JP3120244B2 - Installation start method of shield machine of vertical shield method - Google Patents

Installation start method of shield machine of vertical shield method

Info

Publication number
JP3120244B2
JP3120244B2 JP03182324A JP18232491A JP3120244B2 JP 3120244 B2 JP3120244 B2 JP 3120244B2 JP 03182324 A JP03182324 A JP 03182324A JP 18232491 A JP18232491 A JP 18232491A JP 3120244 B2 JP3120244 B2 JP 3120244B2
Authority
JP
Japan
Prior art keywords
shield machine
shaft
shield
starting
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP03182324A
Other languages
Japanese (ja)
Other versions
JPH0525992A (en
Inventor
勝稔 浅井
正昭 加倉井
隆文 下河内
義文 藤井
秀治 駒井
孝夫 赤津
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Takenaka Civil Engineering and Construction Co Ltd
Original Assignee
Takenaka Corp
Takenaka Civil Engineering and Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp, Takenaka Civil Engineering and Construction Co Ltd filed Critical Takenaka Corp
Priority to JP03182324A priority Critical patent/JP3120244B2/en
Publication of JPH0525992A publication Critical patent/JPH0525992A/en
Application granted granted Critical
Publication of JP3120244B2 publication Critical patent/JP3120244B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、立坑を構築する立型
シールド工法において実施されるシールド機の据え付け
発進方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for installing and starting a shield machine which is carried out in a vertical shield construction method for constructing a shaft.

【0002】[0002]

【従来の技術】通常の水平方向のシールド工法は、施工
事例も非常に数多く、シールド機の据え付け発進に関す
る技術はほぼ確立されている。しかし、立型シールド工
法に関しては、施工事例もほとんどなく、シールド機の
据え付け発進の技術はまだ確立されたものがない。
2. Description of the Related Art The usual horizontal shield construction method has a large number of construction examples, and the technology relating to the installation and start of a shield machine is almost established. However, there have been few construction examples of the vertical shield method, and no technology has been established for the installation and start of the shield machine.

【0003】[0003]

【本発明が解決しようとする課題】立型シールド工法
は、シールド機の推進、掘削の方向が垂直下向きであ
り、その発進は地表部から開始されるため、推進反力を
確保する付帯構造物は発進のためだけに用意する必要が
ある、等々の事情が通常の水平方向シールド工法の場合
とは大きく異なっている。
[Problems to be Solved by the Invention] In the vertical shield construction method, the propulsion and excavation direction of the shield machine is vertically downward, and the start is started from the surface of the ground. Need to be prepared only for the start, etc., are significantly different from the case of the normal horizontal shield method.

【0004】立型シールド機の据え付け発進に関して
は、施工対象地盤の状態、特に地表面近傍の地盤の状態
が大きな問題となる。立型シールド工法の場合、シール
ド機を地表面に据え付けると、その支持方法と、発進に
際しての推進反力のとり方も問題となる。例えば軟弱地
盤のため据え付けたシールド機の支持能力が不足しシー
ルド機が自重で沈下するような場合には、シールド機を
発進方向とは逆向き(垂直上向き)に支持する必要さえ
ある。仮に、シールド機を支持する必要がなくても、シ
ールド機のカッターヘッド部分に自重等による過大な接
地圧が発生すると、カッターヘッドの回転に伴ってシー
ルド機本体も共回りしてしまったりローリングが発生し
たりしてシールド機の初期推進、掘削が困難になること
もある。
[0004] Regarding the installation start of the vertical shield machine, the state of the ground to be constructed, particularly the state of the ground near the ground surface, becomes a serious problem. In the case of the vertical shield construction method, when the shield machine is installed on the ground surface, there are problems in the method of supporting the shield machine and how to take the propulsion reaction force at the time of starting. For example, when the installed capacity of the shield machine is insufficient due to the soft ground and the shield machine sinks by its own weight, it is even necessary to support the shield machine in a direction opposite to the starting direction (vertically upward). Even if it is not necessary to support the shield machine, if the cutter head of the shield machine has an excessive ground pressure due to its own weight, etc., the shield machine body will rotate together with the rotation of the cutter head and rolling will occur. In some cases, initial propulsion and excavation of the shield machine may become difficult.

【0005】従って、本発明の目的は、立型シールド工
法の施工に有用なシールド機の据え付け発進の方法を提
供することにある。
Accordingly, it is an object of the present invention to provide a method of installing and starting a shield machine which is useful for construction of a vertical shield method.

【0006】[0006]

【課題を解決するための手段】上記従来技術の課題を解
決するための手段として、この発明に係る立型シールド
工法のシールド機の据え付け発進方法は、図面に実施例
を示しているとおり、シールド機1を地表部から垂直下
向きに掘進させ立坑を構築する立型シールド工法におい
て、 イ)地表部に所定深さの発進立坑2を構築し、該発進立
坑2の底部にはシールド機1の外径より少し大きい口径
の開口3を有する床版コンクリート4を施工し、シール
ド機1は前記開口3を通じて直下の地盤10に臨む垂直
な配置で発進立坑2内に据え付け支持せしめる段階と、 ロ)シールド機1の外周の発進立坑2内に埋め戻し土5
を充填し、シールド機1内から垂直上方にセグメント6
を組立て、その後セグメント6の外周の発進立坑内にも
埋め戻し土7を充填する段階と、 ハ)発進立坑2の上部に前記セグメント6の頂部に推進
反力を与える反力台8を施工し、その後シールド機1を
垂直下向きに発進させること、 をそれぞれ特徴とする。
As a means for solving the above-mentioned problems of the prior art, a method for installing and starting a shield machine of a vertical shield method according to the present invention is described as follows. In a vertical shield construction method in which a machine 1 is excavated vertically downward from the surface to construct a shaft, a) a start shaft 2 having a predetermined depth is constructed on the surface, and a shield machine 1 is provided at the bottom of the start shaft 2 Constructing a slab concrete 4 having an opening 3 having a diameter slightly larger than the diameter, and mounting and supporting the shield machine 1 in the starting shaft 2 in a vertical arrangement facing the ground 10 immediately below through the opening 3; Backfill soil in the starting shaft 2 on the outer circumference of the machine 1
And from the inside of the shield machine 1 vertically upward segment 6
And then filling backfill soil 7 also in the start shaft on the outer periphery of the segment 6; c) constructing a reaction force table 8 on the top of the start shaft 2 for applying a propulsion reaction force to the top of the segment 6; And then launching the shield machine 1 vertically downward.

【0007】本発明はまた、発進立坑2の底部の地盤1
0がシールド機1が自重で沈下する程度の軟弱地盤であ
る場合は、同地盤10に改良を施した上で床版コンクリ
ート4を施工しシールド機1を据え付け支持せしめるこ
と、及び、シールド機1のスキンプレートの外面に減摩
剤を塗布した後にその外周に埋め戻し土5を充填し、シ
ールド機1及びセグメント6の外周に充填した埋め戻し
土5、7に改良を施すこと、及び、反力台8は、その鉄
筋を発進立坑2の土留壁9の鉄筋またはH鋼芯材等に溶
接し、土留壁9と一体化された鉄筋コンクリート構造と
して施工されていること、及び、発進立坑2内に埋め戻
し土5を充填後、同立坑2内にシールド機1に所定の浮
力を作用させるに十分なレベルまで水を注入し、その後
準備を整えてシールド機1を垂直下向きに発進させるこ
と、もそれぞれ特徴とする。
The present invention also relates to a ground 1 at the bottom of the starting shaft 2.
In the case where 0 is a soft ground where the shield machine 1 sinks under its own weight, the ground 10 is improved, the floor slab concrete 4 is applied, and the shield machine 1 is installed and supported. After applying an anti-friction agent to the outer surface of the skin plate, the outer periphery thereof is filled with backfill soil 5, and the backfill soil 5, 7 filled on the outer circumference of the shield machine 1 and the segment 6 is subjected to improvement. The power platform 8 is constructed by welding the reinforcing steel to the reinforcing steel or the H-steel core material of the retaining wall 9 of the starting shaft 2 and is constructed as a reinforced concrete structure integrated with the retaining wall 9. After filling the backfill soil 5 with water, injecting water into the vertical shaft 2 to a level sufficient to exert a predetermined buoyancy on the shield machine 1, and then preparing to start the shield machine 1 vertically downward; Also special To.

【0008】[0008]

【作用】発進立坑2の床版コンクリート4の開口3を通
じて直下の地盤10に臨む垂直な配置とされたシールド
機1は、地盤10と床版コンクリート4及び埋め戻し土
5、あるいは周辺の立坑土留壁9からの支えによってき
っちり支持され、場合によっては持ち上げる向きに支持
することさえ可能である。シールド機1内から上方に組
立てられたセグメント6も、その外周に充填した埋め戻
し土7によって支持される。シールド機1の発進時の推
進反力は、セグメント6を介してその上の反力台8及び
立坑土留壁9によって十分に確保される。
The shield machine 1 having the vertical arrangement facing the ground 10 directly below the floor 10 through the opening 3 of the floor slab concrete 4 of the starting shaft 2, the ground 10 and the floor slab concrete 4 and the backfill soil 5, or the surrounding pit soil It is firmly supported by the support from the wall 9 and can even be supported in the lifting direction in some cases. The segment 6 assembled upward from the inside of the shield machine 1 is also supported by the backfill soil 7 filled in the outer periphery. The propulsion reaction force of the shield machine 1 at the time of starting is sufficiently secured by the reaction force table 8 and the shaft retaining wall 9 on the segment 6 via the segment 6.

【0009】特に、発進立坑2内に注入された水は、シ
ールド機1に浮力を作用して持ち上げるため、自重等に
よる接地圧を軽減するので、カッターヘッドの回転に必
要なトルクが大幅に軽減され、シールド機1は埋め戻し
土5による支持と摩擦力とによってきっちり保持され、
ローリングも発生しない。
In particular, since the water injected into the starting shaft 2 is lifted by applying buoyancy to the shield machine 1, the ground pressure due to its own weight and the like is reduced, so that the torque required for rotating the cutter head is greatly reduced. And the shield machine 1 is firmly held by the backfill soil 5 and the frictional force,
No rolling occurs.

【0010】[0010]

【実施例】次に、図示した本発明の実施例を説明するま
ず図1A、Bは立型シールド工法を開始するにあたり、
発進立坑2を構築した段階を示している。これは公知の
ソイル柱列工法による土留壁9を施工し、その内側を掘
削すると共に順次腹起し11を設置し、同腹起し11は
斜めの火打ち切梁12により中央にシールド機を配置し
得るだけの空間を残して支持せしめ、シールド機の発進
準備に必要とされる深さまで立坑2が掘削されている。
この発進立坑2の底部には、シールド機の外径よりも2
0〜30cm程度大きい口径の開口3を中央部に有する床
版コンクリート( 捨コンクリート)4が施工される。も
っとも、立坑底部の地盤10が、その上に据付けたシー
ルド機1が自重で沈下するような軟弱地盤であるとき
は、例えば公知の安定材による混合処理工法等による地
盤改良を施し、その改良地盤の上に床版コンクリート4
が施工される。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1A and FIG. 1B show a first embodiment of the present invention.
The stage at which the starting shaft 2 was constructed is shown. In this method, a soil retaining wall 9 is constructed by a well-known soil column method, and the inside thereof is excavated and bulges 11 are sequentially installed. The bulge 11 is provided with a shield machine at the center by an oblique fire cutoff beam 12. The shaft 2 is excavated to a depth required for the preparation for starting the shield machine, leaving a space for obtaining it.
The bottom of the start shaft 2 is larger than the outer diameter of the shield machine by 2 mm.
Floor slab concrete (discarded concrete) 4 having an opening 3 having a large diameter of about 0 to 30 cm at the center is constructed. However, when the ground 10 at the bottom of the shaft is soft ground such that the shield machine 1 installed thereon sinks under its own weight, the ground is improved by, for example, a mixing method using a known stabilizer, and the improved ground is used. Floor slab concrete 4
Is constructed.

【0011】図2は前記発進立坑2内へシールド機1の
建込みを行ない、該シールド機1の外周の発進立坑2内
へ埋め戻し土5を充填してシールド機1を支持せしめた
段階を示している。シールド機1は、その先端部(カッ
ター部)が前記開口3を通じて直下の地盤10に臨む垂
直な配置で発進立坑2内に据え付けられる。そして、詳
しく図示することは省略したが、立坑土留壁9に反力を
とった支え材によってシールド機1の支持が行なわれ
る。あるいは地盤10の支持能力によってはシールド機
1を上向きに持ち上げる支持さえも行なわれる。なお、
埋め戻し土5を充填する以前に、シールド機1のスキン
プレート外面に摩擦低減用の減摩剤を塗布し、発進時の
抵抗を低減し発進を容易ならしめることも必要に応じて
行なう。あるいは埋め戻し土5を充填した立坑2内に所
定レベルまで水を注入し、その浮力によりシールド機1
の先端接地圧を軽減し、カッターヘッドの回転による掘
削の抵抗トルクを軽減し、もってシールド機本体のロー
リング等を防ぎ、垂直精度を確保することも行なわれ
る。
FIG. 2 shows a state in which the shield machine 1 is built into the start shaft 2 and the back shaft 2 on the outer periphery of the shield machine 1 is filled with backfill soil 5 to support the shield machine 1. Is shown. The shield machine 1 is installed in the starting shaft 2 in a vertical arrangement in which the tip end (cutter portion) faces the ground 10 directly below through the opening 3. Although not shown in detail, the shield machine 1 is supported by a support member that takes a reaction force on the shaft shaft retaining wall 9. Alternatively, depending on the support capacity of the ground 10, support for lifting the shield machine 1 upward is also performed. In addition,
Before filling the backfill soil 5, a friction reducing lubricant is applied to the outer surface of the skin plate of the shield machine 1 to reduce the resistance at the time of starting and facilitate the starting as required. Alternatively, water is injected into a shaft 2 filled with backfill soil 5 up to a predetermined level, and the buoyancy causes the shield machine 1
The tip contact pressure is reduced, the resistance torque of the excavation caused by the rotation of the cutter head is reduced, thereby preventing the rolling of the shield machine body, etc., and ensuring the vertical accuracy.

【0012】図3は上記のようにして発進立坑2内に垂
直に据え付け支持せしめたシールド機1内のシールドジ
ャッキの位置から垂直上方に数リングのセグメント6を
所望の高さまで組立て、その後セグメント6の外周の発
進立坑2内にも埋め戻し土7を充填して前記セグメント
6の支持を行ない、さらに発進立坑2の上部にセグメン
ト6の頂部に推進反力を与える反力台8を施工し、今ま
さにシールド機1の発進準備が整った段階を示してい
る。なお、埋め戻し土5、7によるシールド機1及びセ
グンメト6の支持能力が不足すると思われる場合は、例
えば安定材の注入による公知の混合処理工法等により改
良を施し、きっちりと安定した支持を行なわしめる。
FIG. 3 shows the assembly of several rings 6 to the desired height vertically above the position of the shield jack in the shield machine 1 vertically installed and supported in the starting shaft 2 as described above. A backfill soil 7 is also filled in the starting shaft 2 on the outer periphery of the starting shaft 2 to support the segment 6, and a reaction force table 8 for applying a propulsive reaction force to the top of the segment 6 is constructed above the starting shaft 2, This is just the stage when the shield machine 1 is ready to start. If the backing soil 5 or 7 is considered to be insufficient in supporting capacity of the shield machine 1 and Segummet 6, for example, a known mixing treatment method by injecting a stabilizing material or the like is performed to provide a stable and stable support. Close.

【0013】反力台8は1本ないし数本のH形鋼の架設
等により設置することも可能であるが、図3の実施例で
は鉄筋コンクリート構造として施工されている。この場
合、反力台8の鉄筋は立坑土留壁9の鉄筋又はH鋼芯材
に溶接し、応力的に土留壁9と一体化された鉄筋コンク
リート構造として施工される。最上位のセグメントリン
グの継手ボルトは、反力台8のコンクリート中に埋め込
んでやはり一体化が行なわれる。
The reaction table 8 can be installed by erection of one or several H-section steels or the like, but in the embodiment of FIG. 3, it is constructed as a reinforced concrete structure. In this case, the reinforcing bar of the reaction table 8 is welded to the reinforcing bar of the shaft shaft retaining wall 9 or the H steel core material, and is constructed as a reinforced concrete structure that is integrated with the retaining wall 9 in a stressed manner. The joint bolts of the uppermost segment ring are embedded in the concrete of the reaction table 8 and also integrated.

【0014】以上の準備が全て整った後に、シールド機
1は発進される。発進時の推進反力は、セグメント6を
介して反力台8及び土留壁9により確保される。立型シ
ールド工法の場合、シールド機1は密閉加圧型で清水掘
削を基本として掘進される。この場合、発進時のシール
ド機1の位置が地下水位より上方であるときは、清水を
注水しつつ掘削を行なう。地下水位より下方に達したと
きは、清水の注水を調整しつつ掘削を進めることにな
る。
After all the above preparations are completed, the shield machine 1 is started. The propulsion reaction force at the time of starting is secured by the reaction force table 8 and the retaining wall 9 via the segment 6. In the case of the vertical shield method, the shield machine 1 is a closed pressurized type and is excavated on the basis of freshwater excavation. In this case, when the position of the shield machine 1 at the time of starting is above the groundwater level, excavation is performed while pouring fresh water. When the water level falls below the groundwater level, excavation will proceed while adjusting the water injection.

【0015】[0015]

【本発明が奏する効果】本発明に係る立型シールド工法
のシールド機の据え付け発進方法によれば、施工対象地
盤10の状態に応じて、シールド機1の据え付けと支持
を確実、容易に行なえるし、発進時の推進反力の確保に
も問題がないから、立型シールド工法の安全で安定した
施工に寄与する。
[Effects of the present invention] According to the method of installing and starting the shield machine of the vertical shield method according to the present invention, the installation and support of the shield machine 1 can be reliably and easily performed according to the state of the ground 10 to be constructed. Also, there is no problem in securing the propulsion reaction force at the start, which contributes to the safe and stable construction of the vertical shield method.

【図面の簡単な説明】[Brief description of the drawings]

【図1】A、Bは発進立坑の平面図と垂直断面図であ
る。
1A and 1B are a plan view and a vertical sectional view of a starting shaft.

【図2】シールド機を据え付けた発進立坑の断面図であ
る。
FIG. 2 is a sectional view of a starting shaft on which a shield machine is installed.

【図3】シールド機の発進準備が整った状態の断面図で
ある。
FIG. 3 is a cross-sectional view of a state in which the shield machine is ready to start.

【符号の説明】[Explanation of symbols]

1 シールド機 2 発進立坑 3 開口 4 床版コンクリート 10 地盤 5、7 埋め戻し土 6 セグメント 8 反力台 9 土留壁 DESCRIPTION OF SYMBOLS 1 Shield machine 2 Starting shaft 3 Opening 4 Floor slab 10 Ground 5, 7 Backfill soil 6 Segment 8 Reaction bed 9 Earth retaining wall

フロントページの続き (72)発明者 下河内 隆文 東京都江東区南砂二丁目5番14号 株式 会社竹中工務店技術研究所内 (72)発明者 藤井 義文 東京都中央区銀座八丁目21番1号 株式 会社竹中土木内 (72)発明者 駒井 秀治 東京都中央区銀座八丁目21番1号 株式 会社竹中土木内 (72)発明者 赤津 孝夫 東京都中央区銀座八丁目21番1号 株式 会社竹中土木内 (58)調査した分野(Int.Cl.7,DB名) E21D 5/04 E21D 9/06 301 E21D 1/08 E21D 1/03 Continuing from the front page (72) Inventor Takafumi Shimokawachi 2-5-1 Minamisuna, Koto-ku, Tokyo Inside Takenaka Corporation Technical Research Institute (72) Inventor Yoshifumi Fujii 8-2-11, Ginza, Chuo-ku, Tokyo Stock Company Takenaka Civil Engineering Co., Ltd. (72) Inventor Hideharu Komai 8-21-1, Ginza, Chuo-ku, Tokyo, Japan Takenaka Civil Engineering Co., Ltd. (72) Inventor Takao Akatsu 8-2-1, Ginza, Chuo-ku, Tokyo, Japan 58) Field surveyed (Int. Cl. 7 , DB name) E21D 5/04 E21D 9/06 301 E21D 1/08 E21D 1/03

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 シールド機を地表部から垂直下向きに掘
進させ立坑を構築する立型シールド工法において、 イ)地表部に所定深さの発進立坑を構築し、該発進立坑
の底部にはシールド機の外径より少し大きい口径の開口
を有する床版コンクリートを施工し、シールド機は前記
開口を通じて直下の地盤に臨む垂直な配置で発進立坑内
に据え付け支持せしめる段階と、 ロ)シールド機の外周の発進立坑内に埋め戻し土を充填
し、シールド機内から垂直上方にセグメントを組立て、
その後セグメントの外周の発進立坑内に埋め戻し土を充
填する段階と、 ハ)発進立坑の上部に前記セグメントの頂部に推進反力
を与える反力台を施工し、その後シールド機を垂直下向
きに発進させること、 をそれぞれ特徴とする、立型シールド工法のシールド機
の据え付け発進方法。
1. A vertical shield construction method in which a shield machine is excavated vertically downward from the ground surface to construct a shaft, a) a start shaft having a predetermined depth is constructed on the ground surface, and a shield machine is provided at the bottom of the start shaft. Constructing floor slab concrete having an opening having a diameter slightly larger than the outer diameter of the shield machine, and installing and supporting the shield machine in the starting shaft in a vertical arrangement facing the ground immediately below through the opening; Fill the back shaft with backfill soil, assemble the segment vertically from inside the shield machine,
Then, filling backfill soil into the start shaft on the outer periphery of the segment; and c) constructing a reaction table for applying a propulsion reaction force to the top of the segment above the start shaft, and then starting the shield machine vertically downward. A method of installing and starting a shield machine using a vertical shield method, characterized in that:
【請求項2】 発進立坑の底部の地盤がシールド機が自
重で沈下する程度の軟弱地盤である場合は、同地盤に改
良を施した上で床版コンクリートを施工しシールド機を
据え付け支持せしめることを特徴とする、請求項1に記
載した立型シールド工法のシールド機の据え付け発進方
法。
2. In the case where the ground at the bottom of the starting shaft is soft ground such that the shield machine sinks under its own weight, the ground should be improved, and then the slab concrete should be constructed and the shield machine should be installed and supported. 2. The method according to claim 1, further comprising the steps of:
【請求項3】 シールド機のスキンプレート外面に減摩
剤を塗布した後にその外周に埋め戻し土を充填し、シー
ルド機及びセグメントの外周に充填した埋め戻し土に改
良を施すことを特徴とする、請求項1に記載した立型シ
ールド工法のシールド機の据え付け発進方法。
3. The method according to claim 1, wherein the outer surface of the skin plate of the shield machine is coated with a lubricant, and the outer periphery thereof is filled with backfill soil, and the backfill soil filled on the outer periphery of the shield machine and the segment is improved. A method for installing and starting a shield machine using the vertical shield method according to claim 1.
【請求項4】 反力台は、鉄筋を発進立坑の土留壁の鉄
筋又はH鋼芯材に溶接し、土留壁と一体化された鉄筋コ
ンクリート構造として施工されていることを特徴とす
る、請求項1に記載した立型シールド工法のシールド機
の据え付け発進方法。
4. The reaction bed is constructed by welding a reinforcing bar to a reinforcing bar or an H steel core material of a retaining wall of a starting shaft, and is constructed as a reinforced concrete structure integrated with the retaining wall. 1. The method of installing and starting the shield machine of the vertical shield method described in 1.
【請求項5】発進立坑内に埋め戻し土を充填後、同立坑
内にシールド機に所定の浮力を作用させるに十分なレベ
ルまで水を注入し、その後シールド機を垂直下向きに発
進させることを特徴とする、請求項1に記載した立型シ
ールド工法のシールド機の据え付け発進方法。
5. The method according to claim 5, wherein after the backfill soil is filled in the start shaft, water is injected into the shaft in a level sufficient to exert a predetermined buoyancy on the shield machine, and then the shield machine is started vertically downward. The installation start method of a shield machine of a vertical shield method according to claim 1, characterized in that:
JP03182324A 1991-07-23 1991-07-23 Installation start method of shield machine of vertical shield method Expired - Fee Related JP3120244B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP03182324A JP3120244B2 (en) 1991-07-23 1991-07-23 Installation start method of shield machine of vertical shield method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP03182324A JP3120244B2 (en) 1991-07-23 1991-07-23 Installation start method of shield machine of vertical shield method

Publications (2)

Publication Number Publication Date
JPH0525992A JPH0525992A (en) 1993-02-02
JP3120244B2 true JP3120244B2 (en) 2000-12-25

Family

ID=16116321

Family Applications (1)

Application Number Title Priority Date Filing Date
JP03182324A Expired - Fee Related JP3120244B2 (en) 1991-07-23 1991-07-23 Installation start method of shield machine of vertical shield method

Country Status (1)

Country Link
JP (1) JP3120244B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522989A (en) * 2016-09-14 2017-03-22 中交第二航务工程局有限公司 Air shaft structure and shield excavation parallel construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522989A (en) * 2016-09-14 2017-03-22 中交第二航务工程局有限公司 Air shaft structure and shield excavation parallel construction method
CN106522989B (en) * 2016-09-14 2018-12-04 中交第二航务工程局有限公司 The method of ventilating shaft structure and shield driving parallel construction

Also Published As

Publication number Publication date
JPH0525992A (en) 1993-02-02

Similar Documents

Publication Publication Date Title
JP5041223B2 (en) Reinforcement method and structure of existing structure foundation
JP4713297B2 (en) Foundation structure and construction method of foundation structure
JP3120244B2 (en) Installation start method of shield machine of vertical shield method
JP2002364006A (en) Construction method for underwater foundation
JP3453664B2 (en) Shaft construction method
JP2006070513A (en) Height adjusting method of structure
JP3695550B2 (en) Construction method of high-rise building supported by piles
JP3248458B2 (en) Shoring construction underground construction method
CN208563347U (en) Soft Soil Area elevator pit supporting construction
CN104018495B (en) Bilateral haunched beam circular section anti-slide pile and construction method thereof
JPH0442494B2 (en)
CN202039370U (en) Composite anchor pole foundation pit enclosing structure
JP2858998B2 (en) Construction method of temporary supporting column for reverse driving method
JP3711528B2 (en) Reinforcement method of existing building foundation with slant pile
JP3189885B2 (en) Seismic pile structure and seismic pile construction method
JP4196735B2 (en) Suction foundation method
JPS61109822A (en) Construction work of pile
JPH0960311A (en) Lift-up demolition method
JP3519807B2 (en) Pile loading device
JP3637945B2 (en) Construction method of base-isolated building by reverse driving method
JP2884273B2 (en) Construction method for high strength cast-in-place concrete piles
JP2006176962A (en) Semi-rigid joining structure of concrete pile and foundation slab or foundation beam and its construction method
JPH0464618A (en) Pit excavation work method
JP3449279B2 (en) Construction method of underwater substructure
JPH0351879B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees