CN101858142B - Construction method for preventing vertical cracking between main structure and filled wall - Google Patents

Construction method for preventing vertical cracking between main structure and filled wall Download PDF

Info

Publication number
CN101858142B
CN101858142B CN2010102096693A CN201010209669A CN101858142B CN 101858142 B CN101858142 B CN 101858142B CN 2010102096693 A CN2010102096693 A CN 2010102096693A CN 201010209669 A CN201010209669 A CN 201010209669A CN 101858142 B CN101858142 B CN 101858142B
Authority
CN
China
Prior art keywords
filled wall
column
agent structure
main structure
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010102096693A
Other languages
Chinese (zh)
Other versions
CN101858142A (en
Inventor
余建阳
杨慧峰
李克江
应飞禄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd Tianjin Branch
Original Assignee
Zhongtian Construction Group Co Ltd Tianjin Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd Tianjin Branch filed Critical Zhongtian Construction Group Co Ltd Tianjin Branch
Priority to CN2010102096693A priority Critical patent/CN101858142B/en
Publication of CN101858142A publication Critical patent/CN101858142A/en
Application granted granted Critical
Publication of CN101858142B publication Critical patent/CN101858142B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Fencing (AREA)

Abstract

The invention discloses a construction method for preventing vertical cracking between a main structure and a filled wall. After the construction of the main structure is finished, the construction of the filled wall is implemented; when the filled wall is constructed, the side surface of the filled wall in connection with the main structure is made into a zigzag structure; a tension rib in the filled wall penetrates a reserved combination column space to be connected with the main structure at the side surface; a combination column template is supported at the reserved combination column space, and plain concrete is poured and vibrated tightly to form a combination column; and the filled wall and the main structure are connected as a whole through the combination column. The plain concrete combination column is poured between the side surface of the filled wall and the main structure, and the combination column is connected with the main structure through the same material and engaged with the filled wall through the zigzag structure, therefore, the problem of cracking caused by insufficient engaging force between the main concrete structure and the filled wall and the shrinkage of the dissimilar materials of the wall is successfully solved; meanwhile, the combination column can effectively adjust the line snapping size and reduce the loss rate of the building blocks.

Description

Prevent the job practices of vertical cracking between agent structure and the filled wall
Technical field
The present invention relates to a kind of building masonry wall job practices, particularly a kind of job practices that prevents vertical cracking between agent structure and the filled wall.
Background technology
At present, the cracking of wall surface of agent structure and filled wall junction is a common fault, and it is attractive in appearance that it influences metope, and the dispute, the complaint that relate to wall body slit and even seepage are more and more down to lawsuit, have accounted for more than 80% of workmanship complaint.This common quality defect that is ubiquitous has become very directly perceived, the responsive and primary quality specifications that the user passes judgment on construction quality.Although taked multiple strengthening measure at this position at present, the Crack Control resultant effect is not good, and this crack, position is repaired and had repeatability.Therefore formulate serial Prevention Technique measure, become the common problem of paying close attention to of the each side that takes part in building.
Summary of the invention
The present invention provides a kind of job practices that can prevent vertical cracking between agent structure and the filled wall for solving the technical problem that exists in the known technology.
The technical scheme that the present invention takes for the technical problem that exists in the solution known technology is: a kind of job practices that prevents vertical cracking between agent structure and the filled wall; May further comprise the steps: after 1) accomplishing the construction of agent structure; Before the construction filled wall, between filled wall side and agent structure, reserve the column space; 2) construction of completion filled wall; During the construction filled wall, its side that is connected with agent structure is built into horse tooth trough, the tension rib that is provided with in the filled wall connects the column space of passing reservation and is connected with the agent structure of one of which side; 3) install the column template at the place, column space that reserves, build the plain concrete vibration compacting and form column, filled wall and agent structure are linked into an integrated entity through column.
Said plain concrete is the microdilatancy plain concrete.
When said filled wall adopts hollow brick or porous brick to build by laying bricks or stones, the bleed-out silk screen of setting up defences on said horse tooth trough upper berth.
The thickness of said column is identical with the thickness of filled wall, and the length of said column is more than or equal to 100mm.
Advantage and good effect that the present invention has are: between filled wall side and agent structure, build the plain concrete column; Filled wall is connected with agent structure; Agent structure and column all adopt concrete material, have reduced the crack that the difference in shrinkage between the foreign material causes; Column and filled wall effectively are connected through horse tooth trough; Strengthen the snap-in force between the two foreign material bodies of wall greatly; The crack of having reduced effectively between column and the filled wall produces; In sum, the present invention builds the plain concrete column between filled wall side and agent structure, and column is connected with agent structure through same material; Be connected through horse tooth trough and filled wall, successfully solved between main body concrete structure and the filled wall because of the not enough crack problem that contraction causes with the body of wall foreign material of snap-in force between the body of wall; Simultaneously, column is the row's of adjusting brick size effectively, reduces the building block proportion of goods damageds; And simple to operate, compare with maintenance cost and social reputation, with low cost, can produce tangible economic benefit and social benefit.
Description of drawings
Fig. 1 is the structural representation that the present invention implements.
Among the figure: 1, agent structure, 2, column, 3, structural beams, 4, skew brick, 5, filled wall.
The specific embodiment
For further understanding summary of the invention of the present invention, characteristics and effect, the following examples of giving an example now, and conjunction with figs. specifies as follows:
See also Fig. 1, a kind of job practices that prevents vertical cracking between agent structure and the filled wall:
1) after the construction of completion agent structure 1, before construction filled wall 5, between filled wall 5 sides and agent structure 1, reserves the column space;
2) construction of completion filled wall 5; During construction filled wall 5; It is built into horse tooth trough with side that agent structure 1 is connected; Filled wall 5 tops are connected with structural beams 3 through skew brick 4, and the tension rib that is provided with in the filled wall 5 should connect the column space of passing reservation and be connected with the agent structure 1 of its side;
3) install the column template at the place, column space that reserves, build the plain concrete vibration compacting and form column 2, filled wall 5 and agent structure 1 are linked into an integrated entity through column 2.
In order to ensure the anti-seismic performance of filled wall 5, the tension rib in the filled wall 5 still connects at the column position and passes, and must not break off.
The column template is reinforced with screw rod through walls, overlaps pvc pipe on the screw rod through walls, is convenient to form removal, reduces because of the damage of reinforcing template to filled wall.The concrete of building column 2 preferably uses the microdilatancy plain concrete, can further improve the effect that reduces cracking.
Agent structure 1 can be shear wall or structural column.Filled wall 5 can adopt in porous brick, all kinds of hollow brick, concrete small size hollow building block, air-entrained concrete building block, fly ash building block and the shale solid brick etc. any one to build by laying bricks or stones.When filled wall 5 adopted hollow brick or porous brick to build by laying bricks or stones, the gauze wire cloth that need on horse tooth trough, tile in case plain concrete leaks down, guaranteed that column concreting is closely knit.
Above-mentioned column 2 should satisfy the operability of column concrete pouring construction as a kind of structural column, must not be less than 100mm.The length of column 2 can combine to arrange the brick size, and suitably adjustment is to reduce the building block proportion of goods damageds.The thickness of column 2 is identical with the thickness of filled wall 5.
Although combine accompanying drawing that the preferred embodiments of the present invention are described above; But the present invention is not limited to the above-mentioned specific embodiment, and the above-mentioned specific embodiment only is schematically, is not restrictive; Those of ordinary skill in the art is under enlightenment of the present invention; Not breaking away under the scope situation that aim of the present invention and claim protect, can also make a lot of forms, these all belong within protection scope of the present invention.

Claims (4)

1. a job practices that prevents vertical cracking between agent structure and the filled wall is characterized in that, may further comprise the steps:
1) after the construction of completion agent structure, before the construction filled wall, between filled wall side and agent structure, reserves the column space;
2) construction of completion filled wall; During the construction filled wall, its side that is connected with agent structure is built into horse tooth trough, the tension rib that is provided with in the filled wall connects the column space of passing reservation and is connected with the agent structure of one of which side;
3) install the column template at the place, column space that reserves, build the plain concrete vibration compacting and form column, filled wall and agent structure are linked into an integrated entity through column.
2. the job practices that prevents vertical cracking between agent structure and the filled wall according to claim 1 is characterized in that, said plain concrete is the microdilatancy plain concrete.
3. the job practices that prevents vertical cracking between agent structure and the filled wall according to claim 1 and 2 is characterized in that, when said filled wall adopts hollow brick or porous brick to build by laying bricks or stones, and the bleed-out silk screen of setting up defences on said horse tooth trough upper berth.
4. the job practices that prevents vertical cracking between agent structure and the filled wall according to claim 1 is characterized in that, the thickness of said column is identical with the thickness of filled wall, and the length of said column is more than or equal to 100mm.
CN2010102096693A 2010-06-25 2010-06-25 Construction method for preventing vertical cracking between main structure and filled wall Expired - Fee Related CN101858142B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102096693A CN101858142B (en) 2010-06-25 2010-06-25 Construction method for preventing vertical cracking between main structure and filled wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102096693A CN101858142B (en) 2010-06-25 2010-06-25 Construction method for preventing vertical cracking between main structure and filled wall

Publications (2)

Publication Number Publication Date
CN101858142A CN101858142A (en) 2010-10-13
CN101858142B true CN101858142B (en) 2012-01-04

Family

ID=42944280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102096693A Expired - Fee Related CN101858142B (en) 2010-06-25 2010-06-25 Construction method for preventing vertical cracking between main structure and filled wall

Country Status (1)

Country Link
CN (1) CN101858142B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102140842B (en) * 2011-01-07 2013-05-08 清华大学建筑设计研究院有限公司 Industrial construction method for multistory residence system with clamp die frame core wall self-bearing structure
CN102322143A (en) * 2011-06-20 2012-01-18 山东宁建建设集团有限公司 Anti-crack construction method for junction of concrete shear wall and aerated concrete building block
CN103266767B (en) * 2013-05-27 2015-06-10 中国航天建设集团有限公司 Construction method for preventing and treating cracks between concrete structure and filler wall
CN103437562B (en) * 2013-08-20 2016-01-20 钟粤 A kind of building method of hollow wall
CN103615114B (en) * 2013-12-02 2018-03-06 浙江中联建设集团有限公司 Brick setting concrete drawknot anticracking board belt construction engineering method
CN104989100B (en) * 2015-05-25 2017-05-10 中国十七冶集团有限公司 Construction method for crack prevention on connecting portion of masonry wall and concrete wall column
CN105064500B (en) * 2015-07-17 2017-05-17 中如建工集团有限公司 Balcony beam slab inner side filling wall body and main body structure integral casting construction method
CN108457387A (en) * 2017-02-21 2018-08-28 天津市武清区建筑工程总公司 Steel construction and secondary structure transition interface crack resistance construction technology
CN107268810A (en) * 2017-07-04 2017-10-20 山西西建集团有限公司 It is a kind of to prevent from filling the construction method that wall produces crack with concrete wall column joint part
CN107237424A (en) * 2017-07-26 2017-10-10 天津三建建筑工程有限公司 A kind of agent structure and the drawknot construction method of filling wall
CN110439182A (en) * 2019-08-19 2019-11-12 广东永和建设集团有限公司 Three layers of one kind, which is poured, smashes Constructional Col-umn Construction method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2470432Y (en) * 2001-02-23 2002-01-09 景志熙 Board-pillar composite energy-saving wall/board structure
US20050217200A1 (en) * 2004-04-01 2005-10-06 Esche Glen R Modular form for cast-in-place concrete decks federally sponsored research
US20080168728A1 (en) * 2007-01-17 2008-07-17 Edward Scherrer Wall system

Also Published As

Publication number Publication date
CN101858142A (en) 2010-10-13

Similar Documents

Publication Publication Date Title
CN101858142B (en) Construction method for preventing vertical cracking between main structure and filled wall
CN201738463U (en) Vertical connection structure between main body structure and filled wall body
CN103276916B (en) A kind of building method of sealing light weight concrete construction board wall wall hole and filling plate
CN102116092A (en) Method for constructing reinforcing band for compensating contraction of concrete and preventing cracks
CN204676609U (en) The reinforced waterproof construction of a kind of basement bottom plate rear pouring tape
CN206128374U (en) A body structure right angle wall body mortar module and right angle wall body of pouring into a mould with wall body module
CN206956565U (en) A kind of steel box girder bridge hogging moment area pre-stress system
CN204163284U (en) Cracking resistance reinforced mesh
CN101487293A (en) Concrete pouring method for beam-column joints with different strength grades
CN105538820A (en) Plastic-stone modeled reinforcing layer and construction method thereof
CN101302783A (en) Building cast-in-situ roof
CN104674660A (en) Novel hollow plate hinge joint structure and construction method thereof
CN104947846A (en) Assembled integral type frame filling light weight inner wallboard and preparation method thereof
CN205530340U (en) Precast concrete retaining wall block
CN204552085U (en) Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder
CN204163113U (en) A kind of nethike embrane formula ater-casting being applied to basement wall slab
CN105040823A (en) Partition plate and floor beam connecting structure for scissors staircase and construction method of partition plate and floor beam connecting structure
CN204753834U (en) Partition plate of scissors stair and connection structure of floor roof beam
CN206157957U (en) Body structure stalk body mortar module and wall body of pouring into a mould with wall body module
CN207469550U (en) A kind of across wall balcony slab of assembled
CN104652280A (en) One-time continuous forming and pouring method for ultralong post-poured fish ridge wall and ultralong fish ridge wall
CN107268617A (en) Construction technology and device after a kind of anti-float anchor rod
CN202706335U (en) Cushion block of concrete cover
CN202323879U (en) Rock-fill dam for preventing seepage by combining with grouted stone
CN201771081U (en) Built-in core mould of cast-in-situ reinforced concrete anti-floating & positioning combination

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120104

Termination date: 20160625

CF01 Termination of patent right due to non-payment of annual fee