CN106522989A - Air shaft structure and shield excavation parallel construction method - Google Patents

Air shaft structure and shield excavation parallel construction method Download PDF

Info

Publication number
CN106522989A
CN106522989A CN201610822445.7A CN201610822445A CN106522989A CN 106522989 A CN106522989 A CN 106522989A CN 201610822445 A CN201610822445 A CN 201610822445A CN 106522989 A CN106522989 A CN 106522989A
Authority
CN
China
Prior art keywords
ventilating shaft
shield
foundation ditch
construction
parallel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610822445.7A
Other languages
Chinese (zh)
Other versions
CN106522989B (en
Inventor
陈春雷
马超
杨钊
许超
冯朋
杨擎
陈培帅
余村
何源
周鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201610822445.7A priority Critical patent/CN106522989B/en
Publication of CN106522989A publication Critical patent/CN106522989A/en
Application granted granted Critical
Publication of CN106522989B publication Critical patent/CN106522989B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses an air shaft structure and shield excavation parallel construction method. According to the method, the majority of an envelope enclosure of an air shaft is constructed firstly, and then continuous construction station-crossing of an air shaft main structure is completed successively through tunnel excavation, so that the technical problem that the intermediate air shaft and shield tunnel parallel construction cannot be conducted, and a construction period lagged effect is caused is solved.

Description

The method of ventilating shaft structure and shield driving parallel construction
Technical field
The present invention relates to shield-tunneling construction field.It is more particularly related to a kind of ventilating shaft structure and shield driving are flat The method of row construction.
Background technology
As urban rail transit in China construction is developed rapidly, shield method becomes the main engineering method of constructing metro tunnel.Shield Generally require to arrange ventilating shaft in tunnel piercing interval, cause to generally require during Shield Construction Method Used by middle ventilating shaft.Shield is normal It is " tunnel after first standing " that rule pass through middle ventilating shaft method, and the method is to apply portal after the completion of ventilating shaft main structure construction and held Head receive after reinforcing shield machine and it is secondary in middle ventilating shaft originate, or shield pick is completed in advance using " after first tunnel stand " engineering method Middle ventilating shaft is applied after entering construction.Conventional method requires that middle ventilating shaft is laid guide rail after completing to receive portal and termination reinforcing and dug Except portal is secondary originate after can just proceed shield-tunneling construction, the shield driving duration may be affected;" standing after first tunnel " method can have The effect reduction of erection time, but in rich water sandy gravel stratum after apply middle ventilating shaft and there is larger seepage and risk of gushing, need to take it is complicated plus Gu and stability when ventilating shaft agent structure is applied is applied after dewatering measure ensures.
The content of the invention
It is an object of the invention to solve at least the above, and provide the advantage that at least will be described later.
It is a still further object of the present invention to provide a kind of shield machine passes through wind of constructing in advance under internal and external pressure balance state Well building enclosure, the method for reaching ventilating shaft structure and shield driving parallel construction.
In order to realize these purposes of the invention and further advantage, there is provided a kind of ventilating shaft structure and shield driving are flat The method of row construction, comprises the following steps:
S1, ventilating shaft foundation ditch are supported to substrate when digging, and side wall of constructing is located at orlop and supports following part and base plate, The height that boundary zone embedded backfill material are supported to orlop is laid on side wall;
S2, the template for removing plate during orlop is supported and laid in ventilating shaft foundation ditch according to shield tunnel design, bury back The template of filler to the middle plate simultaneously lays boundary zone on backfill material;
S3, the bottom-up remainder for pouring side wall in ventilating shaft foundation ditch successively, support and middle plate, in ventilating shaft foundation ditch Recharge water, it is ensured that Water And Earth Pressures balance inside and outside ventilating shaft foundation ditch;And
S4, shield machine extract the recharge water in foundation ditch by material driving assembled shield duct piece is backfilled after passing through ventilating shaft foundation ditch, Backfill material and shield duct piece is removed, portal and ventilating shaft remaining structure is finally applied.
Preferably, step S1 is further comprising the steps of:
Digging to substrate, two row's central posts are set in the middle part of ventilating shaft foundation ditch, the external boundary of central post described in any side and With the digging that the spacing of the inner boundary of the side wall of its homonymy meets shield machine by space, arrange U-shaped outside the ventilating shaft foundation ditch Ground-connecting-wall and dewatering well;
Wherein, the boundary zone is asphalt felt.
Preferably, the backfill material is included positioned at the M5 mortars of two rows neutrality intercolumniation and positioned at any side central post External boundary and with the plastic concrete between the inner boundary of the side wall of its homonymy.
Preferably, in step S4, when tunneling apart from 2 rings in outer 5 rings of U-shaped ground-connecting-wall and ventilating shaft foundation ditch, increase is synchronous The activity coefficient of slip casting, simultaneous grouting slurry mix micro-expanding agent;Apart from 2 rings in outer 4 rings of the U-shaped ground-connecting-wall of ventilating shaft and ventilating shaft per ring Secondary grouting is carried out all, grouting sequence is to carry out slip casting from bottom to up, from right to left;Cement mortar and water glass is injected during secondary grouting The double oar liquid of glass liquid.
Preferably, the section of jurisdiction of the close portal position of ventilating shaft foundation ditch is supplemented after in step S4, shield machine is passed through Grouting and reinforcing.
Preferably, the construction of recharge water in ventilating shaft is extracted in step S4 for operating stage by stage, is monitored and is recorded foundation ditch Recharge water level in inside and outside land movement situation control ventilating shaft, cuts backfill material simultaneously really from ventilating shaft agent structure two ends after the completion of drawing water In guarantor tunnel, water leakage situation is controllable, carries out supplementing slip casting if uncontrollable.
Preferably, before step S4 shield duct piece in the ventilating shaft foundation ditch the small-sized disintegrating machine in reservation tear down section of jurisdiction lifting space, Disintegrating machine is transported in tunnel after removing at least two endless tube pieces and completes the broken of remaining section of jurisdiction and hang out.
The present invention at least includes following beneficial effect:
1st, with sand and together with laying, asphalt felt is as boundary zone and rationally sets with side wall backfill plastotype concrete for ventilating shaft base plate Put shield driving circuit, solve " after first tunnel stand " method need to adjust shield machine continuously tunnel circuit and get around central post technology it is difficult Topic, the bottom steel for reducing side wall angle are supportted;Need not set up when setting up plate during one asphalt felt is isolated and constructed after the completion of backfill Scaffold and laying bottom template.It is determined that suitably returning filling mixture ratio parameter, middle ventilating shaft of constructing afterwards can quickly cut and complete Subsequent construction, realizes the whole machine of shield quickly through the parallel construction with middle ventilating shaft agent structure.
2nd, using various slip casting measures and grouting sequence reasonable in design, slip casting position and slurry material proportioning, mix swollen Change machine strengthens slurry dilatancy effect and rapid hardening, and after solving " standing after first tunnel " method, in the middle of construction, ventilating shaft portal is prevented with tunnel shaft interface Water problems, realizes middle ventilating shaft residue main body construction and shield driving parallel operations.
3rd, hang out after section of jurisdiction being removed with small-sized disintegrating machine and apply again portal, change traditional shield machine and shut down wait paving Arrange in rail, ventilating shaft steel jacket box, originate the series of measures such as support receive and it is secondary originate the situation missed the stop, effectively shorten shield Driving the duration, simplified and originated and has received portal external end head plain concrete wall and three axes agitating pile reinforcement process, saving engineering into This.
In a word, missed the stop the method with middle ventilating shaft parallel construction using shield driving of the present invention, solve centre The delayed technical barrier that shield acceptable conditionses cannot be provided on time of ventilating shaft construction speed, invented shield miss the stop it is flat with middle ventilating shaft The new technology of row construction, optimizes portal termination reinforcement measure in ventilating shaft of knowing clearly, and realizes shield and misses the stop and originate without the need for secondary, letter Construction technology is changed, has reduced construction cost and effectively shorten the duration, filled up the direct digging of shield machine and missed the stop and ventilating shaft The technological gap of agent structure parallel construction, with good economic benefit and social benefit, this method is particularly well-suited to tunnel When the larger termination consolidation effect of buried depth is difficult to ensure that, shield is by middle ventilating shaft excavation work.
Part is embodied by the further advantage of the present invention, target and feature by description below, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Description of the drawings
Fig. 1 is that shield of the present invention continuously tunnels the process flow frame by middle ventilating shaft and ventilating shaft parallelism structural construction method Frame.
Fig. 2 is that shield continuously tunnels the generalized section missed the stop with ventilating shaft main structure body parallel construction.
Fig. 3 is the plane graph of Fig. 2.
Specific embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings, to make those skilled in the art with reference to description text Word can be implemented according to this.
It should be noted that experimental technique described in following embodiments, if no special instructions, is conventional method, institute Reagent and material is stated, if no special instructions, is commercially obtained;In describing the invention, term " horizontal ", " vertical To ", " on ", D score, "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", the instruction such as " outward " side Position or position relationship are, based on orientation shown in the drawings or position relationship, to be for only for ease of the description present invention and simplify description, Be not indicate or imply the device or element of indication must have specific orientation, with specific azimuth configuration and operation, because This is not considered as limiting the invention.
As shown in figure 1, a kind of method that the present invention provides ventilating shaft structure and shield driving parallel construction, including following step Suddenly:
S1, ventilating shaft foundation ditch are supported to substrate when digging, and side wall of constructing is located at orlop and supports following part and base plate, The height that boundary zone embedded backfill material are supported to orlop is laid on side wall;
S2, the template for removing plate during orlop is supported and laid in ventilating shaft foundation ditch according to shield tunnel design, bury back The template of filler to the middle plate simultaneously lays boundary zone on backfill material;
S3, the bottom-up remainder for pouring side wall in ventilating shaft foundation ditch successively, support and middle plate, in ventilating shaft foundation ditch Recharge water, it is ensured that Water And Earth Pressures balance inside and outside ventilating shaft foundation ditch;And
S4, shield machine extract the recharge water in foundation ditch by material driving assembled shield duct piece is backfilled after passing through ventilating shaft foundation ditch, Backfill material and shield duct piece is removed, portal and ventilating shaft remaining structure is finally applied.This method one can be solve the duration it is delayed, Two can be to avoid once originating the risk for once receiving.
Step S1 is further comprising the steps of:
Digging to substrate, two row's central posts are set in the middle part of ventilating shaft foundation ditch, the external boundary of central post described in any side and With the digging that the spacing of the inner boundary of the side wall of its homonymy meets shield machine by space, arrange U-shaped outside the ventilating shaft foundation ditch Ground-connecting-wall and dewatering well;
Wherein, the boundary zone is asphalt felt.
The backfill material includes the M5 mortars and the external boundary positioned at any side central post positioned at two rows neutrality intercolumniation And with the plastic concrete between the inner boundary of the side wall of its homonymy.
Increase filling out for synchronous grouting when tunneling apart from 2 rings in outer 5 rings of U-shaped ground-connecting-wall and ventilating shaft foundation ditch in step S4 Coefficient is filled, simultaneous grouting slurry mixes micro-expanding agent;Two are carried out apart from 2 rings in outer 4 rings of the U-shaped ground-connecting-wall of ventilating shaft and ventilating shaft all per ring Secondary slip casting, grouting sequence are to carry out slip casting from bottom to up, from right to left;Cement mortar and waterglass liquid double oars is injected during secondary grouting Liquid.
The section of jurisdiction of the close portal position of ventilating shaft foundation ditch is carried out supplementing slip casting after shield machine is passed through in step S4 and added Gu.
The construction of recharge water in ventilating shaft is extracted in step S4 for operating stage by stage, monitors and record the soil body inside and outside foundation ditch Recharge water level in misalignment control ventilating shaft, cuts backfill from ventilating shaft agent structure two ends after the completion of drawing water and expects and guarantee in tunnel Water leakage situation is controllable, carries out supplementing slip casting if uncontrollable.
Before step S4 shield duct piece in the ventilating shaft foundation ditch the small-sized disintegrating machine in reservation tear down section of jurisdiction lifting space, remove at least Disintegrating machine is transported in tunnel after two endless tube pieces and completes the broken of remaining section of jurisdiction and hang out.
The present invention provides the construction embodiment of a kind of ventilating shaft structure and shield driving parallel construction, as Figure 2-3, construction reason Read, and realize the ventilating shaft building enclosure of the theory and antiseepage and draining safeguard and driving outside middle standing pillar design, termination Process grout injection control measure.
Step S1, ventilating shaft building enclosure and neutral post design
S1.1, for need between 5 inner boundary of ventilating shaft building enclosure side wall and 13 external boundary of central post ensure shield continuously dig Enter the space by middle ventilating shaft;
S1.2, neutral post design need to both can guarantee that ventilating shaft agent structure stability and rigidity requirement, can meet shield pick again The radius of turn and the actual cornering ability of shield machine for entering fine adjustment of attitude requirement and tunnel centrage 16 is required.
Step S2, the construction flow process of ventilating shaft building enclosure and backfill
S2.1, excavation of foundation pit are constructed to the absolute altitude of bottom surface uplift pile 1 and base plate 3 under base plate, and the maintenance of base plate 3 is constructed side simultaneously Wall waterproof and last one concrete support 8;
S2.2, the template for installing side wall 5, side wall 5 lay one layer of asphalt felt 4,13 Cast-in-situ Piles in Sand-filling of central post after the completion of constructing Material 2, remaining position backfill plastic concrete 7;
S2.3, the template for removing plate 10 during last one concrete eight support is laid simultaneously;
The template of S2.4, backfill plastic concrete and sand material to middle plate 10, lays asphalt felt;
S2.5, successively bottom-up line production, set up full hall scaffold and are sequentially completed the remainder of side wall, concrete Support the pouring construction with middle plate;
S2.6, facing down from original place is excavated to base plate position, 5 outer 2m of side wall construction 600mm thickness plain concretes wall 15 with Building enclosure ground-connecting-wall 6 forms overlap joint and respectively arranges 2 mouthfuls of dewatering wells 14 in double track tunnel both sides, two ends totally 8 mouthfuls of dewatering wells.
Step S3, shield machine pass through front recharge water
S3.1, according to shield machine under edpth of tunnel Theoretical Calculation Water And Earth Pressures collective effect directly driving passes through when outside press Power scope, arranges recharge water water level;
S3.2, to recharge water in ventilating shaft 12, and monitor soil body lateral displacement and fluctuation in stage change inside and outside foundation ditch;
Horizontal grouting pipe and vertical Grouting Pipe are set in S3.3, ground-connecting-wall, and Grouting Pipe interval 2m, when shield duct piece 9 and side Occur during seepage, to inject the closure of polyurethane serosity between wall 5.
Ventilating shaft is passed through in step S4, shield digging
The full weight of simultaneous grouting slurry when S4.1, shield machine are passed through, need to be ensured, apart from outer 5 rings of ventilating shaft ground-connecting-wall and Increase the activity coefficient of synchronous grouting when 2 rings are tunneled in ventilating shaft, simultaneous grouting slurry mixes micro-expanding agent;
S4.2, secondary grouting is all carried out apart from 2 rings in outer 4 rings of ventilating shaft ground-connecting-wall and ventilating shaft per ring, grouting sequence is under It is supreme, carry out slip casting from right to left;
Synchronous grouting layer is punched using drill rod when S4.3, slip casting, the standard that Stress control slip casting terminates is 3MPa;
Check over 2m before S4.4, shield machine digging ventilating shaft ground-connecting-wall and change cutter, it is ensured that cutterhead digging power and open Digging face diameter, it is to avoid ventilating shaft ground-connecting-wall occur and block shield machine situation;
Ensure when S4.4, shield segment assembling that at least two ring seal jacking blocks are located at the shield tunnel first half, are easy to later stage section of jurisdiction Remove;
S4.5, shield digging each on two endless tube pieces in the outer Fourth Ring of ventilating shaft, ventilating shaft need to increase 2 injected holes newly after passing through ventilating shaft Carry out supplementing slip casting, injection participates in the polyurethane of bulking machine, and grouting sequence is for from bottom to up.Drill rod punches synchronous grouting layer, note Slurry termination criteria is have polyurethane to flow out or water-tight after adjacent holes are opened;
S4.6, cut section of jurisdiction before, open ventilating shaft ground-connecting-wall and shield tunnel intersection section of jurisdiction injected hole, without leak or leak Amount is gradually decreased, and can carry out next step.If still there is water seepage, polyurethane leak stopping is injected by ground-connecting-wall built-in slip casting pipe.
Step S5, dismounting section of jurisdiction apply portal
Small-sized disintegrating machine is transported to middle plate and cuts readjustment material, wherein by S5.1, stage by stage pump drainage recharge water:Tunnel top and Sidepiece mortar is together abolished depending mainly on section of jurisdiction, and the remaining mortar being bonded together with agent structure is by the way of manually abolishing Cut;
After the completion of S5.2, backfill material cut, disintegrating machine is transported to into tunnel after at least 2 endless tube pieces being removed by the BOB(beginning of block) that binds In, complete remaining section of jurisdiction and cut
S5.3, construction tunnel portal, complete ventilating shaft remainder structure construction.
The industrial applicibility of the present invention:
1st, with sand and together with laying, asphalt felt is as boundary zone and rationally sets with side wall backfill plastotype concrete for ventilating shaft base plate Put shield driving circuit, solve " after first tunnel stand " method need to adjust shield machine continuously tunnel circuit and get around central post technology it is difficult Topic, the bottom steel for reducing side wall angle are supportted;Need not set up when setting up plate during one asphalt felt is isolated and constructed after the completion of backfill Scaffold and laying bottom template.It is determined that suitably returning filling mixture ratio parameter, middle ventilating shaft of constructing afterwards can quickly cut and complete Subsequent construction, realizes the whole machine of shield quickly through the parallel construction with middle ventilating shaft agent structure.
2nd, using various slip casting measures and grouting sequence reasonable in design, slip casting position and slurry material proportioning, mix swollen Change machine strengthens slurry dilatancy effect and rapid hardening, and after solving " standing after first tunnel " method, in the middle of construction, ventilating shaft portal is prevented with tunnel shaft interface Water problems, realizes middle ventilating shaft residue main body construction and shield driving parallel operations.
3rd, hang out after section of jurisdiction being removed with small-sized disintegrating machine and apply again portal, change traditional shield machine and shut down wait paving Arrange in rail, ventilating shaft steel jacket box, originate the series of measures such as support receive and it is secondary originate the situation missed the stop, effectively shorten shield Driving the duration, simplified and originated and has received portal external end head plain concrete wall and three axes agitating pile reinforcement process, saving engineering into This.
In a word, missed the stop the method with middle ventilating shaft parallel construction using shield driving of the present invention, solve centre The delayed technical barrier that shield acceptable conditionses cannot be provided on time of ventilating shaft construction speed, invented shield miss the stop it is flat with middle ventilating shaft The new technology of row construction, optimizes portal termination reinforcement measure in ventilating shaft of knowing clearly, and realizes shield and misses the stop and originate without the need for secondary, letter Construction technology is changed, has reduced construction cost and effectively shorten the duration, filled up the direct digging of shield machine and missed the stop and ventilating shaft The technological gap of agent structure parallel construction, with good economic benefit and social benefit, this method is particularly well-suited to tunnel When the larger termination consolidation effect of buried depth is difficult to ensure that, shield is by middle ventilating shaft excavation work.
Although embodiment of the present invention is disclosed as above, which is not restricted to listed by description and embodiment With, it can be applied to various suitable the field of the invention completely, for those skilled in the art, can be easily Other modification is realized, therefore under the general concept limited without departing substantially from claim and equivalency range, the present invention is not limited In specific details and shown here as the legend with description.

Claims (7)

1. a kind of method of ventilating shaft structure and shield driving parallel construction, it is characterised in that comprise the following steps:
S1, ventilating shaft foundation ditch are supported to substrate when digging, and side wall of constructing is located at orlop and supports following part and base plate, in side The height that boundary zone embedded backfill material are supported to orlop is laid on wall;
S2, the template for removing plate during orlop is supported and laid in ventilating shaft foundation ditch according to shield tunnel design, bury backfill material To the middle plate template and backfill material on lay boundary zone;
S3, the bottom-up remainder for pouring side wall in ventilating shaft foundation ditch successively, support and middle plate, the recharge in ventilating shaft foundation ditch Water, it is ensured that Water And Earth Pressures balance inside and outside ventilating shaft foundation ditch;And
S4, shield machine are extracted the recharge water in foundation ditch, are removed by material driving assembled shield duct piece is backfilled after passing through ventilating shaft foundation ditch Backfill material and shield duct piece, finally apply portal and ventilating shaft remaining structure.
2. the method for ventilating shaft structure as claimed in claim 1 and shield driving parallel construction, it is characterised in that step S1 It is further comprising the steps of:
Digging to substrate, two row's central posts are set in the middle part of ventilating shaft foundation ditch, the external boundary of central post described in any side and and its The spacing of the inner boundary of the side wall of homonymy meets the digging of shield machine by space, is arranged U-shapedly even outside the ventilating shaft foundation ditch Wall and dewatering well;
Wherein, the boundary zone is asphalt felt.
3. the method for ventilating shaft structure as claimed in claim 2 and shield driving parallel construction, it is characterised in that the backfill material Including positioned at two rows neutrality the M5 mortars of intercolumniation and the external boundary positioned at any side central post and with the side wall of its homonymy Plastic concrete between inner boundary.
4. the method for ventilating shaft structure as claimed in claim 2 and shield driving parallel construction, it is characterised in that step S4 In increase the activity coefficient of synchronous grouting, synchronous grouting slurry when tunneling apart from 2 rings in outer 5 rings of U-shaped ground-connecting-wall and ventilating shaft foundation ditch Liquid mixes micro-expanding agent;Secondary grouting is carried out apart from 2 rings in outer 4 rings of the U-shaped ground-connecting-wall of ventilating shaft and ventilating shaft all per ring, grouting sequence is From bottom to up, slip casting is carried out from right to left;Cement mortar and waterglass liquid double oar liquid is injected during secondary grouting.
5. the method for ventilating shaft structure as claimed in claim 1 and shield driving parallel construction, it is characterised in that step S4 Middle shield machine carries out supplementing grouting and reinforcing to the section of jurisdiction of the close portal position of ventilating shaft foundation ditch after passing through.
6. the method for ventilating shaft structure as claimed in claim 4 and shield driving parallel construction, it is characterised in that step S4 In extract the construction of recharge water in ventilating shaft for operating stage by stage, monitor and record inside and outside foundation ditch in land movement situation control ventilating shaft Recharge water level, cuts backfill from ventilating shaft agent structure two ends after the completion of drawing water and expects and guarantee that water leakage situation is controllable in tunnel, if not It is controllable, carry out supplementing slip casting.
7. the method for ventilating shaft structure as claimed in claim 1 and shield driving parallel construction, it is characterised in that step S4 shield Before section of jurisdiction in the ventilating shaft foundation ditch the small-sized disintegrating machine in reservation tear down section of jurisdiction lifting space, remove disintegrating machine after at least two endless tube pieces The broken of remaining section of jurisdiction is completed in being transported to tunnel and is hung out.
CN201610822445.7A 2016-09-14 2016-09-14 The method of ventilating shaft structure and shield driving parallel construction Active CN106522989B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610822445.7A CN106522989B (en) 2016-09-14 2016-09-14 The method of ventilating shaft structure and shield driving parallel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610822445.7A CN106522989B (en) 2016-09-14 2016-09-14 The method of ventilating shaft structure and shield driving parallel construction

Publications (2)

Publication Number Publication Date
CN106522989A true CN106522989A (en) 2017-03-22
CN106522989B CN106522989B (en) 2018-12-04

Family

ID=58343926

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610822445.7A Active CN106522989B (en) 2016-09-14 2016-09-14 The method of ventilating shaft structure and shield driving parallel construction

Country Status (1)

Country Link
CN (1) CN106522989B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107514262A (en) * 2017-08-02 2017-12-26 中国建筑第八工程局有限公司 The construction method of shield piping lane
CN107664035A (en) * 2017-10-20 2018-02-06 中国建筑第八工程局有限公司 The construction method of well after shield piping lane elder generation shield
CN108868814A (en) * 2018-08-24 2018-11-23 中铁西安勘察设计研究院有限责任公司 Collapsible loess combination land pebble stratum tunneling air duct connects the ventilating shaft of shield tunnel
CN109162741A (en) * 2018-10-29 2019-01-08 中铁十二局集团有限公司 The method in shield crossing piston air duct and piston air duct superstructure synchronous construction
CN109577999A (en) * 2018-12-27 2019-04-05 中铁十局集团城市轨道工程有限公司 Side-proof wall deformation and shield machine plant the excessively intermediate ventilating shaft ruggedized construction of shield machine and construction method of head
CN109577998A (en) * 2018-12-04 2019-04-05 中铁十二局集团有限公司 A kind of construction method that the backfill of shield section piston air duct is missed the stop
CN109695456A (en) * 2019-01-22 2019-04-30 济南轨道交通集团有限公司 A kind of rail traffic and pipe gallery build structure and its construction method jointly
CN110541722A (en) * 2019-09-30 2019-12-06 中铁第四勘察设计院集团有限公司 Partial shield tunnel segment dismantling method and water stop structure in middle air shaft
CN110685709A (en) * 2019-10-30 2020-01-14 长江勘测规划设计研究有限责任公司 Construction method and structure of connection channel of superposed tunnel
CN112727466A (en) * 2021-01-29 2021-04-30 绍兴市柯桥区轨道交通集团有限公司 Construction method for support-free prefabricated assembled type shield tunnel air shaft structure
CN114593927A (en) * 2022-03-01 2022-06-07 中交隧道工程局有限公司 Method for performing shield tunnel prototype test by using middle air shaft

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5302052A (en) * 1993-04-16 1994-04-12 Groundtech, Inc. Underground work chamber assembly and method for the construction thereof
JP3120244B2 (en) * 1991-07-23 2000-12-25 株式会社竹中工務店 Installation start method of shield machine of vertical shield method
CN102094650A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Construction method for shield holing under complicated working conditions
CN102146679A (en) * 2010-02-09 2011-08-10 中铁十一局集团有限公司 Construction method for complex geological section earth pressure balance shield passing middle air shaft
CN104653188A (en) * 2015-02-04 2015-05-27 北京市政建设集团有限责任公司 Method for arranging large-diameter shield receiving and originating well in underground-excavated air duct

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3120244B2 (en) * 1991-07-23 2000-12-25 株式会社竹中工務店 Installation start method of shield machine of vertical shield method
US5302052A (en) * 1993-04-16 1994-04-12 Groundtech, Inc. Underground work chamber assembly and method for the construction thereof
CN102094650A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Construction method for shield holing under complicated working conditions
CN102146679A (en) * 2010-02-09 2011-08-10 中铁十一局集团有限公司 Construction method for complex geological section earth pressure balance shield passing middle air shaft
CN104653188A (en) * 2015-02-04 2015-05-27 北京市政建设集团有限责任公司 Method for arranging large-diameter shield receiving and originating well in underground-excavated air duct

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107514262A (en) * 2017-08-02 2017-12-26 中国建筑第八工程局有限公司 The construction method of shield piping lane
CN107664035A (en) * 2017-10-20 2018-02-06 中国建筑第八工程局有限公司 The construction method of well after shield piping lane elder generation shield
CN108868814A (en) * 2018-08-24 2018-11-23 中铁西安勘察设计研究院有限责任公司 Collapsible loess combination land pebble stratum tunneling air duct connects the ventilating shaft of shield tunnel
CN108868814B (en) * 2018-08-24 2023-12-29 中铁西安勘察设计研究院有限责任公司 Air shaft of underground excavation air duct shield tunnel of collapsible loess combined pebble soil stratum
CN109162741A (en) * 2018-10-29 2019-01-08 中铁十二局集团有限公司 The method in shield crossing piston air duct and piston air duct superstructure synchronous construction
CN109577998B (en) * 2018-12-04 2020-10-09 中铁十二局集团有限公司 Construction method for backfilling and station-crossing of piston air duct in shield interval
CN109577998A (en) * 2018-12-04 2019-04-05 中铁十二局集团有限公司 A kind of construction method that the backfill of shield section piston air duct is missed the stop
CN109577999A (en) * 2018-12-27 2019-04-05 中铁十局集团城市轨道工程有限公司 Side-proof wall deformation and shield machine plant the excessively intermediate ventilating shaft ruggedized construction of shield machine and construction method of head
CN109577999B (en) * 2018-12-27 2024-02-06 中铁十一局集团城市轨道工程有限公司 Shield machine middle wind shaft reinforcing structure capable of preventing side wall deformation and shield machine planting head and construction method
CN109695456A (en) * 2019-01-22 2019-04-30 济南轨道交通集团有限公司 A kind of rail traffic and pipe gallery build structure and its construction method jointly
CN110541722A (en) * 2019-09-30 2019-12-06 中铁第四勘察设计院集团有限公司 Partial shield tunnel segment dismantling method and water stop structure in middle air shaft
CN110685709A (en) * 2019-10-30 2020-01-14 长江勘测规划设计研究有限责任公司 Construction method and structure of connection channel of superposed tunnel
CN112727466A (en) * 2021-01-29 2021-04-30 绍兴市柯桥区轨道交通集团有限公司 Construction method for support-free prefabricated assembled type shield tunnel air shaft structure
CN114593927A (en) * 2022-03-01 2022-06-07 中交隧道工程局有限公司 Method for performing shield tunnel prototype test by using middle air shaft
CN114593927B (en) * 2022-03-01 2024-01-26 中交隧道工程局有限公司 Method for carrying out prototype test of shield tunnel by using middle wind well

Also Published As

Publication number Publication date
CN106522989B (en) 2018-12-04

Similar Documents

Publication Publication Date Title
CN106522989A (en) Air shaft structure and shield excavation parallel construction method
CN104675403B (en) A kind of underground space construction method and supporting construction
Cao et al. Subway station construction using combined shield and shallow tunnelling method: case study of Gaojiayuan station in Beijing
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN107218046A (en) Mechanical assistance sealing Station structure and construction method in a kind of pilot tunnel
CN108442943A (en) A kind of branch-cut bridge section tunnel and Double side heading method construction method
CN106703814A (en) Mined metro station hole pile construction method
CN105041349A (en) Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN209163805U (en) A kind of big cross section rectangular top pipe construction active well foundation reinforcing structure
CN105464134B (en) Multi-layer underground space is along inverse combining construction method and supporting construction under existing facility
CN105525619B (en) A kind of water rich strata bored tunnel occlusion pipe curtain
CN113565525A (en) Construction protection system and construction method for newly-built shield tunnel super-close ultra-shallow buried upper-span existing tunnel
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN107091101A (en) Mine shield handing-over tunnel folded type joint design and construction method in the middle part of marine site
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN105201516A (en) Subway station body structure and four-joint-arch PBA underground excavation construction method thereof
CN206888992U (en) A kind of water-bed mine shield tunnel combination docking structure form
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
CN110259490A (en) A kind of Underground Subway Station construction method
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant