CN207700197U - Supporting construction is supportted before a kind of bellows - Google Patents

Supporting construction is supportted before a kind of bellows Download PDF

Info

Publication number
CN207700197U
CN207700197U CN201721859474.7U CN201721859474U CN207700197U CN 207700197 U CN207700197 U CN 207700197U CN 201721859474 U CN201721859474 U CN 201721859474U CN 207700197 U CN207700197 U CN 207700197U
Authority
CN
China
Prior art keywords
shaped steel
utricule
bellows
support
rotary churning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721859474.7U
Other languages
Chinese (zh)
Inventor
朱作猛
王建军
胡宝山
张敏杰
刘忠秋
易娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhiping Foundation Engineering Co Ltd
Original Assignee
Shanghai Zhiping Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhiping Foundation Engineering Co Ltd filed Critical Shanghai Zhiping Foundation Engineering Co Ltd
Priority to CN201721859474.7U priority Critical patent/CN207700197U/en
Application granted granted Critical
Publication of CN207700197U publication Critical patent/CN207700197U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses support supporting construction before a kind of bellows, it is inserted into the advanced support in rotary churning pile including support system and by " H " shaped steel, its main feature is that " H " shaped steel one end is equipped with the fixed utricule of seal assembly, after utricule is inserted into the projected depth of rotary churning pile together with " H " shaped steel, and cement mortar is filled in utricule, so that being supportted before the bellows of formation cement packet on rotary churning pile, the seal assembly setting is being fixedly connected for sealing at utricule both ends and with " H " shaped steel, and Specific construction includes:Making, installation and the placement and utricule slip casting of bellows shoe tree and etc..The utility model has the contact area for increasing support end and the soil body compared with prior art, displacement is supportted before can effectively limiting, ensure the stability of supporting construction, supporting effect is good, it is particularly suitable for surrounding enviroment complexity, existing building is more, the excavating sideline foundation pit supporting project construction closer apart from red line.

Description

Supporting construction is supportted before a kind of bellows
Technical field
The utility model is related to foundation pit enclosure technical fields, especially a kind of to be used for muddy soft soil, sand etc. distinguishingly Layer supports supporting construction before increasing support end and the bellows of soil body contact area.
Background technology
With the continuous development of urban construction and Transport Facility Construction, more and more projects need pattern foundation pit supporting structure to ensure The safety of hypogee construction, and the depth of excavation of foundation pit is also increasingly deeper, surrounding enviroment also become increasingly complex, in order to for building The peak use rate on ground, the place usable floor area for leaving pattern foundation pit supporting structure for is also fewer and fewer, also higher and higher to the safety of foundation pit.
Currently, the support forms such as slope, soil cement gravity dam or double-row pile that foundation pit uses, the area of occupancy is larger, and Foundation pit relatively depth and the smaller foundation pit of the place usable floor area for leaving pattern foundation pit supporting structure for, are generally used the branch of board-like supporting+inner support Protection structure, inner support is generally using the horizontally-supported or oblique form for throwing support, but horizontally-supported cost is higher, and difficulty of being unearthed tiltedly is thrown Support influences construction of bottom plates.
The supporting construction of the prior art is difficult to construct in special formations such as muddy soft soil, sands, and position is supportted before be easy to causeing It moves, stability is poor.
Utility model content
The purpose of this utility model is in view of the deficiencies of the prior art and to support supporting construction before a kind of bellows of design, is used Bellows expand the preceding support of body structure, to increase the contact area of support end and the soil body, support displacement before can effectively limiting, ensure supporting knot The stability of structure, supporting effect is good, can fully save the underground space, increase economic efficiency, and is particularly suitable for surrounding enviroment complexity, Existing building is more, the excavating sideline foundation pit supporting project construction closer apart from red line.
What the purpose of this utility model was realized in:Support supporting construction before a kind of bellows, including support system and by " H " shaped steel is inserted into the advanced support in rotary churning pile, and advanced support in the oblique foundation pit of 30~45° angle degree to be arranged, and " H " shaped steel one The Guan Liang held and be arranged at the top of support system connects, and the other end is inserted into the rotary churning pile being arranged under bottom plate, its main feature is that " H " type Steel one end is equipped with the fixed utricule of seal assembly, and utricule is inserted into rotary churning pile together with " H " shaped steel, and cement is formed on rotary churning pile It is supportted before the bellows of packet, the seal assembly setting is being fixedly connected for sealing at utricule both ends and with " H " shaped steel.
The bottom plate is connect equipped with load transfering strip with support system.
The bottom plate or exterior wall intersection of " H " shaped steel and basement are equipped with sealing steel disc.
The utility model has the contact area for increasing support end and the soil body compared with prior art, effectively supports position before limitation It moves, ensures the stability of supporting construction, supporting effect is good, can fully save the underground space, increase economic efficiency, be particularly suitable for Surrounding enviroment are complicated, and existing building is more, the excavating sideline foundation pit supporting project construction closer apart from red line.
Description of the drawings
FIG. 1 is a schematic structural view of the utility model;
Fig. 2~Fig. 3 is the utility model embodiment figure;
Fig. 4 is utricule and " H " shaped steel scheme of installation;
Fig. 5 is Grouting Pipe and " H " shaped steel scheme of installation;
Fig. 6 is bellows shoe tree structural schematic diagram.
Specific implementation mode
Refering to attached drawing 1, the present invention includes support system 1 and is inserted into the advanced branch formed in rotary churning pile 2 by " H " shaped steel 3 Support, advanced support in the oblique foundation pit of 30~45° angle degree to be arranged, and described 3 one end of " H " shaped steel is with setting at 1 top of support system Guan Liang 4 connect, the other end is inserted into the rotary churning pile 2 that is arranged under bottom plate 6;Described 3 one end of " H " shaped steel is solid equipped with seal assembly 10 Fixed utricule 8 after utricule 8 is inserted into the projected depth of rotary churning pile 2 together with " H " shaped steel 3, and fills cement mortar in utricule 8, makes It is supportted before obtaining the bellows for forming cement packet 11 on rotary churning pile 2;The seal assembly 10 is arranged at 8 both ends of utricule and with " H " shaped steel 3 Sealing is fixedly connected;The bottom plate 6 is connect equipped with load transfering strip 7 with slab supporting system 1;The bottom of " H " shaped steel 3 and basement Plate 6 or 16 intersection of exterior wall are equipped with sealing steel disc 5.
Refering to 2~Fig. 3 of attached drawing, board-like support system 1 and slot grooving Guan Liang 4 are set along excavation of foundation pit sideline, with And hole bottom is constructed with the rotary churning pile 2 of lower portion, then carries out the construction of the bottom plate 6 and exterior wall 16 and load transfering strip 7 of basement, In " H " shaped steel 3 and bottom plate 6 and 16 intersection of exterior wall setting sealing steel disc 5;The rotary churning pile 2 uses all hydraulic caterpillar drilling machine Construction, diameter are 800mm, and angle of inclination is 30~45 °.
Refering to 4~Fig. 5 of attached drawing, preceding support main body is by " H profile steel 3 and utricule 8 form, and the utricule 8 uses canvas material system Make, both ends are integrally fixed by seal assembly 10 and 3 end of " H " shaped steel, while Grouting Pipe 9 being inserted into utricule 8 is interior and and H " Shaped steel 3 is fixed together.
Refering to attached drawing 6, after the projected depth of rotary churning pile 2 is inserted into 3 one end of " H " shaped steel equipped with utricule 8 using lash method, Cement mortar will be filled in utricule 8 by Grouting Pipe 9 using grouting pump so that the water of balloon inflation extruding expanding body is formed on rotary churning pile 2 Mud drum 11 need to use oblique bracket to be positioned as angle to be supportted before bellows when " H " shaped steel 3 is inserted into rotary churning pile 2.It waits for bottom plate 6 and passes After power band 7 reaches design strength, the support of oblique bracket is removed, or waits for that the top board construction of basement is complete, the exterior wall 16 of basement Between board-like supporting after backfill, cuts off to construct after indoor " H " shaped steel in underground 3 and terminate;The model of " H " shaped steel 3 and Insertion depth is determined according to stressing conditions.
Above to be only further described to the utility model, not to limit this patent, all is the utility model Equivalence enforcement is intended to be limited solely by within the right of this patent.

Claims (3)

1. supportting supporting construction, including support system before a kind of bellows(1)And by " H " shaped steel(3)It is inserted into rotary churning pile(2)Interior is super Front support, advanced support in the oblique foundation pit of 30~45° angle degree to be arranged, and " H " shaped steel(3)One end is with setting in support system (1)The Guan Liang at top(4)Connection, the other end, which is inserted into, to be arranged in bottom plate(6)Under rotary churning pile(2), it is characterised in that " H " shaped steel (3)One end is equipped with seal assembly(10)Fixed utricule(8), utricule(8)With " H " shaped steel(3)It is inserted into rotary churning pile together(2), and In rotary churning pile(2)Upper formation cement packet(11)Bellows before support, the seal assembly(10)It is arranged in utricule(8)Both ends and with " H " shaped steel(3)For being fixedly connected for sealing.
2. supportting supporting construction before bellows according to claim 1, it is characterised in that the bottom plate(6)Equipped with load transfering strip(7)With Support system(1)Connection.
3. supportting supporting construction before bellows according to claim 1 or claim 2, it is characterised in that " H " shaped steel(3)With basement Bottom plate(6)Or exterior wall(16)Intersection is equipped with sealing steel disc(5).
CN201721859474.7U 2017-12-27 2017-12-27 Supporting construction is supportted before a kind of bellows Active CN207700197U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721859474.7U CN207700197U (en) 2017-12-27 2017-12-27 Supporting construction is supportted before a kind of bellows

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721859474.7U CN207700197U (en) 2017-12-27 2017-12-27 Supporting construction is supportted before a kind of bellows

Publications (1)

Publication Number Publication Date
CN207700197U true CN207700197U (en) 2018-08-07

Family

ID=63029341

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721859474.7U Active CN207700197U (en) 2017-12-27 2017-12-27 Supporting construction is supportted before a kind of bellows

Country Status (1)

Country Link
CN (1) CN207700197U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882042A (en) * 2017-12-27 2018-04-06 上海智平基础工程有限公司 Supporting construction and its construction method are supportted before a kind of bellows

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882042A (en) * 2017-12-27 2018-04-06 上海智平基础工程有限公司 Supporting construction and its construction method are supportted before a kind of bellows

Similar Documents

Publication Publication Date Title
CN105298507B (en) A kind of underground pipe gallery construction method of top open cut bottom tunneler construction
CN107882042A (en) Supporting construction and its construction method are supportted before a kind of bellows
CN105240024B (en) A kind of method of parallel shield method enlarging construction subway station
CN206512701U (en) A kind of miniature steel pipe pile supporting construction of built-in profile steel
CN108035361A (en) A kind of advanced support supporting construction and its construction method
CN104762955B (en) A kind of Belled Pile construction method based on freezing process
CN107542115A (en) Underground project waterproof structure and its construction method
CN108547639A (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN105256810A (en) Construction method for round underground continuous wall two-in-one structure
CN108677926A (en) Coercion underground continuous wall and its construction method
CN105178285A (en) Method for widening grouting reinforcement and seepage and blockage prevention range of rock and soil
CN104818713A (en) Profile steel cement soil pile construction method adaptive to various stratums
WO2018068409A1 (en) Structure underlaid gob area filling expansion bag and construction method
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN102330436A (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN108677925A (en) Half coercion underground continuous wall structure and its construction method
CN206204967U (en) A kind of double perfusion pile cofferdam
CN105672250A (en) Rabbet connecting mechanism and construction method for underground diaphragm wall and underwater concrete
CN207700197U (en) Supporting construction is supportted before a kind of bellows
CN102943480B (en) Loess foundation pit supporting method
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN204941551U (en) A kind of subway station of Curve Pipe Jacking supporting and protection structure enlarging shield-tunneling construction
CN102418348A (en) Construction technology of using occlusive pile to form underground continuous wall
CN202181908U (en) Expanding soft rock roadway waterproof supporting combined structure
CN111594184A (en) Main hole excavating method for hole bias tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant