CN105673074B - The local buried gutter structure of Tunnel Base - Google Patents

The local buried gutter structure of Tunnel Base Download PDF

Info

Publication number
CN105673074B
CN105673074B CN201610033038.8A CN201610033038A CN105673074B CN 105673074 B CN105673074 B CN 105673074B CN 201610033038 A CN201610033038 A CN 201610033038A CN 105673074 B CN105673074 B CN 105673074B
Authority
CN
China
Prior art keywords
tunnel
inspection shaft
buried gutter
drainage pipe
tunnel base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610033038.8A
Other languages
Chinese (zh)
Other versions
CN105673074A (en
Inventor
马志富
杨昌贤
夏勇
冯山群
陈换利
曲耀慧
曾青
王乐明
李岩
王洪昌
俞尚宇
李光京
吴小策
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
China Railway Design Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp filed Critical China Railway Design Corp
Priority to CN201610033038.8A priority Critical patent/CN105673074B/en
Publication of CN105673074A publication Critical patent/CN105673074A/en
Application granted granted Critical
Publication of CN105673074B publication Critical patent/CN105673074B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of local buried gutter structure of Tunnel Base, including the multiple inspection shafts for being located at the central drainage pipe in tunnel inverted arch filling and being set along central drainage pipe length direction;Tunnel Base is provided with the buried gutter in part, the one end in the buried gutter in part is equipped with end inspection shaft, end inspection shaft downstream is equipped with charge for remittance well, is connected between end inspection shaft and charge for remittance well by a plurality of vertical aqueduct and a plurality of longitudinal aqueduct, charge for remittance well is connected with central drainage pipe;Tunnel Base ponding is come together in by the buried gutter in part in the inspection shaft of end, then enters charge for remittance well by vertical aqueduct and longitudinal aqueduct, is then discharged outside hole by central drainage pipe.The present invention is suitable for Tunnel Base local draining, reduce the difficulty of construction of the elongated setting center Deeply buried ditch in tunnel and risk and project cost, reduce the water pressure that tunnel structure is born, it prevents tunnel liner structure percolating water during construction and operation from even causing Lining cracks, ensures operation security.

Description

The local buried gutter structure of Tunnel Base
Technical field
The present invention relates to a kind of Tunnel Base gutter structures, and in particular to a kind of to be arranged on Tunnel Base locally buried Gutter structure.
Background technology
At present, there are two types of modes for Tunnel Base draining:A kind of is that the ponding in tunnel is entered lateral sulcus by abutment wall drain hole, The Central drain being located in inverted arch filling is introduced from lateral sulcus again, this method is more universal;Another kind is at tunnel bottom setting center Deeply buried ditch or drain cavern, by outside the direct ejectment to hole of water, this method in Han Qu or the more use of severe cold area Portal Section, Its situation also has use.Although these drainage systems can smoothly be implemented on all kinds of stratum, and play certain effect, applying It has also been found that many problems, are mainly shown as during work and operation:
When using first method, sole must enter Central drain by abutment wall drain hole, and Central drain position In inverted arch filling in, there are tunnel bottom draining it is difficult the problem of, from the point of view of the tunnel runed, when the ponding of tunnel bottom It can not be successfully when draining, the lighter penetrates into railway roadbed along weak location upwards, and substrate is risen soil, and severe one causes inverted arch to fill and road Bed cracking floats, and even jeopardizes driving when serious.And when using second method, the water base instinct in tunnel is smoothly arranged Go out, but the elongated use center Deeply buried ditch in one side tunnel or drain cavern can make project cost remain high;On the other hand, with reference to Previous construction experience applies center Deeply buried ditch or drain cavern in a wide range of slotting of tunnel bottom, and construction and excavation easily causes just Phase supporting inverted arch can not be closed in time, also easily cause tunnel arch wall unstability when being excavated using explosion means, greatly increase construction Risk, while there is also many hidden danger after the completion of constructing.
Since tunnel is a kind of long and narrow structures, often geological conditions variation is frequent, it is necessary to take the buried row in part Ditch solves the drainage problem of Tunnel Base.
Invention content
The present invention is exactly to solve above-mentioned the problems of the prior art, provides a kind of locally buried draining of Tunnel Base Ditch structure.
In order to achieve the above object, the present invention adopts the following technical scheme that:
The local buried gutter structure of Tunnel Base of the present invention, including being located at the central drainage pipe in tunnel inverted arch filling With the multiple inspection shafts set along central drainage pipe length direction;Tunnel Base is provided with the buried gutter in part, and part is buried The one end in gutter is equipped with end inspection shaft, and end inspection shaft downstream is equipped with charge for remittance well, leads between end inspection shaft and charge for remittance well It crosses a plurality of vertical aqueduct to connect with a plurality of longitudinal aqueduct, charge for remittance well is connected with central drainage pipe;Tunnel Base ponding is by office The buried gutter in portion is come together in the inspection shaft of end, then enters charge for remittance well by vertical aqueduct and longitudinal aqueduct, is then led to It crosses outside central drainage pipe discharge hole.
Central drainage pipe, locally buried gutter and longitudinal aqueduct is consistent with the circuit longitudinal slope gradient.
The central drainage pipe is made of more drainpipes, and crosses end inspection shaft between two parties and in the inspection shaft of end It does not turn off, the single drainpipe tube coupling length setting charge for remittance well of the central drainage pipe of 1.4 ~ 1.6 times of inspection shaft spaced downstream in end.
Concrete pedestal, the buried gutter in part and concrete pedestal are provided with below the buried gutter in the part Between using the good coarse sand of water penetration and gravel backfill it is closely knit.Package is permeable on the outside of the steel floral tube that the buried gutter in part uses Geotextiles install punching bellows in steel floral tube;Steel floral tube top half drills, and 10~16mm of aperture, pitch of holes 10cm are in Quincuncial arrangement.
It is backfilled to and is put down with central drainage pipe top surface using the good coarse sand of water penetration and gravel in the end inspection shaft Together, the four corners position of end inspection shaft sets four vertical aqueducts, vertical aqueduct and the charge for remittance well in downstream and center draining Pipe is connected by longitudinal aqueduct;Vertical aqueduct and longitudinal aqueduct use pvc pipe.
The upstream face side Tunnel Base of the end inspection shaft well bore is poured with lower part using non-fine concrete, with Just water-collecting capacity is improved.
The invention has the advantages and positive effects that:
The local buried gutter structure of Tunnel Base of the present invention, suitable for Tunnel Base local draining, by tunnel The buried gutter in substrate setting part and setting end inspection shaft, after the water of substrate is imported end inspection shaft along buried gutter It is introduced in charge for remittance well through longitudinally, laterally aqueduct and is discharged into Central drain, discharged outside hole, realize self-draining through Central drain Function so as to reduce the difficulty of construction and risk and project cost of the elongated setting center Deeply buried ditch in tunnel or drain cavern, subtracts The water pressure that structure during small constructing tunnel and during operation is born prevents tunnel from being served as a contrast during construction period and operation It builds structural percolating water and even causes Lining cracks, ensure operation security.
Description of the drawings
Fig. 1 is the longitudinal section view of the local buried gutter structure of Tunnel Base of the present invention;
Fig. 2 is the vertical view in the local buried gutter of Tunnel Base of the present invention;
Fig. 3 is the sectional view of I-I lines along Fig. 1;
Fig. 4 is the sectional view of II-II lines along Fig. 1;
Fig. 5 is the profile of III-III lines along Fig. 1.
Critical piece symbol description in attached drawing:
1:Central drainage pipe 2:The buried gutter in part
3:Inspection shaft 4:End inspection shaft
5:Charge for remittance well 6:Vertical aqueduct
7:Longitudinal aqueduct 8:Water penetration filler
9:Concrete bed 10:Non-fine concrete.
Specific embodiment
To the Tunnel Base of the present invention, locally buried gutter structure is done further in the following with reference to the drawings and specific embodiments Explanation.Following each embodiments are merely to illustrate the present invention and not limitation of the present invention.
The local buried gutter structure of Tunnel Base of the present invention, suitable for Tunnel Base local draining.The discharge structure It takes in the buried gutter of Tunnel Base local setting, setting end inspection shaft and charge for remittance well, by the water of substrate along buried draining Ditch is discharged into Central drain after importing end inspection shaft in longitudinally, laterally aqueduct introducing charge for remittance well, and hole is discharged through Central drain Outside.
Fig. 1 is the longitudinal section view of the local buried gutter structure of Tunnel Base of the present invention;Fig. 2 is the tunnel base of the present invention The vertical view in the local buried gutter in bottom.As depicted in figs. 1 and 2, the local buried gutter structure of Tunnel Base of the invention, packet The setting central drainage pipe 1 in tunnel inverted arch filling is included, in the buried gutter 2, Duo Gejian in the part of Tunnel Base local setting Look into 3, end inspection shafts 4 of well, a charge for remittance well 5, a plurality of vertical aqueduct 6 and a plurality of longitudinal aqueduct 7.Central drainage pipe The Tunnel Base part of 1 lower section is provided with the buried gutter 2 in part.The buried gutter 2 in part is adapted to using non-totally-enclosed anti- The tunnel of water, mainly suitable for be arranged on tunnel trunk country rock be rich water Quaternary Strata, tertiary stratum, soft rock strata and ground Matter structural belt;In addition, change of properties section also has certain adaptability after meeting water for rich water ground consisting of hard rock substrate.
Inspection shaft 3 is set along 1 length direction of central drainage pipe, and an inspection shaft is set per 30m.The buried gutter 2 in part Interior water flows into the end inspection shaft 4 of low side setting.Water in end inspection shaft 4 is vertical by four vertical aqueducts 6 and two It is discharged outside hole through central drainage pipe 1 after the inflow charge for remittance of aqueduct 7 well 5, realizes self-draining function.
Central drainage pipe 1, the buried gutter 2 in part and two longitudinal aqueducts 7 and the tunnel inner orbit circuit longitudinal slope gradient Unanimously.
Central drainage pipe 1 is made of more drainpipes, and cross between two parties end inspection shaft 4 and in end inspection shaft 4 not It disconnects, i.e., the water of central drainage pipe 1 does not enter end inspection shaft 4.The center of 1.4 ~ 1.6 times of 4 spaced downstream of inspection shaft in end The single drainpipe tube coupling length setting charge for remittance well 5 of drainpipe.
Fig. 3 is the sectional view of I-I lines along Fig. 1;As shown in figure 3, the buried gutter 2 in part sets concrete bed 9, It is backfilled closely knit between pedestal using water penetration filler 8.The good coarse sand of water penetration and gravel can be used in water penetration filler 8. The buried gutter 2 in part is using the seamless steel floral tube of hot rolling, steel pipe upper half section borehole, 10 mm of aperture~16mm, pitch of holes 10cm, in quincuncial arrangement;Steel floral tube outer wrapping permeable geotextiles install punching bellows in pipe, can effectively prevent part Buried gutter 2 is blocked, and the ponding of Tunnel Base can enter the buried gutter in part.
Fig. 4 is the sectional view of II-II lines along Fig. 1;As shown in figure 4, it is returned in end inspection shaft 4 using water penetration filler 8 Be filled to it is concordant with the top of central drainage pipe 1, and in four vertical drainage pipes 6 of quadrangle setting.Pvc pipe can be used in vertical drainage pipe 6, The good coarse sand of water penetration and gravel can be selected in water penetration filler 8.
Fig. 5 is the profile of III-III lines along Fig. 1.As shown in figure 5,4 well bore upstream face one of end inspection shaft Side Tunnel Base is poured with lower part using non-fine concrete 10, can improve the water-collecting capacity of end inspection shaft.
The present invention is by the buried gutter of Tunnel Base local setting, setting end inspection shaft and charge for remittance well, by perpendicular The water of substrate is ultimately discharged into Central drain heel row to, longitudinal aqueduct and appears outer, realizes automatic drainage function.Reduce tunnel The difficulty of construction and risk and project cost of elongated setting center Deeply buried ditch or drain cavern, during reducing constructing tunnel and are transported The water pressure that structure during battalion is born prevents tunnel liner structure percolating water during construction period and operation from even causing Lining cracks ensure operation security.

Claims (7)

1. a kind of local buried gutter structure of Tunnel Base, including being located at the central drainage pipe in tunnel inverted arch filling( 1) With along central drainage pipe( 1)Multiple inspection shafts of length direction setting( 3);It is characterized in that:Tunnel Base is provided with office The buried gutter in portion( 2), the buried gutter in part( 2)One end be equipped with end inspection shaft( 4), end inspection shaft( 4)Downstream is equipped with charge for remittance well( 5), end inspection shaft( 4)With charge for remittance well( 5)Between pass through four vertical aqueducts( 6) With two longitudinal aqueducts( 7)Even
It is logical, charge for remittance well( 5)With central drainage pipe( 1)Connection;Tunnel Base ponding is by the buried gutter in part( 2)Collect In end inspection shaft( 4)It is interior, then upwardly through vertical aqueduct( 6)With longitudinal aqueduct( 7)Into charge for remittance well( 5), then pass through central drainage pipe( 1)It discharges outside hole.
2. the local buried gutter structure of Tunnel Base according to claim 1, it is characterised in that:Central drainage pipe( 1), the buried gutter in part( 2)With longitudinal aqueduct( 7)It is consistent with the circuit longitudinal slope gradient.
3. the local buried gutter structure of Tunnel Base according to claim 1, it is characterised in that:The center draining Pipe( 1)It is made of more drainpipes, and crosses end inspection shaft between two parties( 4)And do not turned off in the inspection shaft of end, it is holding Portion's inspection shaft( 4)The single drainpipe tube coupling length setting charge for remittance well of central drainage pipe of .6 times of spaced downstream 1 .4 ~ 1( 5).
4. the local buried gutter structure of Tunnel Base according to claim 1, it is characterised in that:The part is buried Gutter( 2)Lower section be provided with concrete pedestal( 9), the buried gutter in part( 2)With concrete pedestal( 9)It Between using the good coarse sand of water penetration and gravel backfill it is closely knit.
5. the local buried gutter structure of Tunnel Base according to claim 4, it is characterised in that:The buried gutter in part ( 2)Permeable geotextiles are wrapped up on the outside of the steel floral tube of use, punching bellows is installed in steel floral tube;Steel floral tube top half drills, 10~16mm of aperture, pitch of holes 10cm, in quincuncial arrangement.
6. the local buried gutter structure of Tunnel Base according to claim 3, it is characterised in that:The end checks Well( 4)It is interior using the good coarse sand of water penetration and gravel is backfilled to and central drainage pipe( 1)Either flush, end inspection shaft ( 4)Four corners position set four vertical aqueducts( 6), vertical aqueduct( 6)With the charge for remittance well in downstream( 5)With in Heart drainpipe( 1)Pass through longitudinal aqueduct( 7)Connection;Vertical aqueduct( 6)With longitudinal aqueduct( 7)Use Pvc pipe.
7. the local buried gutter structure of Tunnel Base according to claim 6, it is characterised in that:End inspection shaft( 4)The upstream face side Tunnel Base of well bore is poured with lower part using non-fine concrete.
CN201610033038.8A 2016-01-19 2016-01-19 The local buried gutter structure of Tunnel Base Active CN105673074B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610033038.8A CN105673074B (en) 2016-01-19 2016-01-19 The local buried gutter structure of Tunnel Base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610033038.8A CN105673074B (en) 2016-01-19 2016-01-19 The local buried gutter structure of Tunnel Base

Publications (2)

Publication Number Publication Date
CN105673074A CN105673074A (en) 2016-06-15
CN105673074B true CN105673074B (en) 2018-06-26

Family

ID=56301428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610033038.8A Active CN105673074B (en) 2016-01-19 2016-01-19 The local buried gutter structure of Tunnel Base

Country Status (1)

Country Link
CN (1) CN105673074B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106150547B (en) * 2016-07-29 2018-05-18 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled drainage system of railway tunnel bottom
CN106049543B (en) * 2016-08-03 2019-07-30 中国铁路设计集团有限公司 Tunnel inspection shaft with sluicing anti-floating function
CN107201908B (en) * 2017-06-16 2023-10-31 中铁五局集团有限公司 Construction method for deep-buried central ditch of tunnel in severe cold region
CN109441489B (en) * 2018-12-29 2024-04-05 中国铁路设计集团有限公司 Tunnel deep-buried central ditch supporting structure and supporting construction method
CN109630194B (en) * 2019-01-29 2024-02-23 中国建筑一局(集团)有限公司 Karst region fault fracture zone tunnel water burst treatment structure and construction method thereof
CN111577383B (en) * 2020-05-11 2021-04-09 中铁一局集团有限公司 Method for treating tunnel leakage water in alpine region
CN113217098B (en) * 2021-05-21 2022-03-22 中铁隧道局集团有限公司 Construction drainage method and device suitable for extra-long deep-buried tunnel
CN117127440B (en) * 2023-10-27 2024-03-12 中国铁路设计集团有限公司 Double-block ballastless track structure of railway tunnel and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102661171A (en) * 2012-05-02 2012-09-12 中铁十一局集团第五工程有限公司 Frost damage prevention drainage system for tunnel
CN102678174A (en) * 2012-05-28 2012-09-19 中交第一公路勘察设计研究院有限公司 Tunnel drainage system passing through permafrost region and non-frozen ground region and arrangement method thereof
CN102996178A (en) * 2012-12-13 2013-03-27 中铁四局集团第二工程有限公司 Drainage system for tunnel in severe cold region
CN104727834A (en) * 2015-01-21 2015-06-24 中铁五局(集团)有限公司 Summer-time face excavation construction method for high and cold permafrost ultra-long highway tunnel
CN204960952U (en) * 2015-08-19 2016-01-13 铁道第三勘察设计院集团有限公司 Tunnel structure with hoop heat preservation rubble french drain

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3445690B2 (en) * 1995-08-11 2003-09-08 タキロン株式会社 Drainage tube mounting structure
JPH09166000A (en) * 1995-12-14 1997-06-24 Kumakigumi:Kk Water leakage preventive method of tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102661171A (en) * 2012-05-02 2012-09-12 中铁十一局集团第五工程有限公司 Frost damage prevention drainage system for tunnel
CN102678174A (en) * 2012-05-28 2012-09-19 中交第一公路勘察设计研究院有限公司 Tunnel drainage system passing through permafrost region and non-frozen ground region and arrangement method thereof
CN102996178A (en) * 2012-12-13 2013-03-27 中铁四局集团第二工程有限公司 Drainage system for tunnel in severe cold region
CN104727834A (en) * 2015-01-21 2015-06-24 中铁五局(集团)有限公司 Summer-time face excavation construction method for high and cold permafrost ultra-long highway tunnel
CN204960952U (en) * 2015-08-19 2016-01-13 铁道第三勘察设计院集团有限公司 Tunnel structure with hoop heat preservation rubble french drain

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
巴朗山隧道中心排水沟设计参数研究;陈子龙等;《四川建筑》;20140630;第34卷(第3期);第106页第2段,图7 *

Also Published As

Publication number Publication date
CN105673074A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN105673074B (en) The local buried gutter structure of Tunnel Base
CN104264557B (en) One is partly filled out and is partly dug ecological road structure and construction method
CN203515597U (en) Tunnel structure applicable to soft stratum
CN105586859B (en) Integral irrigation and drainage pipe system of saline-alkali soil farmland and construction method
CN105937196B (en) A kind of roadbed peg board formula spells wide structure and construction method
CN105863671A (en) Frame type low-position draining system tunnel lining structure
CN102400713B (en) Method for auxiliary construction of water falling in tunnel by communicated channel
CN109797769B (en) Collapsible loess area underground comprehensive pipe gallery foundation structure and construction method thereof
CN103939109B (en) The permanent shutoff inclined shaft structure of isolating with tunnel
CN104404974A (en) High-pressure-bearing water and thick sand and pebble formation deep foundation pit grouting bottom-sealing structure and construction technology thereof
CN103088836A (en) Sedimentation control method for pumping water and performing reinjection in well casing simultaneously
CN107882042A (en) Supporting construction and its construction method are supportted before a kind of bellows
CN105926391B (en) A kind of curb method for widening of existing railway roadbed
CN206942786U (en) A kind of advanced pre-add fixing structure of high-moisture percentage loess tunnel
CN205349419U (en) Escape canal structure is buried deeply to tunnel basement part
CN105604088B (en) A kind of medium-and low-speed maglev is low to put the existing barricade micro-disturbance ruggedized construction of circuit
CN204551510U (en) A kind of filled-up ground catchments pressure reduction well drop and drainage structure
CN207944450U (en) soft foundation reinforcing structure
CN111271118B (en) Drainage structure suitable for reconstruction of karst tunnel bottom structure and construction method thereof
CN203050779U (en) Tunnel drainage structure suitable for bias pressure rich water strata
CN105443141A (en) Tunnel base reinforcement method
CN204252148U (en) High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure
CN110004954A (en) Intratectal anchor caverns structure and its construction method
CN113464174B (en) Construction method of tunnel row waterproof comprehensive treatment system
CN105064384B (en) Vacuum tube well precipitation system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 300142 Hebei District, Zhongshan Road, No. 10,

Applicant after: China Railway Design Group Limited

Address before: 300142 Hebei District, Zhongshan Road, No. 10,

Applicant before: China Railway Third Survey and Design Institute Group Ltd.

GR01 Patent grant
GR01 Patent grant