CN204252148U - High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure - Google Patents

High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure Download PDF

Info

Publication number
CN204252148U
CN204252148U CN201420737294.1U CN201420737294U CN204252148U CN 204252148 U CN204252148 U CN 204252148U CN 201420737294 U CN201420737294 U CN 201420737294U CN 204252148 U CN204252148 U CN 204252148U
Authority
CN
China
Prior art keywords
slurry
slip casting
water
back cover
side wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420737294.1U
Other languages
Chinese (zh)
Inventor
刘建伟
卢致强
贺长俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ranken Railway Construction Group Co Ltd
CRTG Survey and Design Institute Co Ltd
Original Assignee
Ranken Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ranken Railway Construction Group Co Ltd filed Critical Ranken Railway Construction Group Co Ltd
Priority to CN201420737294.1U priority Critical patent/CN204252148U/en
Application granted granted Critical
Publication of CN204252148U publication Critical patent/CN204252148U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses high artesian thick sand-pebble layer deep foundation ditch slip casting back cover slip casting structure and construction technology thereof, comprise the water-stop curtain inserting underground, slurry base plate, slurry side wall and slurry partition wall is formed with by slip casting in the below of water-stop curtain, described slurry side wall and water-stop curtain closely cementing, slurry base plate, slurry side wall and slurry partition wall are enclosed in substrate and form multiple U-shaped slip casting storehouse to lower recess, and above slurry base plate, secondary grouting is formed with slurry strengthening course.The utility model U-shaped slip casting chamber structure increases hole end bulk strength and rigidity, possess the reinforcing of the end, hole and antiseepage double effects, the bottom heave that the high artesian that effectively can solve buried depth increasing causes hole end stability influence and excavation of foundation pit, reduces the sedimentation and deformation of hole wall lateral displacement and surrounding environment simultaneously preferably.

Description

High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure
Technical field
The utility model relates to the artesian water process field of thick sand-pebble layer deep-foundation pit engineering, specifically refers to high artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure.
Background technology
At present, the outer precipitation in hole, curtain vertical partition wall, the full slip casting back cover of substrate three kinds of methods are usually adopted to solve the engineering problem that artesian water causes in deep-foundation pit engineering.
The first is the outer precipitation method in hole, the mentality of designing of the method is: adopt diaphragm wall or drilled pile, interlocking pile and corresponding water-stop curtain etc. as space enclosing structure, first carry out cheating the construction of inside and outside dewatering confined water after space enclosing structure is carried out, drop to the absolute altitude of designing requirement at artesian water head after, carry out excavation.The advantage of the method is, constructs more convenient, and construction quality can ensure.The shortcoming of the method is, precipitation unavoidably causes the sedimentation of foundation ditch surrounding enviroment and relative settlement, especially the very deficient regional engineering of water resource and the engineering higher to sedimentation and deformation requirement, and the program is forbidden to adopt; At the sand-pebble layer that artesian head is higher, the water content of artesian aquifer is enriched, Rainfall Influence scope is wide, pump-out is large, the time of dewatering confined water is long, and precipitation expense and difficulty are very high, higher to the power demands at execution control, municipal drainage and scene, during power-off, emergency plan enforcement difficulty is high, and in hole, dewatering well is closed also suitable risk.
The second is curtain vertical partition wall method, the mentality of designing of the method is: adopt diaphragm wall or drilled pile, interlocking pile and corresponding water-stop curtain as space enclosing structure, water-stop curtain inserts the impervious layer certain depth under artesian aquifer, reaches vertical partition wall artesian water object.The advantage of the method is, the excavation of foundation pit stage does not need dewatering confined water, construction risk and relatively little on the impact of surrounding environment; Construction quality can ensure.The shortcoming of the method is, the degree of depth of water-stop curtain is large, and particularly when artesian aquifer is thicker and buried depth is darker, water-stop curtain inserts deep layer impervious layer, very high to the requirement of construction technology and construction machinery.Water-stop curtain is darker, is more difficult to ensure verticality and the leak tightness of card water-stop curtain, once there is the situation that curtain leaks in digging process, prominent gushing very easily occurs, and consequence is serious, and is difficult to judge breakthrough.
The third is substrate gamut slip casting back cover method, the mentality of designing of the method is: adopt diaphragm wall or drilled pile, interlocking pile and corresponding water-stop curtain as space enclosing structure, substrate adopts gamut slip casting water proof, utilizes injecting cement paste to conduct oneself with dignity and resists artesian pressure.The advantage of the method is, the excavation of foundation pit stage does not need dewatering confined water, construction risk and relatively little on the impact of surrounding environment; Construction quality can ensure.The shortcoming of the method is, grouting amount is very large, and particularly when artesian aquifer is thicker and buried depth is darker, slip casting appropriate litigation fees is high.Injecting cement paste is once there be local quality problem, and leaking appears in substrate, and underground water is rushed to rock-soil layer in substrate, and be difficult to judge leakage area after string water, be also difficult to carry out the process of specific aim compensation and grouting, gamut compensation and grouting is then costly, and the duration is slow.
Utility model content
The purpose of this utility model is to provide high artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure, solve the grouting amount that in prior art, substrate gamut slip casting back cover method exists large, costly, long in time limit, leaking appears in substrate, underground water is rushed to rock-soil layer in substrate, is difficult to the problem judging leakage area after string water.
High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure, comprise the water-stop curtain inserting underground, slurry base plate, slurry side wall and slurry partition wall is formed with by slip casting in the below of water-stop curtain, described slurry side wall and water-stop curtain closely cementing, slurry base plate, slurry side wall and slurry partition wall are enclosed in substrate and form multiple U-shaped slip casting storehouse to lower recess, and above slurry base plate, secondary grouting is formed with slurry strengthening course.The utility model adopts existing equipment in deep foundation pit construction, creatively propose the U-shaped point storehouse slip casting back cover structure of U-shaped, the slurry base plate that slip casting is formed, slurry side wall, slurry partition wall encloses the U-shaped slip casting storehouse back cover structure forming bottom lock, entirely descending in foundation pit construction process, because substrate is divided into several U-shaped slip casting storehouse back cover structures be separated from each other successively, when occurring in certain U-shaped slip casting storehouse that water level raises suddenly or water yield situation jumpy, then can judge to occur leakage point in this U-shaped slip casting storehouse, only need carry out pump drainage to this slip casting storehouse and mend injecting treatment.With technical scheme the most close be substrate gamut slip casting back cover scheme, this scheme grouting amount is very large, and particularly when artesian aquifer is thicker and buried depth is darker, slip casting appropriate litigation fees is high.Injecting cement paste is once there be local quality problem, and leaking appears in substrate, and underground water is rushed to rock-soil layer in substrate, and be difficult to judge leakage area after string water, be also difficult to carry out the process of specific aim compensation and grouting, gamut compensation and grouting is then costly, and the duration is slow; And the technical scheme of the application just can overcome substrate gamut slip casting back cover scheme Problems existing, once find local infiltration, can prominent gush occur before Timeliness coverage seepage place, and have enough buffer time to carry out the stronger compensation and grouting process of specific aim, not only reduce overall cost, and utilize Rock And Soil deadweight opposing artesian pressure, compare the full slip casting back cover of substrate, grouting amount significantly reduces, and greatly reduces engineering cost and duration; Slurry side wall and slurry partition wall is formed by slip casting, substrate is separated into multiple U-shaped slip casting storehouse, dewatering well and water-level observation hole are set in each slip casting storehouse, once certain storehouse water-level observation hole water level or the water yield sharply change, injecting treatment can be compensated in time for this storehouse in time, carry out backfill back-pressure if desired, also there is certain water storage space in storehouse, reserve buffer time to emergency processing, in addition, point storehouse compensation and grouting can the specific aim of safeguard measure, also reduces disposal cost and duration; U-shaped slip casting chamber structure increases hole end bulk strength and rigidity, possess the reinforcing of the end, hole and antiseepage double effects, the bottom heave that the high artesian that effectively can solve buried depth increasing causes hole end stability influence and excavation of foundation pit, reduces the sedimentation and deformation of hole wall lateral displacement and surrounding environment simultaneously preferably.
Slurry base plate, the slurry side wall in described U-shaped slip casting storehouse are formed by mini-valve tube note dual slurry.
Described U-shaped slip casting storehouse, slurry partition wall and slurry strengthening course note single liquid slurry by mini-valve tube and formed.Further, in the technical scheme of the application, sleeve valve barrel grouting warehouse first adopts the dual slurry that gel time is short, consolidation strength is high, injecting cement paste is formed rapidly for water proof on high artesian stratum, namely slurry base plate and slurry side wall is utilized to carry out water proof, then cheap, that technique is simple, anti-permeability performance good, set strength is high single liquid slurry is adopted to carry out reinforcement, consolidate slip casting effect further, both ensure that the requirement of substrate slip casting back cover, there is again stronger economy.
In each U-shaped slip casting storehouse, water-level observation hole and dewatering well are all set.When water level or the water yield sharply change in storehouse, can be used for pump drainage and the process of mini-valve tube compensation and grouting in storehouse.
The construction technology of high artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure, comprises the following steps:
A (), according to artesian water water pressure and the excavation of foundation pit degree of depth, determines the degree of depth, slurry base plate thickness, slurry side wall thicknesses, slurry side wall and the superimposed degree of depth of curtain bottom the curtain degree of depth, substrate U-shaped slip casting storehouse;
(b) construction space enclosing structure: utilize diaphragm wall, interlocking pile or drilled pile to form corresponding water-stop curtain;
C () adopts the grouting of sleeve valve barrel grouting technique to build the grouting back cover structure being formed and have multiple U-shaped slip casting storehouse on ground, and be built up integrally closed structure with water-stop curtain;
D () applies dewatering well and water-level observation hole in hole, by underground water drainage in storehouse;
E () layer and section excavates from the top down, and set up inner support in time, until be excavated to substrate;
F () to be returned along way by open cut and is built agent structure, sequentially remove inner support, and top board backfills.
In construction technology of the present utility model, to form the U-lag of slip casting structure in underground by controlling the slip casting degree of depth of mini-valve tube, grouting amount and injection speed, thus the subregion realizing subterranean layer controls, for substrate of the prior art full slip casting back cover scheme, duration shortens, and the risk of infiltration reduces greatly, and permeable specified place is convenient to excavate and control, be convenient to find permeable point in time, greatly reduce the risk that foundation ditch is permeable.
Described step (c) comprises the following steps:
(c1) first adopt sleeve valve barrel grouting engineering method note dual slurry, form slurry base plate and slurry side wall, the bottom of slurry side wall and water-stop curtain is closely connected, and slurry base plate, slurry side wall and water-stop curtain form substrate U-shaped slip casting storehouse back cover structure jointly;
(c2) then adopt sleeve valve barrel grouting engineering method to note single liquid slurry, form slurry partition wall, U-shaped slip casting storehouse is separated into multiple U-shaped slip casting storehouse;
(c3) finally adopt sleeve valve barrel grouting engineering method to note single liquid slurry, above slurry base plate, carry out secondary grouting, form slurry strengthening course.
Further, in the technical scheme of the application, sleeve valve barrel grouting warehouse first adopts the dual slurry that gel time is short, consolidation strength is high, injecting cement paste is formed rapidly for water proof on high artesian stratum, namely slurry base plate and slurry side wall is utilized to carry out water proof, then cheap, that technique is simple, anti-permeability performance good, set strength is high single liquid slurry is adopted to carry out reinforcement, consolidate slip casting effect further, both ensure that the requirement of substrate slip casting back cover, there is again stronger economy.
The utility model compared with prior art, has following advantage and beneficial effect:
1, the utility model high artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure, slurry partition wall is formed by slip casting, U-shaped for substrate slip casting storehouse is separated into multiple slip casting storehouse, each slip casting storehouse arranges dewatering well and water-level observation hole, once certain storehouse water-level observation hole water level or the water yield sharply change, injecting treatment can be compensated in time in time for this storehouse, carry out backfill back-pressure if desired, also certain water storage space is had in storehouse, buffer time is reserved to emergency processing, in addition, point storehouse compensation and grouting can the specific aim of safeguard measure, also reduces disposal cost and duration; U-shaped slip casting chamber structure increases hole end bulk strength and rigidity, possess the reinforcing of the end, hole and antiseepage double effects, the bottom heave that the high artesian that effectively can solve buried depth increasing causes hole end stability influence and excavation of foundation pit, reduces the sedimentation and deformation of hole wall lateral displacement and surrounding environment simultaneously preferably;
2, the utility model high artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure, first adopt the dual slurry that gel time is short, consolidation strength is high, injecting cement paste is formed rapidly for water proof on high artesian stratum, namely slurry base plate and slurry side wall is utilized to carry out water proof, then cheap, that technique is simple, anti-permeability performance good, set strength is high single liquid slurry is adopted to carry out reinforcement, consolidate slip casting effect further, both ensure that the requirement of substrate slip casting back cover, there is again stronger economy;
3, the utility model high artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure, slurry side wall and the water-stop curtain of slip casting formation are closely cementing, prevent slip casting warehouse and water-stop curtain joint place from seepage erosion occurring, also make up the leakage problems do not closed because of construction reason curtain.
Accompanying drawing explanation
Accompanying drawing described herein is used to provide the further understanding to the utility model embodiment, forms a application's part, does not form the restriction to the utility model embodiment.In the accompanying drawings:
Fig. 1 is the U-shaped slip casting storehouse schematic cross section of the utility model foundation ditch;
Fig. 2 is vertical section, the U-shaped slip casting storehouse schematic diagram of the utility model foundation ditch;
Fig. 3 is the top view in the U-shaped slip casting storehouse of the utility model foundation ditch;
Fig. 4 is the structural representation according to substrate gamut slip casting back cover in embodiment;
Fig. 5 is the constructing structure schematic diagram according to the utility model structure in embodiment.
Mark and corresponding component title in accompanying drawing:
1-water-stop curtain, 2-base plate, 3-side wall, 4-partition wall, 5-strengthening course, 6-inner support, 7-agent structure, 8-actual water level.
Detailed description of the invention
Clearly understand for making the purpose of this utility model, technical scheme and advantage, below in conjunction with embodiment and accompanying drawing, the utility model is described in further detail, exemplary embodiment of the present utility model and explanation thereof are only for explaining the utility model, and conduct is not to restriction of the present utility model.
Embodiment
The present embodiment is Beijing Metro station, and its length is 139.2m, and standard paragraphs foundation depth is 31.6m, width 24.9m.Station base plate is mainly positioned at the very strong boulder bed of water permeability, cheats outer pressure water head distance hole end 13m.
Conventionally middle substrate gamut slip casting back cover scheme: space enclosing structure adopts the thick diaphragm wall of 1.0m, building-in depth 15m, substrate 15m scope adopts the full hall slip casting of mini-valve tube, its at the middle and upper levels 12m scope note single liquid slurry, lower floor 3m scope note dual slurry, as shown in Figure 4.Through estimation, space enclosing structure cost about 6,229 ten thousand, slip casting expense 11,280 ten thousand, 3 months slip casting durations.
And in the work progress of reality, its constructing structure as shown in Figures 1 to 3,
A (), according to artesian water water pressure and the excavation of foundation pit degree of depth, determines the degree of depth 15 meters bottom water-stop curtain 1 degree of depth 9 meters, substrate U-shaped slip casting storehouse, slurry base plate 2 thickness 3 meters, slurry side wall 3 thickness 2 meters, slurry side wall 4 and the superimposed degree of depth of water-stop curtain 19 meters;
(b) construction space enclosing structure: adopt the thick diaphragm wall of 1.0m to form corresponding water-stop curtain 1;
(c1) first adopt sleeve valve barrel grouting engineering method note dual slurry, the bottom forming slurry base plate 2 and slurry side wall 3 slurry side wall 3 and water-stop curtain 1 is closely connected, and slurry base plate 2, slurry side wall 3 and water-stop curtain form substrate U-shaped slip casting storehouse back cover structure jointly; The thick 3m of slurry base plate 2, the thick 2m of slurry side wall 3, slurry side wall 3 and the closely connected superimposed 9m of diaphragm wall;
(c2) then adopt sleeve valve barrel grouting engineering method to note single liquid slurry, form slurry partition wall 4, U-shaped slip casting storehouse is separated into multiple U-shaped slip casting storehouse, the thick 2m of slurry partition wall;
(c3) finally adopt sleeve valve barrel grouting engineering method to note single liquid slurry, above slurry base plate, carry out secondary grouting, form slurry strengthening course 5, slurry reinforcement thickness 2m;
D () applies dewatering well and water-level observation hole in hole, by underground water drainage in storehouse;
E () layer and section excavates from the top down, and set up inner support 6 in time, until be excavated to substrate;
F () to be returned along way by open cut and is built agent structure 7, sequentially remove inner support 6, and top board backfills.
Space enclosing structure adopts the thick diaphragm wall of 1.0m, building-in depth 9m, substrate 15m scope adopts mini-valve tube U-shaped U-shaped to divide storehouse slip casting back cover, the wherein thick 3m of slurry base plate, the all thick 2m of slurry side wall, slurry partition wall and slurry strengthening course, slurry side wall and the closely connected superimposed 9m of diaphragm wall, slurry base plate and side wall note dual slurry, slurry partition wall and strengthening course note single liquid slurry.Construction size as shown in Figure 5, through estimation, space enclosing structure cost about 5,370 ten thousand, slip casting expense 5,264 ten thousand, 1.5 months slip casting durations.
In sum, after adopting substrate U-shaped U-shaped described in the utility model point storehouse slip casting back cover scheme, space enclosing structure expense saves 8,590,000, and slip casting expense saves 6,016 ten thousand, and the duration saves 1.5 months.
Above-described detailed description of the invention; the purpose of this utility model, technical scheme and beneficial effect are further described; be understood that; the foregoing is only detailed description of the invention of the present utility model; and be not used in restriction protection domain of the present utility model; all within spirit of the present utility model and principle, any amendment made, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (4)

1. high artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure, comprise the water-stop curtain (1) inserting underground, it is characterized in that: be formed with slurry base plate (2), slurry side wall (3) and slurry partition wall (4) in the below of water-stop curtain (1) by slip casting, described slurry side wall (3) is closely cementing with water-stop curtain (1), slurry base plate (2), slurry side wall (3) and slurry partition wall (4) are enclosed in substrate and form multiple U-shaped slip casting storehouse to lower recess, and in slurry base plate (2) top, secondary grouting is formed with slurry strengthening course (5).
2. high artesian according to claim 1 thick sand-pebble layer deep foundation ditch slip casting back cover structure, is characterized in that: slurry base plate (2), the slurry side wall (3) in described U-shaped slip casting storehouse are formed by mini-valve tube note dual slurry.
3. high artesian according to claim 1 thick sand-pebble layer deep foundation ditch slip casting back cover structure, is characterized in that: described U-shaped slip casting storehouse, slurry partition wall (4) and slurry strengthening course (5) note single liquid slurry by mini-valve tube and formed.
4. high artesian according to claim 1 thick sand-pebble layer deep foundation ditch slip casting back cover structure, is characterized in that: in each U-shaped slip casting storehouse, all arrange water-level observation hole and dewatering well.
CN201420737294.1U 2014-12-01 2014-12-01 High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure Active CN204252148U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420737294.1U CN204252148U (en) 2014-12-01 2014-12-01 High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420737294.1U CN204252148U (en) 2014-12-01 2014-12-01 High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure

Publications (1)

Publication Number Publication Date
CN204252148U true CN204252148U (en) 2015-04-08

Family

ID=52956473

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420737294.1U Active CN204252148U (en) 2014-12-01 2014-12-01 High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure

Country Status (1)

Country Link
CN (1) CN204252148U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404974A (en) * 2014-12-01 2015-03-11 中铁隆工程集团有限公司 High-pressure-bearing water and thick sand and pebble formation deep foundation pit grouting bottom-sealing structure and construction technology thereof
CN106498960A (en) * 2016-11-27 2017-03-15 黄明利 A kind of harness the river method of stifled row with reference to delamination pour slurry
CN106609508A (en) * 2015-10-22 2017-05-03 中铁十四局集团有限公司 Construction technology and construction method for large-particle-size pebble stratum super-deep foundation pit in strong water permeation environment of Yellow River flood plain

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404974A (en) * 2014-12-01 2015-03-11 中铁隆工程集团有限公司 High-pressure-bearing water and thick sand and pebble formation deep foundation pit grouting bottom-sealing structure and construction technology thereof
CN106609508A (en) * 2015-10-22 2017-05-03 中铁十四局集团有限公司 Construction technology and construction method for large-particle-size pebble stratum super-deep foundation pit in strong water permeation environment of Yellow River flood plain
CN106498960A (en) * 2016-11-27 2017-03-15 黄明利 A kind of harness the river method of stifled row with reference to delamination pour slurry

Similar Documents

Publication Publication Date Title
CN104404974B (en) The thick sand-pebble layer deep basal pit of high artesian slip casting back cover structure and construction technology thereof
CN105002913B (en) A kind of highly permeable stratum deep basal pit back cover water sealing structure and its construction method
CN102966108B (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
CN104099943B (en) Diaphram wall and discarded underground civil defense engineering intersection processing method
CN104612143A (en) Bored composite pile structure under karst cave/soil cave geological condition
CN107119691A (en) One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer and its excavation method
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN108086328A (en) A kind of dynamic sealing, assembled building enclosure and its construction method from recharge
CN207892653U (en) Decompression hydrophobic structure suitable for Weathering-residual soil layer fissure zone
CN108979659A (en) The ruggedized construction and method of structures are worn under weak soil rich water large cross-section tunnel group
CN103088836A (en) Sedimentation control method for pumping water and performing reinjection in well casing simultaneously
CN102162253A (en) Precipitation construction method employing pipe embedding in deep foundation pits
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN204252148U (en) High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN109594575A (en) A kind of open caisson periphery grouting and reinforcing soil body construction method
CN103343534A (en) Closed precipitation method for foundation pit construction
CN101319501B (en) Construction method of deep foundation ditch
CN208605199U (en) The ruggedized construction of structures is worn under a kind of weak soil rich water large cross-section tunnel group
CN205205844U (en) Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit
CN104831742B (en) The Method on Dewatering of Foundation Pit that adjacent two layers low pressure water layer is not cut off by water barrier
CN204825916U (en) Highly permeable stratum deep basal pit back cover stagnant water structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: ZHONGTIE TUNNEL SURVEY AND DESIGN INST., LTD.

Effective date: 20150826

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Liu Jianwei

Inventor after: Li Tiesheng

Inventor after: Shen Xiaobing

Inventor after: Fu Bo

Inventor after: Zhang Meiqin

Inventor after: Meng Wei

Inventor after: Li Minglei

Inventor after: Liu Jingtao

Inventor after: Liu Weihua

Inventor after: Tan Wanzhong

Inventor after: Jia Feiyu

Inventor after: Lu Zhiqiang

Inventor after: Gao Xiongying

Inventor after: Chen Qijiao

Inventor after: Pan Xiuming

Inventor after: Lei Chonghong

Inventor after: Lv Gaofeng

Inventor after: Zhang Jianhai

Inventor after: He Changjun

Inventor after: Cui Zhijie

Inventor after: Hao Zhihong

Inventor before: Liu Jianwei

Inventor before: Lu Zhiqiang

Inventor before: He Changjun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LIU JIANWEI LU ZHIQIANG HE ZHANGJUN TO: LIU JIANWEI LU ZHIQIANG PAN XIUMING LEI CHONGHONG LV GAOFENG ZHANG JIANHAI HE ZHANGJUN CUI ZHIJIE HAO ZHIHONG LI TIESHENG SHEN XIAOBING FU BO ZHANG MEIQIN MENG WEI LI MINGLEI LIU JINGTAO LIU WEIHUA TAN WANZHONG JIA FEIYU GAO XIONGYING CHEN QIJIAO

TR01 Transfer of patent right

Effective date of registration: 20150826

Address after: 610000 Sichuan city of Chengdu province Wuhou District two West Road No. 189 Vuko railway long 8 storey building

Patentee after: RANKEN RAILWAY CONSTRUCTION GROUP CO., LTD.

Patentee after: Zhongtie Tunnel Survey and Design Inst., Ltd.

Address before: 610000 Sichuan city of Chengdu province Wuhou District two West Road No. 189 Vuko railway long 8 storey building

Patentee before: RANKEN RAILWAY CONSTRUCTION GROUP CO., LTD.