CN205605215U - Big section loess tunnel is grooving method construction structures in advance - Google Patents

Big section loess tunnel is grooving method construction structures in advance Download PDF

Info

Publication number
CN205605215U
CN205605215U CN201620224568.6U CN201620224568U CN205605215U CN 205605215 U CN205605215 U CN 205605215U CN 201620224568 U CN201620224568 U CN 201620224568U CN 205605215 U CN205605215 U CN 205605215U
Authority
CN
China
Prior art keywords
lining cutting
construction
loess tunnel
inverted arch
advance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620224568.6U
Other languages
Chinese (zh)
Inventor
刘培硕
杨国柱
路美丽
罗章波
谢勇涛
苏新民
于清浩
李新志
蒋雅君
丁祥
郭庆昊
刘彦文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Shijiazhuang Tiedao University
China Railway Fifth Survey and Design Institute Group Co Ltd
Original Assignee
Southwest Jiaotong University
Shijiazhuang Tiedao University
China Railway Fifth Survey and Design Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University, Shijiazhuang Tiedao University, China Railway Fifth Survey and Design Institute Group Co Ltd filed Critical Southwest Jiaotong University
Priority to CN201620224568.6U priority Critical patent/CN205605215U/en
Application granted granted Critical
Publication of CN205605215U publication Critical patent/CN205605215U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a big section loess tunnel is grooving method construction structures in advance takes the fine slip casting stock of D 32mm glass, two encircle in advance, and the lining cutting horn mouth partially sprays plain concrete or net shotcrete and erect the shaped steel steelframe when needs, and the T76S that side wall and every department of foot of a wall department established 2 root length 6m steps the type stake that declines, before inverted arch excavation erects the shaped steel steelframe, execute the inverted arch steelframe of doing at the pre -buried connector plates of the lining cutting foot of a wall in advance after with and adopt bolted connection. Construction risk and landslide are subsided, are reduced to the earth's surface that not only can control in the construction of big section loess tunnel, more can improve the efficiency of construction, accelerate the construction progress, guarantee construction quality. There is important meaning to improving in advance the grooving method in the adaptability on loess tunnel stratum and the mechanized construction level that improves loess tunnel.

Description

A kind of large-section loess tunnel pre-cut channel process constructing structure
Technical field
This utility model relates to a kind of underground engineering technology, particularly relates to a kind of large-section loess tunnel pre-cut channel process constructing structure.
Background technology
Precutting trough construction technology is to use special arched type pre-cut scouring machine to cut groove in advance along tunnel cross section periphery subregion, irrigates C30 concrete immediately, form a pre-lining cutting in excavation face front after grooving in groove.The face excavation the most just defined by grooving processes; thus can efficiently reduce the surrouding rock deformation and ground settlement produced because of face excavation, and the construction operations such as the excavation in face, dregs shipment, inverted arch, guarded drainage, secondary lining can be operated under the protection of pre-lining cutting safely and efficiently.The method is possible not only to ground settlement, reduction construction risk and the landslide controlling in large-section loess tunnel construction, more can improve efficiency of construction, accelerating construction progress, guarantee construction quality.
Affected bigger for loess tunnel formation condition by its moisture content and sand factor, during the tunnel excavation of poor section of stratum, by can be potentially encountered, face is unstable and arch caves in or the risk of pre-lining cutting integral sinking, there is presently no the connection for the two key technical problem being likely encountered in constructing tunnel and inverted arch and pre-lining cutting and carries out particular study.
Utility model content
The purpose of this utility model is to provide a kind of large-section loess tunnel pre-cut channel process constructing structure that can improve efficiency of construction, accelerating construction progress, guarantee construction quality.
The purpose of this utility model is achieved through the following technical solutions:
Large-section loess tunnel pre-cut channel process constructing structure of the present utility model, including:
Solidifying of the working face structure: take Ф 32mm glass grouted anchor bar;
Prevent the structure of pre-lining cutting integral sinking: two rings pre-lining cutting horn section injection plain concrete or in-network processing also set up at profile steel frame, abutment wall and foundation often place when needed and set the T76S of 2 root lengths 6m and step formula mini pile;
The attachment structure of inverted arch steelframe and pre-lining cutting: before inverted arch excavation sets up profile steel frame, the pre-pre-buried junction steel plate of lining cutting foundation with after the inverted arch steelframe that performs with bolts.
The technical scheme provided by above-mentioned this utility model can be seen that, the large-section loess tunnel pre-cut channel process constructing structure that this utility model embodiment provides, it is possible not only to ground settlement, reduction construction risk and the landslide controlling in large-section loess tunnel construction, more can improve efficiency of construction, accelerating construction progress, guarantee construction quality.For improving the pre-cut channel process adaptability on loess tunnel stratum and improving the mechanization its construction level of loess tunnel and have great significance.
Accompanying drawing explanation
Fig. 1 is cross-sectional configuration schematic diagram in this utility model embodiment;
Fig. 2 is longitudinal plane structure schematic diagram in this utility model embodiment;
Fig. 3 is thin portion connecting structure schematic diagram in this utility model embodiment;
Icon explanation
1. glass anchor pole;2. plain concrete or in-network processing screed-coat;3. profile steel frame;4. step formula mini pile;
5~7. junction steel plates;8. inverted arch steelframe;9. bolt.
Detailed description of the invention
This utility model embodiment will be described in further detail below.
Large-section loess tunnel pre-cut channel process constructing structure of the present utility model, its preferably detailed description of the invention is:
Including:
Solidifying of the working face structure: take Ф 32mm glass grouted anchor bar;
Prevent the structure of pre-lining cutting integral sinking: two rings pre-lining cutting horn section injection plain concrete or in-network processing also set up at profile steel frame, abutment wall and foundation often place when needed and set the T76S of 2 root lengths 6m and step formula mini pile;
The attachment structure of inverted arch steelframe and pre-lining cutting: before inverted arch excavation sets up profile steel frame, the pre-pre-buried junction steel plate of lining cutting foundation with after the inverted arch steelframe that performs with bolts.
In described solidifying of the working face structure, the long 12m of glass anchor pole, longitudinal lap joint is not less than 2m, and spacing uses 1.5*1.5m or 1.2m*1.2m, and equilateral triangle is arranged.
In the described structure preventing pre-lining cutting integral sinking, φ 8mm bar-mat reinforcement screed-coat is set when the thickness spraying plain concrete or in-network processing is more than 20cm.
Described inverted arch steelframe, with the attachment structure of pre-lining cutting, has the paragraph of steelframe at the pre-pre-buried junction steel plate of lining cutting foundation for only inverted arch position.
Precutting trough construction technology is to use special arched type pre-cut scouring machine to cut groove in advance along tunnel cross section periphery subregion, irrigates C30 concrete immediately, form a pre-lining cutting in excavation face front after grooving in groove.The face excavation the most just defined by grooving processes; thus can efficiently reduce the surrouding rock deformation and ground settlement produced because of face excavation, and the construction operations such as the excavation in face, dregs shipment, inverted arch, guarded drainage, secondary lining can be operated under the protection of pre-lining cutting safely and efficiently.
Large-section loess tunnel pre-cut channel process constructing structure of the present utility model, the connection for the two key technical problem being likely encountered in constructing tunnel and inverted arch and pre-lining cutting carries out particular study.It is possible not only to ground settlement, reduction construction risk and the landslide controlling in large-section loess tunnel construction, more can improve efficiency of construction, accelerating construction progress, guarantee construction quality.For improving the pre-cut channel process adaptability on loess tunnel stratum and improving the mechanization its construction level of loess tunnel and have great significance.
This utility model must be accomplished in work progress:
1) determine whether face can be from steady according to combined factors such as the Grades of Surrounding Rock of Loess Layer and moisture content, it is impossible in the case of steady, tackle face carry out consolidation process in advance.
2) it is the integral sinking preventing pre-lining cutting, tackle between two ring pre-lining cutting horn section use plain concrete or or in-network processing leveling, and tackle abutment wall and foundation part arranges T76S and steps formula mini pile lock foot anchoring stock, and if desired profile steel frame is set in horn mouth V-belt according to strata condition.
3) inverted arch steelframe should use the mode of pre-embedded steel slab to be effectively connected with pre-lining cutting.
In whole work progress, the concrete control of construction method:
The necessity of solidifying of the working face, the strengthening length of glass anchor pole, spacing and the lap of splice.
Screed-coat between the two pre-lining cutting of ring processes thickness and the lock foot anchoring stock length of material, abutment wall and foundation and position.
Inverted arch steelframe is effectively connected with the reliable of pre-lining cutting.
The beneficial effects of the utility model are:
Make full use of pre-lining cutting and the protection of stable face (carrying out solidifying of the working face if desired) that pre-cut channel process is formed; it is capable of being operated the construction operations such as the tunneling boring excavation in face, dregs shipment, inverted arch, guarded drainage, secondary lining safely and efficiently, substantially increases efficiency of construction, accelerate construction speed, ensure that construction quality.
Control integral sinking and the stability of pre-lining cutting, will can effectively ensure that construction quality and the working security of pre-cut channel process, thus effectively reduce the construction risk such as ground settlement and surrouding rock deformation, the safety of constructing tunnel personnel and equipment is effectively ensured.
This utility model is applicable for use with the engineering of pre-cut channel process construction large-section loess tunnel, the integral sinking by the advance reinforcement measure of face, preventing pre-lining cutting and three key technologies of integrated connection carrying out pre-lining cutting and inverted arch, can guarantee construction safety and the construction quality of pre-cut channel process to greatest extent.
Specific embodiment:
During pre-cut channel process construction large-section loess tunnel, Chief technology and content are as follows:
As shown in Figure 1,2 and 3,
The stability contorting measure of face 1;
The sharpest edges of pre-cut channel process construction are the functions that the concrete lining that grooving irrigates in advance has advance support, construction supporting and permanent support concurrently, it is possible to achieve large cross section excavation.But due to Loess Layer when moisture content is higher or sandy content is higher it is possible that face cannot be from steady situation, the most in this case, should first use glass anchor pole that face is reinforced, carry out full face tunneling the most again.Solidifying of the working face preferably combines concrete strata condition and adjusts the length of glass anchor pole, the lap of splice and spacing.
The control measure of pre-lining cutting integral sinking;
Owing to pre-cut channel process has certain angle when grooving irrigates in tunnel longitudinal direction, the V-belt of a bell mouth shape can be formed between the two pre-lining cutting of ring, for preventing the integral sinking of pre-lining cutting, this V-belt planted agent arranges C25 element pneumatically placed concrete or in-network processing (when thickness is more than 20cm) screed-coat, and 3 Pin profile steel frame are set if desired depending on strata condition, simultaneously the T76S of 2 root lengths 6m is set at abutment wall and foundation and steps formula mini pile, to guarantee construction safety.
3) pre-lining cutting and the connection of inverted arch steelframe;
Have the paragraph of steelframe for only inverted arch position, for guaranteeing effectively being connected of inverted arch steelframe and pre-lining cutting, employing at the pre-pre-buried junction steel plate of lining cutting foundation, the most again with after the inverted arch steelframe that performs with bolts.
The above; it is only this utility model preferably detailed description of the invention; but protection domain of the present utility model is not limited thereto; any those familiar with the art is in the technical scope that this utility model discloses; the change that can readily occur in or replacement, all should contain within protection domain of the present utility model.Therefore, protection domain of the present utility model should be as the criterion with the protection domain of claims.

Claims (4)

1. a large-section loess tunnel pre-cut channel process constructing structure, it is characterised in that including:
Solidifying of the working face structure: take Ф 32mm glass grouted anchor bar;
Prevent the structure of pre-lining cutting integral sinking: two rings pre-lining cutting horn section injection plain concrete or in-network processing also set up at profile steel frame, abutment wall and foundation often place when needed and set the T76S of 2 root lengths 6m and step formula mini pile;
The attachment structure of inverted arch steelframe and pre-lining cutting: before inverted arch excavation sets up profile steel frame, the pre-pre-buried junction steel plate of lining cutting foundation with after the inverted arch steelframe that performs with bolts.
Large-section loess tunnel pre-cut channel process constructing structure the most according to claim 1, it is characterised in that in described solidifying of the working face structure, the long 12m of glass anchor pole, longitudinal lap joint is not less than 2m, and spacing uses 1.5*1.5m or 1.2m*1.2m, and equilateral triangle is arranged.
Large-section loess tunnel pre-cut channel process constructing structure the most according to claim 1, it is characterised in that described in prevent in the structure of pre-lining cutting integral sinking, when spraying the thickness of plain concrete or in-network processing more than 20cm, φ 8mm bar-mat reinforcement screed-coat is set.
Large-section loess tunnel pre-cut channel process constructing structure the most according to claim 1, it is characterised in that described inverted arch steelframe, with the attachment structure of pre-lining cutting, has the paragraph of steelframe at the pre-pre-buried junction steel plate of lining cutting foundation for only inverted arch position.
CN201620224568.6U 2016-03-22 2016-03-22 Big section loess tunnel is grooving method construction structures in advance Active CN205605215U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620224568.6U CN205605215U (en) 2016-03-22 2016-03-22 Big section loess tunnel is grooving method construction structures in advance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620224568.6U CN205605215U (en) 2016-03-22 2016-03-22 Big section loess tunnel is grooving method construction structures in advance

Publications (1)

Publication Number Publication Date
CN205605215U true CN205605215U (en) 2016-09-28

Family

ID=56962447

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620224568.6U Active CN205605215U (en) 2016-03-22 2016-03-22 Big section loess tunnel is grooving method construction structures in advance

Country Status (1)

Country Link
CN (1) CN205605215U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106703837A (en) * 2017-01-02 2017-05-24 王玉田 Collapse-preventing construction method for subway tunnels
CN108457658A (en) * 2018-03-14 2018-08-28 济南城建集团有限公司 A kind of texture stratum tunnel list hole bidirectional construction crosses section constructing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106703837A (en) * 2017-01-02 2017-05-24 王玉田 Collapse-preventing construction method for subway tunnels
CN108457658A (en) * 2018-03-14 2018-08-28 济南城建集团有限公司 A kind of texture stratum tunnel list hole bidirectional construction crosses section constructing method

Similar Documents

Publication Publication Date Title
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN108204240A (en) Newly built tunnels closely on across existing tunnel anti-floating reinforcement system and its reinforcement means
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN102061923B (en) Tunnel construction method capable of protecting existing building
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN102828520A (en) Ring-shaped inner supporting structure used in deep peat soil deep foundation pit
CN110107310A (en) A kind of construction method at tunnel slope hole
CN205297580U (en) Soft rock bate distension control structure
CN102535474A (en) Construction method for deep-foundation pit excavation
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN207934910U (en) A kind of newly built tunnels closely on across existing tunnel anti-floating reinforcement system
CN107965325B (en) A kind of small interval shallow tunnel just branch arch replacement construction method
CN101487264A (en) Ecological protection construction method for covering layer accumulation body slope
CN107503754A (en) A kind of construction method of VI grade of country rock rich water Shallow tunnel with large cross-section
CN107939415A (en) Stay the micro- two step constructions method of Core Soil in the soft plastic clay tunnel of Shallow-buried Large-span
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN109209389A (en) Hazy tunnel construction method
CN110284885A (en) Shield inspection-pit construction method
CN106121659A (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one
CN105464668A (en) Technology for controlling floor heave of soft rock roadway
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN107165641B (en) High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN109989407B (en) Roadbed pile tube curtain supporting structure behind newly-added two-line platform of railway
CN205605215U (en) Big section loess tunnel is grooving method construction structures in advance

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant