CN105604211A - Anti-crack construction method for joint of filling wall and frame girder - Google Patents
Anti-crack construction method for joint of filling wall and frame girder Download PDFInfo
- Publication number
- CN105604211A CN105604211A CN201610002462.6A CN201610002462A CN105604211A CN 105604211 A CN105604211 A CN 105604211A CN 201610002462 A CN201610002462 A CN 201610002462A CN 105604211 A CN105604211 A CN 105604211A
- Authority
- CN
- China
- Prior art keywords
- cement
- cement mortar
- vierendeel girder
- construction method
- gap
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/02—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
Abstract
The invention discloses an anti-crack construction method for the joint of a filling wall and a frame girder. The method has the advantages that firstly a gap between the frame girder and the upper edge of a brick wall forms a grouting pore channel, and pure cement paste is subjected to double-pressure injection for the second time after M20 cement mortar injected for the first time is initially solidified, so that caves are filled and cracks can be prevented; secondly two through long steel bars are arranged in each of third and second mortar joints in the bottom of the girder and the gap between the frame girder and the upper edge of the brick wall, the two ends of each steel bar are implanted in a column body by more than 100mm, and three supporting lines are formed, so that the temperature stresses of the frame girder and the brick wall can be effectively born and the cracks generated due to the temperature deformation are prevented, wherein the M20 cement mortar adopts 32.2 ordinary Portland cement, and a mass ratio of cement to medium sand to water is 1 to 2.99 to 0.40; and an expansion agent accounting for 9% by mass of the cement is doped, so that the cement mortar has relatively high strength, the temperature stress of the frame girder can be born after the cement mortar matches with the steel bars, and the cracks generated due to the temperature deformation can be effectively prevented.
Description
Technical field
The present invention relates to a kind of infilled wall construction method, especially relate to the anticracking construction method of a kind of infilled wall and Vierendeel girder junction.
Background technology
Building in use, due to the impact of the various factors such as drying shrinkage, temperature of sedimentation, masonry and the mortar joint of ground, causes metope cracking. Wherein, the crack that the impact of temperature causes is modal in body of wall, and the common junction with different materials, this crack, as the horizontal fracture of Vierendeel girder and infilled wall junction. General material has the performance of expanding with heat and contract with cold, building structure causes that because environment temperature changes the distortion of expanding with heat and contract with cold is called temperature deformation, as fruit structure is under no restraint, can Free Transform in the time of variations in temperature, structure can not produce additional stress so, also be that structure suffers restraints can not Free Transform time, can in structure, produce additional stress and also claim temperature stress. Cause the flexible of structure by temperature stress, because the coefficient of expansion of different materials is different, cause producing the crack of temperature, thermal cracking is the main cause that causes body of wall early crack. In order to reduce the horizontal fracture of Vierendeel girder and infilled wall junction, we need to improve the construction of infilled wall, avoid the generation in the crack of the temperature of body of wall as far as possible.
Summary of the invention
Technical problem to be solved by this invention is to provide the anticracking construction method of a kind of infilled wall and Vierendeel girder junction, can reduce the generation in the crack of the temperature of infilled wall and Vierendeel girder junction.
The present invention solves the problems of the technologies described above adopted technical scheme: the anticracking construction method of a kind of infilled wall and Vierendeel girder junction, it is characterized in that, and specifically comprise the following steps:
(1) unwrapping wire; According to Design Requirement Drawing and orientation axis, infilled wall wall body central axis pilot measurement, on base surface or flooring, is then pressed to wall body central axis, eject each wall sideline;
(2) pendulum brick sample; Build mode according to drawing and the selected suitable group of code requirement, at base surface or flooring unwrapping wire position examination pendulum brick sample;
(3) vertical marked rod; From starting reserved 20 ~ 30mm gap at the bottom of beam, mark the thickness of every skin brick and mortar joint at marked rod according to Design Requirement Drawing;
(4) levelling; Before building a wall, according to the absolute altitude of marked rod, a minimum skin height completes by levelling on base surface or flooring while not being inconsistent the modulus of brick;
(5) paving ash is laid bricks; Infilled wall respectively arranges two elongated reinforcing bars while building by laying bricks or stones to Vierendeel girder Di tri-roads and second mortar joint, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm; Adopt flat block from last skin brick at the bottom of Vierendeel girder, the height in the gap between at the bottom of brick good rear upper edge and Vierendeel girder is 20 ~ 30mm, two elongated reinforcing bars are set in gap, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm, the cement mortar edge sealing that is 1:2 with the thick ratio of mud of 20mm on both sides, gap, and in Ge Kaiyi hole, two ends, gap; Then maintenance 8 ~ 12 days;
(6) duct slip casting; Slip casting for the first time adopts M20 cement mortar, and grouting pressure is 0.3 ~ 0.5MPa; After the M20 cement mortar initial set of injecting for the first time, carry out neat slurry for the second time and inject, grouting pressure is 0.6 ~ 1.2MPa;
(7) maintenance, water seasoning 12 ~ 15 days after duct slip casting completes.
In step (4) levelling, cement mortar screeding when a minimum skin height is no more than 25mm, otherwise with the levelling of C20 pea gravel concreten.
Compared with prior art, the invention has the advantages that: be first that the space between edge builds up slip casting duct on frame girder and brick wall, and after the M20 cement mortar initial set of injecting for the first time, carry out neat slurry multiplication of voltage for the second time and inject, well filled slump, can prevent the appearance in crack; Secondly on frame girder Di tri-roads and second mortar joint and frame girder and brick wall, the space between edge is all provided with two elongated reinforcing bars, and frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm, form three road Support Level, the temperature stress that can effectively bear frame girder and build a wall, prevents that temperature deformation from producing crack.
As preferably, described M20 cement mortar adopts 32.2 Portland cements, cement in every part of M20 cement mortar: medium sand: the mass ratio of water is 1:2.99:0.40, and in described M20 cement mortar doped with the swelling agent of cement quality 9%. There is higher intensity, coordinate the temperature stress that can sustain frame girder with reinforcing bar, effectively prevent that temperature deformation from producing crack.
As preferably, the ratio of mud of described neat slurry is 0.4 ~ 0.5.
As preferably, neat slurry injects the condition that stops slip casting and is for the second time: neat slurry overflows from aperture, or grouting pressure exceedes 1.2Mpa, or neat slurry injection rate exceedes 20% of duct, gap volume.
As preferably, in step (3), the height of reserving gaps is 25mm.
As preferably, described in step (5), reinforcing bar is Φ 6 reinforcing bars.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is described in further detail.
This preferred embodiment is the anticracking construction method of a kind of infilled wall and Vierendeel girder junction, specifically comprises the following steps:
(1) unwrapping wire; According to Design Requirement Drawing and orientation axis, infilled wall wall body central axis pilot measurement, on base surface or flooring, is then pressed to wall body central axis, eject each wall sideline, mark door-window opening position.
(2) pendulum brick sample; Build mode according to drawing and the selected suitable group of code requirement, at base surface or flooring unwrapping wire position examination pendulum brick sample; Make door and window buttress meet the modulus of brick by adjusting perps as far as possible, cut brick quantity to reduce, and ensure brick and brickwork joint marshalling, even, to improve lay bricks efficiency and the quality of brick masonry structures; Wherein, the modulus of brick is generally 60mm.
(3) vertical marked rod; From starting reserved 20 ~ 30mm gap at the bottom of beam, mark the thickness of every skin brick and mortar joint at marked rod according to Design Requirement Drawing; The height of reserving gaps is preferably 25mm.
(4) levelling; Before building a wall, according to the absolute altitude of marked rod, a minimum skin height completes by levelling on base surface or flooring while not being inconsistent the modulus of brick; Cement mortar screeding when a minimum skin height is no more than 25mm, otherwise with the levelling of C20 pea gravel concreten. It is can ensure at the bottom of beam with the clearance control of top one skin brick face, at 20 ~ 30mm, can to obtain desirable slip casting condition that levelling is put into vertical marked rod by this construction method, prevents that thermal cracking from producing.
(5) paving ash is laid bricks; Adopt 31 building methods, build full of mortar by laying bricks or stones, smooth vertical and horizontal; Infilled wall respectively arranges two elongated Φ 6(diameter 6mm while building by laying bricks or stones to Vierendeel girder Di tri-roads and second mortar joint) reinforcing bar, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm; Adopt flat block from last skin brick at the bottom of Vierendeel girder, the height in the gap between at the bottom of brick good rear upper edge and Vierendeel girder is 20 ~ 30mm, two elongated Φ 6 reinforcing bars are set in gap, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm, the cement mortar edge sealing that is 1:2 with the thick ratio of mud of 20mm on both sides, gap, and in Ge Kaiyi hole, two ends, gap; Then maintenance 8 ~ 12 days, is generally 10 days; Wherein, a hole is injected hole, and another hole is venthole, and preferably open in beam bottom in hole, the long 20mm in aperture, high 5mm.
(6) duct slip casting; Slip casting for the first time adopts M20 cement mortar, grouting pressure is 0.3 ~ 0.5Mpa, described M20 cement mortar adopts 32.2 Portland cements, cement in every part of M20 cement mortar: medium sand: the mass ratio of water is 1:2.99:0.40, and in described M20 cement mortar doped with the swelling agent of cement quality 9%; After the M20 cement mortar initial set of injecting for the first time, carrying out neat slurry for the second time injects, grouting pressure is 0.6 ~ 1.2Mpa, the ratio of mud of neat slurry is also that the mass ratio of water and cement is 0.4 ~ 0.5, the condition that neat slurry injection for the second time stops slip casting is: neat slurry overflows from aperture, or grouting pressure exceedes 1.2Mpa, or neat slurry injection rate exceedes 20% of duct, gap volume.
(7) maintenance; After duct slip casting completes, water seasoning 12 ~ 15 days, is generally 14 days.
Claims (7)
1. an anticracking construction method for infilled wall and Vierendeel girder junction, is characterized in that, specifically comprises the following steps:
(1) unwrapping wire; According to Design Requirement Drawing and orientation axis, infilled wall wall body central axis pilot measurement, on base surface or flooring, is then pressed to wall body central axis, eject each wall sideline;
(2) pendulum brick sample; Build mode according to drawing and the selected suitable group of code requirement, at base surface or flooring unwrapping wire position examination pendulum brick sample;
(3) vertical marked rod; From starting reserved 20 ~ 30mm gap at the bottom of beam, mark the thickness of every skin brick and mortar joint at marked rod according to Design Requirement Drawing;
(4) levelling; Before building a wall, according to the absolute altitude of marked rod, a minimum skin height completes by levelling on base surface or flooring while not being inconsistent the modulus of brick;
(5) paving ash is laid bricks; Infilled wall respectively arranges two elongated reinforcing bars while building by laying bricks or stones to Vierendeel girder Di tri-roads and second mortar joint, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm; Adopt flat block from last skin brick at the bottom of Vierendeel girder, the height in the gap between at the bottom of brick good rear upper edge and Vierendeel girder is 20 ~ 30mm, two elongated reinforcing bars are set in gap, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm, the cement mortar edge sealing that is 1:2 with the thick ratio of mud of 20mm on both sides, gap, and in Ge Kaiyi hole, two ends, gap; Then maintenance 8 ~ 12 days;
(6) duct slip casting; Slip casting for the first time adopts M20 cement mortar, and grouting pressure is 0.3 ~ 0.5MPa; After the M20 cement mortar initial set of injecting for the first time, carry out neat slurry for the second time and inject, grouting pressure is 0.6 ~ 1.2MPa;
(7) maintenance, water seasoning 12 ~ 15 days after duct slip casting completes.
2. the anticracking construction method of infilled wall according to claim 1 and Vierendeel girder junction, is characterized in that: in step (4) levelling, and cement mortar screeding when a minimum skin height is no more than 25mm, otherwise with the levelling of C20 pea gravel concreten.
3. the anticracking construction method of infilled wall according to claim 1 and Vierendeel girder junction, it is characterized in that: described M20 cement mortar adopts 32.2 Portland cements, cement in every part of M20 cement mortar: medium sand: the mass ratio of water is 1:2.99:0.40, and in described M20 cement mortar doped with the swelling agent of cement quality 9%.
4. the anticracking construction method of infilled wall according to claim 3 and Vierendeel girder junction, is characterized in that: the ratio of mud of described neat slurry is 0.4 ~ 0.5.
5. the anticracking construction method of infilled wall according to claim 4 and Vierendeel girder junction, it is characterized in that: the condition that neat slurry injection for the second time stops slip casting is: neat slurry overflows from aperture, or grouting pressure exceedes 1.2Mpa, or neat slurry injection rate exceedes 20% of duct, gap volume.
6. the anticracking construction method of infilled wall according to claim 1 and Vierendeel girder junction, is characterized in that: in step (3), the height of reserving gaps is 25mm.
7. the anticracking construction method of infilled wall according to claim 1 and Vierendeel girder junction, is characterized in that: described in step (5), reinforcing bar is Φ 6 reinforcing bars.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610002462.6A CN105604211B (en) | 2016-01-06 | 2016-01-06 | Fill wall and the anticracking construction method of Vierendeel girder junction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610002462.6A CN105604211B (en) | 2016-01-06 | 2016-01-06 | Fill wall and the anticracking construction method of Vierendeel girder junction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105604211A true CN105604211A (en) | 2016-05-25 |
CN105604211B CN105604211B (en) | 2017-11-28 |
Family
ID=55984511
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610002462.6A Active CN105604211B (en) | 2016-01-06 | 2016-01-06 | Fill wall and the anticracking construction method of Vierendeel girder junction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105604211B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108547450A (en) * | 2018-04-25 | 2018-09-18 | 中建八局第三建设有限公司 | A kind of self-insulating brick wall construction method for exempting from formwork |
CN111749475A (en) * | 2020-07-17 | 2020-10-09 | 中铁二十二局集团第五工程有限公司 | Autoclaved fly ash brick masonry arrangement method and masonry arrangement system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102182316A (en) * | 2011-04-11 | 2011-09-14 | 山东送变电工程公司 | Building method for controlling temperature cracks of masonry |
CN102251670A (en) * | 2011-06-01 | 2011-11-23 | 重庆建工第三建设有限责任公司 | Construction process for self-heat-insulation system of autoclaved aerated concrete block wall |
CN102808513A (en) * | 2012-07-05 | 2012-12-05 | 江苏武进建筑安装工程有限公司 | Crack controlling construction method for lightweight wall |
CN102877652A (en) * | 2012-10-19 | 2013-01-16 | 厦门特房建设工程集团有限公司 | Construction method for post-injection cement mortar masonry brickwork |
CN103266767A (en) * | 2013-05-27 | 2013-08-28 | 中国航天建设集团有限公司 | Construction method for preventing and treating cracks between concrete structure and filler wall |
-
2016
- 2016-01-06 CN CN201610002462.6A patent/CN105604211B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102182316A (en) * | 2011-04-11 | 2011-09-14 | 山东送变电工程公司 | Building method for controlling temperature cracks of masonry |
CN102251670A (en) * | 2011-06-01 | 2011-11-23 | 重庆建工第三建设有限责任公司 | Construction process for self-heat-insulation system of autoclaved aerated concrete block wall |
CN102808513A (en) * | 2012-07-05 | 2012-12-05 | 江苏武进建筑安装工程有限公司 | Crack controlling construction method for lightweight wall |
CN102877652A (en) * | 2012-10-19 | 2013-01-16 | 厦门特房建设工程集团有限公司 | Construction method for post-injection cement mortar masonry brickwork |
CN103266767A (en) * | 2013-05-27 | 2013-08-28 | 中国航天建设集团有限公司 | Construction method for preventing and treating cracks between concrete structure and filler wall |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108547450A (en) * | 2018-04-25 | 2018-09-18 | 中建八局第三建设有限公司 | A kind of self-insulating brick wall construction method for exempting from formwork |
CN111749475A (en) * | 2020-07-17 | 2020-10-09 | 中铁二十二局集团第五工程有限公司 | Autoclaved fly ash brick masonry arrangement method and masonry arrangement system |
Also Published As
Publication number | Publication date |
---|---|
CN105604211B (en) | 2017-11-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102116061B (en) | Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure | |
CN104234271B (en) | A kind of self-insulating light wallboard system and installation method | |
CN101858142B (en) | Construction method for preventing vertical cracking between main structure and filled wall | |
CN104358341A (en) | Building brickwork and masonry construction method of building brickwork | |
CN104499498B (en) | A kind of construction method of mass concrete building | |
CN105604211A (en) | Anti-crack construction method for joint of filling wall and frame girder | |
CN104389358B (en) | A kind of fire hydrant box back side body of wall and construction method thereof | |
KR100610556B1 (en) | System and method of making hybrid-precasting concrete lining in the tunnel | |
CN110306671B (en) | Construction method of multi-arch closed structure | |
CN210263490U (en) | Assembled wall that possesses adjustable extending structure | |
CN204510813U (en) | L-type cladding panel structure under a kind of novel frame Liang Liang | |
CN206625437U (en) | A kind of building block water proof structure | |
CN102767284B (en) | Semi-prefabricating construction process for concrete thin-wall lower return eave | |
CN109505422B (en) | Reinforcing method for ancient building wall | |
CN213268513U (en) | Outer wall structure | |
CN207878303U (en) | Cement concrete slab and bright culvert bridging arrangement | |
CN106245828A (en) | The method of construction of heat insulation integrated body of wall | |
CN208235783U (en) | Composite fire-proof external thermal insulation block insulation wall system | |
CN102888906B (en) | A kind of mosaic assembled wall and construction method thereof | |
CN206157957U (en) | Body structure stalk body mortar module and wall body of pouring into a mould with wall body module | |
CN110748034A (en) | Hollow wall construction process | |
CN108625609A (en) | A kind of masonry perps grouting energy-saving environmental protection device | |
CN203320499U (en) | Mortar plastering anti-cracking structure of irrigation channel | |
CN211736198U (en) | Concrete terrace | |
CN111155664B (en) | Crack control construction method for aerated concrete block filler wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |