CN107882042A - Supporting construction and its construction method are supportted before a kind of bellows - Google Patents

Supporting construction and its construction method are supportted before a kind of bellows Download PDF

Info

Publication number
CN107882042A
CN107882042A CN201711443576.5A CN201711443576A CN107882042A CN 107882042 A CN107882042 A CN 107882042A CN 201711443576 A CN201711443576 A CN 201711443576A CN 107882042 A CN107882042 A CN 107882042A
Authority
CN
China
Prior art keywords
shaped steel
utricule
construction
bellows
rotary churning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711443576.5A
Other languages
Chinese (zh)
Inventor
朱作猛
王建军
胡宝山
张敏杰
刘忠秋
易娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhiping Foundation Engineering Co Ltd
Original Assignee
Shanghai Zhiping Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhiping Foundation Engineering Co Ltd filed Critical Shanghai Zhiping Foundation Engineering Co Ltd
Priority to CN201711443576.5A priority Critical patent/CN107882042A/en
Publication of CN107882042A publication Critical patent/CN107882042A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses supporting construction and its construction method are supportted before a kind of bellows, including support system and by the advanced support in " H " shaped steel insertion rotary churning pile, it is characterized in that " H " shaped steel one end is provided with the utricule that seal assembly is fixed, after utricule inserts the projected depth of rotary churning pile in the lump with " H " shaped steel, and cement mortar is filled in utricule, so that supportted on rotary churning pile before the bellows of formation cement bag, the seal assembly is arranged on utricule both ends and being fixedly connected for sealing with " H " shaped steel, and Specific construction includes:The steps such as making, installation and the placement and utricule slip casting of bellows shoe tree.The present invention has the contact area of increase support end and the soil body compared with prior art, support displacement before can effectively limiting, and ensures the stability of supporting construction, supporting effect is good, the surrounding enviroment that are particularly suitable for use in are complicated, and existing building is more, the excavating sideline foundation pit supporting project construction nearer apart from red line.

Description

Supporting construction and its construction method are supportted before a kind of bellows
Technical field
The present invention relates to foundation pit enclosure technical field, especially a kind of special formations such as muddy soft soil, sand that are used for increase Add support end with supportting supporting construction and its construction method before the bellows of soil body contact area.
Background technology
With urban construction and the continuous development of Transport Facility Construction, increasing project needs pattern foundation pit supporting structure to ensure The safety of hypogee construction, and the depth of excavation of foundation pit is also increasingly deeper, surrounding enviroment also become increasingly complex, in order to for building The peak use rate on ground, leaves that the place usable floor area of pattern foundation pit supporting structure is also fewer and fewer for, to the security of foundation ditch also more and more higher.
At present, the support forms such as slope, soil cement gravity dam or the double-row pile that foundation ditch uses, the area of occupancy is larger, and Foundation ditch is compared with depth and leaves the less foundation ditch of place usable floor area of pattern foundation pit supporting structure for, typically all uses the branch of board-like supporting+inner support Protection structure, inner support generally throws the form of support using horizontal support or tiltedly, but horizontal support cost is higher, difficulty of being unearthed, tiltedly throws Support influences construction of bottom plates.
The supporting construction of prior art is difficult to construct in special formations such as muddy soft soil, sands, support position before easily causing Move, less stable.
The content of the invention
Supporting construction and its construction are supportted before a kind of bellows that the purpose of the present invention is in view of the shortcomings of the prior art and designed Method, expand the preceding support of body structure using bellows, to increase the contact area of support end and the soil body, support displacement before can effectively limiting, Ensure the stability of supporting construction, supporting effect is good, can fully save the underground space, increase economic efficiency, be particularly suitable for use in week Surrounding environment is complicated, and existing building is more, the excavating sideline foundation pit supporting project construction nearer apart from red line.
The object of the present invention is achieved like this:Support supporting construction before a kind of bellows, including support system and by " H " type Advanced support in steel insertion rotary churning pile, advanced support to be set in the oblique foundation ditch of 30~45° angle degree, and " H " shaped steel one end with The Guan Liang connection being arranged at the top of support system, other end insertion are arranged on the rotary churning pile under bottom plate, are characterized in " H " shaped steel one End is provided with the utricule that seal assembly is fixed, and utricule inserts rotary churning pile in the lump with " H " shaped steel, and cement bag is formed on rotary churning pile Supportted before bellows, the seal assembly is arranged on utricule both ends and being fixedly connected for sealing with " H " shaped steel.
The bottom plate is connected provided with load transfering strip with support system.
The bottom plate of " H " shaped steel and basement or exterior wall intersection are provided with sealing steel disc.
The construction method of supporting construction is supportted before a kind of bellows, is characterized in provided with seal assembly consolidating using " H " shaped steel one end Fixed utricule, after utricule inserts the projected depth of rotary churning pile in the lump with " H " shaped steel, and cement mortar is filled in utricule so that rotation Supportted before the bellows of cement bag are formed in spray stake, Specific construction is carried out in the steps below:
A, the construction of rotary churning pile
Vertical board-like support system and slot grooving Guan Liang is set along excavation of foundation pit sideline, is then excavated to Guan Liang top mark Height, carry out hole bottom and all hydraulic caterpillar drilling machine construction is used with the jet grouting pile construction of lower portion, the rotary churning pile, its footpath is 800mm, angle of inclination are 30~45 °.
B, the making and installation of bellows shoe tree
Preceding support main body by " H profile steel and utricule forms, the utricule using canvas material making, its both ends by seal assembly and " H " shaped steel termination is integrally fixed, while Grouting Pipe is inserted in utricule and is fixed together with H " shaped steel.
C, bellows shoe tree is laid
" H " shaped steel one end provided with utricule is inserted by rotary churning pile using lash method, need to be used when " H " shaped steel inserts rotary churning pile oblique Positioned to bracket as angle, the model and insertion depth of " H " shaped steel determine according to stressing conditions.
D, utricule slip casting
After the projected depth of bellows shoe tree insertion rotary churning pile, cement will be filled in utricule by Grouting Pipe using grouting pump Slurry, make on rotary churning pile formed balloon inflation extruding expanding body cement bag be bellows before support.
E, sealing is set
The bottom plate and exterior wall and load transfering strip of construction basement, and water-stopping steel is set in " H " shaped steel and bottom plate and exterior wall intersection Piece.
F, support is removed
After bottom plate and load transfering strip reach design strength, the support of oblique bracket is removed, or treats that the top board construction of basement is complete, with And between exterior wall and board-like supporting after backfill, cut off to construct after " H " shaped steel in basement and terminate.
The present invention has the contact area of increase support end and the soil body compared with prior art, support displacement effectively before limitation, Ensure the stability of supporting construction, supporting effect is good, can fully save the underground space, increase economic efficiency, be particularly suitable for use in week Surrounding environment is complicated, and existing building is more, the excavating sideline foundation pit supporting project construction nearer apart from red line.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention;
Fig. 2~Fig. 3 is figure of the embodiment of the present invention;
Fig. 4 is utricule and " H " shaped steel scheme of installation;
Fig. 5 is Grouting Pipe and " H " shaped steel scheme of installation;
Fig. 6 is bellows shoe tree structural representation.
Embodiment
Refering to accompanying drawing 1, the present invention includes support system 1 and inserts in rotary churning pile 2 the advanced branch formed by " H " shaped steel 3 Support, is supported to be set in the oblique foundation ditch of 30~45° angle degree in advance, and described one end of " H " shaped steel 3 is with being arranged on the top of support system 1 Guan Liang 4 connect, other end insertion is arranged on rotary churning pile 2 under bottom plate 6;Described one end of " H " shaped steel 3 is solid provided with seal assembly 10 Fixed utricule 8, after utricule 8 inserts the projected depth of rotary churning pile 2 in the lump with " H " shaped steel 3, and cement mortar is filled in utricule 8, made Supportted before obtaining the bellows that cement bag 11 is formed on rotary churning pile 2;The seal assembly 10 is arranged on the both ends of utricule 8 and with " H " shaped steel 3 Sealing is fixedly connected;The bottom plate 6 is connected provided with load transfering strip 7 with slab supporting system 1;The bottom of " H " shaped steel 3 and basement Plate 6 or the intersection of exterior wall 16 are provided with sealing steel disc 5.
Make further to retouch in detail with preceding support supporting of the embodiment of a certain foundation pit enclosure to the present invention and construction method below State and illustrate:
Embodiment 1
Refering to accompanying drawing 2, construction procedure a of the invention, the construction of rotary churning pile:Board-like prop is set along excavation of foundation pit sideline It is 1 and slot grooving Guan Liang 4, and cheats bottom and constructed with the rotary churning pile 2 of lower portion, then carries out the bottom plate 6 and exterior wall of basement 16 and the construction of load transfering strip 7, the rotary churning pile 2 uses all hydraulic caterpillar drilling machine construction, and its footpath is 800mm, inclination angle Spend for 30~45 °.
Refering to 4~Fig. 5 of accompanying drawing, step b of the invention, the making and installation of bellows shoe tree:Preceding support main body is by " H profile steel 3 Formed with utricule 8, the utricule 8 is made using canvas material, and its both ends is fixed into by seal assembly 10 and the termination of " H " shaped steel 3 One, while Grouting Pipe 9 is inserted in utricule 8 and is fixed together with H " shaped steel 3.
Refering to accompanying drawing 6, step c and step d of the invention, bellows shoe tree and utricule slip casting are laid:Will using lash method After the projected depth of the one end of " H " shaped steel 3 insertion rotary churning pile 2 provided with utricule 8, using grouting pump by Grouting Pipe 9 by utricule 8 Fill cement mortar so that the cement bag 11 of balloon inflation extruding expanding body is formed on rotary churning pile 2 to be supportted before bellows, the insertion rotation of " H " shaped steel 3 Oblique bracket need to be used to be positioned as angle when spraying stake 2.
Refering to accompanying drawing 3, step e and step f of the invention, sealing set and removed support:In " H " shaped steel 3 and bottom plate 6 and The intersection of exterior wall 16 sets sealing steel disc 5, after bottom plate 6 and load transfering strip 7 reach design strength, removes the support of oblique bracket, Or treat that the top board construction of basement is complete, between the exterior wall 16 of basement and board-like supporting after backfill, cut off " H " in basement Construction terminates after shaped steel 3;The model and insertion depth of " H " shaped steel 3 determine according to stressing conditions.
Simply the present invention is further illustrated above, and is not used to limit this patent, and all is equivalence enforcement of the present invention, It is intended to be limited solely by within the right of this patent.

Claims (4)

1. support supporting construction before a kind of bellows, including support system and rotary churning pile is inserted by " H " shaped steel(2)Interior advanced branch Support, advanced support in the oblique foundation ditch of 30~45° angle degree to set, and " H " shaped steel one end and the hat that is arranged at the top of support system Beam connects, and other end insertion is arranged on the rotary churning pile under bottom plate, it is characterised in that " H " shaped steel one end is provided with what seal assembly was fixed Utricule, utricule inserts rotary churning pile in the lump with " H " shaped steel, and is supportted on rotary churning pile before the bellows of formation cement bag, the sealing group Part is arranged on utricule both ends and being fixedly connected for sealing with " H " shaped steel.
2. support supporting construction before bellows according to claim 1, it is characterised in that the bottom plate is provided with load transfering strip and prop System's connection.
3. support supporting construction before bellows according to claim 1 or claim 2, it is characterised in that the bottom of " H " shaped steel and basement Plate or exterior wall intersection are provided with sealing steel disc.
4. the construction method of supporting construction is supportted before bellows described in a kind of claim 1, it is characterised in that set using " H " shaped steel one end After thering is the utricule that seal assembly is fixed, utricule to insert the projected depth of rotary churning pile in the lump with " H " shaped steel, and water is filled in utricule Mud so that supportted before the bellows of cement bag are formed on rotary churning pile, Specific construction is carried out in the steps below:
A, the construction of rotary churning pile
Vertical support system and slot grooving Guan Liang are set along excavation of foundation pit sideline, Guan Liang top mark height is then excavated to, enters Row hole bottom is with the jet grouting pile construction of lower portion, and the rotary churning pile uses all hydraulic caterpillar drilling machine construction, and its footpath is 800mm, Angle of inclination is 30~45 °;
B, the making and installation of bellows shoe tree
Preceding support main body is by " H profile steel and utricule are formed, and the utricule is made using canvas material, and its both ends is by seal assembly and " H " Shaped steel termination is integrally fixed, while Grouting Pipe is inserted in utricule and is fixed together with H " shaped steel;
C, bellows shoe tree is laid
" H " shaped steel one end provided with utricule is inserted by rotary churning pile using lash method, " H " shaped steel need to use oblique when inserting rotary churning pile Bracket positions as angle, and the model and insertion depth of " H " shaped steel determine according to stressing conditions;
D, utricule slip casting
After the projected depth of bellows shoe tree insertion rotary churning pile, cement will be filled in utricule by Grouting Pipe using grouting pump Slurry, make on rotary churning pile formed balloon inflation extruding expanding body cement bag be bellows before support;
E, sealing is set
The bottom plate and exterior wall and load transfering strip of construction basement, and water-stopping steel is set in " H " shaped steel and bottom plate and exterior wall intersection Piece;
F, support is removed
After bottom plate and load transfering strip reach design strength, the support of oblique bracket is removed, or treats that the top board construction of basement is complete, with And between exterior wall and board-like supporting after backfill, cut off to construct after " H " shaped steel in basement and terminate.
CN201711443576.5A 2017-12-27 2017-12-27 Supporting construction and its construction method are supportted before a kind of bellows Pending CN107882042A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711443576.5A CN107882042A (en) 2017-12-27 2017-12-27 Supporting construction and its construction method are supportted before a kind of bellows

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711443576.5A CN107882042A (en) 2017-12-27 2017-12-27 Supporting construction and its construction method are supportted before a kind of bellows

Publications (1)

Publication Number Publication Date
CN107882042A true CN107882042A (en) 2018-04-06

Family

ID=61772562

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711443576.5A Pending CN107882042A (en) 2017-12-27 2017-12-27 Supporting construction and its construction method are supportted before a kind of bellows

Country Status (1)

Country Link
CN (1) CN107882042A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951646A (en) * 2018-07-18 2018-12-07 江苏东合南岩土科技股份有限公司 Pit Bracing in Soft Soil structure and construction method
CN109083128A (en) * 2018-09-10 2018-12-25 浙江吉通地空建筑科技有限公司 Fashioned iron column assembled underground continuous wall with high-bearing capacity
CN112127373A (en) * 2020-10-16 2020-12-25 中建四局第六建设有限公司 Deep foundation pit pile-support integrated supporting system structure and segmented accurate grouting construction technology
CN112761166A (en) * 2021-02-23 2021-05-07 广东科能工程管理有限公司 Construction method for shallow foundation pit of combined support of piles and pre-grouting steel pipes based on SMW (soil mixing wall) construction method
CN116876529A (en) * 2023-09-08 2023-10-13 中建交通建设集团有限公司 Central type supporting system for deep and large foundation pit and construction method of central type supporting system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148877A (en) * 2007-10-16 2008-03-26 中国京冶工程技术有限公司 Multistage bag-type compression anchor bar
CN101864773A (en) * 2010-04-14 2010-10-20 江苏江中集团有限公司 Deep foundation pit support process
CN101929163A (en) * 2009-12-17 2010-12-29 浙江中联建设集团有限公司 Support construction process of lotus root-shaped segmental expanded soil anchor rod
CN205348195U (en) * 2016-01-11 2016-06-29 浙江宝业建设集团有限公司 Anchor rope spouts supporting construction that anchor double row pile was drawn in stake soon
CN206768832U (en) * 2017-01-05 2017-12-19 上海城地建设股份有限公司 Support, anchor cable post-tensioning H type component building enclosures before a kind of steel pipe
CN207700197U (en) * 2017-12-27 2018-08-07 上海智平基础工程有限公司 Supporting construction is supportted before a kind of bellows

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148877A (en) * 2007-10-16 2008-03-26 中国京冶工程技术有限公司 Multistage bag-type compression anchor bar
CN101929163A (en) * 2009-12-17 2010-12-29 浙江中联建设集团有限公司 Support construction process of lotus root-shaped segmental expanded soil anchor rod
CN101864773A (en) * 2010-04-14 2010-10-20 江苏江中集团有限公司 Deep foundation pit support process
CN205348195U (en) * 2016-01-11 2016-06-29 浙江宝业建设集团有限公司 Anchor rope spouts supporting construction that anchor double row pile was drawn in stake soon
CN206768832U (en) * 2017-01-05 2017-12-19 上海城地建设股份有限公司 Support, anchor cable post-tensioning H type component building enclosures before a kind of steel pipe
CN207700197U (en) * 2017-12-27 2018-08-07 上海智平基础工程有限公司 Supporting construction is supportted before a kind of bellows

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951646A (en) * 2018-07-18 2018-12-07 江苏东合南岩土科技股份有限公司 Pit Bracing in Soft Soil structure and construction method
CN109083128A (en) * 2018-09-10 2018-12-25 浙江吉通地空建筑科技有限公司 Fashioned iron column assembled underground continuous wall with high-bearing capacity
CN112127373A (en) * 2020-10-16 2020-12-25 中建四局第六建设有限公司 Deep foundation pit pile-support integrated supporting system structure and segmented accurate grouting construction technology
CN112761166A (en) * 2021-02-23 2021-05-07 广东科能工程管理有限公司 Construction method for shallow foundation pit of combined support of piles and pre-grouting steel pipes based on SMW (soil mixing wall) construction method
CN116876529A (en) * 2023-09-08 2023-10-13 中建交通建设集团有限公司 Central type supporting system for deep and large foundation pit and construction method of central type supporting system
CN116876529B (en) * 2023-09-08 2023-12-15 中建交通建设集团有限公司 Construction method of central type supporting system for deep and large foundation pit

Similar Documents

Publication Publication Date Title
CN107882042A (en) Supporting construction and its construction method are supportted before a kind of bellows
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN105298507B (en) A kind of underground pipe gallery construction method of top open cut bottom tunneler construction
CN105089061B (en) Ultra-deep foundation pit supporting method
CN107201908B (en) Construction method for deep-buried central ditch of tunnel in severe cold region
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN108035361A (en) A kind of advanced support supporting construction and its construction method
CN101270579B (en) Foundation pit guard method for expansion construction from deep foundation pit to shallow foundation pit
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN106930321A (en) Underground structure novel construction method is built in a kind of pipe-jacking with large diameter combination hole stake
CN113463670A (en) Water pumping and draining method and water pumping and draining structure for deep foundation pit bottom plate construction
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN103437370A (en) Method and supporting structure for slip resisting and soil retaining of abrupt slope
CN104818713A (en) Profile steel cement soil pile construction method adaptive to various stratums
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN210002425U (en) structure of seepage roadbed side slope drainage system
CN107237332A (en) A kind of foundation pit stope support containing drifting sand layer method of use composite soil-nailed retaining wall
CN112112657B (en) New construction method for digging and building inclined shaft of coal mine
CN107044135A (en) A kind of tunnel portal excavates the construction method built
CN108277815A (en) The cofferdam structure and its construction method constructed for water intaking header structure in river
CN207700197U (en) Supporting construction is supportted before a kind of bellows
CN216475087U (en) Prefabricated earth-retaining plate with earth-receiving function
CN208563278U (en) The rainy season construction structure of major diameter vertical shaft in a kind of soft soil layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination