CN204552085U - Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder - Google Patents

Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder Download PDF

Info

Publication number
CN204552085U
CN204552085U CN201520113419.8U CN201520113419U CN204552085U CN 204552085 U CN204552085 U CN 204552085U CN 201520113419 U CN201520113419 U CN 201520113419U CN 204552085 U CN204552085 U CN 204552085U
Authority
CN
China
Prior art keywords
base plate
constructional column
feeding mouth
column template
side plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520113419.8U
Other languages
Chinese (zh)
Inventor
曹振田
蒋成龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201520113419.8U priority Critical patent/CN204552085U/en
Application granted granted Critical
Publication of CN204552085U publication Critical patent/CN204552085U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder, it comprises constructional column template and mould, side constructional column template setting concordant with constructional column top in constructional column template and the constructional column template of opposite side are arranged lower than constructional column top, reserved concrete perfusion hole is surrounded between the constructional column template of opposite side and Vierendeel girder and masonry wall, the feeding mouth base plate that mould comprises haunch place base plate and tilts to be connected with haunch place base plate, right-angled triangle haunched slab base plate side plate is provided with in the both sides of haunch place base plate, the both sides of feeding mouth base plate are provided with feeding mouth side plate, the metope of the masonry wall of haunched slab base plate side plate front end face and reserved concrete perfusion Kong Chu both sides is close to setting, haunched slab base plate and form oblique preformed hole between haunched slab base plate side plate and constructional column.Adopt this structure can ensure constructional column top concrete quality, and hopper Mold Making is simple, can have enough to meet the need use.

Description

Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder
Technical field
The utility model relates to formwork concreting structure, and the utility model particularly relates to formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder.
Background technology
In frame structure building, infilled wall length should add constructional column more than 6 meters of centres, due to working procedure restriction, infilled wall be all main body concrete complete after again row build by laying bricks or stones, then concreting constructional column, by the restriction of locus, makes junction concreting at the bottom of constructional column and Vierendeel girder leave one section of gap, can only to fill out with artificial piecemeal plug or floating with mortar, concrete quality herein be can not be guaranteed.
Summary of the invention
The purpose of this utility model is the deficiency overcoming prior art, provides a kind of and can ensure formwork concreting structure in constructional column top at the bottom of the Vierendeel girder of constructional column top concrete quality.
Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder of the present utility model, it comprises constructional column template and mould, side constructional column template setting concordant with constructional column top in described constructional column template and the constructional column template of opposite side are arranged lower than constructional column top, reserved concrete perfusion hole is surrounded between the constructional column template of opposite side and Vierendeel girder and masonry wall, the feeding mouth base plate that described mould comprises haunch place base plate and tilts to be connected with haunch place base plate, right-angled triangle haunched slab base plate side plate is provided with in the both sides of described haunch place base plate, the both sides of described feeding mouth base plate are provided with feeding mouth side plate, haunched slab base plate side plate rear end and feeding mouth side plate front end are spliced and are linked into an integrated entity, the metope of the masonry wall of described haunched slab base plate side plate front end face and reserved concrete perfusion Kong Chu both sides is close to setting, the constructional column template at base plate lower surface, haunch place and reserving hole place is fixed, haunch place base plate is along inclined direction arranged, haunched slab base plate and form oblique preformed hole between haunched slab base plate side plate and constructional column.
Advantage of the present utility model: constructional column top concrete quality can be ensured, and hopper Mold Making is simple, can have enough to meet the need use.
Accompanying drawing explanation
Fig. 1 is the formwork erecting structure schematic diagram of formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder of the present utility model;
Fig. 2 is the mold use structural representation adopted in the structure shown in Fig. 1;
Fig. 3 is the structural representation of the mould shown in Fig. 2.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in detail.
Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder of the present utility model as shown in drawings, it comprises constructional column template and mould, side constructional column template setting concordant with constructional column top in described constructional column template and the constructional column template 8 of opposite side are arranged lower than constructional column top, reserved concrete perfusion hole is surrounded between the constructional column template 8 of opposite side and Vierendeel girder 7 and masonry wall 5, the feeding mouth base plate 2 that described mould comprises haunch place base plate 1 and tilts to be connected with haunch place base plate 1, right-angled triangle haunched slab base plate side plate 4 is provided with in the both sides of described haunch place base plate 1, the both sides of described feeding mouth base plate 2 are provided with feeding mouth side plate 3, haunched slab base plate side plate 4 rear end and feeding mouth side plate 3 front end are spliced and are linked into an integrated entity, the metope of the masonry wall 5 of described haunched slab base plate side plate front end face and reserved concrete perfusion Kong Chu both sides is close to setting, the constructional column template at base plate 1 lower surface, haunch place and reserving hole place is fixed, haunch place base plate 1 is along inclined direction arranged, haunched slab base plate 1 and form oblique preformed hole between haunched slab base plate side plate 4 and constructional column.
In Fig. 1, constructional column one side template formwork is to structure capital, and the capital that opposite side template is propped up apart from constructional column 6 is preferably 200mm place, reserves concrete perfusion hole.
The mould shown in installation drawing 3 on preformed hole concrete perfusion hole site, haunched slab base plate side plate 4 front end face and reserved concrete perfusion Kong Chu both sides metope are close to, the constructional column template splicing at base plate 1 lower surface, haunch place and reserving hole place, mould is reinforced, as Fig. 2, haunched slab base plate 1 and form preformed hole between haunched slab base plate side plate 4 and constructional column.
Concrete is placed on mould feeding mouth base plate 2, concrete is filled in constructional column from concrete perfusion hole, after being progressively poured into the capital of constructional column 6, oblique preformed hole inner concrete is also built closely knit.
Remove mould after concrete initial set, the concrete protruding constructional column plane is rejected.

Claims (1)

1. formwork concreting structure in constructional column top at the bottom of a Vierendeel girder, it comprises constructional column template and mould, it is characterized in that: the side constructional column template setting concordant with constructional column top in described constructional column template and the constructional column template of opposite side are arranged lower than constructional column top, reserved concrete perfusion hole is surrounded between the constructional column template of opposite side and Vierendeel girder and masonry wall, the feeding mouth base plate that described mould comprises haunch place base plate and tilts to be connected with haunch place base plate, right-angled triangle haunched slab base plate side plate is provided with in the both sides of described haunch place base plate, the both sides of described feeding mouth base plate are provided with feeding mouth side plate, haunched slab base plate side plate rear end and feeding mouth side plate front end are spliced and are linked into an integrated entity, the metope of the masonry wall of described haunched slab base plate side plate front end face and reserved concrete perfusion Kong Chu both sides is close to setting, the constructional column template at base plate lower surface, haunch place and reserving hole place is fixed, haunch place base plate is along inclined direction arranged, haunched slab base plate and form oblique preformed hole between haunched slab base plate side plate and constructional column.
CN201520113419.8U 2015-02-16 2015-02-16 Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder Expired - Fee Related CN204552085U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520113419.8U CN204552085U (en) 2015-02-16 2015-02-16 Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520113419.8U CN204552085U (en) 2015-02-16 2015-02-16 Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder

Publications (1)

Publication Number Publication Date
CN204552085U true CN204552085U (en) 2015-08-12

Family

ID=53827214

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520113419.8U Expired - Fee Related CN204552085U (en) 2015-02-16 2015-02-16 Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder

Country Status (1)

Country Link
CN (1) CN204552085U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284653A (en) * 2016-09-10 2017-01-04 广西建工集团第四建筑工程有限责任公司 The construction method that a kind of balcony construct capital interspaces in advance
CN107217845A (en) * 2017-07-19 2017-09-29 北京城建七建设工程有限公司 Core column concrete pours mouth mold tool and pours a mouthful method for shaping
CN109113338A (en) * 2018-09-13 2019-01-01 中铁十六局集团城市建设发展有限公司 A kind of tool-type mould bases of constructional column top one-piece casting
CN113863663A (en) * 2021-09-14 2021-12-31 中国建筑第八工程局有限公司 Forming template structure for bell mouth of constructional column and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284653A (en) * 2016-09-10 2017-01-04 广西建工集团第四建筑工程有限责任公司 The construction method that a kind of balcony construct capital interspaces in advance
CN106284653B (en) * 2016-09-10 2018-09-21 广西建工集团第四建筑工程有限责任公司 A kind of construction method that balcony construct capital interspaces in advance
CN107217845A (en) * 2017-07-19 2017-09-29 北京城建七建设工程有限公司 Core column concrete pours mouth mold tool and pours a mouthful method for shaping
CN109113338A (en) * 2018-09-13 2019-01-01 中铁十六局集团城市建设发展有限公司 A kind of tool-type mould bases of constructional column top one-piece casting
CN109113338B (en) * 2018-09-13 2024-03-19 中铁十六局集团城市建设发展有限公司 Tool type die carrier for integrally pouring top of constructional column
CN113863663A (en) * 2021-09-14 2021-12-31 中国建筑第八工程局有限公司 Forming template structure for bell mouth of constructional column and construction method thereof

Similar Documents

Publication Publication Date Title
CN103422606B (en) Structural column erecting-free block and construction method
CN207538350U (en) A kind of assembled cantilever stair
CN103469825B (en) The prefabricated water resistant template in ater-casting and mounting method
CN204552085U (en) Formwork concreting structure in constructional column top at the bottom of a kind of Vierendeel girder
CN103195087B (en) Mould support method of foundation pit basement haunch shearing wall
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN206128374U (en) A body structure right angle wall body mortar module and right angle wall body of pouring into a mould with wall body module
CN203129839U (en) Gypsum hollow block internal parting wall hole structure for door and window
CN102535841A (en) Construction technology of prefabricated wall panel
CN204753834U (en) Partition plate of scissors stair and connection structure of floor roof beam
CN108343234B (en) Modification module capable of being used as cast-in-situ ring beam template of hollow block masonry and application thereof
CN203256930U (en) Connection structure for concrete wall body and masonry wall face
CN207582763U (en) Two-way close spelling laminated floor slab connecting joint structure with groove type embedded part
CN207513002U (en) A kind of concrete prefabricated wallboard
CN215519946U (en) Wall body corner constructional column exempts from formwork construction structures
CN215630069U (en) Waterproof integrated prefabricated component for independent basement foundation
CN206581482U (en) A kind of assembled architecture of concrete prefabricated wallboard and its composition
CN208830582U (en) A kind of secondary structure PCization construction masonry
CN107142956A (en) A kind of prefabricated assembled elevator basis
CN208618800U (en) It can be used as the modification module of the cast-in-place ring beam template of hollowed-block masonry
CN205475322U (en) Tongue -and -groove template under multicavity
CN109680719A (en) A kind of jigsaw assembled pipe gallery and construction method
CN104908150A (en) Piping shaft manufacturing formwork and industrialized piping shaft production method
CN206267352U (en) A kind of inclined hole grouting shear wall of L-shaped
CN203891299U (en) Hollow block connecting piece

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150812