CN108547450A - A kind of self-insulating brick wall construction method for exempting from formwork - Google Patents
A kind of self-insulating brick wall construction method for exempting from formwork Download PDFInfo
- Publication number
- CN108547450A CN108547450A CN201810377222.3A CN201810377222A CN108547450A CN 108547450 A CN108547450 A CN 108547450A CN 201810377222 A CN201810377222 A CN 201810377222A CN 108547450 A CN108547450 A CN 108547450A
- Authority
- CN
- China
- Prior art keywords
- wall
- concrete
- self
- insulation board
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Building Environments (AREA)
- Finishing Walls (AREA)
Abstract
本发明公开了一种免支模的自保温砖墙施工方法,包括如下步骤:浇筑素混凝土翻边、排砖和植筋、砌筑腰梁下方自保温墙体、砌筑腰梁、浇筑腰梁混凝土、砌筑腰梁上方自保温墙体,同时使用U型砖砌筑构造柱外框、对墙体上方进行水平塞顶、粘贴保温板后、进行抹灰罩面施工。保温砖砌筑过程中,对需要粘贴保温板的部位,预留出保温板安装空间,使得保温板安装于冷桥部位后,可以与墙体的外壁面保持平齐,便于后期的墙体粉刷,降低了空鼓、开裂的问题。
The invention discloses a construction method for a self-insulating brick wall free of formwork, comprising the following steps: pouring plain concrete flanging, arranging bricks and planting bars, building a self-insulating wall below a girder, building a girder, pouring a girder Beam concrete, masonry self-insulation wall above the waist beam, and use U-shaped bricks to build the outer frame of the structural column, level the top of the wall, paste the insulation board, and then carry out plastering and overlay construction. During the masonry process of the insulation bricks, the installation space of the insulation board is reserved for the part where the insulation board needs to be pasted, so that after the insulation board is installed on the cold bridge, it can be kept flush with the outer wall of the wall, which is convenient for the later wall painting , reducing the problem of hollowing and cracking.
Description
技术领域technical field
本发明涉及建筑施工技术领域,具体涉及一种免支模的自保温砖墙施工方法。The invention relates to the technical field of building construction, in particular to a formwork-free self-insulating brick wall construction method.
背景技术Background technique
随着我国基础建设的大力发展和绿色设计的全面推广,建筑节能在绿色设计中承担着重要作用。相对传统砌筑用砖而言,自保温烧结砖能有效降低墙体的内部传热,提高墙体的保温性能。With the vigorous development of my country's infrastructure and the comprehensive promotion of green design, building energy conservation plays an important role in green design. Compared with traditional masonry bricks, self-insulating sintered bricks can effectively reduce the internal heat transfer of the wall and improve the thermal insulation performance of the wall.
传统保温砖砌筑过程中,施工顺序:放线→植筋→立皮数杆排砖→腰梁施工→腰梁以上墙体砌筑→构造柱施工→水平塞顶→保温板粘贴→抹灰罩面。传统腰梁、构造柱施工都需要支模后浇筑混凝土,施工工序繁杂,工期进展慢,成型效果差,开锯出的小木方、小模板不符合绿色施工的要求。同时,在冷桥部位粘贴保温板后,保温板凸出墙体立面,导致墙体粉刷层过厚,施工质量难以控制,容易造成空鼓、开裂等现象。In the process of traditional thermal insulation brick masonry, the construction sequence: laying out → planting reinforcement → row of bricks with vertical bars → waist beam construction → wall masonry above the waist beam → structural column construction → horizontal plug top → insulation board pasting → plastering overlay. The construction of traditional waist beams and structural columns requires the pouring of concrete after setting up the formwork. The construction process is complicated, the progress of the construction period is slow, and the forming effect is poor. The small wooden squares and small formworks produced by sawing do not meet the requirements of green construction. At the same time, after the insulation board is pasted on the cold bridge, the insulation board protrudes from the facade of the wall, resulting in an excessively thick wall plaster layer, difficult to control the construction quality, and easy to cause hollowing, cracking and other phenomena.
发明内容Contents of the invention
本发明的目的在于提供一种免支模的自保温砖墙施工方法,以解决上述背景技术中提及的传统保温砖砌筑施工方式中,需对腰梁、构造柱等冷桥部位支模浇筑混凝土后,再进行保温板的粘贴,保温板凸出墙体立面,导致墙体粉刷层过厚,施工质量难以控制,容易造成空鼓、开裂的问题。The purpose of the present invention is to provide a self-insulation brick wall construction method free of formwork, to solve the traditional insulation brick masonry construction method mentioned in the above-mentioned background technology, it is necessary to formwork on cold bridge positions such as waist beams and structural columns After the concrete is poured, the insulation board is pasted. The insulation board protrudes from the wall elevation, resulting in an excessively thick wall plaster layer, difficult to control the construction quality, and easy to cause problems such as hollowing and cracking.
为实现上述目的,本发明提供如下技术方案:一种免支模的自保温砖墙施工方法,包括如下步骤:In order to achieve the above object, the present invention provides the following technical solutions: a formwork-free self-insulating brick wall construction method, comprising the following steps:
(1)依据图纸弹好建筑物的主要轴线及砌体的砌筑控制边线,并按规范要求,在设置构造柱的位置植筋;(1) Play the main axis of the building and the masonry control sideline of the masonry according to the drawings, and plant reinforcement at the position where the structural column is set according to the requirements of the specification;
(2)在外墙或者有防水要求的位置,浇筑高为150mm-250mm的素混凝土翻边,所述素混凝土翻边的宽度为墙体厚度减去保温板的厚度,且所述素混凝土翻边的内壁与墙体内壁面齐平;(2) On the outer wall or where there is a waterproof requirement, pour a plain concrete flanging with a height of 150mm-250mm. The width of the plain concrete flanging is the thickness of the wall minus the thickness of the insulation board, and the plain concrete flanging The inner wall of the wall is flush with the inner wall surface of the wall;
(3)使用皮数杆对墙体进行排砖,并对腰梁位置进行植筋;(3) Arrange bricks on the wall with a number rod, and plant reinforcement at the position of the waist beam;
(4)腰梁下方自保温墙体开始砌筑;(4) Masonry starts from the insulation wall below the waist beam;
(5)腰梁处采用U型砖砌筑并排布钢筋,且U型砖的宽度为墙体厚度减去保温板的厚度,且所述U型砖的内壁与墙体内壁面齐平;(5) The waist beam is built with U-shaped bricks and the steel bars are arranged, and the width of the U-shaped bricks is the thickness of the wall minus the thickness of the insulation board, and the inner wall of the U-shaped bricks is flush with the inner wall of the wall;
(6)浇筑腰梁混凝土;(6) Pouring waist beam concrete;
(7)腰梁混凝土强度达到要求后,开始砌筑腰梁上方自保温墙体,同时使用U型砖砌筑构造柱外框;(7) After the concrete strength of the waist beam meets the requirements, start to build the self-insulation wall above the waist beam, and use U-shaped bricks to build the outer frame of the structural column;
(8)墙体砌筑完成后,浇筑构造柱混凝土,所述构造柱混凝土的宽度为墙体厚度减去保温板的厚度,且所述构造柱混凝土的内壁与墙体内壁面齐平;(8) After the wall masonry is completed, pour the structural column concrete. The width of the structural column concrete is the thickness of the wall minus the thickness of the insulation board, and the inner wall of the structural column concrete is flush with the inner wall surface of the wall;
(9)经14天后,对墙体上方进行水平塞顶;(9) After 14 days, carry out horizontal plugging on the top of the wall;
(10)粘贴保温板后,所粘贴的保温板外壁面均与墙体外壁面齐平;(10) After the insulation board is pasted, the outer wall of the pasted insulation board is flush with the outer wall of the wall;
(11)进行抹灰罩面施工。(11) Carry out plastering and overlay construction.
进一步地,所述素混凝土翻边采用与楼板混凝土同等级的混凝土浇筑施工。Further, the plain concrete flanging is constructed by pouring concrete of the same grade as the floor concrete.
进一步地,所述保温板通过锚固件与墙体固连。Further, the insulation board is fixedly connected to the wall through anchors.
进一步地,所述墙体采用煤矸石砖砌筑。Further, the wall is built with gangue bricks.
与现有技术相比,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:
(1)保温砖砌筑过程中,对需要粘贴保温板的部位,预留出保温板安装空间,使得保温板安装于冷桥部位后,可以与墙体的外壁面保持平齐,便于后期的墙体粉刷,降低了空鼓、开裂的问题;(1) During the masonry process of insulation bricks, reserve the installation space for the insulation board at the part where the insulation board needs to be pasted, so that after the insulation board is installed on the cold bridge, it can be kept flush with the outer wall of the wall, which is convenient for later installation. The wall is painted to reduce the problems of hollowing and cracking;
(2) 本发明大大提高了成型质量,提高了工作效率,缩短了施工工期;同时,也降低了板材和木材的消耗,全面实现了绿色施工,并带来极大的经济效益。(2) The present invention greatly improves the molding quality, improves work efficiency, and shortens the construction period; at the same time, it also reduces the consumption of plates and wood, fully realizes green construction, and brings great economic benefits.
附图说明Description of drawings
图1为本发明未粘贴保温板的结构示意图;Fig. 1 is the structural representation of not pasting insulation board of the present invention;
图2为AA面剖视图;Figure 2 is a cross-sectional view of plane AA;
图3为节点1的放大示意图;Figure 3 is an enlarged schematic diagram of node 1;
图4为本发明粘贴保温板的结构示意图;Fig. 4 is the structural representation of sticking insulation board of the present invention;
图5为BB面剖视图;Figure 5 is a sectional view of the BB plane;
图中:1-构造柱,2-水平塞顶,3-墙体,4-腰梁,5-素混凝土翻边,6-保温板,7-U型砖。In the figure: 1-structural column, 2-horizontal plug top, 3-wall, 4-waist beam, 5-plain concrete flanging, 6-insulation board, 7-U-shaped brick.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述。显然,所描述的实施例仅仅是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the drawings in the embodiments of the present invention. Apparently, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
实施例1:请参阅图1-图5,本发明提供一种技术方案:一种免支模的自保温砖墙施工方法,包括如下步骤:Embodiment 1: Please refer to Fig. 1-Fig. 5, the present invention provides a kind of technical solution: a kind of formwork-free self-insulation brick wall construction method, comprises the following steps:
(1)依据图纸弹好建筑物的主要轴线及砌体的砌筑控制边线,并按规范要求,在设置构造柱1的位置植筋;(1) Play the main axis of the building and the masonry control sideline of the masonry according to the drawings, and plant reinforcement at the position where the structural column 1 is set according to the requirements of the specification;
(2)在外墙或者有防水要求的位置,浇筑高为200mm的与楼板混凝土同等级的素混凝土翻边5,所述素混凝土翻边5的宽度为墙体3厚度减去保温板6的厚度,且所述素混凝土翻边5的内壁与墙体3内壁面齐平;(2) On the external wall or where there is a waterproof requirement, pour plain concrete flanging 5 with a height of 200 mm and the same level as the floor concrete. The width of the plain concrete flanging 5 is the thickness of the wall 3 minus the thickness of the insulation board 6 , and the inner wall of the plain concrete flange 5 is flush with the inner wall of the wall 3;
(3)使用皮数杆对墙体3进行排砖,并对腰梁4位置进行植筋;(3) Arrange the bricks on the wall 3 with a number rod, and plant reinforcements at the position of the waist beam 4;
(4)腰梁4下方自保温墙体3开始砌筑;(4) The lower part of the waist beam 4 is built from the insulation wall 3;
(5)腰梁4处采用U型砖7砌筑并排布钢筋,且U型砖7的宽度为墙体3厚度减去保温板6的厚度,且所述U型砖7的内壁与墙体3内壁面齐平;(5) U-shaped bricks 7 are used to build the waist beam 4 and the steel bars are arranged, and the width of the U-shaped brick 7 is the thickness of the wall 3 minus the thickness of the insulation board 6, and the inner wall of the U-shaped brick 7 and the wall 3 The inner wall is flush;
(6)浇筑腰梁混凝土;(6) Pouring waist beam concrete;
(7)腰梁混凝土强度达到要求后,开始砌筑腰梁4上方自保温墙体,同时使用U型砖7砌筑构造柱1外框;(7) After the concrete strength of the waist beam meets the requirements, start to build the self-insulation wall above the waist beam 4, and use U-shaped bricks 7 to build the outer frame of the structural column 1;
(8)墙体3砌筑完成后,浇筑构造柱混凝土,所述构造柱混凝土的宽度为墙体3厚度减去保温板6的厚度,且所述构造柱混凝土的内壁与墙体3内壁面齐平;(8) After the masonry of the wall 3 is completed, pour the structural column concrete. The width of the structural column concrete is the thickness of the wall 3 minus the thickness of the insulation board 6, and the inner wall of the structural column concrete and the inner wall surface of the wall 3 flush;
(9)经14天后,对墙体3上方进行水平塞顶2;(9) After 14 days, perform horizontal plugging 2 above the wall 3;
(10)粘贴保温板6后,所粘贴的保温板6外壁面均与墙体3外壁面齐平;(10) After pasting the insulation board 6, the outer wall surface of the pasted insulation board 6 is flush with the outer wall surface of the wall body 3;
(11)进行抹灰罩面施工。(11) Carry out plastering and overlay construction.
所述保温板6通过锚固件与墙体3固连。The insulation board 6 is fixedly connected with the wall body 3 through anchors.
所述墙体3采用煤矸石砖砌筑。The wall body 3 is built with coal gangue bricks.
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下,可对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, Alternatives and modifications, the scope of the present invention is defined by the appended claims and their equivalents.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810377222.3A CN108547450A (en) | 2018-04-25 | 2018-04-25 | A kind of self-insulating brick wall construction method for exempting from formwork |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810377222.3A CN108547450A (en) | 2018-04-25 | 2018-04-25 | A kind of self-insulating brick wall construction method for exempting from formwork |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN108547450A true CN108547450A (en) | 2018-09-18 |
Family
ID=63512421
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810377222.3A Pending CN108547450A (en) | 2018-04-25 | 2018-04-25 | A kind of self-insulating brick wall construction method for exempting from formwork |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108547450A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109253593A (en) * | 2018-09-28 | 2019-01-22 | 广东芬蓝环境科技有限公司 | Drying unit |
| CN110030965A (en) * | 2019-05-22 | 2019-07-19 | 宁波希澈机械科技有限公司 | A kind of automation high-rise building exposed wall facing brick intensity detection machine |
| CN110565839A (en) * | 2019-08-26 | 2019-12-13 | 常州第一建筑集团有限公司 | Construction method for tenon-and-mortise connection of self-insulation wall constructional column |
| CN116950387A (en) * | 2023-09-19 | 2023-10-27 | 上海宝冶集团南京建筑有限公司 | Construction method for reducing weight of main body structure of aluminum formwork climbing frame of high-rise building |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102116061A (en) * | 2009-12-30 | 2011-07-06 | 中铁建工集团有限公司 | Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure |
| CN103883064A (en) * | 2014-02-20 | 2014-06-25 | 顾世章 | Manufacturing and building method of heat preservation block (building plate) for inorganic self thermal insulation wall body |
| CN104612283A (en) * | 2015-02-02 | 2015-05-13 | 西安建筑科技大学 | On-site built reinforcing rib ecological composite wall structure and construction method thereof |
| US20150218805A1 (en) * | 2014-02-04 | 2015-08-06 | Daniel Max Jensen | Modular units for insulating concrete forms |
| CN205242706U (en) * | 2015-12-22 | 2016-05-18 | 中建六局土木工程有限公司 | Cast -in -place constructional column of infilled wall and wall body synchronous construction structure between high -rise outer eaves window |
| CN105604211A (en) * | 2016-01-06 | 2016-05-25 | 宁波中洲建设工程有限公司 | Anti-crack construction method for joint of filling wall and frame girder |
| CN107366385A (en) * | 2017-08-02 | 2017-11-21 | 中国十七冶集团有限公司 | A kind of thermal insulation structure post and its construction method |
-
2018
- 2018-04-25 CN CN201810377222.3A patent/CN108547450A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102116061A (en) * | 2009-12-30 | 2011-07-06 | 中铁建工集团有限公司 | Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure |
| US20150218805A1 (en) * | 2014-02-04 | 2015-08-06 | Daniel Max Jensen | Modular units for insulating concrete forms |
| CN103883064A (en) * | 2014-02-20 | 2014-06-25 | 顾世章 | Manufacturing and building method of heat preservation block (building plate) for inorganic self thermal insulation wall body |
| CN104612283A (en) * | 2015-02-02 | 2015-05-13 | 西安建筑科技大学 | On-site built reinforcing rib ecological composite wall structure and construction method thereof |
| CN205242706U (en) * | 2015-12-22 | 2016-05-18 | 中建六局土木工程有限公司 | Cast -in -place constructional column of infilled wall and wall body synchronous construction structure between high -rise outer eaves window |
| CN105604211A (en) * | 2016-01-06 | 2016-05-25 | 宁波中洲建设工程有限公司 | Anti-crack construction method for joint of filling wall and frame girder |
| CN107366385A (en) * | 2017-08-02 | 2017-11-21 | 中国十七冶集团有限公司 | A kind of thermal insulation structure post and its construction method |
Non-Patent Citations (1)
| Title |
|---|
| 候光等: "《建筑结构工程》", 30 April 2013, 北京:中国铁道出版社 * |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109253593A (en) * | 2018-09-28 | 2019-01-22 | 广东芬蓝环境科技有限公司 | Drying unit |
| CN109253593B (en) * | 2018-09-28 | 2023-11-28 | 广东芬蓝环境科技有限公司 | Drying device |
| CN110030965A (en) * | 2019-05-22 | 2019-07-19 | 宁波希澈机械科技有限公司 | A kind of automation high-rise building exposed wall facing brick intensity detection machine |
| CN110030965B (en) * | 2019-05-22 | 2019-11-19 | 东阳阿语机械科技有限公司 | A kind of automation high-rise building exposed wall facing brick intensity detection machine |
| CN110565839A (en) * | 2019-08-26 | 2019-12-13 | 常州第一建筑集团有限公司 | Construction method for tenon-and-mortise connection of self-insulation wall constructional column |
| CN116950387A (en) * | 2023-09-19 | 2023-10-27 | 上海宝冶集团南京建筑有限公司 | Construction method for reducing weight of main body structure of aluminum formwork climbing frame of high-rise building |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101831985B (en) | Precast concrete wallboard and preparation method thereof | |
| CN101818541B (en) | Precast composite wallboard with door/window holes and manufacturing method thereof | |
| CN103469825B (en) | Post-pouring prefabricated water-resistant formwork and its installation method | |
| CN104790436B (en) | Basement in high rise building top board pouring after settlement advance water stop construction method | |
| CN102643057B (en) | Construction method of EPS (expanded polystyrene) light aggregate concrete thermal insulation building mould | |
| CN103306501B (en) | Energy-saving domestic architecture with cast-in-place industrial gypsum bearing wall and manufacturing method thereof | |
| CN108547450A (en) | A kind of self-insulating brick wall construction method for exempting from formwork | |
| CN103132633A (en) | Permanent shuttering cast-in-place extra light concrete self-insulation composite wall body and construction technology | |
| CN110344535A (en) | A kind of prefabricated assembled combined wall board and construction method realized concealed beam and exempt from formwork | |
| CN215167030U (en) | Cast-in-place glass fiber reinforced concrete superimposed sheet of steel bar truss | |
| CN102535841A (en) | Construction technology of prefabricated wall panel | |
| CN218758102U (en) | Energy-conserving integration assembled shear force wall | |
| CN116104209A (en) | Seepage prevention construction method of window sill groove and groove prefabricated board | |
| CN101666117A (en) | Gypsum-concrete mixed structure energy-conserving residential building and manufacture method | |
| CN207194239U (en) | Lightgage steel joist concrete anticracking fills wall | |
| CN101942867B (en) | Novel thermal insulation structure of building beam column and production method thereof | |
| CN104294962A (en) | Method for manufacturing pre-placed recycled aggregate grouted concrete energy-saving and heat-preservation building block and wall system | |
| CN116220244B (en) | Construction method of thermal insulation exterior wall structure with window sill opening | |
| CN101418602B (en) | In-situ casting construction method of reinforced concrete structural system using phosphogypsum as wall material | |
| CN209099563U (en) | A waterproof and seepage-proof structure for building mold mesh bathroom wall | |
| CN101285331B (en) | Construction method of heat-storing and energy saving block for external insulation of shear wall | |
| CN101603373B (en) | Ceramsite concrete, integral prefabricated ceramsite concrete washroom and production method of ceramsite concrete | |
| CN211397147U (en) | Windowsill coping structure | |
| CN203373872U (en) | Cast-in-place concrete self-warm-keeping wall with dismounting-free outer formworks | |
| CN108394004A (en) | Mixing wallboard of assembled architecture plate and preparation method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180918 |
|
| RJ01 | Rejection of invention patent application after publication |