CN1312203A - Air and water lift platform with barrel-shaped footing - Google Patents

Air and water lift platform with barrel-shaped footing Download PDF

Info

Publication number
CN1312203A
CN1312203A CN 00103402 CN00103402A CN1312203A CN 1312203 A CN1312203 A CN 1312203A CN 00103402 CN00103402 CN 00103402 CN 00103402 A CN00103402 A CN 00103402A CN 1312203 A CN1312203 A CN 1312203A
Authority
CN
China
Prior art keywords
barrel
pile
platform
water
air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 00103402
Other languages
Chinese (zh)
Inventor
王翎羽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN HAIWANGXING OFFSHORE ENGINEERING TECHN Co Ltd
Original Assignee
TIANJIN HAIWANGXING OFFSHORE ENGINEERING TECHN Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN HAIWANGXING OFFSHORE ENGINEERING TECHN Co Ltd filed Critical TIANJIN HAIWANGXING OFFSHORE ENGINEERING TECHN Co Ltd
Priority to CN 00103402 priority Critical patent/CN1312203A/en
Publication of CN1312203A publication Critical patent/CN1312203A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The present invention relates to a barrel-type foundation air-water lifting platform, consisting pile column and ship body with pile column lifting holes, in which the pile column is equipped with rack bar, on the ship body there is a pile-fixing frame with matched toothed pin, the interior of the ship body possesses a balance water cabin. It is characterized by that the lower end of the described pile column possesses barrel-type foundation, and on the barrel-type foundation the charging and discharging air-water pipeline is mounted, and its advantages lie in that it utilizes barrel-type foundation and its charging and discharging air-water pipeline to implement platform lift, can save complex electric hydraulic or mechanical lifting device and matched power equipment of traditional platform, can reduce cost, and can be easily mounted and quickly moved.

Description

Air and water lift platform with barrel-shaped footing
The invention belongs to a kind of novel self-lifting type platform in the marine oil and gas development tool.
Traditional jack-up platform general-duty jacking apparatus is electric hydraulic and electric gear rack-and-pinion, these two kinds of jacking apparatus complex structures, and need to be equipped with big power facility, involving great expense, the during-operation service expense is also high.
The objective of the invention is to design a kind of air and water lift platform with barrel-shaped footing, save habitual jacking apparatus, the problem that the complicated jacking apparatus of above-mentioned traditional jack-up platform is produced is satisfactorily resolved.
Technical scheme of the present invention: a kind of air and water lift platform with barrel-shaped footing, form by some piles and hull with pile lift span; Tooth bar is arranged on the pile, wedge bracket and alligator are arranged on the hull, the balance sump is arranged in the hull, it is characterized in that there is bucket base described pile lower end, be equipped with at the bucket base top can be to filling the pipeline of exhaust-water in the bucket.
Principle of work of the present invention: this platform is in towage, pile sinking, jacking and final fixing whole job procedure, and flat-bed hull and relative motion between the pile all are to rely on to fill exhaust-water and cooperate pile and the operation of hull nog realizes in the bucket base of pile.The bucket base that fills exhaust-water plays the hydraulic cylinder effect at this, presses decision jacking ability in it, and its traverse determines top lifting height one time.During the platform towage, the bucket base inflation is from floating, and the hull drinking water is shown in Fig. 3-a.When hull casts anchor enforcement pile sinking in place, then to the bucket base exhaust, make down and put into mud, the step-down of drawing water then makes it to sink to the seabed, shown in Fig. 3-b.Hull jacking subsequently can have dual mode to select, the one, from the seabed jacking, the 2nd, from water surface jacking, shown in Fig. 3-c: from the seabed jacking is to appoint to get one group of diagonal angle pile, pins hull with alligator, then to setting-out in the bucket base that sinks to the seabed, with it from seabed jack-up certain distance, thereby make upper post and hull jacking corresponding height, to go deep into the seabed motionless for another group diagonal angle bucket base in this process, and pile play the guiding role on it.From water surface jacking also is to appoint to get one group of diagonal angle pile, the floating nearly water surface place of its bucket base inflation further to bucket in plenum, with hull jack-up certain altitude, this mode can repeat under the alligator operation cooperates, until satisfying required top lifting height with its surplus buoyancy.In dual mode jacking process, the center of gravity of hull can be harmonious with the centre of form through the adjustment of balance sump, thereby keeps the steady of jacking.Be that the diagonal angle bucket base sinking that will carry out jacking resets and sinks to the seabed at last, with alligator hull and pile locked simultaneously that platform installs and is fixed in the sea and enters normal working, shown in Fig. 3-d.
But the preceence of air and water lift platform with barrel-shaped footing involved in the present invention is 1. bucket bases itself and intrinsic fills the just implementation platform jacking of exhaust-water pipeline, thereby save complicated jacking apparatus and relevant power facility, can reduce the platform cost greatly; 2. platform structure is simple makes easily; 3. platform is installed rapidly, is convenient to resettlement.
Be described further below in conjunction with drawings and Examples
Fig. 1 is the related air and water lift platform with barrel-shaped footing birds-eye view of the present invention
Fig. 2 is the related air and water lift platform with barrel-shaped footing front elevation of the present invention
Wherein 1 is hull; 2 is pile; 3 is bucket base; 4 is tooth bar; 5 is wedge bracket; 6 is the balance sump.
Fig. 3-a is the related platform towing condition of a present invention scheme drawing
Fig. 3-b is scheme drawing behind the related platform of the present invention pile sinking in place
Fig. 3-c is two kinds of jacking modes of the related platform of the present invention scheme drawing
Fig. 3-d installs scheme drawing for the related platform of the present invention
Embodiment: a kind of air and water lift platform with barrel-shaped footing (is seen Fig. 1,2), form by pile (2) and hull (1) with pile lift span, tooth bar (4) is arranged on the pile, there is wedge bracket (5) to be furnished with alligator on the hull, balance sump (6) is arranged in the hull, it is characterized in that there is bucket base described pile lower end, be equipped with at the bucket base top can be to filling the pipeline of exhaust-water in the bucket.Fill exhaust-water lines and comprise diving pump, valve, flexible pipe, link operating console on the hull, belong to the conventional equipment that to buy from the city of interim installation, do not give illustrating among the figure by the bucket base top.The flat-bed hull is the steel structure that plate-girder is formed, and pile and the bucket base thin walled steel structure for being made by steel plate, bucket base top board generally have rib system to strengthen.Flat-bed erection procedure of the present invention is seen Fig. 3-a to Fig. 3-d.

Claims (1)

  1. A kind of air and water lift platform with barrel-shaped footing is made up of some piles and hull with pile lift span; Tooth bar is arranged on the pile, wedge bracket and alligator are arranged on the hull, the balance sump is arranged in the hull, it is characterized in that there is bucket base described pile lower end, be equipped with at the bucket base top can be to filling the pipeline of exhaust-water in the bucket.
CN 00103402 2000-03-08 2000-03-08 Air and water lift platform with barrel-shaped footing Pending CN1312203A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 00103402 CN1312203A (en) 2000-03-08 2000-03-08 Air and water lift platform with barrel-shaped footing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 00103402 CN1312203A (en) 2000-03-08 2000-03-08 Air and water lift platform with barrel-shaped footing

Publications (1)

Publication Number Publication Date
CN1312203A true CN1312203A (en) 2001-09-12

Family

ID=4576958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 00103402 Pending CN1312203A (en) 2000-03-08 2000-03-08 Air and water lift platform with barrel-shaped footing

Country Status (1)

Country Link
CN (1) CN1312203A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100567079C (en) * 2005-05-27 2009-12-09 中国石化集团胜利石油管理局钻井工艺研究院 End jack-up platform and using method thereof are sat in split
CN103863526A (en) * 2012-12-11 2014-06-18 湖北华舟重工应急装备股份有限公司 Buoyancy box with standard connecting opening
CN104326063A (en) * 2014-07-16 2015-02-04 罗煜 Dynamic balance structure of overwater wharf
CN104376886A (en) * 2014-11-10 2015-02-25 中国海洋石油总公司 Offshore nuclear power platform with cylindrical foundation bodies
CN105256780A (en) * 2015-09-09 2016-01-20 中铁大桥局集团有限公司 Multipurpose over-water construction platform and construction method
CN115787755A (en) * 2023-01-18 2023-03-14 西南石油大学 Simulation test system and method for pile inserting and pulling operation of self-elevating drilling platform

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100567079C (en) * 2005-05-27 2009-12-09 中国石化集团胜利石油管理局钻井工艺研究院 End jack-up platform and using method thereof are sat in split
CN103863526A (en) * 2012-12-11 2014-06-18 湖北华舟重工应急装备股份有限公司 Buoyancy box with standard connecting opening
CN104326063A (en) * 2014-07-16 2015-02-04 罗煜 Dynamic balance structure of overwater wharf
CN104326063B (en) * 2014-07-16 2017-05-10 罗煜 Dynamic balance structure of overwater wharf
CN104376886A (en) * 2014-11-10 2015-02-25 中国海洋石油总公司 Offshore nuclear power platform with cylindrical foundation bodies
CN104376886B (en) * 2014-11-10 2017-01-18 中国海洋石油总公司 Offshore nuclear power platform with cylindrical foundation bodies
CN105256780A (en) * 2015-09-09 2016-01-20 中铁大桥局集团有限公司 Multipurpose over-water construction platform and construction method
CN115787755A (en) * 2023-01-18 2023-03-14 西南石油大学 Simulation test system and method for pile inserting and pulling operation of self-elevating drilling platform

Similar Documents

Publication Publication Date Title
US3896628A (en) Marine structures
CN100419164C (en) Method for moving large-scale heavy member to launch and float on water, and member mounting method
CN107542101B (en) Construction method of offshore four-buoy-buoyancy tank combined foundation structure
CN107653895B (en) Combined offshore six-buoy buoyancy tank foundation structure and construction method thereof
CN100343454C (en) Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure
CN200971492Y (en) Pile submarine drilling basal disc with suction
CN107630461B (en) Combined offshore four-buoy buoyancy tank foundation structure and construction method thereof
CN101666101A (en) Movable prefabricated multi-barrel type gravity mixed foundation
CN110155262B (en) Trunk tree semi-submersible platform with self-installation function
CN107806108A (en) Three floating drum buoyancy tank foundation structures and its construction method on a kind of combined type sea
CN104210627B (en) Build the device and method of lower water for jack-up unit level land
JPH05503124A (en) Method and apparatus for constructing artificial islands and islands thus obtained
CN1440904A (en) Self-installed suction anchor
CN1312203A (en) Air and water lift platform with barrel-shaped footing
CN101876174A (en) Foundation structure of marine wind electric field fan
CN103374905B (en) Movable self-installation platform
CN113863357A (en) Gravity center deviation single-column three-cylinder jacket foundation and construction method
CN202610780U (en) Movable self-installing platform
CN108951631B (en) Four-pile jacket installation construction process
KR101031571B1 (en) Method for constructing seperating type caisson
CN111472377A (en) Offshore wind power integral installation device and method utilizing mat-buoyancy tank
CN201347191Y (en) Suction pile type ocean floor drilling novel basal disc
CN108951629B (en) Pile inserting process for jacket
CN201362340Y (en) Lift type drain bar striking boat
JP3135208U (en) Towing self-sinking anchor block

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Tianjin Haiwangxing Offshore Engineering Techn Co., Ltd.

Document name: Request for approval of patent right renewal

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication