CN106498960A - A kind of harness the river method of stifled row with reference to delamination pour slurry - Google Patents

A kind of harness the river method of stifled row with reference to delamination pour slurry Download PDF

Info

Publication number
CN106498960A
CN106498960A CN201611058417.9A CN201611058417A CN106498960A CN 106498960 A CN106498960 A CN 106498960A CN 201611058417 A CN201611058417 A CN 201611058417A CN 106498960 A CN106498960 A CN 106498960A
Authority
CN
China
Prior art keywords
slip casting
grouting
station
stifled
thickness
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611058417.9A
Other languages
Chinese (zh)
Inventor
黄明利
安声镛
潘政
肖祖通
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201611058417.9A priority Critical patent/CN106498960A/en
Publication of CN106498960A publication Critical patent/CN106498960A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material

Abstract

The present invention relates to a kind of stifled row comprises the steps with reference to the method for harnessing the river of delamination pour slurry:1) scope in station agent structure grouting and reinforcing area, is determined according to construction Preliminary design and on-site actual situations;2) thickness of station base plate and side wall grouting stabilization zone, is determined by Theoretical Calculation and engineering experience;3), before grouting and reinforcing is carried out, slip casting region division is carried out to the station bottom surface of rectangle according to construction way, and core wall is set;4), the arrangement drilled according to the slip casting region for dividing, and carry out slip casting;5), while slip casting, drainage well is arranged according to slip casting subregion on underground space base plate plane, draining is carried out simultaneously with grouting for water blocking;6) after the completion of, treating slip casting, by arranging multiple water-level observation points, the stifled effect for arranging method of harnessing the river with reference to subregion slip casting is judged with this.The present invention is processed to subsoil water using the theory of " row in blocking up outward " " subregion slip casting ", improves the efficiency of high water head tunneling Underground Space Excavation operation.

Description

A kind of harness the river method of stifled row with reference to delamination pour slurry
【Technical field】
The method the present invention relates to one kind is harnessed the river, and in particular to a kind of stifled row of high water head tunneling Underground Space Excavation combines and divides The method of harnessing the river of layer slip casting, belongs to Tunnel Engineering technical field.
【Background technology】
The anhydrous construction method of the tunneling underground space more ripe at present mainly has well-point dewatering method, the method that intercepts water, curtain+draining The three major types such as method.Well-point dewatering method process is simple, into well expense is low and pattern of well adjustment flexibly, but cone of depression during big drawdown Greatly, surrounding is affected;The method that intercepts water safe reliable, hold one's breath, displacement is little, effect on environment is little, but cost is high, construction speed Slowly;Curtain+drainage cloth hole flexibly, low cost, water percolating capacity little, but closure is poor, and pore-creating is more difficult.
In high water head tunneling Underground Space Excavation operation, generally existing is without implementing dewatering well position and rich water ovum gravel erratic boulder The stratum method of intercepting water performs the problems such as difficulty, cost are high, and conventional curtain water stop is difficult to carry out.
Therefore, it is to solve above-mentioned technical problem, it is necessory to provide a kind of stifled row's harnessing the river with reference to delamination pour slurry of innovation Method, to overcome the defect of the prior art.
【Content of the invention】
It is an object of the invention to provide a kind of stifled row of high water head tunneling Underground Space Excavation harnesses the river with reference to subregion slip casting Method, is processed to subsoil water using " row in blocking up outward ", the theory of " subregion slip casting ", so that existing tunneling underground is greatly improved The deficiency of the anhydrous construction method in space, improves the efficiency of high water head tunneling Underground Space Excavation operation.
For achieving the above object, the technical scheme taken of the present invention is:A kind of harness the river method of stifled row with reference to delamination pour slurry, Which comprises the technical steps that:
1) scope in station agent structure grouting and reinforcing area, is determined according to construction Preliminary design and on-site actual situations;
2) thickness of station base plate and side wall grouting stabilization zone, is determined by Theoretical Calculation and engineering experience;
3), before grouting and reinforcing is carried out, slip casting region division is carried out to the station bottom surface of rectangle according to construction way, and Core wall is set;
4), the arrangement drilled according to the slip casting region for dividing, and carry out slip casting;
5), while slip casting, a series of drainage well, row are arranged according to slip casting subregion on underground space base plate plane Water is carried out simultaneously with grouting for water blocking;
6) after the completion of, treating slip casting, by arranging multiple water-level observation points, to judge that stifled row harnesses the river with reference to subregion slip casting with this The effect of method.
The present invention stifled row with reference to the method for harnessing the river of delamination pour slurry be further:The step 2) in station base plate and side wall The thickness in grouting and reinforcing area is checked by impervious checking computations, Anti-floating design and base plate bending resistance, and it is next to combine live practical engineering experience Determine;Under the conditions of high water head, station side wall grouting stabilization zone top thickness be 2~3m, bottom be 3~4m, station base plate note The thickness of slurry stabilization zone is 5m or so, while the trapezoidal thickness in side wall grouting stabilization zone increases 1m per 5m.
The present invention stifled row with reference to the method for harnessing the river of delamination pour slurry be further:The step 3) in station bottom surface slip casting Region division is determined by section length during middle floor slab construction;According to engineering practical experience, typically by the station bottom surface of rectangle According to the grouting and reinforcing area that the 30m length deciles of are in strip;Meanwhile, core wall curtain, water proof are set between slip casting area The thickness of wall hanging curtain is generally 3m.
The present invention stifled row with reference to the method for harnessing the river of delamination pour slurry be further:The step 4) in arrange on the base plate of station Be vertical drilling, drill pitch of holes 800mm, trestle column 800mm, using Flos Mume arrange, below drilling depth to station base plate Distance for floor grouting stabilization zone thickness;Meanwhile, station side wall grouting drilling dilling angle and side wall formed 9 °, 18 °, 28 °, 36 ° of angle, drilling length are obtained by the thickness and dilling angle in station side wall grouting area.
The present invention stifled row with reference to the method for harnessing the river of delamination pour slurry be further:The step 5) in each slip casting subregion Four mouthfuls of drainage wells of interior general setting, in the bottom configuration Water pumping installation of drainage well, draining is carried out simultaneously with grouting for water blocking.
The present invention stifled row with reference to the method for harnessing the river of delamination pour slurry be also:The step 6) in water-level observation point position cloth Put after decile near bar shaped slip casting area minor face midpoint, each slip casting area arranges two.
Compared with prior art, the present invention has the advantages that:
(1) the determination method of station base plate and side wall grouting stabilization zone thickness, is given, slip casting can be effectively played and be added The waterproof action of Gu Qu, while the side wall grouting stabilization zone thickness for having gradient also saves injecting paste material.
(2), using subregion slip casting, the sealing mode of outer stifled interior row, work efficiency had both been greatly improved, had only been increased again Water effect and can implement in the tunneling underground space for cannot apply dewatering well, method workable.
(3), this method employ arrange water-level observation point mode, can real-time detection grouting consolidation effect, be follow-up The development of engineering provides guidance.
(4), the present invention carries out the engineering of Underground Space Excavation using subsurface excavation method in the case of being applied to high water head.Meanwhile, this Invention can overcome the shortcomings of the anhydrous construction method of the existing conventional tunneling underground space, using subregion slip casting, the side of outer stifled interior row Formula is processed to subsoil water, is a kind of good method for carrying out the anhydrous construction of the rich water ovum gravel erratic boulder stratum underground space.
【Description of the drawings】
Fig. 1 is that subway station base plate and side wall grouting stabilization zone arrange schematic diagram.
Fig. 2 is subway station subregion slip casting plane graph.
Icon explanation
1. the underground space;2. dewatering well;3. abutment wall;4. underground space side wall grouting stabilization zone;5. underground space base plate is noted Slurry stabilization zone;6. waterline;7. water-bearing layer;8. core wall.
【Specific embodiment】
Below in conjunction with the accompanying drawings 1,2 and specific embodiment the invention will be further described.
The present invention relates to a kind of stifled row of high water head tunneling Underground Space Excavation harnesses the river method with reference to subregion slip casting, main control The content of project processed and construction procedure is as follows:
Step one, according to the model that construction Preliminary design and on-site actual situations determine station agent structure grouting and reinforcing area Enclose.
In this step, the size in grouting and reinforcing area is substantially determined according to construction Preliminary design drawing.Both car had been passed through Base areas of standing determine the scope of floor grouting stabilization zone, the scope for determining station side wall grouting stabilization zone by height of water level.
Step 2, the thickness that station base plate and side wall grouting stabilization zone are determined by Theoretical Calculation and engineering experience.
In this step, checked, and combine live practical engineering experience to come according to impervious design, Anti-floating design and base plate bending resistance Determine the thickness in grouting and reinforcing area.
In this step, impervious design can the variant of Darcy's law as the following formula carry out:
In formula:L is seepage flow approach, and generally seepage flow approach is identical with the thickness of grouting and reinforcing body;
Q is the average water percolating capacity empirical value of every square metre of area of stratum deep basal pit, takes maximum after grouting and reinforcing;
Δ h is head difference, typically takes the above height of water level h of base plate.
In this step, Anti-floating design can be carried out as the following formula:
γ H=k γwh
In formula:Thickness of the H for excavation of foundation pit grouting behind shaft or drift lining body;
γ is injecting cement paste severe, generally takes 2.3;
γ w are the severe of water, take 1.0;
It is higher than injecting cement paste bottom plate heights that h is water level, generally presses the above height of water level of base plate plus slip casting body thickness Calculate.
Finally give:Under the conditions of high water head, station side wall grouting stabilization zone top thickness be 2~3m, bottom be 3~ 4m, the thickness of station floor grouting stabilization zone is 5m or so, while the trapezoidal thickness in side wall grouting stabilization zone increases 1m per 5m.Ground The thickness range of ferrum station base plate and side wall grouting stabilization zone is as shown in Figure 1.
Step 3, before grouting and reinforcing is carried out, carries out slip casting region according to construction way and draws to the station bottom surface of rectangle Point, and core wall is set.
In this step, the slip casting region division of station bottom surface is mainly determined by section length during middle floor slab construction.Root According to engineering practical experience, typically by the station bottom surface of rectangle according to 30m mono- the grouting and reinforcing area that is in strip of length decile.With When, core wall curtain is set between slip casting area, the thickness of core wall curtain is generally 3m.Subway station subregion slip casting plane graph As shown in Figure 2.
Step 4, the arrangement drilled according to the slip casting region for dividing simultaneously carry out slip casting.
In this step, on the base plate of station, arrangement is vertical drilling, and drill pitch of holes 800mm, and trestle column 800mm is adopted Blossom type arranges that the distance below drilling depth to station base plate is the thickness of floor grouting stabilization zone.Meanwhile, station side wall is noted Slurry drilling dilling angle and side wall formed 9 °, 18 °, 28 °, 36 ° of angle, creep into length by station side wall grouting area thickness and Dilling angle is obtained.
Step 5, while slip casting, arranges a series of drainage according to slip casting subregion on underground space base plate plane Well, draining are carried out simultaneously with grouting for water blocking.
In this step, four mouthfuls of drainage wells are typically set, draining in the bottom configuration of drainage well in each slip casting subregion Pump, draining are carried out simultaneously with grouting for water blocking.The deployment scenarios of drainage well are as shown in Figure 2.
With this, step 6, after the completion for the treatment of slip casting, by arranging multiple water-level observation points, to judge that stifled row combines subregion slip casting The effect of method of harnessing the river.
In this step, the location arrangements of water-level observation point after decile near bar shaped slip casting area minor face midpoint, ordinary circumstance Under, each slip casting area arranges two.
Above specific embodiment is only the preferred embodiment of this creation, not in order to limit this creation, all in this wound Any modification, equivalent substitution and improvements for being done etc. within the spirit of work and principle, should be included in this creation protection domain it Interior.

Claims (6)

1. harness the river method of a kind of stifled row with reference to delamination pour slurry, it is characterised in that:Comprise the technical steps that:
1) scope in station agent structure grouting and reinforcing area, is determined according to construction Preliminary design and on-site actual situations;
2) thickness of station base plate and side wall grouting stabilization zone, is determined by Theoretical Calculation and engineering experience;
3), before grouting and reinforcing is carried out, slip casting region division is carried out to the station bottom surface of rectangle according to construction way, and is arranged Core wall;
4), the arrangement drilled according to the slip casting region for dividing, and carry out slip casting;
5), while slip casting, a series of drainage well is arranged according to slip casting subregion on underground space base plate plane, draining with Grouting for water blocking is carried out simultaneously;
6) after the completion of, treating slip casting, by arranging multiple water-level observation points, to judge that stifled row harnesses the river method with reference to subregion slip casting with this Effect.
2. harness the river method of the row as claimed in claim 1 stifled with reference to delamination pour slurry, it is characterised in that:The step 2) in station The thickness of base plate and side wall grouting stabilization zone is checked by impervious checking computations, Anti-floating design and base plate bending resistance, and it is actual to combine scene Engineering experience is determining;Under the conditions of high water head, station side wall grouting stabilization zone top thickness is 2~3m, and bottom is 3~4m, The thickness of station floor grouting stabilization zone is 5m or so, while the trapezoidal thickness in side wall grouting stabilization zone increases 1m per 5m.
3. harness the river method of the row as claimed in claim 1 stifled with reference to delamination pour slurry, it is characterised in that:The step 3) in station The slip casting region division of bottom surface is determined by section length during middle floor slab construction;According to engineering practical experience, typically by rectangle Station bottom surface according to 30m mono- the grouting and reinforcing area that is in strip of length decile;Meanwhile, core wall is set between slip casting area Curtain, the thickness of core wall curtain are generally 3m.
4. harness the river method of the row as claimed in claim 1 stifled with reference to delamination pour slurry, it is characterised in that:The step 4) in station On base plate, arrangement is vertical drilling, and drill pitch of holes 800mm, using Flos Mume, trestle column 800mm arranges that drilling depth is to car Thickness of the distance that stands below base plate for floor grouting stabilization zone;Meanwhile, station side wall grouting drilling dilling angle and side wall shape Into 9 °, 18 °, 28 °, 36 ° of angle, drilling length is obtained by the thickness and dilling angle in station side wall grouting area.
5. harness the river method of the row as claimed in claim 1 stifled with reference to delamination pour slurry, it is characterised in that:The step 5) in each Four mouthfuls of drainage wells are typically set in individual slip casting subregion, in the bottom configuration Water pumping installation of drainage well, draining and grouting for water blocking Carry out simultaneously.
6. harness the river method of the row as claimed in claim 1 stifled with reference to delamination pour slurry, it is characterised in that:The step 6) in water level After decile near bar shaped slip casting area minor face midpoint, each slip casting area arranges two to the location arrangements of observation station.
CN201611058417.9A 2016-11-27 2016-11-27 A kind of harness the river method of stifled row with reference to delamination pour slurry Pending CN106498960A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611058417.9A CN106498960A (en) 2016-11-27 2016-11-27 A kind of harness the river method of stifled row with reference to delamination pour slurry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611058417.9A CN106498960A (en) 2016-11-27 2016-11-27 A kind of harness the river method of stifled row with reference to delamination pour slurry

Publications (1)

Publication Number Publication Date
CN106498960A true CN106498960A (en) 2017-03-15

Family

ID=58328545

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611058417.9A Pending CN106498960A (en) 2016-11-27 2016-11-27 A kind of harness the river method of stifled row with reference to delamination pour slurry

Country Status (1)

Country Link
CN (1) CN106498960A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021248424A1 (en) * 2020-06-09 2021-12-16 广西路桥工程集团有限公司 Induced grouting method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020291A (en) * 1999-07-12 2001-01-23 Ohbayashi Corp Groundwater draining method
CN204252148U (en) * 2014-12-01 2015-04-08 中铁隆工程集团有限公司 High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020291A (en) * 1999-07-12 2001-01-23 Ohbayashi Corp Groundwater draining method
CN204252148U (en) * 2014-12-01 2015-04-08 中铁隆工程集团有限公司 High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021248424A1 (en) * 2020-06-09 2021-12-16 广西路桥工程集团有限公司 Induced grouting method

Similar Documents

Publication Publication Date Title
CN110242301B (en) Two-step grouting modification water-retention coal mining method for roof aquifer
CN101781889B (en) H-shaped waterproof curtain construction process
CN204023501U (en) A kind of reinforcement Anti-seeping technology structure for earth and rockfill dam
CN105464056B (en) A kind of leakage preventing structure for adapting to Earth-rockfill Dam Settlements
CN108842840A (en) Perforating causes the weak intercalated layer slip-casting lifting method of building settlement under a kind of compensation subway tunnel
CN103821538B (en) J-type horizontal assistant branched hole surface advance grouting paste-making method
CN102493822A (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN105201001B (en) Composite seepage preventing structure for large karst cave in karst region and construction method thereof
CN109083682A (en) A kind of construction method of mine working antiseepage high intensity fire dam
CN106522989A (en) Air shaft structure and shield excavation parallel construction method
CN102926392A (en) Foundation pit dewatering system and construction method thereof
CN205260041U (en) Method of freezing supporting construction is spouted soon to level
CN211081894U (en) Water-rich stratum tunnel is precipitation structure in coordination
CN206448286U (en) It is a kind of to be used to reduce the radial system of grey field dam seepage line
CN204825923U (en) Relay formula underground structure
CN107060821A (en) A kind of many lithology method for protecting support of face
CN103243721B (en) Highrise Building With Raft Foundation and Core Walls Structure excavation construction method under Unfavorable geology condition
CN206204967U (en) A kind of double perfusion pile cofferdam
CN208152063U (en) A kind of superelevation infiltration coefficient sand ovum stratum Groundwater Control system
CN106498960A (en) A kind of harness the river method of stifled row with reference to delamination pour slurry
CN103866779B (en) A kind of construction method of sealing space enclosing structure of soft foundation building foundation pit
CN102787608A (en) Gravity type foundation pit supporting system under vacuum effect and construction method
CN203320576U (en) Waterproof and drainage system for basement external wall of super high-rise buildings
CN105350544A (en) Waterproof curtain used for stone-contained area and construction method thereof
CN206220104U (en) A kind of Frozen Soil Cylinder Foundation Supported with Composite Soil Nailing system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170315

WD01 Invention patent application deemed withdrawn after publication