport.After engineering terminates, prefabricated platform and lift platform can be reused after removing, and improve resource utilization.
Advantage and disadvantage of the present invention, by for illustration and explanation for the non-limitative illustration passing through preferred embodiment below, these embodiments, only provide as an example with reference to accompanying drawing.
Accompanying drawing explanation
Fig. 1 is the structural representation that lift platform of the present invention is in state concordant with prefabricated platform;
Fig. 2 is the structural representation that lift platform of the present invention carries that Large Caisson is lowered to water state;
Fig. 3 is the A-A sectional view of Fig. 1;
Fig. 4 is the B-B cutaway view Amplified image of Fig. 2.
Detailed description of the invention
Below in conjunction with drawings and Examples, the invention will be further described.
As shown in Figure 1 to 4, the present invention includes and be severally supported on prefabricated platform 1 in water and lift platform 2, several prefabricated platform 1 is spliced into a platform harbour, the length of its quantity needed for platform harbour and determining.Lean against on prefabricated platform 1 limit of platform harbour on the left of lift platform 2, prefabricated platform 1 is all obliquely installed with two adjacent side of lift platform 2, to reduce both splicing seams, is convenient to the movement of Large Caisson 3.Prefabricated platform 1 is identical with lift platform 2 top structure, be followed successively by the girder truss 12 of panel 11, network from top to bottom, girder truss 12 comprises crisscross and by the many longerons 121 that are welded and fixed and Duo Gen crossbeam 122, be supported on by welding steel pipe pile 13 top that many become matrix arrangement on the downside of the girder truss 12 of prefabricated platform 1, steel pipe pile 13 can adopt pile driving barge that vibration hammer also can be adopted to be thrown in water-bed mud ground, the wall thickness of steel pipe pile 13, on the basis meeting bearing capacity, should meet piling requirement.The steel pipe pile 13 of lift platform 2 also adopts same method to construct, and difference is, the steel pipe pile 13 of lift platform 2 inserts elevating lever 21, and the steel pipe pile 13 upper end end face of supporting elevation bar 21 is concordant with water-bed mud face.
Elevating lever 21 top becoming matrix to arrange with 12 respectively by latch on the downside of the girder truss 12 of lift platform 2 is hinged, and lateral force when avoiding lift platform 2 to be elevated causes adverse influence to elevating lever 21.Elevating lever 21 lower end puts in steel pipe pile 13.As shown in Figure 1,2 meters of thick concrete foundations 131 are built in bottom the steel pipe pile 13 of supporting elevation bar 21, concrete foundation 131 is placed several bearing 211, and by soldered to bearing 211 and steel pipe pile 13 inwall, be supported on by several bearing 211 bottom elevating lever 21 on the precast concrete foundation 131 of steel pipe pile 13 lower end, 12 become the elevating lever 21 of matrix arrangement to support by the girder truss 12 of lift platform 2 and panel 11 Large Caisson 3 be carried on lift platform 2.
Elevating lever 21 is the lifting plunger cylinder of more piece plunger, to meet the longer needs of elevating lever 21 stroke.Inside there is steel pipe pile 13 internal diameter of elevating lever 21 to be greater than maximum size bottom elevating lever 21, be convenient to elevating lever 21 to insert in steel pipe pile 13.Push up at steel pipe pile 13 pole 23 that mouth is provided with several support cylinder cylinder body, make elevating lever 21 stably remain on plumbness, thus guarantee that lift platform 2 is elevated steadily.
In order to improve the stability that lift platform 2 is elevated further, as shown in Figure 4, lifting and guiding device 22 is also respectively equipped with at the two ends of lift platform 2 side adjacent with prefabricated platform 1, described lifting and guiding device 22 comprises guide collar 221 and junction plate 222, guide collar 221 and lift platform 2 top surface being parallel, be enclosed within the steel pipe pile 13 of the contiguous prefabricated platform lower with lift platform, be welded and fixed on the downside of vertically disposed junction plate 222 upper end and girder truss 12, the extended end of lower end and guide collar 221 is welded and fixed and connects.When lift platform 2 is elevated, the steel pipe pile 13 that guide collar 221 is overlapped along it moves up and down, and prevents lift platform 2 from occurring crooked.
As shown in Figure 2, elevating lever 21 stroke after being greater than Large Caisson 3 times water undersurface depth H 1 and lift platform 2 end face apart from low water stage water surface distance H2 sum.When guaranteeing that lift platform 2 drops to underwater, Large Caisson 3 can swim in waterborne completely, is convenient to tugboat band cable and tows to destination, replaces partly diving of cost of use costliness and refutes.
In addition to the implementation, the present invention can also have other embodiments, and all employings are equal to the technical scheme of replacement or equivalent transformation formation, all drop in the protection domain of application claims.

Claims (6)

1. a water lifting platform system under Large Caisson, is characterized in that: comprise and be severally supported on prefabricated platform in water and lift platform, described several prefabricated platform is spliced into a platform harbour, and lift platform side leans against on platform quayside; Prefabricated platform is identical with lift platform top structure, be followed successively by the girder truss of panel, network from top to bottom, described girder truss comprises crisscross and is fixedly connected with many integral longerons and Duo Gen crossbeam, be supported on the downside of the girder truss of prefabricated platform on the many steel pipe pile tops becoming matrix arrangement, steel pipe pile lower end is squeezed in water-bed mud ground; The elevating lever top becoming matrix to arrange with many on the downside of the girder truss of lift platform is hinged, elevating lever lower end puts in steel pipe pile, bottom elevating lever by several seat supports on the precast concrete foundation of steel pipe pile lower end, the steel pipe pile upper end end face of supporting elevation bar is concordant with water-bed mud face.
2. water lifting platform system under Large Caisson as claimed in claim 1, it is characterized in that: the two ends of described lift platform side adjacent with prefabricated platform are also respectively equipped with lifting and guiding device, described lifting and guiding device comprises guide collar and junction plate, described guide collar and lift platform top surface being parallel, be enclosed within the steel pipe pile of the contiguous prefabricated platform lower with lift platform, vertically disposed junction plate upper end is fixedly connected with on the downside of girder truss, and junction plate lower end is fixedly connected with the extended end of guide collar.
3. water lifting platform system under Large Caisson as claimed in claim 1, is characterized in that: two adjacent side of prefabricated platform and lift platform are all obliquely installed.
4. water lifting platform system under Large Caisson as claimed in claim 1, is characterized in that: described elevating lever is the lifting plunger cylinder of more piece plunger.
5. water lifting platform system under the Large Caisson as described in claim 1 or 4, is characterized in that: the steel pipe pile internal diameter that elevating lever is housed is greater than the maximum transverse size bottom elevating lever; The pole of several support cylinder cylinder body is provided with at steel pipe pile top mouth.
6. water lifting platform system under Large Caisson as claimed in claim 1, is characterized in that: elevating lever stroke to be greater than under Large Caisson after water undersurface depth H 1 with lift platform end face apart from low water stage water surface distance H2 sum.
CN201510031048.3A 2015-01-22 2015-01-22 Lifting platform system for placing large caisson in water Pending CN104746525A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510031048.3A CN104746525A (en) 2015-01-22 2015-01-22 Lifting platform system for placing large caisson in water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510031048.3A CN104746525A (en) 2015-01-22 2015-01-22 Lifting platform system for placing large caisson in water

Publications (1)

Publication Number Publication Date
CN104746525A true CN104746525A (en) 2015-07-01

Family

ID=53586725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510031048.3A Pending CN104746525A (en) 2015-01-22 2015-01-22 Lifting platform system for placing large caisson in water

Country Status (1)

Country Link
CN (1) CN104746525A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105253270A (en) * 2015-10-30 2016-01-20 青岛海西重机有限责任公司 Combined buoyancy tank type offshore platform launching device and offshore platform launching method
CN106149742A (en) * 2016-07-07 2016-11-23 中交二航局第三工程有限公司 Launching caisson device and method
CN111005400A (en) * 2019-12-04 2020-04-14 天津大学 Equipment and method capable of performing migration and prefabrication of offshore wind power barrel type foundation
CN112832290A (en) * 2021-01-04 2021-05-25 中交第四航务工程局有限公司 Construction method for prefabricating and shipping immersed tube
CN117644946A (en) * 2024-01-30 2024-03-05 中交一航局第五工程有限公司 Rigid connection device for double caisson assembly

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL8901834A (en) * 1989-07-14 1991-02-01 Volker Stevin Offshore B V Vessel mounted lowering unit - positions steel-concrete base sections for under water oil platform
CN1129272A (en) * 1995-02-17 1996-08-21 大栋营造股份有限公司 Jack propelling method for under water working of coffer
CN1763314A (en) * 2005-05-26 2006-04-26 广东省航盛工程有限公司 Method for moving large-scale heavy member to launch and float on water, and member mounting method
CN101033613A (en) * 2006-06-21 2007-09-12 苗德政 Construction method of transferring launching caisson by gasbag
CN102762447A (en) * 2009-12-11 2012-10-31 大洋洲工程集团有限公司 Universal floating and launching system and operating method
CN103774672A (en) * 2012-10-27 2014-05-07 山东港湾建设集团有限公司 Method for shipping caissons through ramp

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL8901834A (en) * 1989-07-14 1991-02-01 Volker Stevin Offshore B V Vessel mounted lowering unit - positions steel-concrete base sections for under water oil platform
CN1129272A (en) * 1995-02-17 1996-08-21 大栋营造股份有限公司 Jack propelling method for under water working of coffer
CN1763314A (en) * 2005-05-26 2006-04-26 广东省航盛工程有限公司 Method for moving large-scale heavy member to launch and float on water, and member mounting method
CN101033613A (en) * 2006-06-21 2007-09-12 苗德政 Construction method of transferring launching caisson by gasbag
CN102762447A (en) * 2009-12-11 2012-10-31 大洋洲工程集团有限公司 Universal floating and launching system and operating method
CN103774672A (en) * 2012-10-27 2014-05-07 山东港湾建设集团有限公司 Method for shipping caissons through ramp

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105253270A (en) * 2015-10-30 2016-01-20 青岛海西重机有限责任公司 Combined buoyancy tank type offshore platform launching device and offshore platform launching method
CN106149742A (en) * 2016-07-07 2016-11-23 中交二航局第三工程有限公司 Launching caisson device and method
CN111005400A (en) * 2019-12-04 2020-04-14 天津大学 Equipment and method capable of performing migration and prefabrication of offshore wind power barrel type foundation
CN112832290A (en) * 2021-01-04 2021-05-25 中交第四航务工程局有限公司 Construction method for prefabricating and shipping immersed tube
CN117644946A (en) * 2024-01-30 2024-03-05 中交一航局第五工程有限公司 Rigid connection device for double caisson assembly
CN117644946B (en) * 2024-01-30 2024-04-12 中交一航局第五工程有限公司 Rigid connection device for double caisson assembly

Similar Documents

Publication Publication Date Title
CN102953342B (en) Assembling and lifting method of half-span skeleton of tied arch bridge
CN104746525A (en) Lifting platform system for placing large caisson in water
US20220002961A1 (en) Suction Anchors and Their Methods of Manufacture
EP2837554A1 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
CN105926628B (en) One kind is floated, fixed convertible pile foundation in water construction platform device
CN104594377A (en) Steel cylinder type foundation structure of offshore wind turbine
CN205399220U (en) Whole system of erectting of large -scale arched bridge over strait
CN105544575A (en) Underwater bottom sealing concrete construction method using steel truss for reinforcement
CN101858083A (en) Low spatial pile pulling construction method and device of steel pipe pile in water
CN108179735A (en) A kind of boulder bed large-sized deep water foundation construction platform and method
CN103362113A (en) Local buoyancy ocean platform of offshore wind power, bridge and ocean structure, and construction method
CN211849244U (en) Novel assembled high-pile beam-slab wharf structure
CN106759340A (en) Steel-pipe pile pile-pulling construction method and device in low spatial water
CN101792015A (en) Multi-functional assembling type waterborne movable device
CN110939148A (en) Construction method of double-wall steel suspension box cofferdam serving as drilling platform
CN103119222A (en) Surface-breaking re-usable submergeable template for installing one or more submerged columns/piles
US4080916A (en) Maritime platform assemblies
CN106522263A (en) Construction method for wind power complete machine of structure composed of four barrel-type foundations and supported by concrete
CN102587377B (en) Drop hammer type pile sinking device and pile sinking method thereof
KR101703441B1 (en) Cassion manufacturing method of bottom-up, pre-cast and a base plate type using floating dock, system, floating dock and cassion using thereof
CN115387207A (en) Shallow covering layer steel-concrete composite pile pier structure and construction method
GB2501459A (en) Platform removal and transportation system comprising flotation and stabilization units
CN104746476A (en) Wharf additionally provided with batter pile on rear edge and method for reinforcing wharf rear edge by applying batter pile
CN202969246U (en) Semi-stride hoisting bowstring arch bridge
CN205259216U (en) Adopt steel truss to add concrete structure of back cover under water of muscle

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150701