CN105863049A - Prefabricated assembled integral framework column bottom grouting structure - Google Patents

Prefabricated assembled integral framework column bottom grouting structure Download PDF

Info

Publication number
CN105863049A
CN105863049A CN201610357661.9A CN201610357661A CN105863049A CN 105863049 A CN105863049 A CN 105863049A CN 201610357661 A CN201610357661 A CN 201610357661A CN 105863049 A CN105863049 A CN 105863049A
Authority
CN
China
Prior art keywords
prefabricated
plasma discharge
discharge hole
grouting
framework column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610357661.9A
Other languages
Chinese (zh)
Inventor
李宁
吴敦军
王流金
陈乐琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Yangtze River Urban Architectural Design Co Ltd
Original Assignee
Nanjing Yangtze River Urban Architectural Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Yangtze River Urban Architectural Design Co Ltd filed Critical Nanjing Yangtze River Urban Architectural Design Co Ltd
Priority to CN201610357661.9A priority Critical patent/CN105863049A/en
Publication of CN105863049A publication Critical patent/CN105863049A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves

Abstract

The invention relates to a prefabricated assembled integral framework column bottom grouting structure, which comprises a prefabricated framework column and an anti-shearing groove formed in the bottom of the prefabricated framework column; a grouting sleeve is prefabricated at the bottom of the prefabricated framework column at the same time, is arranged on the periphery of the prefabricated framework column, and is used for connecting a load-bearing steel bar of the prefabricated framework column; the lower part of the tube wall of the grouting sleeve is provided with a grouting hole; a slurry discharging hole is formed in the upper part of the tube wall of the grouting sleeve, i.e., the slurry discharging hole and the grouting hole are formed in the periphery of the prefabricated framework column from top to bottom; a PVC (polyvinyl chloride) pipe is arranged on the anti-shearing groove, and is arranged in an L shape; the vertical part of the PVC pipe is communicated with the anti-shearing groove; the transverse part of the PVC pipe extends out of the other side of the prefabricated framework column to form a high-position slurry discharging hole; the high-position slurry discharging hole is formed above the slurry discharging hole of the grouting sleeve. The prefabricated assembled integral framework column bottom grouting structure solves the problem that during the prefabricated framework column bottom grouting, air in the anti-shearing groove cannot be thoroughly exhausted.

Description

Grouting structure at the bottom of a kind of fabricated assembly overall frame column
Technical field
The present invention relates to be in the milk at the bottom of a kind of fabricated assembly overall frame column structure, belongs to building industrialization and prefabrication and assembly construction technical field.
Background technology
When using prefabricated frame trestle, by current national codes requirement, for ensureing the transmission of prefabricated post junction horizontal force, need at the bottom of prefabricated frame trestle, arranging shearing resistance groove.Then, when post reinforcing bar grout sleeve slip casting, shearing resistance groove is filled slurry.But shearing resistance groove exists the problem that can not be drained by air in filling process, cavity at the bottom of post, can be formed, make precast frame column section weakened, have certain potential safety hazard.
Summary of the invention
The present invention provides be in the milk at the bottom of a kind of fabricated assembly overall frame column structure, when solving grouting at the bottom of prefabricated frame trestle post, the problem that in shearing resistance groove, air can not drain.
The technical solution adopted for the present invention to solve the technical problems is:
Grouting structure at the bottom of a kind of fabricated assembly overall frame column, including prefabricated frame trestle and the shearing resistance groove being arranged at precast frame column bottom, grout sleeve is preset in the bottom of described prefabricated frame trestle simultaneously, described grout sleeve is laid in prefabricated frame trestle surrounding, for connecting the steel bar stress of prefabricated frame trestle, the barrel bottom of described grout sleeve is provided with grout hole, the barrel top of described grout sleeve is provided with plasma discharge hole, i.e. plasma discharge hole and grout hole is from top to bottom successively set on the surrounding of prefabricated frame trestle, described shearing resistance groove is provided with pvc pipe, the L-shaped setting of pvc pipe, its vertical component is connected with shearing resistance groove, the opposite side of prefabricated frame trestle is stretched out in lateral part, form high-order plasma discharge hole, described high-order plasma discharge hole is located at above grout sleeve plasma discharge hole;
As present invention further optimization, high-order plasma discharge hole is located at above plasma discharge hole at 150mm;
As present invention further optimization, described pvc pipe is arranged at the middle position of shearing resistance groove.
By above technical scheme, relative to prior art, the method have the advantages that
When the present invention solves to be in the milk at the bottom of prefabricated frame trestle post, in shearing resistance groove, air is arranged endless, the problem being easily generated cavity;Ensure that the bearing capacity of prefabricated frame trestle, improve switching performance;Use high-order plasma discharge hole, utilize the pressure differential of grouting, it is ensured that the density of grouting material in shearing resistance groove.
Accompanying drawing explanation
The present invention is further described with embodiment below in conjunction with the accompanying drawings.
Fig. 1 is the overall structure figure of the preferred embodiments of the present invention;
Fig. 2 is the axonometric chart of the preferred embodiments of the present invention.
In figure: 1 is prefabricated frame trestle, 2 is grout hole, and 3 is plasma discharge hole, and 4 is high-order plasma discharge hole.
Detailed description of the invention
In conjunction with the accompanying drawings, the present invention is further detailed explanation.These accompanying drawings are the schematic diagram of simplification, and the basic structure of the present invention is described the most in a schematic way, and therefore it only shows the composition relevant with the present invention.
As Figure 1-Figure 2, grouting structure at the bottom of a kind of fabricated assembly overall frame column of the present invention, including prefabricated frame trestle and the shearing resistance groove being arranged at precast frame column bottom, grout sleeve is preset in the bottom of described prefabricated frame trestle simultaneously, described grout sleeve is laid in prefabricated frame trestle surrounding, for connecting the steel bar stress of prefabricated frame trestle, the barrel bottom of described grout sleeve is provided with grout hole, the barrel top of described grout sleeve is provided with plasma discharge hole, i.e. plasma discharge hole and grout hole is from top to bottom successively set on the surrounding of prefabricated frame trestle, described shearing resistance groove is provided with pvc pipe, the L-shaped setting of pvc pipe, its vertical component is connected with shearing resistance groove, the opposite side of prefabricated frame trestle is stretched out in lateral part, form high-order plasma discharge hole, described high-order plasma discharge hole is located at above grout sleeve plasma discharge hole;
As present invention further optimization, high-order plasma discharge hole is located at above plasma discharge hole at 150mm;
As present invention further optimization, described pvc pipe is arranged at the middle position of shearing resistance groove.
During the grouting of fabricated assembly overall frame column reinforcing bar grout sleeve, first seal at component piece joint face surrounding seat slurry, slurry is poured into by the grout hole below reinforcing bar grout sleeve, grouting material enters all cavitys at the bottom of reinforcing bar grout sleeve and post under pressure, when the pulp of plasma discharge hole, it is in the milk in showing cavity at the bottom of post and reinforcing bar grout sleeve closely knit.Additional high-order plasma discharge hole, it is ensured that the cavity grouting in shearing resistance groove is closely knit, and the Grouted density being not less than in reinforcing steel bar connecting sleeve tube.
When the present invention solves to be in the milk at the bottom of prefabricated frame trestle post, in shearing resistance groove, air is arranged endless, the problem being easily generated cavity;Ensure that the bearing capacity of prefabricated frame trestle, improve switching performance;Use high-order plasma discharge hole, utilize the pressure differential of grouting, it is ensured that the density of grouting material in shearing resistance groove.
Those skilled in the art of the present technique are appreciated that unless otherwise defined, all terms used herein (including technical term and scientific terminology) have with the those of ordinary skill in the application art be commonly understood by identical meaning.Should also be understood that those terms defined in such as general dictionary should be understood that have the meaning consistent with the meaning in the context of prior art, and unless defined as here, will not explain by idealization or the most formal implication.
The implication of "and/or" described herein refers to respective individualism or both simultaneous situations are included in interior.
The implication of " connection " described herein can be being directly connected between parts can also be by being indirectly connected with of other parts between parts.
With the above-mentioned desirable embodiment according to the present invention for enlightenment, by above-mentioned description, relevant staff can carry out various change and amendment completely in the range of without departing from this invention technological thought.The content that the technical scope of this invention is not limited in description, it is necessary to determine its technical scope according to right.

Claims (3)

1. grouting structure at the bottom of a fabricated assembly overall frame column, including prefabricated frame trestle and the shearing resistance groove being arranged at precast frame column bottom, grout sleeve is preset in the bottom of described prefabricated frame trestle simultaneously, described grout sleeve is laid in prefabricated frame trestle surrounding, for connecting the steel bar stress of prefabricated frame trestle, the barrel bottom of described grout sleeve is provided with grout hole, the barrel top of described grout sleeve is provided with plasma discharge hole, i.e. plasma discharge hole and grout hole is from top to bottom successively set on the surrounding of prefabricated frame trestle, it is characterized in that: described shearing resistance groove is provided with pvc pipe, the L-shaped setting of pvc pipe, its vertical component is connected with shearing resistance groove, the opposite side of prefabricated frame trestle is stretched out in lateral part, form high-order plasma discharge hole, described high-order plasma discharge hole is located at above grout sleeve plasma discharge hole.
It is in the milk at the bottom of fabricated assembly overall frame column the most according to claim 1 structure, it is characterised in that: high-order plasma discharge hole is located at above plasma discharge hole at 150mm.
Grouting structure at the bottom of fabricated assembly overall frame column the most according to claim 1, it is characterised in that: described pvc pipe is arranged at the middle position of shearing resistance groove.
CN201610357661.9A 2016-05-26 2016-05-26 Prefabricated assembled integral framework column bottom grouting structure Pending CN105863049A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610357661.9A CN105863049A (en) 2016-05-26 2016-05-26 Prefabricated assembled integral framework column bottom grouting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610357661.9A CN105863049A (en) 2016-05-26 2016-05-26 Prefabricated assembled integral framework column bottom grouting structure

Publications (1)

Publication Number Publication Date
CN105863049A true CN105863049A (en) 2016-08-17

Family

ID=56641276

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610357661.9A Pending CN105863049A (en) 2016-05-26 2016-05-26 Prefabricated assembled integral framework column bottom grouting structure

Country Status (1)

Country Link
CN (1) CN105863049A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193329A (en) * 2016-08-29 2016-12-07 朱凤起 Concrete wall structure and construction method thereof
CN106480996A (en) * 2016-10-20 2017-03-08 深圳市鹏城建筑集团有限公司 A kind of method are in the milk by docking structure of levels prefabricated component and the faying face to levels prefabricated component
CN106760224A (en) * 2016-11-25 2017-05-31 北京汇丰鸿信科技有限公司 One kind grouting shrinkage compensation process
CN107700656A (en) * 2017-08-18 2018-02-16 国网上海市电力公司 A kind of prefabricated column bottom grout construction method
CN107782880A (en) * 2017-10-22 2018-03-09 山东科技大学 Grouting in soil mass simulation test device and its test method in a kind of multifunctional room
CN108086130A (en) * 2016-11-23 2018-05-29 重庆市中科大业建筑科技有限公司 A kind of T-shaped steel tube confinement reinforced concrete bridge pier beam-column connection of assembled
CN109555272A (en) * 2018-12-26 2019-04-02 合肥工业大学 A kind of grouting mouth is in upper reinforcing bar connection grout sleeve
CN109853862A (en) * 2019-03-06 2019-06-07 河北冀科工程项目管理有限公司 A kind of assembly prefabricated components series connection sleeve connection structure and grouting method
CN110593486A (en) * 2019-09-25 2019-12-20 中国电力工程顾问集团中南电力设计院有限公司 Assembled concrete column node connection structure
CN112211319A (en) * 2020-10-13 2021-01-12 上海城建市政工程(集团)有限公司 Same-layer grouting method for mounting prefabricated shear wall of fabricated building
CN112302165A (en) * 2020-10-16 2021-02-02 上海市建筑科学研究院有限公司 Box-shaped sleeve type connecting structure of assembled concrete member, construction method and application

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003301526A (en) * 2002-04-12 2003-10-24 Tokyo Tekko Co Ltd Connecting construction method for precast concrete vertical member
CN2621196Y (en) * 2003-04-21 2004-06-23 润弘精密工程事业股份有限公司 Exhaust structure of continuous junction of precast post
CN204040202U (en) * 2013-11-01 2014-12-24 润弘精密工程事业股份有限公司 Precasting structure with air guiding function
CN105442727A (en) * 2015-12-09 2016-03-30 浙江大学 Compound type connection shear wall structure and assembling method thereof
CN205242694U (en) * 2015-11-24 2016-05-18 绍兴宝业西伟德混凝土预制件有限公司 Vertical connected node of uniform thickness superimposed shear wall
CN205776737U (en) * 2016-05-26 2016-12-07 南京长江都市建筑设计股份有限公司 Grouting structure at the bottom of a kind of fabricated assembly overall frame column

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003301526A (en) * 2002-04-12 2003-10-24 Tokyo Tekko Co Ltd Connecting construction method for precast concrete vertical member
CN2621196Y (en) * 2003-04-21 2004-06-23 润弘精密工程事业股份有限公司 Exhaust structure of continuous junction of precast post
CN204040202U (en) * 2013-11-01 2014-12-24 润弘精密工程事业股份有限公司 Precasting structure with air guiding function
CN205242694U (en) * 2015-11-24 2016-05-18 绍兴宝业西伟德混凝土预制件有限公司 Vertical connected node of uniform thickness superimposed shear wall
CN105442727A (en) * 2015-12-09 2016-03-30 浙江大学 Compound type connection shear wall structure and assembling method thereof
CN205776737U (en) * 2016-05-26 2016-12-07 南京长江都市建筑设计股份有限公司 Grouting structure at the bottom of a kind of fabricated assembly overall frame column

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193329A (en) * 2016-08-29 2016-12-07 朱凤起 Concrete wall structure and construction method thereof
CN106193329B (en) * 2016-08-29 2019-03-15 朱凤起 Concrete wall structure and its construction method
CN106480996A (en) * 2016-10-20 2017-03-08 深圳市鹏城建筑集团有限公司 A kind of method are in the milk by docking structure of levels prefabricated component and the faying face to levels prefabricated component
CN108086130B (en) * 2016-11-23 2023-10-13 重庆市中科大业建筑科技有限公司 Assembled T-shaped steel pipe constraint reinforced concrete bridge pier beam column connection node
CN108086130A (en) * 2016-11-23 2018-05-29 重庆市中科大业建筑科技有限公司 A kind of T-shaped steel tube confinement reinforced concrete bridge pier beam-column connection of assembled
CN106760224B (en) * 2016-11-25 2019-04-02 北京汇丰鸿信科技有限公司 A kind of grouting shrinkage compensation process
CN106760224A (en) * 2016-11-25 2017-05-31 北京汇丰鸿信科技有限公司 One kind grouting shrinkage compensation process
CN107700656A (en) * 2017-08-18 2018-02-16 国网上海市电力公司 A kind of prefabricated column bottom grout construction method
CN107782880B (en) * 2017-10-22 2020-01-07 山东科技大学 Multifunctional indoor soil body grouting simulation test device and test method thereof
CN107782880A (en) * 2017-10-22 2018-03-09 山东科技大学 Grouting in soil mass simulation test device and its test method in a kind of multifunctional room
CN109555272A (en) * 2018-12-26 2019-04-02 合肥工业大学 A kind of grouting mouth is in upper reinforcing bar connection grout sleeve
CN109853862A (en) * 2019-03-06 2019-06-07 河北冀科工程项目管理有限公司 A kind of assembly prefabricated components series connection sleeve connection structure and grouting method
CN110593486A (en) * 2019-09-25 2019-12-20 中国电力工程顾问集团中南电力设计院有限公司 Assembled concrete column node connection structure
CN112211319A (en) * 2020-10-13 2021-01-12 上海城建市政工程(集团)有限公司 Same-layer grouting method for mounting prefabricated shear wall of fabricated building
CN112302165A (en) * 2020-10-16 2021-02-02 上海市建筑科学研究院有限公司 Box-shaped sleeve type connecting structure of assembled concrete member, construction method and application

Similar Documents

Publication Publication Date Title
CN105863049A (en) Prefabricated assembled integral framework column bottom grouting structure
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN202831402U (en) Concrete filled steel tubular column with inner-connected circular pipe and outer-sleeved concrete filled steel tube
CN105544801A (en) Bolted connection technique for prefabricated large plate shear wall provided with concealed bracing and construction method
CN205954921U (en) Novel big board shear wall structure is secretly supported in bolted connection's prefabricated assembled area
CN101769154A (en) Excavation supporting method for tunnel construction
CN102561553A (en) Prefabricated concrete-filled steel tube frame-shear wall and construction method thereof
CN205776737U (en) Grouting structure at the bottom of a kind of fabricated assembly overall frame column
CN203821876U (en) Concrete column reinforcement device
CN108385871A (en) The precast wall body of fabricated structure
CN103603434A (en) Transitional junction from concrete-filled steel tube combination column to reinforced concrete column
CN203769116U (en) Prefabricated through hole assembly type reinforced concrete shear wall
CN203961099U (en) A kind of high strength hollow constructional column template brick and the constructional column of building thereof
CN203160540U (en) Novel precast column
CN205907846U (en) Prevent structure of a secondary structure and two secondary structure handing -over department feather checkings
CN107761764A (en) It is a kind of can independent assortment prefabricated piping lane system and construction method
CN204551897U (en) With the steel framework post of joint type linkage
CN106193902A (en) A kind of prefabricated window and installation method of wafing
CN204491678U (en) For the attractive joint of outer wall of basement
CN106400960A (en) Building framework
CN106401191B (en) Grouting device for steel shear structure assembly type building and construction method thereof
CN204728484U (en) A kind of precast concrete primary-secondary beam syndeton
CN104153361B (en) Prestressed concrete pipe pile underground pile connection construction method
CN105971117B (en) A kind of pseudo-classic architecture steel-frame structure using Box section beam
CN104452962A (en) Built-in inverted-corbel type concrete structure frame beam-column joint

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160817