CN105442727B - Combined type connects shear wall structure and its assembly method - Google Patents

Combined type connects shear wall structure and its assembly method Download PDF

Info

Publication number
CN105442727B
CN105442727B CN201510901229.7A CN201510901229A CN105442727B CN 105442727 B CN105442727 B CN 105442727B CN 201510901229 A CN201510901229 A CN 201510901229A CN 105442727 B CN105442727 B CN 105442727B
Authority
CN
China
Prior art keywords
wall member
shear
shear key
shearing
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510901229.7A
Other languages
Chinese (zh)
Other versions
CN105442727A (en
Inventor
张沈斌
卓新
吴建挺
陆其荣
周观根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University ZJU
Zhejiang Zhancheng Construction Group Co Ltd
Zhejiang Southeast Space Frame Co Ltd
Original Assignee
Zhejiang University ZJU
Zhejiang Zhancheng Construction Group Co Ltd
Zhejiang Southeast Space Frame Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University ZJU, Zhejiang Zhancheng Construction Group Co Ltd, Zhejiang Southeast Space Frame Co Ltd filed Critical Zhejiang University ZJU
Priority to CN201510901229.7A priority Critical patent/CN105442727B/en
Publication of CN105442727A publication Critical patent/CN105442727A/en
Application granted granted Critical
Publication of CN105442727B publication Critical patent/CN105442727B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • E04B1/043Connections specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of combined type connection shear wall structure and its assembly method.Shear and connected between wall member, every two pieces of shearings wall member by compound shear key and keyway including N block structures identical, constitute combined type connection shear wall.Because the mutual importing of compound shear key and keyway is acted on, construction precision is improved, it is to avoid because of the generation of the inaccurate eccentric compression of assembling;The shear key sheared because of lower section on wall member can undertake the weight of upper shear wall member when assembling next layer, therefore reach intensity without waiting for floorslab concrete after the completion of concrete floor slab placement, the assembling of last layer wall can be carried out at once, can greatly shorten the assembly period of floor;Among the keyway of the shear key insertion upper shear wall member of lower section shearing wall member, shear key can undertake transverse shearing force effect, the shear behavior of reinforcement structure, enhancing structure reliability.

Description

Combined type connects shear wall structure and its assembly method
Technical field
The present invention relates to a kind of fabricated shear wall structure and its assembly method, and in particular to a kind of combined type connection shearing Wall construction and its assembly method.
Background technology
Relative to traditional cast-in-place concrete structure, prefabricated concrete structure has that component quality is good, the construction period is short, money Many advantages, such as source is used less, production wastes few.It is mainly characterized by primary structural member and is prefabricated in the factory, and then passes through vehicle Component is transported to job site by the modes such as transport, carries out component assembly and connection by modes such as mechanical hoistings at the scene, greatly Amount job site work operations are replaced by factory's centralized production.
Sleeve grouting technique is one of common practice of shear wall above and below the connection of assembly concrete shear wall structure.Construction When the reserved steel bar at the top of the shear wall of bottom is inserted into the shear wall of top in pre-buried good butt muff, then use grouter Grouting material is injected into sleeve, after after grouting material hardening, is securely attached together between reinforcing bar and sleeve.It is existing to grind Study carefully result to show, cast-in-place concrete is essentially identical to using the bending strength of the shearing wall member connecting node of sleeve grouting connection Node, and its ductility and energy dissipation capacity are also more reliable.But between the wall up and down using the connection of conventional sleeve grouting construction process Accurate docking is often difficult to, easily causes the phenomenon misplaced between levels shear wall to produce, this is not only outer to building See and water resistance is adversely affected, can also influence the security of structure because of shear wall eccentric compression.In addition, existing correlation Specification provides floor it is necessary to have in-situ layer, and uses existing construction technology to assemble top shear wall, it is necessary to wait floor to mix Solidifying soil reaches could be carried out after some strength, and this will slow down construction speed.
The content of the invention
It is an object of the invention to provide a kind of combined type connection shear wall structure and its assembly method, conventional sleeve is solved The deficiency of the shear wall of cylinder grouting connection, to improve the accuracy and convenience of fabricated shear wall construction.
For up to reaching above-mentioned purpose, the technical solution adopted by the present invention is:
First, a kind of combined type connection shear wall structure
The present invention includes N block structures identical and sheared between wall member, every two pieces of shearings wall member by being combined shear key With keyway connection, combined type connection shear wall is constituted.
Every piece of shearing wall member upper end both sides are embedded with the middle of 1-2 row's longitudinal reinforcements, upper end at least provided with one Compound shear key, it is shear key embedded part to be combined shear key top, and bottom is shear key inlet part, shear key inlet part Be shaped as cuboid, equal highly with the thickness of laminated floor slab, width is less than the thickness of shear wall, and is provided with multiple for cutting The floor bar preformed hole of the laminated floor slab bar connecting of power wall both sides;Shear key embedded part is shaped as truncated rectangular pyramids, four ribs The bed-plate dimension of platform is identical with shear key inlet part, the longitudinal steel of the pre-buried rows of top planes of truncated rectangular pyramids for connection of being in the milk Muscle;Shear wall member lower both sides are equipped with the middle of grout sleeve, lower end at least provided with a keyway, the pre-buried position of grout sleeve Put corresponding with the position for the longitudinal reinforcement that shearing wall member upper end is pre-buried, and multiple injected holes for grouting are provided with side With slurry outlet, multiple injected holes for grouting are connected with respective grout sleeve respectively with slurry outlet;Keyway is recessed four Terrace with edge, its shape and size are identical with shear key embedded part.
The keyway sets the steel wire of U-shaped reinforcing together respectively at shearing wall member wall both sides.
2nd, the step of a kind of combined type connects the assembly method of shear wall structure, this method is as follows:
1)Floor is lifted with pouring:
Assembled on ground after first piece of shearing wall member, two blocks of precast floor slabs are respectively assembled to wall both sides, frame If simultaneously two pieces of precast floor slab top barses of colligation, and the insertion floor reinforced steel into floor bar preformed hole, then pour coagulation At soil to the line of demarcation up and down of compound shear key;
2)The assembling of second piece of shearing wall member
After needing junction to lay one layer of grouting material as pulp layer is sat, by second piece of shear wall lifting component to first piece Shear above wall member, all longitudinal reinforcements of first piece of shearing wall member is inserted into second piece of shearing wall member correspondence position Grout sleeve in, while make first piece shearing wall member shear key embedded part insert second piece shearing wall member keyway Among.
3)Grouting connection
Slip casing by pressure is carried out into all injected holes in shearing wall member side by the way of slip casing by pressure, works as grouting material Stop slip casting after the respective slurry outlet in outflow the top, close all injected holes and slurry outlet, after grouting material condensation is hardened i.e. Complete the assembling of first layer;
Repeat step 1-3, can assemble the number of plies of needs.
The present invention has an advantageous effect in that compared with background technology:
1. because the mutual importing for being combined shear key and keyway is acted on, wall easier, essence when constructing assembling can be made Really, assembly work amount is reduced, construction precision is improved, it is to avoid because of the generation of the inaccurate eccentric compression of assembling;
2. the shear key sheared because of lower section on wall member can undertake the weight of upper shear wall member when assembling next layer Amount, therefore intensity is reached without waiting for floorslab concrete after the completion of concrete floor slab placement, the assembling of last layer wall can be carried out at once, The assembly period of floor can be greatly shortened;
3. among the keyway of the shear key insertion upper shear wall member of lower section shearing wall member, shear key can undertake horizontal stroke To shearing action, the shear behavior of reinforcement structure, enhancing structure reliability.
Brief description of the drawings
Fig. 1 is the stereogram of present invention shearing wall member.
Fig. 2 is Fig. 1 upward view.
Fig. 3 is the stereogram after two pieces of shearing wall member assemblings(It is not drawn into laminated floor slab).
Fig. 4 is Fig. 3 A-A partial sectional views.
Fig. 5 is the stereogram of present invention shearing wall member.
Fig. 6 is the stereogram after present invention shearing wall member is assembled with laminated floor slab pre-erection.
Fig. 7 is the stereogram after present invention shearing wall member is assembled with laminated floor slab.
Fig. 8 is the stereogram after two pieces of shearing wall members of the present invention are assembled with Prefabricated stacking floor.
In figure:1st, wall member is sheared, 2, longitudinal reinforcement, 3, compound shear key, 4, shear key embedded part, 5, shear key buries Enter part, 6, floor bar preformed hole, 7, grout sleeve, 8, keyway, 9, injected hole, 10, slurry outlet, 11, reinforcing steel wire, 12nd, laminated floor slab, 13, laminated floor slab pre-erection, 14, floor upper reinforcement, 15, floor reinforced steel, 16, laminated floor slab it is existing Pour part, 17, sit pulp layer.
Embodiment
The present invention will be further described with reference to the accompanying drawings and examples.
As shown in Figure 1, Figure 2, Figure 3 shows, the present invention includes N block structures identical shearing wall member 1, every two pieces of shearings wall member Between connected by compound shear key 3 and keyway 8, constitute combined type connection shear wall.
Every piece of shearing wall member 1 upper end both sides are embedded with 1-2 rows(It is 2 rows in Fig. 1, Fig. 3)Longitudinal reinforcement 2, upper end Centre is at least provided with a compound shear key 3(It is 1 that shear key is combined in Fig. 1~3), it is that shear key is embedding to be combined shear key top Enter part 4, bottom is shear key inlet part 5, shear key inlet part 5 is shaped as cuboid, highly with laminated floor slab 12 Thickness it is equal, width is less than the thickness of shear wall, and is provided with the bar connecting of laminated floor slab 12 of multiple confession shear wall both sides Floor bar preformed hole 6;Shear key embedded part 4 is shaped as truncated rectangular pyramids, and bed-plate dimension and the shear key of truncated rectangular pyramids be embedded to Part 5 is identical, the longitudinal reinforcement 2 of the pre-buried rows of top planes of truncated rectangular pyramids for connection of being in the milk;Shear wall member lower both sides It is equipped with the middle of grout sleeve 7, lower end at least provided with a keyway(Keyway is 1 in Fig. 2), the pre-buried position of grout sleeve 7 Position with the longitudinal reinforcement 2 that shearing wall member 1 upper end is pre-buried is corresponding, and is provided with multiple injected holes for grouting in side 9 connect with respective grout sleeve 7 respectively with slurry outlet 10, multiple injected holes 9 for grouting with slurry outlet 10;Keyway 8 is Recessed truncated rectangular pyramids, its shape and size are identical with shear key embedded part 4.
As shown in Figure 4, it is contemplated that keyway 8 is more weak in wall two side portions, in keyway 8 close to the shearing wall of wall member 1 The steel wire 11 of U-shaped reinforcing together is set respectively at body both sides, prevents it to be destroyed in transport and assembling.
As shown in Fig. 5~Fig. 8, the construction assembling process of shear wall of the present invention is as follows:
1)Laminated floor slab is lifted with pouring:
First as shown in figure 5, assembling after first piece of shearing wall member 1, you can carry out the lifting of Prefabricated stacking floor 12 With pouring work.Shear wall structure is placed on as shown in fig. 6, Prefabricated stacking floor pre-erection 13 is lifted and supported using crane The both sides of part 1;Set up and colligation floor upper reinforcement 14;Floor is inserted in plate muscle preformed hole 6 into shear wall shear key to add Gu reinforcing bar 15, and floor reinforced steel 15 is effectively connected with floor upper reinforcement 14;Using pump concrete to laminated floor slab Cast-in-place part 16 is poured, and is vibrated when pouring, until concrete surface reaches the shear key embedded part of compound shear key 3 4 with the line of demarcation of shear key inlet part 5 when stop pouring.As shown in fig. 7, after concrete floor slab placement is finished first piece of shear wall structure The shear key embedded part 4 that the compound shear key 3 of part 1 only has its top is exposed to slab surfaces.
2)Prepare before second piece of shearing wall member assembling:
Determine the lifting sequence of component, it would be desirable to which the component of assembling stacks in order to on-site hoisting arrangement in order;Check With the grout sleeve 7 and its injected hole 9 and slurry outlet 10 of cleaning shearing wall member 1, prevent from being blocked by debris, it is ensured that follow-up grouting What is worked is smoothed out;The faying face cleared up between laminated floor slab 12, compound shear key 3 and second piece of shearing wall member 1, and One layer of grouting material is laid on faying face as seat pulp layer 17 to cohere two pieces of shearing wall members;
3)Second piece of shearing wall member assembling work:
Because compound shear key 3 is acted on, second piece of shearing wall member 1 shears the compound of wall member 1 in assembling by first piece Shear key 3 is supported, and is reached without waiting for floorslab concrete and is carried out second piece of shearing wall member assembling after intensity again, is substantially shorter Construction period.With crane by above the precalculated position of second piece of shear wall lifting component to first piece of shear wall during assembling, then Member position is reduced, the longitudinal reinforcement 2 of first piece of shear wall is inserted into the grout sleeve 7 of second piece of shear wall, and The shear key embedded part 4 for making to be exposed to first piece of shearing wall member 1 on laminated floor slab 12 inserts second piece of shear wall structure In the keyway 8 of part 1.Because four sides around keyway 8 and shear key embedded part 4 are inclined-plane and shape is mutually coincide, Second piece of shearing wall member 1 will be automatic by the interaction between keyway 8 and shear key embedded part 4 under Gravitative Loads Predetermined plan-position is fallen on exactly, without being manually adjusted again;Afterwards, hanging down for second piece of shear wall of adjustment need to only be checked Straight degree;
4)Grouting connection:
After second piece of shearing wall member 1 is installed, grouting connection is carried out to it, two pieces of shearing wall members 1 are connected It is integral.Slip casing by pressure is carried out to grout sleeve 7 by the way of slip casing by pressure, to ensure that grouting material densely fills up whole filling Sleeve 7 is starched, grouting material is injected into grout sleeve 7 from injected hole 9, treats that after the outflow grouting material of slurry outlet 10 pulp can be closed Hole and injected hole;After grouting material condenses hardening, shear wall body is that connection is integral up and down.The shear wall completed is connected as schemed Shown in 8.
Repeat step 1-4, can assemble the number of plies of needs.

Claims (3)

1. a kind of combined type connects shear wall structure, it is characterised in that:Including N block structures identical shearing wall member (1), every two Connected between block shearing wall member by compound shear key (3) and keyway (8), constitute combined type connection shear wall;
Described every piece of shearing wall member (1) upper end both sides are embedded with multiple at least provided with one in the middle of 1-2 row's longitudinal reinforcements, upper end Shear key (3) is closed, it is shear key embedded part (4) to be combined shear key top, bottom is shear key inlet part (5), shear key Inlet part (5) is shaped as cuboid, highly with the thickness of laminated floor slab (12) equal, and width is less than the thickness of shear wall, And it is provided with the floor bar preformed hole (6) of laminated floor slab (12) bar connecting of multiple confession shear wall both sides;Shear key is embedded in Partly (4) are shaped as truncated rectangular pyramids, and the bed-plate dimension of truncated rectangular pyramids is identical with shear key inlet part (5), the top horizontal of truncated rectangular pyramids Longitudinal reinforcement of the pre-buried row in face for connection of being in the milk;Shearing wall member (1) lower end both sides are equipped with grout sleeve (7), lower end Centre is at least provided with a keyway (8), the pre-buried position of grout sleeve (7) the longitudinal steel pre-buried with shearing wall member (1) upper end The position of muscle is corresponding, and in side provided with multiple injected holes (9) for grouting and slurry outlet (10), multiple for grouting Injected hole (9) is connected with respective grout sleeve (7) respectively with slurry outlet (10);Keyway (8) is recessed truncated rectangular pyramids, its shape It is identical with shear key embedded part (4) with size.
2. a kind of combined type connection shear wall structure according to claim 1, it is characterised in that:The keyway (8) is close The steel wire (11) of U-shaped reinforcing together is set respectively at shearing wall member (1) wall both sides.
3. the assembly method of shear wall structure is connected for a kind of combined type described in claim 1, it is characterised in that this method The step of it is as follows:
1)Floor is lifted with pouring:
Assembled on ground after first piece of shearing wall member (1) lower wall body, two blocks of precast floor slabs are respectively assembled to wall Both sides, set up and two pieces of precast floor slab top barses of colligation, and the insertion floor reinforced steel into floor bar preformed hole (6) (15), then at casting concrete to the line of demarcation up and down of compound shear key (3);
2)The assembling of second piece of shearing wall member
After needing junction to lay one layer of grouting material as pulp layer (17) are sat, second piece of shearing wall member (1) is lifted into the Above one piece of shearing wall member (1), all longitudinal reinforcements (2) of first piece of shearing wall member (1) are made to be inserted into second piece of shearing In the grout sleeve (7) of wall member (1) correspondence position, while making the shear key embedded part (4) of first piece of shearing wall member (1) Among the keyway (8) of second piece of shearing wall member (1) of insertion;
3)Grouting connection
Slip casing by pressure is carried out into all injected holes (9) in shearing wall member (1) side by the way of slip casing by pressure, works as grouting Stream goes out topmost each slurry outlet (10) and stops slip casting, all injected holes (9) of closing and slurry outlet (10) afterwards, treats grouting material Condense the assembling that first layer is completed after hardening;
Repeat step 1-3, can assemble the number of plies of needs.
CN201510901229.7A 2015-12-09 2015-12-09 Combined type connects shear wall structure and its assembly method Active CN105442727B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510901229.7A CN105442727B (en) 2015-12-09 2015-12-09 Combined type connects shear wall structure and its assembly method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510901229.7A CN105442727B (en) 2015-12-09 2015-12-09 Combined type connects shear wall structure and its assembly method

Publications (2)

Publication Number Publication Date
CN105442727A CN105442727A (en) 2016-03-30
CN105442727B true CN105442727B (en) 2017-08-04

Family

ID=55553320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510901229.7A Active CN105442727B (en) 2015-12-09 2015-12-09 Combined type connects shear wall structure and its assembly method

Country Status (1)

Country Link
CN (1) CN105442727B (en)

Families Citing this family (51)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672533A (en) * 2016-04-05 2016-06-15 朱彦超 Assembled composite insulating wall, composite insulating wall structure and construction method
CN105756202A (en) * 2016-04-20 2016-07-13 天津大学建筑设计研究院 Tooth groove type connection structure of assembled shear wall in combination with superimposed floor slab
CN105863049A (en) * 2016-05-26 2016-08-17 南京长江都市建筑设计股份有限公司 Prefabricated assembled integral framework column bottom grouting structure
CN106013499A (en) * 2016-06-08 2016-10-12 浙江新华建设有限公司 High-strength building wall body structure
CN105888077B (en) * 2016-06-17 2018-06-08 福建工程学院 Fabricated shear wall attachment device and its construction method
CN106223486A (en) * 2016-07-29 2016-12-14 初明进 A kind of precast reinforced concrete structure method of attachment
CN106223487A (en) * 2016-07-29 2016-12-14 初明进 A kind of precast reinforced concrete structure method of attachment
CN106223472A (en) * 2016-07-29 2016-12-14 初明进 A kind of precast reinforced concrete structure method of attachment
CN106193324A (en) * 2016-07-29 2016-12-07 初明进 A kind of precast concrete method of attachment
CN106193323A (en) * 2016-07-29 2016-12-07 初明进 A kind of precast concrete method of attachment
CN106088348A (en) * 2016-07-29 2016-11-09 初明进 A kind of precast concrete method of attachment
CN106245787A (en) * 2016-07-29 2016-12-21 初明进 A kind of precast reinforced concrete structure method of attachment
CN106088352A (en) * 2016-07-29 2016-11-09 初明进 A kind of precast reinforced concrete structure method of attachment
CN106223473A (en) * 2016-07-29 2016-12-14 初明进 A kind of precast reinforced concrete structure method of attachment
CN106121051A (en) * 2016-08-25 2016-11-16 初明进 A kind of interlayer connection node
CN106121050A (en) * 2016-08-25 2016-11-16 初明进 A kind of interlayer connection node
CN106088354A (en) * 2016-08-25 2016-11-09 初明进 A kind of interlayer connection node
CN106245759A (en) * 2016-08-31 2016-12-21 初明进 A kind of precast concrete method of attachment
CN106245756A (en) * 2016-08-31 2016-12-21 初明进 A kind of precast concrete method of attachment
CN106223476A (en) * 2016-08-31 2016-12-14 初明进 A kind of precast reinforced concrete structure method of attachment
CN108729564B (en) * 2017-04-19 2024-04-16 北京清华同衡规划设计研究院有限公司 Assembled building system
CN107100290A (en) * 2017-04-28 2017-08-29 广东省建科建筑设计院有限公司 A kind of prefabricated shear wall and overlapping plate node
CN108385857B (en) * 2018-02-05 2019-07-05 西安建筑科技大学 A kind of precast prestressed connecting structure of wall of abnormity and assembly method
CN108265835B (en) * 2018-03-16 2024-01-30 中冶建工集团有限公司 Prefabricated shear wall component assembly grouting sealing mechanism and sealing grouting method
CN110593418B (en) * 2018-06-12 2024-10-01 迈瑞司(北京)抗震住宅技术有限公司 Assembled shear wall and installation method thereof
CN108978938B (en) * 2018-07-20 2020-06-23 山东科技大学 Prefabricated reinforced concrete shear wall and construction method
CN109235943B (en) * 2018-09-30 2024-08-23 央固工程科技(上海)有限公司 Reinforced concrete prefabricated assembly type cinema stand structure
CN109252603A (en) * 2018-10-17 2019-01-22 阜阳市卓创科技服务生产力促进中心 A kind of stalk is the precast concrete sandwich wall of thermal insulation material
CN109610654B (en) * 2018-12-07 2020-05-19 青岛理工大学 Prefabricated assembly type double-steel-plate concrete shear wall connecting assembly and using method thereof
CN109736427A (en) * 2019-01-24 2019-05-10 浙江立恒建设有限公司 A kind of Antiseismic house builds structure
CN111002462A (en) * 2019-07-19 2020-04-14 中国二十冶集团有限公司 Processing method of reinforcing through-length steel bar at bottom of prefabricated overlapped wallboard
CN110438988A (en) * 2019-08-14 2019-11-12 中铁二院工程集团有限责任公司 A kind of prefabricated bulkhead and pore digging method
CN110512748B (en) * 2019-09-11 2020-09-29 湖南工学院 Wall-beam-plate connecting structure of prefabricated building and construction method
CN110593437B (en) * 2019-09-11 2020-10-30 湖南工学院 Construction method of assembled shear wall
CN110528729B (en) * 2019-09-11 2020-11-17 湖南工学院 Laminated lapped assembled self-stabilizing shear wall
CN110644646A (en) * 2019-09-16 2020-01-03 佛山建装建筑科技有限公司 Split-level grouting sleeve connected assembled shear wall system
CN111733697A (en) * 2019-11-25 2020-10-02 湖南工业大学 Prefabricated assembled composite slab structure
CN110965668A (en) * 2019-12-23 2020-04-07 北京工业大学 Mortise and tenon structure-based assembled concrete shear wall connection method
CN111321821B (en) * 2020-02-28 2021-06-22 南京工程学院 Adopt prefabricated shear force wall steel bar connection structure tied in a bundle of full assembled level seam
CN111794435A (en) * 2020-07-06 2020-10-20 重庆中航新型材料科技有限公司 Green assembled energy-saving panel wall system
CN112878535B (en) * 2021-01-19 2022-03-08 中国十七冶集团有限公司 Precast concrete wallboard connecting structure and construction method thereof
CN113293882B (en) * 2021-05-28 2023-11-03 宿迁学院 Assembled building structure convenient to dock and grout
CN113756471B (en) * 2021-10-11 2022-08-26 佰昱建设集团有限公司 Connecting structure of thin-wall steel concrete shear wall and lower steel reinforced concrete shear wall
CN114753517B (en) * 2022-04-15 2024-03-26 浙江省建工集团有限责任公司 Assembled shear wall and construction method thereof
CN115450378A (en) * 2022-04-30 2022-12-09 张轶鹏 Positioning, aligning and grouting self-locking connection of connecting steel bars of PC (polycarbonate) component of assembled shear wall
CN115233833B (en) * 2022-08-17 2024-02-06 山西省安装集团股份有限公司 Sleeve-free connecting structure of assembled shear wall
CN115653189A (en) * 2022-09-06 2023-01-31 中南大学 Full-assembly composite shear wall panel with key grooves and centralized reinforcing bars
CN116335309A (en) * 2022-09-06 2023-06-27 中南大学 Full-assembled building composite external wall board with key slot type joint
CN115492305A (en) * 2022-09-06 2022-12-20 中南大学 Key groove connected fully-assembled building composite inner wall board and application thereof
CN117926908B (en) * 2024-03-21 2024-05-28 中一达建设集团有限公司 Superimposed concrete member
CN118345949B (en) * 2024-06-14 2024-09-27 广东省建科建筑设计院有限公司 Concrete modularized system based on novel fully assembled shear wall and construction method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4826249B2 (en) * 2005-12-19 2011-11-30 鹿島建設株式会社 Side wall structure and bottom plate structure of low diffusion layer structure of tunnel type radioactive waste burial disposal facility
JP2008223242A (en) * 2007-03-08 2008-09-25 Takenaka Komuten Co Ltd Manufacturing method for precast concrete panel
CN101503887B (en) * 2009-02-04 2011-02-16 南通建筑工程总承包有限公司 Interlayer connection node between inner shear wall, plate and shear walls
CN101818527B (en) * 2010-06-04 2011-07-20 北京万科企业有限公司 Assembled integral shear wall structure system and construction method thereof
CN102433945B (en) * 2011-08-30 2013-09-04 东南大学 Vertical mixed connection structure and method of prefabricated internal wallboards for assembling shear wall structure
CN103104053B (en) * 2013-03-08 2015-10-14 郑州大学 A kind of assembly concrete shear wall and construction method
CN104847039A (en) * 2015-05-27 2015-08-19 天津大学建筑设计研究院 Reinforcing fabricated shear wall structure with shear keys
CN205242683U (en) * 2015-12-09 2016-05-18 浙江大学 Shear wall structure is connected to combined type

Also Published As

Publication number Publication date
CN105442727A (en) 2016-03-30

Similar Documents

Publication Publication Date Title
CN105442727B (en) Combined type connects shear wall structure and its assembly method
EP3670778B1 (en) Prefabricated frame
CN205242683U (en) Shear wall structure is connected to combined type
CN105803925B (en) Quick connection method for prefabricated steel pipe constraint type steel concrete pier columns and cover beam
CN104847014B (en) The vertical connecting structure of assembly concrete shear wall and construction method
CN105088937B (en) Hollow slab bridge with hinge joint having opposite grooves and building method of hollow slab bridge
CN106065669A (en) Steel bar connection mode in prefabricated shear wall connection component
CN211036679U (en) Socket joint connection structure of prefabricated pier stud of assembled bridge and cushion cap
CN206707124U (en) Prefabricated assembling type reinforced concrete component with joint of steel structure
KR101227099B1 (en) Hybrid Column Composed of Centrifugal Concrete Cylinder with Steel Skeleton & Steel Bars
CN109518858A (en) Fabricated Beam-Slab connection structure and its construction method
CN109138210A (en) Assembled arthitecutral structure system
CN108951955A (en) A kind of assembled integral reinforced concrete band keyway Coupled Shear Wall structure
CN108018972B (en) Full prefabricated floor slab and composite floor slab combined structure, manufacturing and assembling method
CN109779090A (en) Prefabricated shear wall, building structure and the construction method of the building structure
CN206956949U (en) Overlap wall and intermediate layer laminated floor slab connecting node
CN108775086A (en) The additional assembled integral beam-column node structure and construction method for being closed connection reinforcing bar
CN109281422A (en) Prefabricated concrete structure wall-column all steel key connection structure and assembling method
CN211143393U (en) Frame for preparing assembly type concrete core-filled wall and assembly type concrete core-filled wall
CN207525960U (en) Easy connect band shear key reinforced concrete slab structure
CN208347063U (en) The prefabricated double board wall units of one kind, shear-wall element and assembly concrete shear wall
CN205954967U (en) A superimposed sheet for green building
CN212772979U (en) Prestress assembly type shear wall system
CN211341282U (en) Transverse connection structure of cast-in-place shear wall and prefabricated shear wall
CN210369030U (en) Split-assembled L-shaped prefabricated retaining wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant