CN105464668A - Technology for controlling floor heave of soft rock roadway - Google Patents

Technology for controlling floor heave of soft rock roadway Download PDF

Info

Publication number
CN105464668A
CN105464668A CN201610030174.1A CN201610030174A CN105464668A CN 105464668 A CN105464668 A CN 105464668A CN 201610030174 A CN201610030174 A CN 201610030174A CN 105464668 A CN105464668 A CN 105464668A
Authority
CN
China
Prior art keywords
grouting
roadway
concrete
soft rock
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610030174.1A
Other languages
Chinese (zh)
Inventor
李承胜
朱庆文
马齐
张国朋
刘启顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201610030174.1A priority Critical patent/CN105464668A/en
Publication of CN105464668A publication Critical patent/CN105464668A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a technology for controlling a floor heave of a soft rock roadway. Coupling supporting is formed for a bottom plate of the soft rock roadway through multiple supporting methods of grouting cable anchors, inverted arch reinforced concrete ring beams and bottom plate concrete pouring. The technology includes the specific steps that 1, after deformation of surrounding rock of the soft rock roadway is stable, whole-section excavation is conducted on a bottom plate, and the excavation depth is 300 mm larger than the original design size; 2, arc-shaped grooves are excavated in the bottom plate of the roadway every other 2-3 m, the grooves are 1,000 mm far way from the bottom plate in the center of the roadway, and the sizes of the grooves are gradually reduced to 400 mm to the two sides; 3, three grouting anchor cables are driven into each arc-shaped groove, and bottom plate grouting is conducted through the grouting anchor cables; 4, C60 concrete is poured into the arc-shaped grooves, and protective layers with the thickness not smaller than 100 mm are formed; 5, after the grouting anchor cables are pressurized, C40 concrete is poured into the arc-shaped grooves and the bottom plate, and the original design size is achieved. The problem of repeated floor heave deformation and fracture generated after the soft rock roadway is excavated and supported can be effectively solved, repeated maintenance on the soft rock roadway is avoided, and high economic value is achieved.

Description

A kind of Control Technique of Soft Rock Roadway Floor Heave
Technical field
The present invention relates to soft rock roadway support field, particularly relate to a kind of Control Technique of Soft Rock Roadway Floor Heave.
Background technology
The distortion of soft-rock tunnel is one of mining in soft rock mining main harm affecting Safety of Coal Mine Production, and end distension often accounts for more than 3/4ths of Deformation in Soft Rock Tunnel total amount.End distension distortion causes soft-rock tunnel section to reduce, and causes drift closure, affect tunnel and normally use, bring hidden danger to mine safety production time serious.
Country rock squeezing flow, rock expansion, the shearing changing of the relative positions, several mechanism compound action of compaction flexture are formed the end distension of soft-rock tunnel often.The scheme that present stage administers end distension mainly contains by various forms of high strong supportings such as baseboard anchor cable, base plate anchor pole, floor grouting, FLOOR ANCHOR.Many methods often working procedure are complicated and effect is poor, and the end distension of single anchor pole, slip casting often uncontrollable soft-rock tunnel, bring unnecessary trouble also can to repair of laneway process.
As patent 201210472254.4 discloses a kind of simple anchor note technique, this method is poor effect in the end distension of the soft-rock tunnel having ponding or back trickle at roadway floor is administered.Patent 200910030300.3 discloses the method for a kind of base angle anchor note control end distension, and the method only strengthens base angle, but ignores the reinforcing to floor rocks, produces little effect in practical engineering application.
Summary of the invention
The object of the invention is to, a kind of Control Technique of Soft Rock Roadway Floor Heave is provided, effectively can control the end distension of soft-rock tunnel, avoid tunnel constantly to reprocess because of the appearance of end distension phenomenon, ensure safety, the High-efficient Production in colliery, mining in soft rock mining.
Adopting following technical scheme for realizing above object the present invention, specifically comprising the steps:
First: soft-rock tunnel is according to after design size excavation, and base plate is in and opens wide not supporting state, after deformation of the surrounding rock in tunnel speed tends towards stability, every 10 meters is a unit, carry out full face excavation to roadway floor, cutting depth is compared with the dark 300mm of the former design size in tunnel, drift section width 4.5-5m.This process should note the release of pressure from surrounding rock, impels floor rocks crack to reach full growth, and ensures effective diffusion of slurries during slip casting;
Second: the roadway floor excavated, excavate an arcuate furrow, groove apart from the dark 1000mm of terrace at an end, is decremented to 400mm to roadway's sides, ditch groove width 600mm, spacing 2000-3000mm between groove center line and center line in center, tunnel;
3rd: after arcuate furrow digs by design, in arcuate furrow, set three grouting cable anchors, by grouting cable anchor to floor grouting.The cement paste that grouting serous fluid selects 42.5MPa Portland cement to prepare, water/binder ratio 0.6:1, in slip casting process, adds suitable quantity of water glass and controls running pulp amount.Choose the hollow grouting cable anchor of Φ 22mm × 6000mm, improve the stress of roadway floor deep wall rock, improve the resistance to overturning of roadway floor;
4th: by grouting cable anchor to after the slip casting of base plate deep wall rock, by the arched ribs that processes and stirrup colligation at the scene, arched ribs spacing 150mm, every layer 4 side by side, the vertical distance of lower floor's arched ribs distance roadway floor country rock is not less than 100mm, ensures that the exposed parts of grouting cable anchor passes from reinforcing bar hole in process of binding.In arcuate furrow, water C60 concrete, vibrate while water, reinforcing bar wraps up by concrete completely, and reinforcing bar periphery formed be not less than the thick topping of 50mm, rear anchor cable pallet is added to grouting cable anchor exposed parts after pressurize, pretightning force is not less than 120KN.Steel concrete is combined into steel concrete bearing-load arch, and by the prestressing force that grouting cable anchor applies, the bearing pressure transmitted is helped in effective carrying two, improves the stress of floor rocks;
5th: after grouting cable anchor has pressurizeed, to arcuate furrow and base plate pouring C40 concrete extremely former design size, mixing ratio by weight is cement: sand: stone=1:1.62:2.54, ground mixes, underground site adds water stirring, water/binder ratio is 0.37, adds the waterproof agent of concrete gross mass 1 ~ 2%.
The present invention has following beneficial effect:
(1) base plate deep wall rock adopts grouting cable anchor, effectively encloses crack, improves floor rocks stress, improve bearing capacity and the stability of floor rocks;
(2) baseplate reinforcing bar and concrete form arch ring beam of the anti-end, by means of the prestressing force that grouting cable anchor applies, form effective bearing-load arch, improve the stressed of country rock, improve the stability of floor rocks;
(3) the building of underplate concrete, has effectively completely cut off tunnel trickle, base plate ponding etc. to the erosion of base plate, destruction.
Accompanying drawing explanation
Fig. 1 is roadway grouting anchor cable, arch ring beam of the anti-end, underplate concrete section arrangement diagram;
Fig. 2 is the top view of end distension control program;
Fig. 3 is the location diagram of arch ring beam arched ribs of the anti-end and stirrup;
In figure, 1-roadway's sides, 2-terrace, 3-stirrup, 5-grouting cable anchor, 6-anchor cable pallet, 7-base plate, 8-concrete, 9-arched ribs.
Detailed description of the invention
The present invention adopts a kind of slip casting closed bottom wall-rock crack, arch ring beam of the anti-end improves floor rocks stress, improves the end distension integrated control method of country rock self bearing capacity, for realizing the effective control to Soft Rock Roadway Floor Heave.Concrete implementation step is as follows:
First: soft-rock tunnel is according to after design size excavation, and base plate is in and opens wide not supporting state, after deformation of the surrounding rock in tunnel speed tends towards stability, every 10m is a unit, full face excavation is carried out to roadway floor, cutting depth 300mm darker in terrace 2, drift section width 4.5-5m.This process should note the release of pressure from surrounding rock, impels floor rocks crack to reach full growth, and ensures effective diffusion of slurries during slip casting;
Second: the roadway floor excavated, excavate an arcuate furrow, groove apart from the dark 1000mm of terrace, is decremented to 400mm to roadway's sides, ditch groove width 600mm, spacing 2000-3000mm between groove center line and center line in center, tunnel;
3rd: after arcuate furrow digs by design, in arcuate furrow, set three grouting cable anchors 5, by grouting cable anchor 5 to floor grouting.The cement paste that grouting serous fluid selects 42.5MPa Portland cement to prepare, water/binder ratio 0.6:1, in slip casting process, adds suitable quantity of water glass and controls running pulp amount.Grouting cable anchor 5 chooses the hollow grouting cable anchor of Φ 22mm × 6000mm, and every root grouting cable anchor 5 coordinates 3 K2550 type water resistant Anchor Agents, improves the stress of roadway floor deep wall rock, improves the resistance to overturning of roadway floor;
4th: after the slip casting of grouting cable anchor 5 pairs of base plate deep wall rocks, by the arched ribs 9 that processes and stirrup 3 colligation at the scene, arched ribs spacing 150mm, every layer 4 side by side, lower floor's arched ribs 9 is not less than 100mm apart from the vertical distance of roadway floor 7, ensures that the exposed parts of grouting cable anchor 5 passes from reinforcing bar hole in process of binding.In arcuate furrow, water C60 concrete eight, vibrate while water, reinforcing bar wraps up by concrete eight completely, and is formed in reinforcing bar periphery and be not less than the thick topping of 50mm, adds pressurization after anchor cable pallet 6 to grouting cable anchor 5 exposed parts afterwards, and pretightning force is not less than 120KN.Reinforcing bar and concrete eight are combined into steel concrete bearing-load arch, and by the pretightning force that grouting cable anchor 5 applies, the bearing pressure passing to floor rocks is helped in effective carrying two, improves the stability of floor rocks;
5th: after grouting cable anchor has pressurizeed, to arcuate furrow and an end section pouring C40 concrete eight extremely former design size, mixing ratio by weight is cement: sand: stone=1:1.62:2.54, ground mixes, underground site adds water stirring, and water/binder ratio is 0.37, adds the waterproof agent of concrete gross mass 1 ~ 2%, improve the permeability resistance of underplate concrete, reduce the interference of extraneous water to floor rocks.
Base plate release during beginning, effectively facilitates the cranny development of floor rocks, and ensure that effective diffusion of slurries during the slip casting by grouting cable anchor 5 pairs of base plate deep wall rocks, slip casting encloses the crack of deep wall rock, improves the resistance to overturning of floor rocks.Arched ribs 9 and stirrup 3 form the bar construction of section as shown in Figure 3, arch ring beam of the anti-end is formed after this structure placing of concrete, by means of the pretightning force that grouting cable anchor 5 applies, this concrete collar tie beam effectively carries the pressure helping 1 to pass to base plate by two, improves the stress of floor rocks.
The enforcement of the program effectively can prevent Soft Rock Roadway Floor Heave, ensures that large end distension distortion can not occur in tunnel after supports of soft rock excavation, avoid tunnel repeat reprocess, reduce human and material resources and drop into, ensure safety, the High-efficient Production in colliery, mining in soft rock mining.

Claims (3)

1. a Control Technique of Soft Rock Roadway Floor Heave, is characterized in that, comprises the following steps:
(1) soft-rock tunnel is according to after design size excavation, and base plate is in and opens wide not supporting state, after deformation of the surrounding rock in tunnel speed tends towards stability, every 10m is a unit, carry out full face excavation to roadway floor, cutting depth is compared with the dark 300mm of the former design size in tunnel, drift section width 4.5-5m;
(2) roadway floor excavated, excavates an arcuate furrow, and groove apart from the dark 1000mm of terrace at an end, is decremented to 400mm to roadway's sides, ditch groove width 600mm, groove pitch 2000-3000mm in center, tunnel;
(3), after arcuate furrow digs by design, in arcuate furrow, three grouting cable anchors are set, by grouting cable anchor to floor grouting; The cement paste that grouting serous fluid selects 42.5MPa Portland cement to prepare, water/binder ratio 0.6:1, in slip casting process, adds suitable quantity of water glass and controls running pulp amount;
(4) after grouting cable anchor slip casting, by the arched ribs that processes and stirrup colligation at the scene, arched ribs spacing 150mm, every layer 4 side by side, lower floor's arched ribs is not less than 100mm apart from the vertical height of base plate, ensures that the exposed parts of grouting cable anchor passes from reinforcing bar hole in process of binding; In arcuate furrow, water C60 concrete, vibrate while water, reinforcing bar wraps up by concrete completely, and reinforcing bar periphery formed be not less than the thick topping of 50mm, rear anchor cable pallet is added to grouting cable anchor exposed parts after pressurize, pretightning force is not less than 120KN;
(5) after grouting cable anchor has pressurizeed, to arcuate furrow and base plate pouring C40 concrete extremely former design size, mixing ratio by weight is cement: sand: stone=1:1.62:2.54, ground mixes, underground site adds water stirring, water/binder ratio is 0.37, adds the waterproof agent of concrete gross mass 1 ~ 2%.
2. a kind of Control Technique of Soft Rock Roadway Floor Heave according to claim 1, is characterized in that, described grouting cable anchor selects the hollow grouting cable anchor of Φ 22mm × 6000mm.
3. a kind of Control Technique of Soft Rock Roadway Floor Heave according to claim 1, is characterized in that, described arched ribs selects Φ 20-22mm screw-thread steel, and divide two-layer up and down, 4 every layer, every root arched ribs spacing 150mm, is inserted in ready made stirrup; Φ 10mm screw-thread steel selected by stirrup, and ground makes in advance is processed into the rectangle that height × wide is 300 × 450mm, and stirrup and arched ribs infall adopt 14# iron wire and arched ribs colligation to fix.
CN201610030174.1A 2016-01-18 2016-01-18 Technology for controlling floor heave of soft rock roadway Pending CN105464668A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610030174.1A CN105464668A (en) 2016-01-18 2016-01-18 Technology for controlling floor heave of soft rock roadway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610030174.1A CN105464668A (en) 2016-01-18 2016-01-18 Technology for controlling floor heave of soft rock roadway

Publications (1)

Publication Number Publication Date
CN105464668A true CN105464668A (en) 2016-04-06

Family

ID=55602773

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610030174.1A Pending CN105464668A (en) 2016-01-18 2016-01-18 Technology for controlling floor heave of soft rock roadway

Country Status (1)

Country Link
CN (1) CN105464668A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476814A (en) * 2017-09-28 2017-12-15 滨州学院 A kind of self-vibration jet grouted anchor bar integrated construction device and method
CN109083660A (en) * 2018-08-22 2018-12-25 山东建筑大学 Soft Rock Roadway (tunnel) road pucking based on armored concrete bottom beam administers supporting construction and method
CN109268017A (en) * 2018-09-14 2019-01-25 中国矿业大学 A method of control high stress breaking surrounding rock main entry pucking
CN110030014A (en) * 2019-03-18 2019-07-19 辽宁工程技术大学 A kind of Soft Rock Roadway Floor Heave allows pressure camber shell administering method
CN111502701A (en) * 2020-04-24 2020-08-07 哈尔滨龙源河矿山机械技术开发有限公司 Method for repairing deformed and damaged roadway and roadway structure thereof
CN113006817A (en) * 2021-05-08 2021-06-22 上海应用技术大学 Upper and bottom combined supporting structure capable of yielding and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101967983A (en) * 2010-09-03 2011-02-09 安徽理工大学 Method for over-dredging, anchoring, backfilling and controlling deep well rock roadway floor heave
CN202181908U (en) * 2011-08-12 2012-04-04 中国矿业大学 Expanding soft rock roadway waterproof supporting combined structure
CN102797486A (en) * 2012-08-30 2012-11-28 中国矿业大学 Fabricated grilling anti-invert method for treating pucking
CN103206224A (en) * 2013-04-26 2013-07-17 山东科技大学 Strong resistance and strong evasion floor heave governing construction method of high-stress large-deformation soft rock drift
CN103388481A (en) * 2013-08-05 2013-11-13 中国矿业大学 Combined prefabricated slab for governing floor heave and method for governing floor heave
CN103670438A (en) * 2013-12-04 2014-03-26 河南理工大学 Novel high-strength and high-deformation piston type inverted arch
CN204253052U (en) * 2014-11-13 2015-04-08 安徽理工大学 A kind of lattice steel reinforced concrete antiarch support
CN204253061U (en) * 2014-06-06 2015-04-08 安徽理工大学 The lining cutting of mine working three-dimensional bar frame antiarch
CN104533453A (en) * 2014-12-12 2015-04-22 山东科技大学 Substep dynamic coupling support method for roadway fault fracture zone

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101967983A (en) * 2010-09-03 2011-02-09 安徽理工大学 Method for over-dredging, anchoring, backfilling and controlling deep well rock roadway floor heave
CN202181908U (en) * 2011-08-12 2012-04-04 中国矿业大学 Expanding soft rock roadway waterproof supporting combined structure
CN102797486A (en) * 2012-08-30 2012-11-28 中国矿业大学 Fabricated grilling anti-invert method for treating pucking
CN103206224A (en) * 2013-04-26 2013-07-17 山东科技大学 Strong resistance and strong evasion floor heave governing construction method of high-stress large-deformation soft rock drift
CN103388481A (en) * 2013-08-05 2013-11-13 中国矿业大学 Combined prefabricated slab for governing floor heave and method for governing floor heave
CN103670438A (en) * 2013-12-04 2014-03-26 河南理工大学 Novel high-strength and high-deformation piston type inverted arch
CN204253061U (en) * 2014-06-06 2015-04-08 安徽理工大学 The lining cutting of mine working three-dimensional bar frame antiarch
CN204253052U (en) * 2014-11-13 2015-04-08 安徽理工大学 A kind of lattice steel reinforced concrete antiarch support
CN104533453A (en) * 2014-12-12 2015-04-22 山东科技大学 Substep dynamic coupling support method for roadway fault fracture zone

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476814A (en) * 2017-09-28 2017-12-15 滨州学院 A kind of self-vibration jet grouted anchor bar integrated construction device and method
CN107476814B (en) * 2017-09-28 2023-08-25 滨州学院 Integrated construction equipment and method for self-vibration jet grouting anchor rod
CN109083660A (en) * 2018-08-22 2018-12-25 山东建筑大学 Soft Rock Roadway (tunnel) road pucking based on armored concrete bottom beam administers supporting construction and method
CN109268017A (en) * 2018-09-14 2019-01-25 中国矿业大学 A method of control high stress breaking surrounding rock main entry pucking
CN110030014A (en) * 2019-03-18 2019-07-19 辽宁工程技术大学 A kind of Soft Rock Roadway Floor Heave allows pressure camber shell administering method
CN111502701A (en) * 2020-04-24 2020-08-07 哈尔滨龙源河矿山机械技术开发有限公司 Method for repairing deformed and damaged roadway and roadway structure thereof
CN113006817A (en) * 2021-05-08 2021-06-22 上海应用技术大学 Upper and bottom combined supporting structure capable of yielding and construction method thereof
CN113006817B (en) * 2021-05-08 2023-06-20 上海应用技术大学 Combined support structure capable of yielding and construction method thereof

Similar Documents

Publication Publication Date Title
CN205297580U (en) Soft rock bate distension control structure
CN105464668A (en) Technology for controlling floor heave of soft rock roadway
CN107447765B (en) Side slope construction supported with framed anchor construction
CN105839643B (en) A kind of tunnel construction method of use pattern foundation pit supporting structure
CN106907159B (en) Shallow-buried underground excavation subway station separated open type structure and construction method thereof
CN104032758B (en) Extra-high reinforced construction method in discarded pit
CN106499413A (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN109538216B (en) Tunnel construction process for crossing mining and subsidence areas
CN107313431A (en) Close on not contour foundation ditch method for synchronously constructing
CN107965325B (en) A kind of small interval shallow tunnel just branch arch replacement construction method
CN103321235A (en) Composite soil nailing wall slope support method
CN110284885A (en) Shield inspection-pit construction method
CN211340827U (en) Structure for newly building bridge by passing through existing bridge piles in subway tunnel
CN102235007A (en) Method for supporting deep foundation with upper nail-lower pile combination
CN104213567B (en) Underground pipe gallery controls the construction method of slope section slippage
CN105840209B (en) Construction method for controlling deformation of anchor pile in tunnel body section
CN104328788B (en) Double rows slip casting stake with draw shotcrete layer combined supporting construction method
CN104453915A (en) Large-section vertical shaft pre-grouting reinforcement quick excavation method
CN203891047U (en) Equipment equipped with steel platform for foundation construction of land bridge
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN205605215U (en) Big section loess tunnel is grooving method construction structures in advance
CN106120853B (en) A kind of inverted construction method of frame bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160406

WD01 Invention patent application deemed withdrawn after publication