CN201738463U CN2010202376219U CN201020237621U CN201738463U CN 201738463 U CN201738463 U CN 201738463U CN 2010202376219 U CN2010202376219 U CN 2010202376219U CN 201020237621 U CN201020237621 U CN 201020237621U CN 201738463 U CN201738463 U CN 201738463U
Authority
CN
China
Prior art keywords
filled wall
column
main body
wall body
agent structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202376219U
Other languages
Chinese (zh)
Inventor
余建阳
杨慧峰
李克江
应飞禄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd Tianjin Branch
Original Assignee
Zhongtian Construction Group Co Ltd Tianjin Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd Tianjin Branch filed Critical Zhongtian Construction Group Co Ltd Tianjin Branch
Priority to CN2010202376219U priority Critical patent/CN201738463U/en
Application granted granted Critical
Publication of CN201738463U publication Critical patent/CN201738463U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a vertical connection structure between a main body structure and a filled wall body. The vertical connection structure is characterized in that the side surface of the filled wall body, connected with the main body structure, is built to be a combed joint; the filled wall body and the main body structure are connected into a whole by a cast-in-situ combining column; and a binding rebar arranged in the filled wall body penetrates through the cast-in-situ combining column and is connected with the main body structure at one side of the cast-in-situ combining column. A plain concrete combining column is cast between the side surface of the filled wall body and the main body structure; the combining column is connected with the main body structure by the same material and occlude-connected with the filled wall body by the combed joint, thus successfully solving the problem of cracks caused by insufficient occluding force between the main body concrete structure and the filled wall body and the shrink of different materials of the wall body; and simultaneously, the combing column can effectively adjust the size of row-bricks and reducing the loss rate of building blocks.

Description

Vertical syndeton between agent structure and the filled wall
Technical field
The utility model relates to a kind of body of wall syndeton, the vertical syndeton between particularly a kind of agent structure and the filled wall.
Background technology
At present, the cracking of wall surface of agent structure and filled wall junction is a common fault, and it is attractive in appearance that it influences metope, and the dispute, the complaint that relate to wall body slit and even seepage are more and more down to lawsuit, have accounted for more than 80% of workmanship complaint.This common quality defect that is ubiquitous has become very directly perceived, the responsive and primary quality specifications that the user passes judgment on construction quality.Although taked multiple strengthening measure at this position at present, the Crack Control resultant effect is not good, and this crack, position is repaired and had repeatability.Therefore formulate serial Prevention Technique measure, become the common problem of paying close attention to of the each side that takes part in building.
The utility model content
The utility model provides vertical syndeton between a kind of agent structure and the filled wall for solving the technical problem that exists in the known technology, and this syndeton can prevent vertical cracking between agent structure and the filled wall.
The technical scheme that the utility model is taked for the technical problem that exists in the solution known technology is: the vertical syndeton between a kind of agent structure and the filled wall, described filled wall is built into horse tooth trough with the side that described agent structure is connected, described filled wall and described agent structure link into an integrated entity by cast-in-place column, and the tension rib perforation that is provided with in the described filled wall is passed described cast-in-place column and is connected with the agent structure of one side.
When described filled wall is brick cavity wall or porous brick wall, on described horse tooth trough, be equipped with the leakproof gauze wire cloth.
The thickness of described column is identical with the thickness of filled wall, and the length of described column is more than or equal to 100mm.
Advantage and the good effect that the utlity model has are: build the plain concrete column between filled wall side and agent structure, filled wall is connected with agent structure, agent structure and column all adopt concrete material, have reduced the crack that the difference in shrinkage between the foreign material causes; Column and filled wall effectively are connected by horse tooth trough, strengthen the snap-in force between the two foreign material bodies of wall greatly, the crack of having reduced effectively between column and the filled wall produces, in sum, the utility model is built the plain concrete column between filled wall side and agent structure, column is connected with agent structure by same material, be connected by horse tooth trough and filled wall, successfully solved between main body concrete structure and the filled wall crack problem not enough because of snap-in force between the body of wall and that the contraction of body of wall foreign material causes; Simultaneously, column is the row's of adjusting brick size effectively, reduces the building block proportion of goods damageds; And simple to operate, compare with maintenance cost and social reputation, with low cost, can produce tangible economic benefit and social benefit.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Among the figure: 1, agent structure, 2, column, 3, structural beams, 4, skew brick, 5, filled wall.
The specific embodiment
For further understanding summary of the invention of the present utility model, characteristics and effect, exemplify following examples now, and conjunction with figs. is described in detail as follows:
See also Fig. 1, vertical syndeton between a kind of agent structure and the filled wall, filled wall 5 is built into horse tooth trough with the side that agent structure 1 is connected, filled wall 5 links into an integrated entity by cast-in-place column 2 with agent structure 1, and the tension rib perforation that is provided with in the filled wall 5 is passed cast-in-place column 2 and is connected with the agent structure 1 of one side.When filled wall is brick cavity wall or porous brick wall, on horse tooth trough, should lay the leakproof gauze wire cloth.The thickness of column is identical with the thickness of filled wall, and the length of column is more than or equal to 100mm.
Job practices of the present utility model:
1) finish the construction of agent structure 1 after, before construction filled wall 5, reservation column space between filled wall 5 sides and agent structure 1;
2) finish the construction of filled wall 5; During construction filled wall 5, it is built into horse tooth trough with side that agent structure 1 is connected, filled wall 5 tops are connected with structural beams 3 by skew brick 4, and the tension rib that is provided with in the filled wall 5 should connect the column space of passing reservation and be connected with the agent structure 1 of its side;
3) install the column template at the place, column space that reserves, build the plain concrete vibration compacting and form column 2, filled wall 5 and agent structure 1 are linked into an integrated entity by column 2.
In order to ensure the anti-seismic performance of filled wall 5, the tension rib in the filled wall 5 still connects at the column position and passes, and must not disconnect.
The column template is reinforced with screw rod through walls, overlaps pvc pipe on the screw rod through walls, is convenient to form removal, reduces because of the damage of reinforcing template to filled wall.The concrete of building column 2 preferably uses the microdilatancy plain concrete, can further improve the effect that reduces cracking.
Agent structure 1 can be shear wall or structural column.Filled wall 5 can adopt in porous brick, all kinds of hollow brick, concrete small size hollow building block, air-entrained concrete building block, fly ash building block and the shale solid brick etc. any one to build by laying bricks or stones.When filled wall 5 adopted hollow brick or porous brick to build by laying bricks or stones, the gauze wire cloth that need tile on horse tooth trough in case plain concrete leaks down, guaranteed that column concreting is closely knit.
Above-mentioned column 2 should satisfy the operability of column concrete pouring construction as a kind of structural column, must not be less than 100mm.The length of column 2 can suitably be adjusted, to reduce the building block proportion of goods damageds in conjunction with row's brick size.The thickness of column 2 is identical with the thickness of filled wall 5.
Although in conjunction with the accompanying drawings preferred embodiment of the present utility model is described above; but the utility model is not limited to the above-mentioned specific embodiment; the above-mentioned specific embodiment only is schematic; be not restrictive; those of ordinary skill in the art is under enlightenment of the present utility model; not breaking away under the scope situation that the utility model aim and claim protect, can also make a lot of forms, these all belong within the protection domain of the present utility model.

Claims (3)

1. the vertical syndeton between agent structure and the filled wall, it is characterized in that, described filled wall is built into horse tooth trough with the side that described agent structure is connected, described filled wall and described agent structure link into an integrated entity by cast-in-place column, and the tension rib perforation that is provided with in the described filled wall is passed described cast-in-place column and is connected with the agent structure of one side.
2. the vertical syndeton between agent structure according to claim 1 and the filled wall is characterized in that, when described filled wall is brick cavity wall or porous brick wall, is equipped with the leakproof gauze wire cloth on described horse tooth trough.
3. the vertical syndeton between agent structure according to claim 1 and the filled wall is characterized in that, the thickness of described column is identical with the thickness of filled wall, and the length of described column is more than or equal to 100mm.
CN2010202376219U 2010-06-25 2010-06-25 Vertical connection structure between main body structure and filled wall body Expired - Fee Related CN201738463U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202376219U CN201738463U (en) 2010-06-25 2010-06-25 Vertical connection structure between main body structure and filled wall body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202376219U CN201738463U (en) 2010-06-25 2010-06-25 Vertical connection structure between main body structure and filled wall body

Publications (1)

Publication Number Publication Date
CN201738463U true CN201738463U (en) 2011-02-09

Family

ID=43553741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202376219U Expired - Fee Related CN201738463U (en) 2010-06-25 2010-06-25 Vertical connection structure between main body structure and filled wall body

Country Status (1)

Country Link
CN (1) CN201738463U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535511A (en) * 2012-01-11 2012-07-04 重庆大学 Grouted rubble and concrete combined gravity retaining wall
CN103669651A (en) * 2013-12-26 2014-03-26 北京工业大学 Infilled wall with build-in cross steel bars and manufacturing method of infilled wall
CN103669652A (en) * 2013-12-26 2014-03-26 北京工业大学 Filled wall with light-material energy-dissipation stripes and production method thereof
CN103912072A (en) * 2013-12-26 2014-07-09 北京工业大学 Filler wall with built-in crossed ladder reinforcing steel bars and manufacture method of filler wall
CN103981978A (en) * 2013-11-01 2014-08-13 桂林永福龙港绿色环保建材有限公司 Inner catch connector capable of effectively preventing vertical cracking of light inner wallboard
CN104405061A (en) * 2014-11-25 2015-03-11 新疆农业大学 Masonry structure with plant stems and manufacturing method thereof
CN104481055A (en) * 2014-12-06 2015-04-01 塔里木大学 Dense-rib column anti-seismic ecological wall body system for villages and small town dwelling house
CN106245807A (en) * 2016-08-25 2016-12-21 中国十七冶集团有限公司 There is the body of wall in crack in a kind of junction being avoided that with beams of concrete

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535511A (en) * 2012-01-11 2012-07-04 重庆大学 Grouted rubble and concrete combined gravity retaining wall
CN103981978A (en) * 2013-11-01 2014-08-13 桂林永福龙港绿色环保建材有限公司 Inner catch connector capable of effectively preventing vertical cracking of light inner wallboard
CN103669651A (en) * 2013-12-26 2014-03-26 北京工业大学 Infilled wall with build-in cross steel bars and manufacturing method of infilled wall
CN103669652A (en) * 2013-12-26 2014-03-26 北京工业大学 Filled wall with light-material energy-dissipation stripes and production method thereof
CN103912072A (en) * 2013-12-26 2014-07-09 北京工业大学 Filler wall with built-in crossed ladder reinforcing steel bars and manufacture method of filler wall
CN103669652B (en) * 2013-12-26 2016-08-17 北京工业大学 Filling wall with light material energy dissipation strip and preparation method thereof
CN103912072B (en) * 2013-12-26 2016-11-09 北京工业大学 A kind of built-in ladder lattice reinforcing bar that intersects fills wall and way
CN103669651B (en) * 2013-12-26 2017-01-11 北京工业大学 Infilled wall with build-in cross steel bars and manufacturing method of infilled wall
CN104405061A (en) * 2014-11-25 2015-03-11 新疆农业大学 Masonry structure with plant stems and manufacturing method thereof
CN104481055A (en) * 2014-12-06 2015-04-01 塔里木大学 Dense-rib column anti-seismic ecological wall body system for villages and small town dwelling house
CN106245807A (en) * 2016-08-25 2016-12-21 中国十七冶集团有限公司 There is the body of wall in crack in a kind of junction being avoided that with beams of concrete

Similar Documents

Publication Publication Date Title
CN201738463U (en) Vertical connection structure between main body structure and filled wall body
CN101858142B (en) Construction method for preventing vertical cracking between main structure and filled wall
CN101832026B (en) Construction method of sole plate post-poured strip form bracing system
CN104594210B (en) A kind of concrete prefabricated board and its preparation method and application
CN102900162B (en) Heat-insulation fireproof integral wallboard and preparation method thereof
CN204676609U (en) The reinforced waterproof construction of a kind of basement bottom plate rear pouring tape
CN206956565U (en) A kind of steel box girder bridge hogging moment area pre-stress system
CN206128374U (en) A body structure right angle wall body mortar module and right angle wall body of pouring into a mould with wall body module
CN102116092A (en) Method for constructing reinforcing band for compensating contraction of concrete and preventing cracks
CN104060760B (en) High Rise Building Transfer Floor Structure concrete super large beam construction in layer method
CN104947846A (en) Assembled integral type frame filling light weight inner wallboard and preparation method thereof
CN201531035U (en) Foundation slab late poured band and construction joint steel wire mesh isolating device
CN101793068B (en) Precast spliced concrete slab wall body
CN202865751U (en) Temporary support for sulphur-bonded mortar
CN102409788A (en) Phase change material (PCM) cast-in-place reinforced concrete large-size sandwiched floor and construction method thereof
CN101831971A (en) Concrete shear wall with short piers
CN204163113U (en) A kind of nethike embrane formula ater-casting being applied to basement wall slab
CN207504539U (en) A kind of cable trough with cable protection external member
CN203256930U (en) Connection structure for concrete wall body and masonry wall face
CN203080796U (en) Reinforced concrete sandwich thermal insulating wallboard of prefabricated house
CN201762847U (en) Prefabricated spliced concrete slab wall body
CN206157957U (en) Body structure stalk body mortar module and wall body of pouring into a mould with wall body module
CN104652280A (en) One-time continuous forming and pouring method for ultralong post-poured fish ridge wall and ultralong fish ridge wall
CN101851968A (en) Construction method for preventing outer wall of basement from cracking
CN108018972A (en) Full precast floor slab and laminated floor slab combining structure, making and assembly method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110209