CN106065669A CN201610547611.7A CN201610547611A CN106065669A CN 106065669 A CN106065669 A CN 106065669A CN 201610547611 A CN201610547611 A CN 201610547611A CN 106065669 A CN106065669 A CN 106065669A
Authority
CN
China
Prior art keywords
shear wall
prefabricated
connecting elements
precast shear
bonding pad
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610547611.7A
Other languages
Chinese (zh)
Inventor
伍军
吴吉祥
周新亚
董燕囡
张文禄
施大震
余辉云
程海庆
李明
马珂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201610547611.7A priority Critical patent/CN106065669A/en
Publication of CN106065669A publication Critical patent/CN106065669A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • E04B1/043Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • E04B1/043Connections specially adapted therefor
    • E04B1/046Connections specially adapted therefor using reinforcement loops protruding from the elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/64Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete
    • E04B2/68Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete made by filling-up wall cavities
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/18Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly cast between filling members

Abstract

The invention discloses the bar connecting mode in a kind of precast shear wall connecting elements, it is characterized in that: the dowel being in the bonding pad between two blocks of prefabricated components is set by straight muscle bending in " U " type " U " type muscle, " U " type muscle is during at least one end is embedded in prefabricated component, form " U " the type dowel extending in prefabricated component end, two blocks of prefabricated components each extend over Chu Ge road " U " type dowel interlaced arrangement and mutually overlaps, formation is in same lengthwise position Shang Ge road rectangle frame, between each road rectangle frame, it is positioned on the position at four angles of rectangle frame the form being connected in series to form rectangle steel reinforcement cage with the most straight muscle.The present invention is applied in precast shear wall connecting elements, and it connects reliable, and globality is strong, meets requirement for bearing capacity, advantageously reduces the realization of prefabricated components kind, beneficially industrialized production.

Description

Bar connecting mode in precast shear wall connecting elements
The application is that Application No. 2014105158261, filing date JIUYUE in 2014 29 days, invention entitled one are pre- The bar connecting mode of concrete component processed and application, the divisional application of the artificial China Railway No.4 Bureau Group Co., Ltd of application.
Technical field
The present invention relates to bar connecting mode and the application thereof of prefabricated concrete element, more specifically apply at prefabrication and assembly construction Connected mode between prefabricated concrete element and application thereof in formula building.
Background technology
At present in China's fabricated shear wall house, the connection one routine side of precast concrete shear wall member reinforcing steel bar Formula is " plug-in type preformed hole grouting reinforcing bar connects overlap joint and connects ", and it is in the lower end of precast concrete embedded bar is reserved with Wall is the hole of the rough surface such as corrugated or helical form, when, after precast concrete installation, overlap joint reinforcing bar is inserted simultaneously Enter in hole to setting the lap of splice, in hole, pour into grouting material by the grout hole being connected with hole and steam vent, filling Slurry i.e. realizes the connection of reinforcing bar after condensing hardening.This bar connecting mode is primarily present problems with:
1, the accurate positioning of the substantive requirements of form scene reinforcing bar of its plug-in type preformed hole, it is impossible to having deviation, otherwise reinforcing bar is difficult to It is properly inserted in preformed hole, but it practice, the off-position of steel reinforcing bar phenomenon of job site is commonplace, therefore implements to hang at prefabricated components Before dress, it is necessary to manually correct, but correcting process not only increases workload, reinforcing bar may be made impaired because of rectification simultaneously, And then affect reinforcement property.
2, preformed hole is an omnidistance blind bore hole, and naked eyes cannot be seen the structure within hole, pour in hole Grouting material whole during, it is impossible to judging that grouting material the most tightly fills real whole hole, this makes reinforcing bar and prefabricated components Connect the most uncontrollable, and in cast-in-place structural, concrete needs to vibrate with vibration apparatus, but this In mode, process of not vibrating, more cause grouting material the most closely knit uncontrollable.
3, the reinforcing bar length during the connection request reinforcing bar of its vertical muscle inserts hole to reach not less than 30 times of bar diameters The degree of depth, and hole circumferential arrangement tie hoop, the configuration height of tie hoop is not less than the tension reinforcement lap of splice, and this is the most not It is beneficial to the saving of reinforcing bar.
In prior art, use the construction of overlaid plate type floor connected mode at the floor built for precast shear wall In, laminated floor slab is the reinforced concrete floor being formed by stacking by precast floor slab and cast-in-situ steel reinforced concrete layer, and this form is mainly deposited In following problem:
1, according to the regulation of related specifications, the prefabricated components thickness in laminated floor slab is no less than 50mm, and cast-in-place part is thick Degree is not preferably less than 100mm, and namely floor integral thickness is not less than 150mm, but the slab thickness in cast-in-place structural is normally only For 100-120mm, it is clear that laminated floor slab thickness relatively cast-in-situ floor thickness adds 50%-25%, and this form considerably increases Dead load.
2, pre-buried lattice type steel bar in precast floor unit, its reinforcing bar entirety consumption can be big compared with common cast-in-situ floor Big increase.
3, laminated floor slab needs to carry out at the scene pouring of reinforcing bar binding and concrete, in work progress on-the-spot need substantial amounts of Labour force operates, and this is unfavorable for improving engineering efficiency.
In sum, in prior art, the form of precast shear wall bar connecting mode and laminated floor slab is primarily present following Problem:
1, " " grouting construction quality is difficult to inaccurate to control and reserved steel bar location that to affect engineering reliable to plug-in type preformed hole Degree.
2, laminated floor slab dead load is big, wastes concrete, and its prefabricated components ratio only reaches 50%, and wet trade amount ratio is relatively Greatly.
3, plug-in type preformed hole grouting reinforcing bar even connect the lattice muscle connected mode with laminated floor slab be two kinds the most not Same connected mode does not the most have versatility.
Summary of the invention
The present invention is for avoiding the weak point existing for above-mentioned prior art, it is provided that a kind of structural safety is the most prefabricated Bar connecting mode in shear wall connecting elements, so that building structure possesses fully meets structural-load-carrying capacity, antidetonation entirety Property strong, convenient construction transport and quickly realize the requirement of industrialized production, be applied in fabricated shear wall house, to Reduce wet trade quantity, improve assembling ratio, simplify construction technology, reduce construction costs.
The present invention solves that technical problem adopts the following technical scheme that
The feature of the bar connecting mode of prefabricated concrete element of the present invention is: arranges and is in the bonding pad between two blocks of prefabricated components In dowel by straight muscle bending in " U " type " U " type muscle, described " U " type muscle is during at least one end is embedded in prefabricated component, shape Become and extend in " U " type dowel of prefabricated component end, two blocks of prefabricated components each extend over Chu Ge road " U " type dowel and interlocks cloth Put and mutually overlap, formed and be in same lengthwise position Shang Ge road rectangle frame, between described each road rectangle frame, be positioned at rectangle It is connected in series to form the form of rectangle steel reinforcement cage with the most straight muscle on the position at four angles of frame.
The feature of the bar connecting mode of prefabricated concrete element of the present invention lies also in:
Described " U " type dowel both-end extending in prefabricated component end is all embedded in prefabricated component, forms " U " type closed Dowel.
Described " U " type dowel extending in prefabricated component end is to be embedded in prefabricated component with single-ended, forms " U " of opening Type dowel, " U " type dowel aperture position that a pair mutually overlaps is contrary.
The bar connecting mode of prefabricated concrete element of the present invention applies the feature in precast floor unit to be: existing in bonding pad Pouring concrete, completes to connect through maintenance after jolt ramming, forms the monoblock type floor that can substitute laminated floor slab.
The bar connecting mode of prefabricated concrete element of the present invention applies the feature in precast floor unit to lie also in:
Large Floor is divided into little surface elemant floor, between adjacent unit floor, forms bonding pad.
Arranging described precast floor unit towards the end face of bonding pad is male and fomale(M&F), makes described precast floor unit and is connected Match with male and fomale(M&F) between the cast-in-place concrete in district, increase cast-in-place concrete and the end contact of precast floor slab part of bonding pad Area.
The bar connecting mode of prefabricated concrete element of the present invention applies the feature in precast shear wall connecting elements to be: include The vertical connecting elements of precast shear wall and precast shear wall level connection joint component, through maintenance after the casting concrete jolt ramming of bonding pad Complete to connect.
The bar connecting mode of prefabricated concrete element of the present invention applies the feature in precast shear wall connecting elements to lie also in:
" L " shape, " C " shape or "T"-shaped shear wall are divided into " one " font prefabricated components, at described " one " the prefabricated structure of font Bonding pad is formed between part;Or described " C " shape shear wall is divided into two panels " L " shape prefabricated components, and in shape each other Become bonding pad;Or described "T"-shaped shear wall is divided into a piece of "T"-shaped prefabricated components and a piece of " one " font prefabricated components, And forming bonding pad each other.
Arranging described precast shear wall connecting elements towards the end face of bonding pad is male and fomale(M&F), makes described precast shear wall even Match with male and fomale(M&F) between connection member and the cast-in-place concrete of bonding pad, increase the cast-in-place concrete of bonding pad and prefabricated shearing The end contact area of wall connecting elements.
Compared with the prior art, the present invention has the beneficial effect that:
1, the present invention uses " U " type muscle overlap joint, and then form the form of rectangle steel reinforcement cage, its stabilized structure, coordinate concrete Pour and closely knit make bonding pad can obtain the component load-bearing ability being equal to cast in place process.
2, in the present invention, the width of bonding pad can reach 250mm, it is ensured that the working place of workmen, due to bonding pad For exposed form, concrete is poured vibrator can be used to vibrate, coordinate manual observation to carry out control, can be well Control the construction quality of Cast-in-place concrete, it is ensured that the overall performance of node bonding pad;In the present invention, " U " type muscle overlap joint can reduce reinforcing bar The length about 20% of overlap joint flat segments.
3, due to the fact that and obtain the component load-bearing ability being equal to cast in place process in bonding pad so that it is can be various Assembling structure is applied, connects including being applied to floor prefabricated components, be applied to the connection of shear wall prefabricated components, wherein The connection of shear wall prefabricated components includes: in the Vertical bar connection of shear wall floor gap, same floor, longer shear wall divides The various forms such as the connection between section connection and corner different directions shear wall component;Effectively reduce the kind of prefabricated components Class, largely facilitates modularized design.
4, utilize the connected mode of the present invention can be by erose shear wall, such as " L " shape, " C " shape and "T"-shaped cut Power wall is divided into " one " font that specification is identical, produces in batches with the form of " one " word;Or " C " shape shear wall is divided into two Individual " L " combination of shapes, and "T"-shaped shear wall is divided into segmentation journey " T " and " one " font combination, can also be according to construction Large Floor is divided into some fritters by demand, is very easy to transport and lifting, can substantially reduce prefabrication structure The kind that part produces, facilitates site operation.
5, utilize connected mode of the present invention can be greatly improved prefabricated components ratio, substantially reduce wet trade quantity.Especially It is the application in floor prefabricated components, can change into using integral prefabricated floor to abandon the form of laminated floor slab, make floor real Show 100% prefabricated.This is significant for improving the prefabricated ratio of assembled system.
6, connected mode of the present invention overcomes that other connected mode construction quality is uncontrollable, node bonding pad complicated, construction The shortcoming of length waiting period that cost being high, scene exists a large amount of wet trade and constructs.
The connected mode 7, in the present invention with versatility reduces the difficulty that workman masters a skill, for improving workman's Work efficiency and the proficiency level that develops skill have help greatly.
Accompanying drawing explanation
Fig. 1 a is that the present invention is applied to precast shear wall level connection joint component decomposition sectional schematic diagram;
Fig. 1 b is that the present invention is applied to precast shear wall level connection joint component connection sectional schematic diagram;
Fig. 1 c is that the present invention is applied to precast shear wall level connection joint component exploded isometric schematic diagram;
Fig. 1 d is that the present invention is applied to precast shear wall level connection joint component connecting shaft and measures intention;
Fig. 2 a is that the present invention is applied to precast shear wall vertical connecting elements decomposition sectional schematic diagram;
Fig. 2 b is that the present invention is applied to precast shear wall vertical connecting elements connection sectional schematic diagram;
Fig. 2 c is that the present invention is applied to precast shear wall vertical connecting elements exploded isometric schematic diagram;
Fig. 2 d is that the present invention is applied to precast shear wall vertical connecting elements connecting shaft and measures intention;
Fig. 3 a is that the present invention is applied to corner precast shear wall level connection joint component decomposition sectional schematic diagram;
Fig. 3 b is that the present invention is applied to corner precast shear wall level connection joint component connection sectional schematic diagram;
Fig. 3 c is that the present invention is applied to corner precast shear wall level connection joint component exploded isometric schematic diagram;
Fig. 3 d is that the present invention is applied to corner precast shear wall level connection joint component connecting shaft and measures intention;
Fig. 4 a is that the present invention is applied to precast floor unit decomposition sectional schematic diagram;
Fig. 4 b is that the present invention is applied to precast floor unit connection sectional schematic diagram;
Fig. 4 c is that the present invention is applied to precast floor unit exploded isometric schematic diagram;
Fig. 4 d is that the present invention is applied to precast floor unit connecting shaft and measures intention;
Label in figure: 11 first precast shear wall level connection joint components, 12 first level connection joint muscle, 21 second prefabricated shearings Wall level connection joint component, 22 second level connection joint muscle, the 31 first vertical connecting elements of precast shear wall, 32 first vertically connect Muscle, the 41 second vertical connecting elements of precast shear wall, 42 second vertical dowels;51 first corner precast shear wall level connection joints Component, 52 first corner level connection joint muscle, 61 second corner precast shear wall level connection joint components, 62 second corner level connection joints Muscle;71 first floor prefabricated components, 72 first floor dowels, 81 second floor prefabricated components, 82 second floor dowels, 9 The most straight muscle, 10 bonding pads;
Detailed description of the invention
The bar connecting mode of prefabricated concrete element of the present invention is: arranges and is in the company in the bonding pad between two blocks of prefabricated components Connecing muscle by straight muscle bending in " U " type " U " type muscle, described " U " type muscle during at least one end is embedded in prefabricated component, is formed and extends At " U " type dowel of prefabricated component end, two blocks of prefabricated components each extend over Chu Ge road " U " type dowel interlaced arrangement phase Overlap joint mutually, is formed and is in same lengthwise position Shang Ge road rectangle frame, between described each road rectangle frame, be positioned at rectangle frame four It is connected in series to form the form of rectangle steel reinforcement cage with the most straight muscle on the position at angle.
In being embodied as, " U " type dowel both-end extending in prefabricated component end is all embedded in prefabricated component, is formed and closes " U " type dowel." U " the type dowel extending in prefabricated component end can also be to be embedded in prefabricated component with single-ended, is formed " U " type dowel of opening, " U " type dowel aperture position that a pair mutually overlaps is contrary.
Application mode:
Application mode one: in the present embodiment, the bar connecting mode of prefabricated concrete element is applied in precast floor unit, Bonding pad cast-in-place concrete, completes to connect through maintenance after jolt ramming, forms the monoblock type floor that can substitute laminated floor slab.
In being embodied as, Large Floor can be divided into little surface elemant floor, between adjacent unit floor Form bonding pad;Arranging described precast floor unit towards the end face of bonding pad is male and fomale(M&F), make described precast floor unit with Match with male and fomale(M&F) between the cast-in-place concrete of bonding pad, increase cast-in-place concrete and the end face of precast floor slab part of bonding pad Contact area.
Application mode two: in the present embodiment, the bar connecting mode of prefabricated concrete element is applied at precast shear wall connecting elements In, including the vertical connecting elements of precast shear wall and precast shear wall level connection joint component, in bonding pad casting concrete jolt ramming Complete to connect by maintenance.
In being embodied as, can be that " L " shape, " C " shape or "T"-shaped shear wall are divided into " one " font prefabricated components, Bonding pad is formed between described " one " font prefabricated components;Or described " C " shape shear wall is divided into the prefabricated structure of two panels " L " shape Part, and forming bonding pad each other;Can also is that described "T"-shaped shear wall is divided into a piece of "T"-shaped prefabricated components and A piece of " one " font prefabricated components, and forming bonding pad each other.
Arranging described precast shear wall connecting elements towards the end face of bonding pad is male and fomale(M&F), makes described precast shear wall even Match with male and fomale(M&F) between connection member and the cast-in-place concrete of bonding pad, increase the cast-in-place concrete of bonding pad and prefabricated shearing The end contact area of wall connecting elements.
The composite can be widely applied at floor longer shearing in upper and lower floor two pieces of shear wall prefabricated components, same floors If the dry tablet shear wall prefabricated components at the segmentation prefabricated components of wall, same floor inside lock, two blocks of floor prefabricated components etc. it Between connection, component node can be greatly simplified and connect kind, be conducive to improving factory streamlined work degree.
Work progress:
1, on-site hoisting two blocks of prefabricated components in place, and carry out temporary support;
2, penetrate straight muscle as connecting reinforcing bar to being in Zhong Ge road, bonding pad rectangle frame, fasten formation with iron wire fixing Structure;
3, pour bonding pad concrete, make each component connect in the way of wet connection and form entirety.
See Fig. 1 a, Fig. 1 b, Fig. 1 c and Fig. 1 d, at the first precast shear wall level connection joint component 11 and the second prefabricated shearing Carry out level connection joint between wall level connection joint component 21, the first precast shear wall level connection joint component 11 be positioned in bonding pad One level connection joint muscle 12 is " U " type muscle, and same is, and the second precast shear wall level connection joint component 21 is positioned in bonding pad Two level connection joint muscle 22 are also " U " type muscle, as shown in Fig. 1 a and Fig. 1 c;In bonding pad 10, the first level connection joint muscle 12 and Two level connection joint muscle 22 mutually overlap formation rectangle frame, are positioned on the position at four angles of rectangle frame and are connected in series with the most straight muscle 9, As shown in Fig. 1 b and Fig. 1 d, after the connection of the most straight muscle 9 completes, implement the concreting of bonding pad 10.
See Fig. 2 a, Fig. 2 b, Fig. 2 c and Fig. 2 d, at the first vertical connecting elements of precast shear wall 31 and the second prefabricated shearing Vertically connect between the vertical connecting elements of wall 41, the first vertical connecting elements of precast shear wall 31 be positioned in bonding pad One vertical dowel 32 is " U " type muscle, and same is, and the second vertical connecting elements of precast shear wall 41 is positioned in bonding pad Two vertical dowels 42 are also " U " type muscle, as shown in Fig. 2 a and Fig. 2 c;In bonding pad 10, the first vertical dowel 32 and Two vertical dowels 42 mutually overlap formation rectangle frame, are positioned on the position at four angles of rectangle frame and are connected in series with the most straight muscle 9, As shown in Fig. 2 b and Fig. 2 d, after the connection of the most straight muscle 9 completes, implement the concreting of bonding pad 10.
See Fig. 3 a, Fig. 3 b, Fig. 3 c and Fig. 3 d, at the first corner precast shear wall level connection joint component 51 and the second corner Carrying out level connection joint between precast shear wall level connection joint component 61, the first corner precast shear wall level connection joint component 51 is positioned at The first corner level connection joint muscle 52 in bonding pad is " U " type muscle, and same is the second corner precast shear wall level connection joint structure The second corner level connection joint muscle 62 that part 61 is positioned in bonding pad is also " U " type muscle, as shown in Fig. 3 a and Fig. 3 c;In bonding pad 10 In, the first corner level connection joint muscle 52 and the second corner level connection joint muscle 62 mutually overlap formation rectangle frame, are positioned at rectangle frame four It is connected in series with the most straight muscle 9 on the position at individual angle, as shown in Fig. 3 b and Fig. 3 d, implements after the connection of the most straight muscle 9 completes The concreting of bonding pad 10.
See Fig. 4 a, Fig. 4 b, Fig. 4 c and Fig. 4 d, between the first floor prefabricated components 71 and the second floor prefabricated components 81 Being attached, the first floor dowel 72 that the first floor prefabricated components 71 are positioned in bonding pad is " U " type muscle, and same is the The second floor dowel 82 that second floor plate prefabricated member 81 is positioned in bonding pad is also " U " type muscle, as shown in Fig. 4 a and Fig. 4 c;? In bonding pad 10, the first floor dowel 72 and the second floor dowel 82 mutually overlap formation rectangle frame, are positioned at rectangle frame four It is connected in series with the most straight muscle 9 on the position at individual angle, as shown in Fig. 4 b and Fig. 4 d, implements after the connection of the most straight muscle 9 completes The concreting of bonding pad 10.

Claims (5)

1. the bar connecting mode in precast shear wall connecting elements, is characterized in that: the reinforcing bar of described prefabricated concrete element is even The mode of connecing is to arrange the dowel being in the bonding pad between two blocks of prefabricated components by straight muscle bending in " U " type " U " type muscle, Described " U " type muscle during at least one end is embedded in prefabricated component, forms " U " the type dowel extending in prefabricated component end, and two pieces pre- Product each extend over Chu Ge road " U " type dowel interlaced arrangement and mutually overlaps, being formed and be in same lengthwise position Each road rectangle frame, between described each road rectangle frame, is positioned on the position at four angles of rectangle frame and is connected in series shape with longitudinally straight muscle The form of rectangular steel reinforcement cage;Described precast shear wall connecting elements includes the vertical connecting elements of precast shear wall and prefabricated shearing Wall level connection joint component, completes even through maintenance after the bonding pad casting concrete jolt ramming of precast shear wall connecting elements described Connect.
Bar connecting mode in precast shear wall connecting elements the most according to claim 1, is characterized in that: by " L " shape, " C " shape or "T"-shaped shear wall are divided into " one " font prefabricated components, formed and connect between described " one " font prefabricated components District;Or described " C " shape shear wall is divided into two panels " L " shape prefabricated components, and forming bonding pad each other;Or will Described "T"-shaped shear wall is divided into a piece of "T"-shaped prefabricated components and a piece of " one " font prefabricated components, and is being formed each other Bonding pad.
Bar connecting mode in precast shear wall connecting elements the most according to claim 1, is characterized in that: arrange described Precast shear wall connecting elements is male and fomale(M&F) towards the end face of bonding pad, makes described precast shear wall connecting elements and bonding pad Match with male and fomale(M&F) between cast-in-place concrete, increase the cast-in-place concrete of bonding pad and the end face of precast shear wall connecting elements Contact area.
Bar connecting mode in precast shear wall connecting elements the most according to claim 1, is characterized in that: described extension " U " type dowel both-end in prefabricated component end is all embedded in prefabricated component, forms " U " the type dowel closed.
Bar connecting mode in precast shear wall connecting elements the most according to claim 1, is characterized in that: described extension " U " type dowel in prefabricated component end is to be embedded in prefabricated component with single-ended, forms " U " type dowel of opening, a pair phase " U " type dowel aperture position of overlap joint is contrary mutually.
CN201610547611.7A 2014-09-29 2014-09-29 Bar connecting mode in precast shear wall connecting elements Pending CN106065669A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610547611.7A CN106065669A (en) 2014-09-29 2014-09-29 Bar connecting mode in precast shear wall connecting elements

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201410515826.1A CN104264786B (en) 2014-09-29 2014-09-29 The bar connecting mode of a kind of prefabricated concrete element and application thereof
CN201610547611.7A CN106065669A (en) 2014-09-29 2014-09-29 Bar connecting mode in precast shear wall connecting elements

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201410515826.1A Division CN104264786B (en) 2014-09-29 2014-09-29 The bar connecting mode of a kind of prefabricated concrete element and application thereof

Publications (1)

Publication Number Publication Date
CN106065669A true CN106065669A (en) 2016-11-02

Family

ID=52156349

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610547611.7A Pending CN106065669A (en) 2014-09-29 2014-09-29 Bar connecting mode in precast shear wall connecting elements
CN201410515826.1A Active CN104264786B (en) 2014-09-29 2014-09-29 The bar connecting mode of a kind of prefabricated concrete element and application thereof

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201410515826.1A Active CN104264786B (en) 2014-09-29 2014-09-29 The bar connecting mode of a kind of prefabricated concrete element and application thereof

Country Status (1)

Country Link
CN (2) CN106065669A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106854899A (en) * 2017-01-18 2017-06-16 黄坤坤 Assembled ring muscle is fastened and is anchored concrete shear force wall vertical connection structure
CN107060133A (en) * 2017-04-29 2017-08-18 福州大学 A kind of fabricated shear wall and its installation method suitable for frame-shear-wall structure
CN107217596A (en) * 2017-06-07 2017-09-29 中铁十六局集团第四工程有限公司 It is a kind of to collect construction method that is prefabricated and installing urban viaduct baffle plate
CN108005261A (en) * 2018-01-03 2018-05-08 浙江绿筑集成科技有限公司 A kind of horizontal joining method of embedded reinforcing bar type shear wall
CN108265671A (en) * 2018-03-12 2018-07-10 中交上海港湾工程设计研究院有限公司 A kind of prefabricated panel and the connection system and method for longitudinal and transverse beam
CN108442536A (en) * 2018-03-30 2018-08-24 沈阳建筑大学 A kind of prefabricated assembled shear wall groove slurry anchor horizontal connection construction
CN108797834A (en) * 2017-05-03 2018-11-13 李聪 A kind of exterior wall and its construction method of form bracing
CN109208783A (en) * 2018-10-09 2019-01-15 中国建筑第七工程局有限公司 A kind of connecting node positioning device, connection structure and its construction method for exempting from binding
CN113404190A (en) * 2021-05-20 2021-09-17 上海建工二建集团有限公司 Self-supporting double-sided superposed shear wall and construction method
CN113756473A (en) * 2021-10-18 2021-12-07 福建金鼎建筑发展有限公司 A L type self preservation temperature shear force wall prefabricated plate for prefabricated construction corner
CN114086699A (en) * 2021-12-06 2022-02-25 何毅 Reinforced concrete partition wall connected node structure

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612241B (en) * 2015-02-05 2019-02-26 河北合创建筑节能科技有限责任公司 The unit prefabricated part of civil buildings and its assembly method
JP6635801B2 (en) * 2016-01-21 2020-01-29 三井住友建設株式会社 Precast concrete wall joining structure and precast concrete wall joining method
CN106400952A (en) * 2016-07-29 2017-02-15 刘祥锦 Assembly type prefabricated structure wallboard unit and connecting joints thereof
JP6959019B2 (en) * 2017-03-06 2021-11-02 大成ユーレック株式会社 Precast concrete member joint structure
CN106948548A (en) * 2017-04-26 2017-07-14 广西大学 A kind of precast concrete frame beam structure
CN107254933A (en) * 2017-07-17 2017-10-17 广东省建科建筑设计院有限公司 The high-rise single through hole precast shear wall of assembled and its assembling structure and construction method
CN107327047A (en) * 2017-07-24 2017-11-07 远大住宅工业(上海)有限公司 Overlap the vertical openings connecting node of wall and overlapping wall
WO2019038989A1 (en) * 2017-08-25 2019-02-28 住友電工スチールワイヤー株式会社 Concrete structure and method for manufacturing same
CN108049504B (en) * 2017-12-19 2023-11-10 浙江绿筑集成科技有限公司 Connecting method for assembled type combined wall
CN108661221A (en) * 2018-04-25 2018-10-16 李藏柱 A kind of precast floor slab and its connection structure and its construction method
CN108842962A (en) * 2018-07-24 2018-11-20 浙江大学宁波理工学院 A kind of assembly concrete beam connection structure
CN110185155B (en) * 2019-06-25 2024-03-15 中国建筑标准设计研究院有限公司 Joint connector of prefabricated part, prefabricated wall system and construction method of prefabricated wall system
CN112095777B (en) * 2020-09-15 2021-08-31 湖北正茂新材料科技股份有限公司 High-strength prefabricated part convenient to install
CN115405014A (en) * 2022-08-02 2022-11-29 中建八局第二建设有限公司 Fabricated concrete shear wall structure and splitting construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010091697A (en) * 2000-03-17 2001-10-23 배종렬 PC wall member connection method with loop bar
CN201395875Y (en) * 2009-02-04 2010-02-03 南通建筑工程总承包有限公司 L-shaped shear wall vertical connection node
CN102433945A (en) * 2011-08-30 2012-05-02 东南大学 Vertical mixed connection structure and method of prefabricated internal wallboards for assembling shear wall structure
CN102691366A (en) * 2012-06-02 2012-09-26 江苏金砼预制装配建筑发展有限公司 Precast concrete self-insulating shear wall and assembly type concrete building shear wall structure
CN102787681A (en) * 2012-09-07 2012-11-21 初明进 Connecting structure of prefabricated concrete wall body
CN102808465A (en) * 2012-08-08 2012-12-05 沈阳建筑大学 Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination
CN103276663A (en) * 2013-05-28 2013-09-04 桂林理工大学 Method for manufacturing assembled integral plate for reinforced concrete slab bridge
CN103790265A (en) * 2014-01-28 2014-05-14 江苏建筑职业技术学院 Method for manufacturing and assembling prefabricated concrete filled steel tube core column stiffening shear wall
CN203808292U (en) * 2014-05-01 2014-09-03 西安科技大学 Assembly type gridded shear wall structure system

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2319463Y (en) * 1998-01-08 1999-05-19 刘凤新 Integral net structure for connecting box shape house
CN101139849A (en) * 2006-09-07 2008-03-12 张兴汉 Modular building component and on-site hoisting building method
CN202131679U (en) * 2011-05-13 2012-02-01 中国航空规划建设发展有限公司 Connecting structure capable of enhancing integrity of precast slabs
CN103526868B (en) * 2013-10-23 2016-08-31 张英保 Assemblingization building floor and the building of composition thereof and method of construction

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010091697A (en) * 2000-03-17 2001-10-23 배종렬 PC wall member connection method with loop bar
CN201395875Y (en) * 2009-02-04 2010-02-03 南通建筑工程总承包有限公司 L-shaped shear wall vertical connection node
CN102433945A (en) * 2011-08-30 2012-05-02 东南大学 Vertical mixed connection structure and method of prefabricated internal wallboards for assembling shear wall structure
CN102691366A (en) * 2012-06-02 2012-09-26 江苏金砼预制装配建筑发展有限公司 Precast concrete self-insulating shear wall and assembly type concrete building shear wall structure
CN102808465A (en) * 2012-08-08 2012-12-05 沈阳建筑大学 Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination
CN102787681A (en) * 2012-09-07 2012-11-21 初明进 Connecting structure of prefabricated concrete wall body
CN103276663A (en) * 2013-05-28 2013-09-04 桂林理工大学 Method for manufacturing assembled integral plate for reinforced concrete slab bridge
CN103790265A (en) * 2014-01-28 2014-05-14 江苏建筑职业技术学院 Method for manufacturing and assembling prefabricated concrete filled steel tube core column stiffening shear wall
CN203808292U (en) * 2014-05-01 2014-09-03 西安科技大学 Assembly type gridded shear wall structure system

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106854899A (en) * 2017-01-18 2017-06-16 黄坤坤 Assembled ring muscle is fastened and is anchored concrete shear force wall vertical connection structure
CN107060133A (en) * 2017-04-29 2017-08-18 福州大学 A kind of fabricated shear wall and its installation method suitable for frame-shear-wall structure
CN107060133B (en) * 2017-04-29 2019-06-07 福州大学 A kind of fabricated shear wall and its installation method suitable for frame-shear-wall structure
CN108797834A (en) * 2017-05-03 2018-11-13 李聪 A kind of exterior wall and its construction method of form bracing
CN107217596A (en) * 2017-06-07 2017-09-29 中铁十六局集团第四工程有限公司 It is a kind of to collect construction method that is prefabricated and installing urban viaduct baffle plate
CN108005261A (en) * 2018-01-03 2018-05-08 浙江绿筑集成科技有限公司 A kind of horizontal joining method of embedded reinforcing bar type shear wall
CN108265671A (en) * 2018-03-12 2018-07-10 中交上海港湾工程设计研究院有限公司 A kind of prefabricated panel and the connection system and method for longitudinal and transverse beam
CN108442536A (en) * 2018-03-30 2018-08-24 沈阳建筑大学 A kind of prefabricated assembled shear wall groove slurry anchor horizontal connection construction
CN109208783A (en) * 2018-10-09 2019-01-15 中国建筑第七工程局有限公司 A kind of connecting node positioning device, connection structure and its construction method for exempting from binding
CN113404190A (en) * 2021-05-20 2021-09-17 上海建工二建集团有限公司 Self-supporting double-sided superposed shear wall and construction method
CN113756473A (en) * 2021-10-18 2021-12-07 福建金鼎建筑发展有限公司 A L type self preservation temperature shear force wall prefabricated plate for prefabricated construction corner
CN113756473B (en) * 2021-10-18 2022-11-01 福建金鼎建筑发展有限公司 A L type self preservation temperature shear force wall prefabricated plate for prefabricated construction corner
CN114086699A (en) * 2021-12-06 2022-02-25 何毅 Reinforced concrete partition wall connected node structure

Also Published As

Publication number Publication date
CN104264786B (en) 2016-08-17
CN104264786A (en) 2015-01-07

Similar Documents

Publication Publication Date Title
CN104264786B (en) The bar connecting mode of a kind of prefabricated concrete element and application thereof
CN204059601U (en) A kind of steel bar connecting structure of prefabricated concrete element
CN206070835U (en) A kind of assembled architecture bottom composite floor
CN106284846B (en) A kind of assembled steel reinforced concrete-constituted pile and system, construction method using the column
CN107780576A (en) A kind of assembled architecture bottom composite floor and its connected mode
CN206707124U (en) Prefabricated assembling type reinforced concrete component with joint of steel structure
CN206428872U (en) A kind of close splicing seam superimposed sheet
CN106968381B (en) Assembled prefabricated shear wall and superimposed sheet node connected by combined grouting sleeve
CN216109005U (en) Support-free or few-support connection joint of full-prefabricated floor slab and superposed beam
CN206144031U (en) Assembled reinforced concrete constructional column and utilize system of this post
CN209227836U (en) Prefabricated concrete structure wall-column all steel is keyed structure
CN110644662A (en) Prefabricated flat slab composite slab based on stress and splitting method thereof
CN106760036A (en) A kind of prefabricated steel combined concrete shear wall
CN110670770A (en) Solid shear wall and laminated plate type edge member combined structure and construction method
CN111851827A (en) Assembly type prefabricated steel bar truss disassembly-free template system and manufacturing method thereof
CN208347063U (en) The prefabricated double board wall units of one kind, shear-wall element and assembly concrete shear wall
CN217175201U (en) Assembled concrete column connected node
CN207525960U (en) Easy connect band shear key reinforced concrete slab structure
CN212772979U (en) Prestress assembly type shear wall system
CN211312950U (en) Assembled integral elevator shaft prefabricated part
CN212271326U (en) Cast-in-place concrete wall body of combined truss reinforcing steel bars and steel plates
CN105952044B (en) A kind of full precast prestressed concrete floor construction and prestressing force assembly method
CN212452765U (en) Two-in-one underground pipe gallery structure
CN212295166U (en) Assembly type wall body connecting structure based on ribbed box
CN108018972A (en) Full precast floor slab and laminated floor slab combining structure, making and assembly method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161102