CN105756317B - One kind is used for wet extension stone material or the wet hanging method of ceramic tile - Google Patents
One kind is used for wet extension stone material or the wet hanging method of ceramic tile Download PDFInfo
- Publication number
- CN105756317B CN105756317B CN201610118180.2A CN201610118180A CN105756317B CN 105756317 B CN105756317 B CN 105756317B CN 201610118180 A CN201610118180 A CN 201610118180A CN 105756317 B CN105756317 B CN 105756317B
- Authority
- CN
- China
- Prior art keywords
- ceramic tile
- stone material
- wet
- vertical connection
- connection piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000004575 stone Substances 0.000 title claims abstract description 66
- 239000000463 material Substances 0.000 title claims abstract description 63
- 239000000919 ceramic Substances 0.000 title claims abstract description 56
- 238000000034 method Methods 0.000 title claims abstract description 30
- 239000000725 suspension Substances 0.000 claims abstract description 13
- 230000002787 reinforcement Effects 0.000 claims description 9
- 239000004570 mortar (masonry) Substances 0.000 claims description 6
- 239000002002 slurry Substances 0.000 claims description 6
- 239000011083 cement mortar Substances 0.000 claims description 5
- 239000008267 milk Substances 0.000 claims description 5
- 210000004080 milk Anatomy 0.000 claims description 5
- 235000013336 milk Nutrition 0.000 claims description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000003466 welding Methods 0.000 claims description 4
- 210000003739 neck Anatomy 0.000 claims 4
- 239000004744 fabric Substances 0.000 claims 1
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 238000005034 decoration Methods 0.000 abstract description 7
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 6
- 238000010276 construction Methods 0.000 description 5
- 239000000853 adhesive Substances 0.000 description 4
- 230000001070 adhesive effect Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- WSFSSNUMVMOOMR-UHFFFAOYSA-N Formaldehyde Chemical compound O=C WSFSSNUMVMOOMR-UHFFFAOYSA-N 0.000 description 3
- 239000004568 cement Substances 0.000 description 3
- 229910052602 gypsum Inorganic materials 0.000 description 3
- 239000010440 gypsum Substances 0.000 description 3
- 229910052742 iron Inorganic materials 0.000 description 3
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 2
- 239000003963 antioxidant agent Substances 0.000 description 2
- 230000003078 antioxidant effect Effects 0.000 description 2
- 230000003143 atherosclerotic effect Effects 0.000 description 2
- 239000011449 brick Substances 0.000 description 2
- 150000001875 compounds Chemical class 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 241001014327 Anodontia Species 0.000 description 1
- 239000004836 Glue Stick Substances 0.000 description 1
- 239000011398 Portland cement Substances 0.000 description 1
- BGYHLZZASRKEJE-UHFFFAOYSA-N [3-[3-(3,5-ditert-butyl-4-hydroxyphenyl)propanoyloxy]-2,2-bis[3-(3,5-ditert-butyl-4-hydroxyphenyl)propanoyloxymethyl]propyl] 3-(3,5-ditert-butyl-4-hydroxyphenyl)propanoate Chemical group CC(C)(C)C1=C(O)C(C(C)(C)C)=CC(CCC(=O)OCC(COC(=O)CCC=2C=C(C(O)=C(C=2)C(C)(C)C)C(C)(C)C)(COC(=O)CCC=2C=C(C(O)=C(C=2)C(C)(C)C)C(C)(C)C)COC(=O)CCC=2C=C(C(O)=C(C=2)C(C)(C)C)C(C)(C)C)=C1 BGYHLZZASRKEJE-UHFFFAOYSA-N 0.000 description 1
- 238000010521 absorption reaction Methods 0.000 description 1
- 206010002583 anodontia Diseases 0.000 description 1
- 230000005212 anodontia Effects 0.000 description 1
- OSGAYBCDTDRGGQ-UHFFFAOYSA-L calcium sulfate Inorganic materials [Ca+2].[O-]S([O-])(=O)=O OSGAYBCDTDRGGQ-UHFFFAOYSA-L 0.000 description 1
- ZOMBKNNSYQHRCA-UHFFFAOYSA-J calcium sulfate hemihydrate Chemical compound O.[Ca+2].[Ca+2].[O-]S([O-])(=O)=O.[O-]S([O-])(=O)=O ZOMBKNNSYQHRCA-UHFFFAOYSA-J 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000003670 easy-to-clean Effects 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 239000011507 gypsum plaster Substances 0.000 description 1
- 238000001746 injection moulding Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- SSDSCDGVMJFTEQ-UHFFFAOYSA-N octadecyl 3-(3,5-ditert-butyl-4-hydroxyphenyl)propanoate Chemical compound CCCCCCCCCCCCCCCCCCOC(=O)CCC1=CC(C(C)(C)C)=C(O)C(C(C)(C)C)=C1 SSDSCDGVMJFTEQ-UHFFFAOYSA-N 0.000 description 1
- 230000010412 perfusion Effects 0.000 description 1
- 230000000505 pernicious effect Effects 0.000 description 1
- 239000011505 plaster Substances 0.000 description 1
- 229910052573 porcelain Inorganic materials 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 239000012783 reinforcing fiber Substances 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0832—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements
- E04F13/0833—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements not adjustable
- E04F13/0839—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements not adjustable the fastening elements situated at the corners of the covering elements, not extending through the covering
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Finishing Walls (AREA)
Abstract
The present invention relates to decoration decoration technique field, is specifically related to use the hook used when the paving stone material or ceramic tile of wet extension mode and the wet hanging method using the hook.This kind is used for the suspension member of wet extension stone material or ceramic tile, it is characterised in that:Including hanger bulk and position line;The hanger bulk includes horizontal hanging groove, backgauge piece and vertical connection piece, and the backgauge piece arranges that the vertical connection piece both ends are connected with horizontal hanging groove and backgauge piece and are provided with threading hole on vertical connection piece respectively parallel to horizontal hanging groove;The position line is detachably secured on vertical connection piece after passing through threading hole.Compared with existing wet hanging method, there are several features using provided by the present invention for wet extension stone material or the suspension member of ceramic tile and wet hanging method:First, technique is simple, easy to operation, reduction production cost;Second, paving is firm, it is easy to fall off not allow;Third, it is applied widely, it is applicable to the paving of indoor and outdoor stone material or ceramic tile.
Description
Technical field
The present invention relates to decoration decoration technique field, is specifically related to make when the paving stone material or ceramic tile using wet extension mode
Wet hanging method.
Background technology
With the continuous improvement of people's living standards, the requirement to decoration decoration also improves constantly, the paving stone on wall
Material or large-sized ceramic tile can seem that space class is high and easy to clean, increasingly be favored by people.
It is existing mainly to have two kinds to the laying method of stone material and ceramic tile, first, using the wet combining method of cement mortar, another
One kind is by keel shoe dry-hanging method;The wet combining method construction technology of cement mortar is simple, paving cost is low is widely used,
But because the material of stone material or ceramic tile is close, water absorption rate is low, thus cause stone material and metope adhesive strength poor, easily produce hollowing
Even come off;Its is solid and reliable for keel shoe dry-hanging method, facing flatness is good, but construction technology is complicated, production cost is high, and
Typically require that sheet metal thickness is big in more than 30mm space-consumings, therefore be only applicable to the exterior wall installation of stone material, and be not suitable for room
Interior or ceramic tile installation.
To solve the above problems, application publication number, which is CN102839804A, discloses a kind of side of paving stone material or ceramic tile
Method, this kind of method equally exist many problems:Need that back of the body bolt and suspender member are installed first, paving complex process, during paving, also need
Adhesive is smeared on extruded sheet two sides, its paving efficiency is low, cost is high;Second, service life is short, stone material or ceramic tile pass through glue
Stick bonds with extruded sheet, and adhesive service life can lose viscosity and cause stone material or porcelain after being grown well below cement, time
Brick comes off;Third, pollute environment, healthy hidden danger be present, containing substantial amounts of formaldehyde and other harmful substances in adhesive, therefore such as
Fruit can constantly distribute pernicious gas using when above method paving stone material or ceramic tile in room indoors, influence the body of user
Health.
Therefore how to carry solves the problems, such as stone material or ceramic tile wet extension be decorate decoration industry in urgent need to resolve.
The content of the invention
To overcome deficiency of the prior art, the present invention provides that a kind of security performance is high, use cost is low is used for wet extension
The suspension member of stone material or ceramic tile.
To achieve the above object, the technical solution adopted by the present invention is as follows:One kind is used for wet extension stone material or the wet extension side of ceramic tile
Method, it is characterised in that using suspension member, the suspension member includes hanger bulk and position line;The hanger bulk includes horizontal hanging groove, gear
Tablet and vertical connection piece, the backgauge piece arrange parallel to horizontal hanging groove, the vertical connection piece both ends respectively with horizontal hanging groove and
Backgauge piece connects and is provided with threading hole on vertical connection piece;The position line is detachably secured to vertically after passing through threading hole
In connection sheet,
Step is as follows:
Step 1, slot, at least two cards being adapted with horizontal hanging groove hook are cut out at the back side of stone material or ceramic tile
Groove;
Step 2, mounting hook, by the horizontal hanging groove of hanger bulk stretch into the neck that step 1 cut out with stone material or
Ceramic tile clamping;
Step 3, fixed steel bars net and snap the line, one layer of colligation or welding in metope basic unit according to the size of stone material or ceramic tile
Bar-mat reinforcement, and the outer contour of stone material or ceramic tile metope is ejected on the ground;
Step 4, stone material or ceramic tile are installed, by position line colligation on bar-mat reinforcement, while adjust the vertical of stone material or ceramic tile
Degree and flatness, interim fixing stone or ceramic tile;
Step 5, it is in the milk, divides the hole that 2-5 layers are poured between metope basic unit and ceramic tile cement mortar match, in filling
Stone surface is gently tapped with rubber hammer to be made to pour into mortar exhaust;
Step 6, wiping seam, all remaining slurry vestiges are removed after whole slabstones or ceramic tile install, and by slabstone or ceramic tile
Color modulation mill base filleting.
Further, neck is opened in more than 1/3rd position of stone material or stone material, and the neck includes opening in stone material
Or the vertical slot of ceramic tile side and the translot in stone material or the ceramic tile back side is opened, and vertical slot is connected with translot.
Seen from the above description, using provided by the present invention for it is wet extension stone material or ceramic tile wet hanging method with it is existing wet
Hanging method is compared, and has following feature:First, technique is simple, easy to operation, Bartlit or ceramic tile paving enormously simplify
The technique of patch, meet the operation sequence of site operation, improve operating efficiency, reduce production cost;Second, paving is firm, is not easy
Come off, between stone material or ceramic tile and metope after grouting, slurry be closely connected with backgauge piece so that stone material or ceramic tile and metope into
It is integrated;Third, it is applied widely, more than 100kg weight can be born using suspension member provided by the invention and wet hanging method
Amount, and the distance between ceramic tile and metope only has 5-10mm, therefore it is applicable to the paving of indoor and outdoor stone material or ceramic tile.
Brief description of the drawings
Fig. 1 is the structural representation for the suspension member that the present invention is used for wet extension stone material or ceramic tile.
Fig. 2 is that the present invention is used for the stone material of wet extension or the structural representation of ceramic tile.
Fig. 3 is the work structure diagram for the suspension member that the present invention is used for wet extension stone material or ceramic tile.
Fig. 4 is the process chart of the wet hanging method of stone material of the present invention.
Embodiment
Below by way of embodiment, the invention will be further described.
It is a kind of for wet extension stone material or the suspension member of ceramic tile referring to figs. 1 to shown in Fig. 3, including hanger bulk 1 and position line 2.
Hanger bulk 1 includes horizontal hanging groove 11, backgauge piece 12 and vertical connection piece 13, and the hanger bulk 1 uses PA materials
Integrated injection molding, reinforcing fiber agent and 0.1~0.9% antioxidant is added with PA materials, antioxidant is antioxidant 1010
With the compound of antioxidant 1076;
Horizontal hanging groove 1 includes the lacing film connection sheet 112 of lacing film 111 and one of two panels parallel arrangement, is protected between two lacing films 111
5-15mm distance is held, the both ends of lacing film connection sheet 112 are connected with two lacing films 111 and surround " H " shape structure with two lacing films respectively, this
6mm distance is kept in embodiment between two lacing films 111;
Backgauge piece 12 is parallel to horizontal hanging groove arrangement 11;
The both ends of vertical connection piece 13 are connected with horizontal hanging groove 1 and backgauge piece 12 respectively, and the vertical connection piece 13 is hung with horizontal
The junction of groove is provided with threading hole 131, on vertical connection piece 13 formed with raw reinforcement 132 is prolonged along its length, this hangs down
The length of direct-connected contact pin is 10mm-20mm, and the length of vertical connection piece is 13mm in the present embodiment.
Position line 2 is detachably secured on vertical connection piece 13 after passing through threading hole 131, and the position line 2 uses copper wire
Or galvanized iron wire is made.
Referring to figs. 1 to shown in Fig. 4, a kind of wet hanging method of stone material, using above-mentioned suspension member, comprise the following steps:
First, preparation of construction
1st, material:
Cement:32.5 Portland cements, there should be appearance to prove and retrial return on qualification;
Sand:Using fine sand;
Vitrified tile:The ㎜ of the ㎜ of specification 1200 × 600, it is desirable to which solid colour, brick face is upright, no edge damage, hidden defect, unfilled corner;
Suspension member:Hanger bulk 1 and position line 2;
Other materials:30 cement nails, cloud stone glue, caulking compounds (being used for pointing seam).
2nd, construction technology
Technological process:Basic unit's face cleaning --- slotted at the vitrified tile back side --- mounting hook --- fixed steel bars net and bullet
Line --- installation vitrified tile --- grouting --- wiping seam
Specific construction flow is as follows:
Step 1, slot, using the saw blade of the anodontia cutting machine of motor-driven hand-held stone material, the back side three of vitrified tile 100/
More than one opening position cuts out the neck that twice are arranged symmetrically, and per pass neck is by opening the He of vertical slot 101 in the side of vitrified tile 100
Open the translot 102 in the back side of vitrified tile 100 to form, and vertical slot 101 is connected with translot 102;
Step 2, mounting hook, the lacing film connection sheet 112 of hanger bulk 1 is inserted to the translot 102 at the back side of vitrified tile 100
In, ' U ' type groove and the phase clamping of neck 100 that now lacing film forms with lacing film connection sheet, the both ends of position line 2 are each passed through two extensions
It is fixed after positional punch on hook body, two hooks are connected;
Step 3, fixed steel bars net and snap the line, one layer of colligation or welding in metope basic unit according to the size of stone material or ceramic tile
Bar-mat reinforcement, size during bar-mat reinforcement colligation first according to vitrified tile 100 weld vertical reinforcement, then fix first of horizontal bar on ground
With stud firm welding, the lower mouth as colligation first layer sheet material fixes copper wire or galvanized iron wire, second horizontal bar at upper+10cm places
At colligation low 2-3cm more suitable for reading than stone plate, according to stone material block size successively upward colligation horizontal bar;
Eject the outer contour of stone material or ceramic tile metope on the ground, thickness, the perfusion of vitrified tile are mainly considered during snap the line
The perpendicularity of size and former metope shared by the space of mortar and bar-mat reinforcement, when metope deviation is larger, in not structural damage
In the case of locally pick chisel meet finishing require.The general wet vitrified tile or the general thickness of stone material hung should be advisable in 4-7mm.Look for
After going out vertically, the outer profile size control line of stone wall surface is ejected on the ground, this line is the reference for installation of first layer stone material
Line, the number of finishing stone plate mark in place on the good datum line of bullet, and (such as design requirement pulls open seam, then by design in every piece of 1mm gap
Regulation reserves gap);
Step 4, vitrified tile is installed, by position line colligation on bar-mat reinforcement, carried out successively to the opposing party, first layer installs
Finish and looked for vertically with plaster ground again, square chi looks for negative and positive angle upright, when mounted as find vitrified tile specification inaccuracy or vitrified tile it
Between gap be not inconsistent, with sheet lead pad jail, gap uniformity is consistent between making slabstone, and keeps suitable for reading straight of first layer slabstone,
Looked for it is straight, upright, smooth after, with bowl modulate the plaster of paris, the gypsum for being tuned into atherosclerotic is attached to vitrified tile in-between, make this two
Layer vitrified tile knot is integral, also Pasting gypsum, then check for deforming with guiding ruler at timber wedge, waits gypsum to be filled after hardening
Slurry;
Step 5, it is in the milk, is 1 match ratio:2.5 cement mortar be put into half drum add water to be tuned into atherosclerotic (denseness is generally
8-12cm), slurry pouring into slowly with iron dustpan, stone surface is gently tapped with rubber hammer when filling makes to pour into mortar exhaust, and first
It is 15cm that layer, which pours height, it is impossible to more than the 1/3 of slabstone height, stops 1~2 hour after pouring into 15cm mortars for the first time, waits mortar
Initial set carries out second layer grouting again, and grouting height is generally 20-30cm, is further continued for being in the milk after initial set, third layer is in the milk to low
Untill at the plate 5cm suitable for reading.
Step 6, wiping seam, after whole vitrified tiles install, all remaining slurry vestiges are removed, and by the color of slabstone or ceramic tile
Modulate mill base filleting.
Some embodiments of the present invention are above are only, but the design concept of the present invention is not limited thereto, all profits
The change of unsubstantiality is carried out to the present invention with this design, the behavior for invading the scope of the present invention all should be belonged to.
Claims (2)
1. one kind is used for the wet extension stone material or wet hanging method of ceramic tile, it is characterised in that using suspension member, the suspension member include hanger bulk and
Position line;The hanger bulk includes horizontal hanging groove, backgauge piece and vertical connection piece, and the backgauge piece is parallel to horizontal hanging groove cloth
Put, the vertical connection piece both ends are connected with horizontal hanging groove and backgauge piece and are provided with threading hole on vertical connection piece respectively;It is described fixed
Bit line is detachably secured on vertical connection piece after passing through threading hole,
Step is as follows:
Step 1, slot, at least two necks being adapted with horizontal hanging groove hook are cut out at the back side of stone material or ceramic tile;
Step 2, mounting hook, by the horizontal hanging groove of hanger bulk stretch into the neck that step 1 cut out with stone material or ceramic tile
Clamping;
Step 3, fixed steel bars net and snap the line, according to the size of stone material or ceramic tile in metope basic unit one layer of reinforcing bar of colligation or welding
Net, and the outer contour of stone material or ceramic tile metope is ejected on the ground;
Step 4, stone material or ceramic tile are installed, by position line colligation on bar-mat reinforcement, while adjust stone material or ceramic tile perpendicularity and
Flatness, interim fixing stone or ceramic tile;
Step 5, it is in the milk, divides the hole that 2-5 layers are poured between metope basic unit and ceramic tile cement mortar match, rubber is used in filling
Skin hammer, which gently taps stone surface, to be made to pour into mortar exhaust;
Step 6, wiping seam, after whole slabstones or ceramic tile install, all remaining slurry vestiges are removed, and by the color of slabstone or ceramic tile
Modulate mill base filleting.
2. according to claim 1 be used for wet extension stone material or the wet hanging method of ceramic tile, it is characterised in that:The neck is opened in
More than/3rd position of stone material or stone material, the neck include opening in stone material or ceramic tile side vertical slot and open in stone material or
The translot at the ceramic tile back side, and vertical slot is connected with translot.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610118180.2A CN105756317B (en) | 2014-04-10 | 2014-04-10 | One kind is used for wet extension stone material or the wet hanging method of ceramic tile |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410142568.7A CN103899072B (en) | 2014-04-10 | 2014-04-10 | A kind of for wet extension stone material or the suspension member of ceramic tile and wet hanging method |
CN201610118180.2A CN105756317B (en) | 2014-04-10 | 2014-04-10 | One kind is used for wet extension stone material or the wet hanging method of ceramic tile |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410142568.7A Division CN103899072B (en) | 2014-04-10 | 2014-04-10 | A kind of for wet extension stone material or the suspension member of ceramic tile and wet hanging method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105756317A CN105756317A (en) | 2016-07-13 |
CN105756317B true CN105756317B (en) | 2018-01-23 |
Family
ID=56332369
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610118180.2A Expired - Fee Related CN105756317B (en) | 2014-04-10 | 2014-04-10 | One kind is used for wet extension stone material or the wet hanging method of ceramic tile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105756317B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107035090A (en) * | 2017-06-09 | 2017-08-11 | 北京广佳建筑装饰股份有限公司 | A kind of anti-hollowing construction method of stone wall surface |
CN112095972B (en) * | 2020-08-19 | 2021-08-13 | 江苏恒龙装饰工程有限公司 | Stone background wall construction method capable of reducing hollowing |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101131030A (en) * | 2007-09-18 | 2008-02-27 | 深圳市明远氟涂料有限公司 | Exterior wall heat-preserving decorating curtain wall and construction method thereof |
CN101191376A (en) * | 2006-11-24 | 2008-06-04 | 周述文 | Dry hanging device for stone or ceramic tile and assembling method thereof |
CN101302782A (en) * | 2008-06-30 | 2008-11-12 | 深圳市明远氟涂料有限公司 | Dried hanging thermal insulation decorative curtain wall and mounting process thereof |
CN101666145A (en) * | 2008-09-05 | 2010-03-10 | 成龙建设集团有限公司 | Method for upward hanging projecting eave stones |
CN101748868A (en) * | 2008-12-10 | 2010-06-23 | 周述文 | Stone material or ceramic-based dovetail plug arranging device and arranging method |
CN101962982A (en) * | 2010-10-18 | 2011-02-02 | 易科美德(天津)环保建材有限公司 | Process for mounting splicing type low-carbon heat insulating energy-saving plate |
CN101967877A (en) * | 2010-10-22 | 2011-02-09 | 徐小勇 | Insulating fireproof decorating plate and production method thereof |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1627116A4 (en) * | 2003-04-24 | 2011-01-12 | Steven Kenessey | Shaping member and method |
KR200327057Y1 (en) * | 2003-06-26 | 2003-09-19 | (주)로자 | cramp type panel for decorating the inside and the outside of building |
-
2014
- 2014-04-10 CN CN201610118180.2A patent/CN105756317B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101191376A (en) * | 2006-11-24 | 2008-06-04 | 周述文 | Dry hanging device for stone or ceramic tile and assembling method thereof |
CN101131030A (en) * | 2007-09-18 | 2008-02-27 | 深圳市明远氟涂料有限公司 | Exterior wall heat-preserving decorating curtain wall and construction method thereof |
CN101302782A (en) * | 2008-06-30 | 2008-11-12 | 深圳市明远氟涂料有限公司 | Dried hanging thermal insulation decorative curtain wall and mounting process thereof |
CN101666145A (en) * | 2008-09-05 | 2010-03-10 | 成龙建设集团有限公司 | Method for upward hanging projecting eave stones |
CN101748868A (en) * | 2008-12-10 | 2010-06-23 | 周述文 | Stone material or ceramic-based dovetail plug arranging device and arranging method |
CN101962982A (en) * | 2010-10-18 | 2011-02-02 | 易科美德(天津)环保建材有限公司 | Process for mounting splicing type low-carbon heat insulating energy-saving plate |
CN101967877A (en) * | 2010-10-22 | 2011-02-09 | 徐小勇 | Insulating fireproof decorating plate and production method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN105756317A (en) | 2016-07-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103899072B (en) | A kind of for wet extension stone material or the suspension member of ceramic tile and wet hanging method | |
CN203905374U (en) | Hanging piece for hanging stones or tiles in wet hanging mode | |
CN103276916B (en) | A kind of building method of sealing light weight concrete construction board wall wall hole and filling plate | |
CN108343181A (en) | A kind of novel clay brick exterior wall and construction method | |
CN105756317B (en) | One kind is used for wet extension stone material or the wet hanging method of ceramic tile | |
CN202090569U (en) | Plastering screed template | |
CN107938966A (en) | A kind of permanent ornamental moulded plate for building | |
CN207553505U (en) | Assembled wall anchoring assembly | |
CN104847069A (en) | Dry-hanging serpenggiante GRC prefabricated composite board and construction method thereof | |
CN205063052U (en) | Newly build a wall to personally experience sth. part of body and end water bar structure in bathroom | |
CN208950155U (en) | The compound stripe shape wallboard of hard PVC skeleton foam concrete and combined wall | |
CN207228439U (en) | A kind of viscous anchor combination ceramic thin plate decoration wall | |
CN110878594A (en) | Glass wool composite board and external thermal insulation construction process for glass wool composite board external wall | |
CN110847436A (en) | Phosphogypsum-based light ribbed internal partition wall board | |
CN106906987B (en) | A kind of functional form floating screed does angle equipment and its installation method | |
CN206554360U (en) | A kind of assembled porcelain earthenware brick for building and the house built using the porcelain earthenware brick | |
CN107975183A (en) | The building block of zigzag metope, building block building wall and building block preparation method can be built into by laying bricks or stones | |
CN209429435U (en) | A kind of trough of belt granite plates for metope paving | |
CN209099683U (en) | A kind of heat-preserving wall | |
CN207484805U (en) | One kind can build into the building block of zigzag metope, building block building wall by laying bricks or stones | |
CN210011167U (en) | Ceramic tile perforator | |
CN208950100U (en) | A kind of hard PVC skeleton foam concrete composite partition | |
CN207469781U (en) | A kind of control device of concrete layer thickness and flatness | |
CN206571338U (en) | Windowsill marble waterproof construction | |
CN105863151A (en) | Light foaming ceramsite concrete board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180123 |