CN105604211A - Anti-crack construction method for joint of filling wall and frame girder - Google Patents

Anti-crack construction method for joint of filling wall and frame girder Download PDF

Info

Publication number
CN105604211A
CN105604211A CN201610002462.6A CN201610002462A CN105604211A CN 105604211 A CN105604211 A CN 105604211A CN 201610002462 A CN201610002462 A CN 201610002462A CN 105604211 A CN105604211 A CN 105604211A
Authority
CN
China
Prior art keywords
cement
cement mortar
vierendeel girder
construction method
gap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610002462.6A
Other languages
Chinese (zh)
Other versions
CN105604211B (en
Inventor
陈宏波
金士元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGBO ZHONGZHOU BUILDING ENGINEERING Co Ltd
Original Assignee
NINGBO ZHONGZHOU BUILDING ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGBO ZHONGZHOU BUILDING ENGINEERING Co Ltd filed Critical NINGBO ZHONGZHOU BUILDING ENGINEERING Co Ltd
Priority to CN201610002462.6A priority Critical patent/CN105604211B/en
Publication of CN105604211A publication Critical patent/CN105604211A/en
Application granted granted Critical
Publication of CN105604211B publication Critical patent/CN105604211B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members

Abstract

The invention discloses an anti-crack construction method for the joint of a filling wall and a frame girder. The method has the advantages that firstly a gap between the frame girder and the upper edge of a brick wall forms a grouting pore channel, and pure cement paste is subjected to double-pressure injection for the second time after M20 cement mortar injected for the first time is initially solidified, so that caves are filled and cracks can be prevented; secondly two through long steel bars are arranged in each of third and second mortar joints in the bottom of the girder and the gap between the frame girder and the upper edge of the brick wall, the two ends of each steel bar are implanted in a column body by more than 100mm, and three supporting lines are formed, so that the temperature stresses of the frame girder and the brick wall can be effectively born and the cracks generated due to the temperature deformation are prevented, wherein the M20 cement mortar adopts 32.2 ordinary Portland cement, and a mass ratio of cement to medium sand to water is 1 to 2.99 to 0.40; and an expansion agent accounting for 9% by mass of the cement is doped, so that the cement mortar has relatively high strength, the temperature stress of the frame girder can be born after the cement mortar matches with the steel bars, and the cracks generated due to the temperature deformation can be effectively prevented.

Description

The anticracking construction method of infilled wall and Vierendeel girder junction
Technical field
The present invention relates to a kind of infilled wall construction method, especially relate to the anticracking construction method of a kind of infilled wall and Vierendeel girder junction.
Background technology
Building in use, due to the impact of the various factors such as drying shrinkage, temperature of sedimentation, masonry and the mortar joint of ground, causes metope cracking. Wherein, the crack that the impact of temperature causes is modal in body of wall, and the common junction with different materials, this crack, as the horizontal fracture of Vierendeel girder and infilled wall junction. General material has the performance of expanding with heat and contract with cold, building structure causes that because environment temperature changes the distortion of expanding with heat and contract with cold is called temperature deformation, as fruit structure is under no restraint, can Free Transform in the time of variations in temperature, structure can not produce additional stress so, also be that structure suffers restraints can not Free Transform time, can in structure, produce additional stress and also claim temperature stress. Cause the flexible of structure by temperature stress, because the coefficient of expansion of different materials is different, cause producing the crack of temperature, thermal cracking is the main cause that causes body of wall early crack. In order to reduce the horizontal fracture of Vierendeel girder and infilled wall junction, we need to improve the construction of infilled wall, avoid the generation in the crack of the temperature of body of wall as far as possible.
Summary of the invention
Technical problem to be solved by this invention is to provide the anticracking construction method of a kind of infilled wall and Vierendeel girder junction, can reduce the generation in the crack of the temperature of infilled wall and Vierendeel girder junction.
The present invention solves the problems of the technologies described above adopted technical scheme: the anticracking construction method of a kind of infilled wall and Vierendeel girder junction, it is characterized in that, and specifically comprise the following steps:
(1) unwrapping wire; According to Design Requirement Drawing and orientation axis, infilled wall wall body central axis pilot measurement, on base surface or flooring, is then pressed to wall body central axis, eject each wall sideline;
(2) pendulum brick sample; Build mode according to drawing and the selected suitable group of code requirement, at base surface or flooring unwrapping wire position examination pendulum brick sample;
(3) vertical marked rod; From starting reserved 20 ~ 30mm gap at the bottom of beam, mark the thickness of every skin brick and mortar joint at marked rod according to Design Requirement Drawing;
(4) levelling; Before building a wall, according to the absolute altitude of marked rod, a minimum skin height completes by levelling on base surface or flooring while not being inconsistent the modulus of brick;
(5) paving ash is laid bricks; Infilled wall respectively arranges two elongated reinforcing bars while building by laying bricks or stones to Vierendeel girder Di tri-roads and second mortar joint, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm; Adopt flat block from last skin brick at the bottom of Vierendeel girder, the height in the gap between at the bottom of brick good rear upper edge and Vierendeel girder is 20 ~ 30mm, two elongated reinforcing bars are set in gap, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm, the cement mortar edge sealing that is 1:2 with the thick ratio of mud of 20mm on both sides, gap, and in Ge Kaiyi hole, two ends, gap; Then maintenance 8 ~ 12 days;
(6) duct slip casting; Slip casting for the first time adopts M20 cement mortar, and grouting pressure is 0.3 ~ 0.5MPa; After the M20 cement mortar initial set of injecting for the first time, carry out neat slurry for the second time and inject, grouting pressure is 0.6 ~ 1.2MPa;
(7) maintenance, water seasoning 12 ~ 15 days after duct slip casting completes.
In step (4) levelling, cement mortar screeding when a minimum skin height is no more than 25mm, otherwise with the levelling of C20 pea gravel concreten.
Compared with prior art, the invention has the advantages that: be first that the space between edge builds up slip casting duct on frame girder and brick wall, and after the M20 cement mortar initial set of injecting for the first time, carry out neat slurry multiplication of voltage for the second time and inject, well filled slump, can prevent the appearance in crack; Secondly on frame girder Di tri-roads and second mortar joint and frame girder and brick wall, the space between edge is all provided with two elongated reinforcing bars, and frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm, form three road Support Level, the temperature stress that can effectively bear frame girder and build a wall, prevents that temperature deformation from producing crack.
As preferably, described M20 cement mortar adopts 32.2 Portland cements, cement in every part of M20 cement mortar: medium sand: the mass ratio of water is 1:2.99:0.40, and in described M20 cement mortar doped with the swelling agent of cement quality 9%. There is higher intensity, coordinate the temperature stress that can sustain frame girder with reinforcing bar, effectively prevent that temperature deformation from producing crack.
As preferably, the ratio of mud of described neat slurry is 0.4 ~ 0.5.
As preferably, neat slurry injects the condition that stops slip casting and is for the second time: neat slurry overflows from aperture, or grouting pressure exceedes 1.2Mpa, or neat slurry injection rate exceedes 20% of duct, gap volume.
As preferably, in step (3), the height of reserving gaps is 25mm.
As preferably, described in step (5), reinforcing bar is Φ 6 reinforcing bars.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is described in further detail.
This preferred embodiment is the anticracking construction method of a kind of infilled wall and Vierendeel girder junction, specifically comprises the following steps:
(1) unwrapping wire; According to Design Requirement Drawing and orientation axis, infilled wall wall body central axis pilot measurement, on base surface or flooring, is then pressed to wall body central axis, eject each wall sideline, mark door-window opening position.
(2) pendulum brick sample; Build mode according to drawing and the selected suitable group of code requirement, at base surface or flooring unwrapping wire position examination pendulum brick sample; Make door and window buttress meet the modulus of brick by adjusting perps as far as possible, cut brick quantity to reduce, and ensure brick and brickwork joint marshalling, even, to improve lay bricks efficiency and the quality of brick masonry structures; Wherein, the modulus of brick is generally 60mm.
(3) vertical marked rod; From starting reserved 20 ~ 30mm gap at the bottom of beam, mark the thickness of every skin brick and mortar joint at marked rod according to Design Requirement Drawing; The height of reserving gaps is preferably 25mm.
(4) levelling; Before building a wall, according to the absolute altitude of marked rod, a minimum skin height completes by levelling on base surface or flooring while not being inconsistent the modulus of brick; Cement mortar screeding when a minimum skin height is no more than 25mm, otherwise with the levelling of C20 pea gravel concreten. It is can ensure at the bottom of beam with the clearance control of top one skin brick face, at 20 ~ 30mm, can to obtain desirable slip casting condition that levelling is put into vertical marked rod by this construction method, prevents that thermal cracking from producing.
(5) paving ash is laid bricks; Adopt 31 building methods, build full of mortar by laying bricks or stones, smooth vertical and horizontal; Infilled wall respectively arranges two elongated Φ 6(diameter 6mm while building by laying bricks or stones to Vierendeel girder Di tri-roads and second mortar joint) reinforcing bar, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm; Adopt flat block from last skin brick at the bottom of Vierendeel girder, the height in the gap between at the bottom of brick good rear upper edge and Vierendeel girder is 20 ~ 30mm, two elongated Φ 6 reinforcing bars are set in gap, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm, the cement mortar edge sealing that is 1:2 with the thick ratio of mud of 20mm on both sides, gap, and in Ge Kaiyi hole, two ends, gap; Then maintenance 8 ~ 12 days, is generally 10 days; Wherein, a hole is injected hole, and another hole is venthole, and preferably open in beam bottom in hole, the long 20mm in aperture, high 5mm.
(6) duct slip casting; Slip casting for the first time adopts M20 cement mortar, grouting pressure is 0.3 ~ 0.5Mpa, described M20 cement mortar adopts 32.2 Portland cements, cement in every part of M20 cement mortar: medium sand: the mass ratio of water is 1:2.99:0.40, and in described M20 cement mortar doped with the swelling agent of cement quality 9%; After the M20 cement mortar initial set of injecting for the first time, carrying out neat slurry for the second time injects, grouting pressure is 0.6 ~ 1.2Mpa, the ratio of mud of neat slurry is also that the mass ratio of water and cement is 0.4 ~ 0.5, the condition that neat slurry injection for the second time stops slip casting is: neat slurry overflows from aperture, or grouting pressure exceedes 1.2Mpa, or neat slurry injection rate exceedes 20% of duct, gap volume.
(7) maintenance; After duct slip casting completes, water seasoning 12 ~ 15 days, is generally 14 days.

Claims (7)

1. an anticracking construction method for infilled wall and Vierendeel girder junction, is characterized in that, specifically comprises the following steps:
(1) unwrapping wire; According to Design Requirement Drawing and orientation axis, infilled wall wall body central axis pilot measurement, on base surface or flooring, is then pressed to wall body central axis, eject each wall sideline;
(2) pendulum brick sample; Build mode according to drawing and the selected suitable group of code requirement, at base surface or flooring unwrapping wire position examination pendulum brick sample;
(3) vertical marked rod; From starting reserved 20 ~ 30mm gap at the bottom of beam, mark the thickness of every skin brick and mortar joint at marked rod according to Design Requirement Drawing;
(4) levelling; Before building a wall, according to the absolute altitude of marked rod, a minimum skin height completes by levelling on base surface or flooring while not being inconsistent the modulus of brick;
(5) paving ash is laid bricks; Infilled wall respectively arranges two elongated reinforcing bars while building by laying bricks or stones to Vierendeel girder Di tri-roads and second mortar joint, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm; Adopt flat block from last skin brick at the bottom of Vierendeel girder, the height in the gap between at the bottom of brick good rear upper edge and Vierendeel girder is 20 ~ 30mm, two elongated reinforcing bars are set in gap, frame column is implanted at reinforcing bar two ends or constructional column is greater than 100mm, the cement mortar edge sealing that is 1:2 with the thick ratio of mud of 20mm on both sides, gap, and in Ge Kaiyi hole, two ends, gap; Then maintenance 8 ~ 12 days;
(6) duct slip casting; Slip casting for the first time adopts M20 cement mortar, and grouting pressure is 0.3 ~ 0.5MPa; After the M20 cement mortar initial set of injecting for the first time, carry out neat slurry for the second time and inject, grouting pressure is 0.6 ~ 1.2MPa;
(7) maintenance, water seasoning 12 ~ 15 days after duct slip casting completes.
2. the anticracking construction method of infilled wall according to claim 1 and Vierendeel girder junction, is characterized in that: in step (4) levelling, and cement mortar screeding when a minimum skin height is no more than 25mm, otherwise with the levelling of C20 pea gravel concreten.
3. the anticracking construction method of infilled wall according to claim 1 and Vierendeel girder junction, it is characterized in that: described M20 cement mortar adopts 32.2 Portland cements, cement in every part of M20 cement mortar: medium sand: the mass ratio of water is 1:2.99:0.40, and in described M20 cement mortar doped with the swelling agent of cement quality 9%.
4. the anticracking construction method of infilled wall according to claim 3 and Vierendeel girder junction, is characterized in that: the ratio of mud of described neat slurry is 0.4 ~ 0.5.
5. the anticracking construction method of infilled wall according to claim 4 and Vierendeel girder junction, it is characterized in that: the condition that neat slurry injection for the second time stops slip casting is: neat slurry overflows from aperture, or grouting pressure exceedes 1.2Mpa, or neat slurry injection rate exceedes 20% of duct, gap volume.
6. the anticracking construction method of infilled wall according to claim 1 and Vierendeel girder junction, is characterized in that: in step (3), the height of reserving gaps is 25mm.
7. the anticracking construction method of infilled wall according to claim 1 and Vierendeel girder junction, is characterized in that: described in step (5), reinforcing bar is Φ 6 reinforcing bars.
CN201610002462.6A 2016-01-06 2016-01-06 Fill wall and the anticracking construction method of Vierendeel girder junction Active CN105604211B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610002462.6A CN105604211B (en) 2016-01-06 2016-01-06 Fill wall and the anticracking construction method of Vierendeel girder junction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610002462.6A CN105604211B (en) 2016-01-06 2016-01-06 Fill wall and the anticracking construction method of Vierendeel girder junction

Publications (2)

Publication Number Publication Date
CN105604211A true CN105604211A (en) 2016-05-25
CN105604211B CN105604211B (en) 2017-11-28

Family

ID=55984511

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610002462.6A Active CN105604211B (en) 2016-01-06 2016-01-06 Fill wall and the anticracking construction method of Vierendeel girder junction

Country Status (1)

Country Link
CN (1) CN105604211B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108547450A (en) * 2018-04-25 2018-09-18 中建八局第三建设有限公司 A kind of self-insulating brick wall construction method for exempting from formwork
CN111749475A (en) * 2020-07-17 2020-10-09 中铁二十二局集团第五工程有限公司 Autoclaved fly ash brick masonry arrangement method and masonry arrangement system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182316A (en) * 2011-04-11 2011-09-14 山东送变电工程公司 Building method for controlling temperature cracks of masonry
CN102251670A (en) * 2011-06-01 2011-11-23 重庆建工第三建设有限责任公司 Construction process for self-heat-insulation system of autoclaved aerated concrete block wall
CN102808513A (en) * 2012-07-05 2012-12-05 江苏武进建筑安装工程有限公司 Crack controlling construction method for lightweight wall
CN102877652A (en) * 2012-10-19 2013-01-16 厦门特房建设工程集团有限公司 Construction method for post-injection cement mortar masonry brickwork
CN103266767A (en) * 2013-05-27 2013-08-28 中国航天建设集团有限公司 Construction method for preventing and treating cracks between concrete structure and filler wall

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182316A (en) * 2011-04-11 2011-09-14 山东送变电工程公司 Building method for controlling temperature cracks of masonry
CN102251670A (en) * 2011-06-01 2011-11-23 重庆建工第三建设有限责任公司 Construction process for self-heat-insulation system of autoclaved aerated concrete block wall
CN102808513A (en) * 2012-07-05 2012-12-05 江苏武进建筑安装工程有限公司 Crack controlling construction method for lightweight wall
CN102877652A (en) * 2012-10-19 2013-01-16 厦门特房建设工程集团有限公司 Construction method for post-injection cement mortar masonry brickwork
CN103266767A (en) * 2013-05-27 2013-08-28 中国航天建设集团有限公司 Construction method for preventing and treating cracks between concrete structure and filler wall

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108547450A (en) * 2018-04-25 2018-09-18 中建八局第三建设有限公司 A kind of self-insulating brick wall construction method for exempting from formwork
CN111749475A (en) * 2020-07-17 2020-10-09 中铁二十二局集团第五工程有限公司 Autoclaved fly ash brick masonry arrangement method and masonry arrangement system

Also Published As

Publication number Publication date
CN105604211B (en) 2017-11-28

Similar Documents

Publication Publication Date Title
CN102116061B (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN104234271B (en) A kind of self-insulating light wallboard system and installation method
CN101858142B (en) Construction method for preventing vertical cracking between main structure and filled wall
CN104358341A (en) Building brickwork and masonry construction method of building brickwork
CN104499498B (en) A kind of construction method of mass concrete building
CN105604211A (en) Anti-crack construction method for joint of filling wall and frame girder
CN104389358B (en) A kind of fire hydrant box back side body of wall and construction method thereof
KR100610556B1 (en) System and method of making hybrid-precasting concrete lining in the tunnel
CN110306671B (en) Construction method of multi-arch closed structure
CN210263490U (en) Assembled wall that possesses adjustable extending structure
CN204510813U (en) L-type cladding panel structure under a kind of novel frame Liang Liang
CN206625437U (en) A kind of building block water proof structure
CN102767284B (en) Semi-prefabricating construction process for concrete thin-wall lower return eave
CN109505422B (en) Reinforcing method for ancient building wall
CN213268513U (en) Outer wall structure
CN207878303U (en) Cement concrete slab and bright culvert bridging arrangement
CN106245828A (en) The method of construction of heat insulation integrated body of wall
CN208235783U (en) Composite fire-proof external thermal insulation block insulation wall system
CN102888906B (en) A kind of mosaic assembled wall and construction method thereof
CN206157957U (en) Body structure stalk body mortar module and wall body of pouring into a mould with wall body module
CN110748034A (en) Hollow wall construction process
CN108625609A (en) A kind of masonry perps grouting energy-saving environmental protection device
CN203320499U (en) Mortar plastering anti-cracking structure of irrigation channel
CN211736198U (en) Concrete terrace
CN111155664B (en) Crack control construction method for aerated concrete block filler wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant