CN205242683U - Shear wall structure is connected to combined type - Google Patents
Shear wall structure is connected to combined type Download PDFInfo
- Publication number
- CN205242683U CN205242683U CN201521012719.3U CN201521012719U CN205242683U CN 205242683 U CN205242683 U CN 205242683U CN 201521012719 U CN201521012719 U CN 201521012719U CN 205242683 U CN205242683 U CN 205242683U
- Authority
- CN
- China
- Prior art keywords
- shear
- shear wall
- key
- grouting
- keyway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
- 230000002787 reinforcement Effects 0.000 claims description 17
- 229910000831 Steel Inorganic materials 0.000 claims description 12
- 239000010959 steel Substances 0.000 claims description 12
- 150000001875 compounds Chemical class 0.000 claims description 5
- 239000011440 grout Substances 0.000 claims description 4
- 239000002002 slurry Substances 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims 2
- 239000002131 composite material Substances 0.000 abstract description 19
- 238000010276 construction Methods 0.000 abstract description 13
- 230000003993 interaction Effects 0.000 abstract description 3
- 230000006835 compression Effects 0.000 abstract description 2
- 238000007906 compression Methods 0.000 abstract description 2
- 239000000463 material Substances 0.000 description 7
- 238000005516 engineering process Methods 0.000 description 4
- 210000001503 joint Anatomy 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 230000021715 photosynthesis, light harvesting Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Sewage (AREA)
Abstract
本实用新型公开了一种复合式连接剪力墙结构。包括N块结构相同的剪力墙构件,每两块剪力墙构件之间通过复合抗剪键和键槽连接,构成复合式连接剪力墙。因复合抗剪键与键槽的相互导入作用,提高施工精度,避免因装配不准的偏心受压的产生;因下方剪力墙构件上的抗剪键可以在装配下一层时承担上方剪力墙构件的重量,故在楼板浇筑完成后无需等待楼板混凝土达到强度,可以马上进行上一层墙体的装配,可以大大缩短楼层的装配周期;下方剪力墙构件的抗剪键嵌入上方剪力墙构件的键槽之中,抗剪键能够承担横向剪力作用,加强结构的抗剪性能,增强结构可靠度。
The utility model discloses a composite connection shear wall structure. It includes N pieces of shear wall components with the same structure, and every two shear wall components are connected by composite shear keys and key grooves to form a composite connected shear wall. Due to the interaction between the composite shear key and the keyway, the construction accuracy is improved, and the eccentric compression caused by inaccurate assembly is avoided; because the shear key on the lower shear wall member can bear the upper shear force when the next layer is assembled The weight of the wall components, so there is no need to wait for the floor concrete to reach strength after the floor is poured, and the upper wall can be assembled immediately, which can greatly shorten the assembly cycle of the floor; the shear keys of the lower shear wall components are embedded in the upper shear force In the keyway of the wall member, the shear key can bear the transverse shear force, strengthen the shear performance of the structure, and enhance the reliability of the structure.
Description
技术领域 technical field
本实用新型涉及一种装配式剪力墙结构,具体涉及一种复合式连接剪力墙结构。 The utility model relates to an assembled shear wall structure, in particular to a composite connection shear wall structure.
背景技术 Background technique
相对于传统现浇混凝土结构,装配式混凝土结构具有构件质量好、施工工期短、资源使用少、生产浪费少等诸多优点。其主要特点是主要结构构件在工厂预制,然后通过车辆运输等方式将构件运送到施工现场,在现场通过机械吊装等方式进行构件拼装和连接,大量施工现场作业工作被工厂集中生产所代替。 Compared with the traditional cast-in-place concrete structure, the prefabricated concrete structure has many advantages such as good component quality, short construction period, less resource use, and less production waste. Its main feature is that the main structural components are prefabricated in the factory, and then the components are transported to the construction site by means of vehicle transportation, etc., and the components are assembled and connected by means of mechanical hoisting on site. A large number of construction site operations are replaced by centralized production in the factory.
套筒灌浆技术是装配式混凝土剪力墙结构连接上下剪力墙的普遍做法之一。施工时将下部剪力墙顶部的预留钢筋插入到上部剪力墙中预埋好的对接套筒中,然后用灌浆机向套筒内注入灌浆材料,待灌浆材料硬化后,钢筋与套筒之间即牢固地连接在一起。现有研究结果表明,采用套筒灌浆连接的剪力墙构件连接节点的抗弯强度基本等同于现浇混凝土节点,且其延性及耗能能力也较为可靠。但采用传统套筒灌浆施工工艺连接的上下墙体间往往难以实现精确对接,极易造成上下层剪力墙体之间错位的现象产生,这不仅对建筑外观和防水性能造成不利影响,还会因剪力墙偏心受压而影响结构的安全性。此外,现有相关规范规定楼板必须要有现浇层,而采用现有施工工艺装配上部剪力墙体,必须要等楼板混凝土达到一定强度后才能进行,这将减缓施工进度。 Sleeve grouting technology is one of the common methods for connecting upper and lower shear walls in prefabricated concrete shear wall structures. During construction, insert the reserved steel bar at the top of the lower shear wall into the pre-buried butt joint sleeve in the upper shear wall, and then inject grouting material into the sleeve with a grouting machine. After the grouting material hardens, the steel bar and the sleeve are firmly connected together. The existing research results show that the flexural strength of the joints of shear wall members connected by sleeve grouting is basically the same as that of cast-in-place concrete joints, and its ductility and energy dissipation capacity are also relatively reliable. However, it is often difficult to achieve precise docking between the upper and lower walls connected by the traditional sleeve grouting construction technology, which can easily cause misalignment between the upper and lower shear walls, which not only adversely affects the appearance and waterproof performance of the building, but also The safety of the structure is affected by the eccentric compression of the shear wall. In addition, the existing relevant regulations stipulate that the floor slab must have a cast-in-situ layer, and the assembly of the upper shear wall with the existing construction technology must wait for the floor concrete to reach a certain strength before proceeding, which will slow down the construction progress.
实用新型内容 Utility model content
本实用新型的目的在于提供一种复合式连接剪力墙结构,解决了传统套筒灌浆连接的剪力墙的不足,以提高装配式剪力墙施工的准确性和便利性。 The purpose of the utility model is to provide a composite connection shear wall structure, which solves the shortcomings of the traditional sleeve grouting connection shear wall, so as to improve the accuracy and convenience of the assembly shear wall construction.
为达了达到上述目的,本实用新型采用的技术方案是: In order to achieve the above object, the technical solution adopted in the utility model is:
本实用新型包括N块结构相同的剪力墙构件,每两块剪力墙构件之间通过复合抗剪键和键槽连接,构成复合式连接剪力墙。 The utility model comprises N shear wall components with the same structure, and every two shear wall components are connected by composite shear keys and key grooves to form a composite connected shear wall.
所述每块剪力墙构件上端两侧均预埋有1-2排纵向钢筋,上端中间至少设置一个复合抗剪键,复合抗剪键上部为抗剪键嵌入部分,下部为抗剪键埋入部分,抗剪键埋入部分的形状为长方体,高度与叠合楼板的厚度相等,宽度小于剪力墙的厚度,并设置有多个供剪力墙两侧的叠合楼板钢筋连接的楼板钢筋预留孔;抗剪键嵌入部分的形状为四棱台,四棱台的底面尺寸与抗剪键埋入部分相同,四棱台的顶部平面预埋一排供灌浆连接用的纵向钢筋;剪力墙构件下端两侧均设有灌浆套筒,下端中间至少设置一个键槽,灌浆套筒预埋的位置与剪力墙构件上端预埋的纵向钢筋的位置相对应,并在侧面设有多个供灌浆用的注浆孔与出浆孔,多个供灌浆用的注浆孔与出浆孔分别与各自的灌浆套筒连通;键槽为下凹的四棱台,其形状和尺寸均与抗剪键嵌入部分相同。 1-2 rows of longitudinal steel bars are pre-embedded on both sides of the upper end of each shear wall member, and at least one composite shear key is arranged in the middle of the upper end. The shape of the embedded part of the shear key is a cuboid, the height is equal to the thickness of the laminated floor, and the width is smaller than the thickness of the shear wall, and there are multiple floors for the connection of the laminated floor reinforcement on both sides of the shear wall Reserved holes for steel bars; the shape of the embedded part of the shear key is a square truss, the size of the bottom surface of the four prism is the same as that of the embedded part of the shear key, and a row of longitudinal steel bars for grouting connection is pre-embedded on the top plane of the four prism; Both sides of the lower end of the shear wall member are provided with grouting sleeves, and at least one keyway is provided in the middle of the lower end. A grouting hole and a grouting hole for grouting, and a plurality of grouting holes and grouting holes for grouting are respectively connected with their respective grouting sleeves; the keyway is a concave quadrangular platform, and its shape and size are consistent with the grouting sleeve. The shear key embedding part is the same.
所述键槽靠近剪力墙构件墙体两侧处分别设置一道U型加固用的钢丝网。 A U-shaped steel wire mesh for reinforcement is respectively arranged at the two sides of the wall body of the shear wall member close to the keyway.
本实用新型与背景技术相比具有的有益效果是: The beneficial effect that the utility model has compared with background technology is:
1.因复合抗剪键与键槽的相互导入作用,可以使墙体在施工装配时更加简便、精确,减少装配工作量,提高施工精度,避免因装配不准的偏心受压的产生; 1. Due to the interaction between the composite shear key and the keyway, it can make the construction and assembly of the wall more convenient and accurate, reduce the assembly workload, improve the construction accuracy, and avoid the occurrence of eccentric pressure due to inaccurate assembly;
2.因下方剪力墙构件上的抗剪键可以在装配下一层时承担上方剪力墙构件的重量,故在楼板浇筑完成后无需等待楼板混凝土达到强度,可以马上进行上一层墙体的装配,可以大大缩短楼层的装配周期; 2. Because the shear key on the lower shear wall component can bear the weight of the upper shear wall component when the next layer is assembled, there is no need to wait for the floor concrete to reach strength after the floor is poured, and the upper layer of wall can be carried out immediately The assembly of the floor can greatly shorten the assembly cycle of the floor;
3.下方剪力墙构件的抗剪键嵌入上方剪力墙构件的键槽之中,抗剪键能够承担横向剪力作用,加强结构的抗剪性能,增强结构可靠度。 3. The shear key of the lower shear wall component is embedded in the keyway of the upper shear wall component. The shear key can bear the transverse shear force, strengthen the shear performance of the structure, and enhance the reliability of the structure.
附图说明 Description of drawings
图1是本实用新型剪力墙构件的立体图。 Fig. 1 is a perspective view of a shear wall member of the present invention.
图2是图1的仰视图。 Fig. 2 is a bottom view of Fig. 1 .
图3是两块剪力墙构件装配后的立体图(未画出叠合楼板)。 Figure 3 is a perspective view of two shear wall components after assembly (the laminated floor is not drawn).
图4是图3的A-A局部剖视图。 Fig. 4 is a partial cross-sectional view along line A-A of Fig. 3 .
图5是本实用新型剪力墙构件的立体图。 Fig. 5 is a perspective view of a shear wall component of the present invention.
图6是本实用新型剪力墙构件与叠合楼板预制部分装配后的立体图。 Fig. 6 is a perspective view of the shear wall member of the present invention after being assembled with the prefabricated part of the laminated floor.
图7是本实用新型剪力墙构件与叠合楼板装配后的立体图。 Fig. 7 is a perspective view of the assembled shear wall member and laminated floor slab of the present invention.
图8是本实用新型两块剪力墙构件与预制叠合楼板装配后的立体图。 Fig. 8 is a perspective view after assembly of two shear wall components and prefabricated laminated floor slabs of the present invention.
图中:1、剪力墙构件,2、纵向钢筋,3、复合抗剪键,4、抗剪键嵌入部分,5、抗剪键埋入部分,6、楼板钢筋预留孔,7、灌浆套筒,8、键槽,9、注浆孔,10、出浆孔,11、加固用钢丝网,12、叠合楼板,13、叠合楼板预制部分,14、楼板上部钢筋,15、楼板加固钢筋,16、叠合楼板现浇部分,17、坐浆层。 In the figure: 1. Shear wall component, 2. Longitudinal reinforcement, 3. Composite shear key, 4. Embedded part of shear key, 5. Embedded part of shear key, 6. Reserved hole for floor reinforcement, 7. Grouting Sleeve, 8, keyway, 9, grouting hole, 10, grouting hole, 11, steel wire mesh for reinforcement, 12, laminated floor slab, 13, prefabricated part of laminated floor slab, 14, upper reinforcement of floor slab, 15, floor slab reinforcement Steel bars, 16, the cast-in-place part of the laminated floor, 17, the slurry layer.
具体实施方式 detailed description
下面结合附图和实施例对本实用新型做进一步说明。 Below in conjunction with accompanying drawing and embodiment the utility model is described further.
如图1、图2、图3所示,本实用新型包括N块结构相同的剪力墙构件1,每两块剪力墙构件之间通过复合抗剪键3和键槽8连接,构成复合式连接剪力墙。 As shown in Fig. 1, Fig. 2 and Fig. 3, the utility model includes N shear wall members 1 with the same structure, and every two shear wall members are connected by a composite shear key 3 and a keyway 8 to form a composite Connect shear walls.
所述每块剪力墙构件1上端两侧预埋有1-2排(图1、图3中为2排)纵向钢筋2,上端中间至少设置一个复合抗剪键3(图1~3中复合抗剪键为1个),复合抗剪键上部为抗剪键嵌入部分4,下部为抗剪键埋入部分5,抗剪键埋入部分5的形状为长方体,高度与叠合楼板12的厚度相等,宽度小于剪力墙的厚度,并设置有多个供剪力墙两侧的叠合楼板12钢筋连接的楼板钢筋预留孔6;抗剪键嵌入部分4的形状为四棱台,四棱台的底面尺寸与抗剪键埋入部分5相同,四棱台的顶部平面预埋一排供灌浆连接用的纵向钢筋2;剪力墙构件下端两侧均设有灌浆套筒7,下端中间至少设置一个键槽(图2中键槽为1个),灌浆套筒7预埋的位置与剪力墙构件1上端预埋的纵向钢筋2的位置相对应,并在侧面设有多个供灌浆用的注浆孔9与出浆孔10,多个供灌浆用的注浆孔9与出浆孔10分别与各自的灌浆套筒7连通;键槽8为下凹的四棱台,其形状和尺寸均与抗剪键嵌入部分4相同。 1-2 rows (2 rows in Fig. 1 and Fig. 3) of longitudinal steel bars 2 are pre-buried on both sides of the upper end of each shear wall member 1, and at least one composite shear key 3 is arranged in the middle of the upper end (Fig. 1-3). One composite shear key), the upper part of the composite shear key is the embedded part 4 of the shear key, and the lower part is the embedded part 5 of the shear key. The thickness is equal to the thickness of the shear wall, and the width is smaller than the thickness of the shear wall, and there are a plurality of reserved holes 6 for the reinforcement of the laminated floor 12 on both sides of the shear wall to connect the steel bars; the shape of the shear key embedded part 4 is a square platform , the size of the bottom surface of the four-sided platform is the same as that of the embedded part 5 of the shear key, and a row of longitudinal steel bars 2 for grouting connection is pre-embedded on the top plane of the four-sided platform; grouting sleeves 7 are arranged on both sides of the lower end of the shear wall member , at least one keyway is set in the middle of the lower end (there is one keyway in Figure 2), the pre-embedded position of the grouting sleeve 7 corresponds to the position of the pre-embedded longitudinal reinforcement 2 at the upper end of the shear wall member 1, and there are multiple The grouting hole 9 and the grouting hole 10 for grouting, a plurality of grouting holes 9 and the grouting hole 10 for grouting are communicated with the grouting sleeve 7 respectively; The shape and size are the same as the shear key embedded part 4.
如图4所示,考虑到键槽8在墙体两侧部分较为薄弱,在键槽8靠近剪力墙构件1墙体两侧处分别设置一道U型加固用的钢丝网11,防止其在运输和装配中被破坏。 As shown in Figure 4, considering that the keyway 8 is relatively weak on both sides of the wall, a U-shaped steel wire mesh 11 for reinforcement is respectively arranged on both sides of the keyway 8 close to the wall of the shear wall member 1 to prevent it from being transported. was destroyed during assembly.
如图5~图8所示,本实用新型剪力墙的施工装配过程如下: As shown in Figures 5 to 8, the construction and assembly process of the shear wall of the utility model is as follows:
1)叠合楼板吊装与浇筑: 1) Hoisting and pouring of laminated slabs:
首先如图5所示,装配好第一块剪力墙构件1后,即可进行预制叠合楼板12的吊装与浇筑工作。如图6所示,利用吊车将预制叠合楼板预制部分13吊装并支撑放置在剪力墙构件1的两侧;架设并绑扎楼板上部钢筋14;向剪力墙抗剪键中的板筋预留孔6内插入楼板加固钢筋15,并使楼板加固钢筋15与楼板上部钢筋14有效连接;利用泵送混凝土对叠合楼板现浇部分16进行浇筑,边浇筑边振捣,直到混凝土表面达到复合抗剪键3的抗剪键嵌入部分4与抗剪键埋入部分5的分界线时停止浇筑。如图7所示,待楼板浇筑完毕后第一块剪力墙构件1的复合抗剪键3只有其上部的抗剪键嵌入部分4露出于楼板表面。 First, as shown in FIG. 5 , after the first shear wall component 1 is assembled, the hoisting and pouring of the prefabricated laminated floor 12 can be carried out. As shown in Figure 6, the prefabricated laminated floor slab prefabricated part 13 is hoisted and supported by a crane and placed on both sides of the shear wall member 1; the upper reinforcement 14 of the floor slab is erected and bound; Insert the floor reinforcement bars 15 into the holes 6, and effectively connect the floor reinforcement bars 15 with the upper reinforcement bars 14 of the floor; use pumped concrete to pour the cast-in-place part 16 of the laminated floor, and vibrate while pouring until the concrete surface reaches a composite level. Stop pouring when the boundary line between the shear key embedded part 4 and the shear key embedded part 5 of the shear key 3 is reached. As shown in Figure 7, only the upper shear key embedded part 4 of the composite shear key 3 of the first shear wall member 1 is exposed on the floor surface after the floor slab is poured.
2)第二块剪力墙构件装配前准备: 2) Preparations before assembly of the second shear wall component:
确定构件的吊装顺序,将需要装配的构件按次序叠放以便于现场吊装安排;检查和清理剪力墙构件1的灌浆套筒7及其注浆孔9和出浆孔10,防止被杂物堵塞,保证后续灌浆工作的顺利进行;清理叠合楼板12、复合抗剪键3与第二块剪力墙构件1之间的结合面,并在结合面上铺设一层灌浆料作为坐浆层17用以黏结两块剪力墙构件; Determine the hoisting sequence of the components, and stack the components to be assembled in order to facilitate on-site hoisting arrangements; check and clean the grouting sleeve 7 of the shear wall component 1 and its grouting hole 9 and grouting hole 10 to prevent debris from being To ensure the smooth progress of the subsequent grouting work; clean the joint surface between the laminated floor 12, the composite shear key 3 and the second shear wall member 1, and lay a layer of grouting material on the joint surface as the sitting grout layer 17 is used to bond two shear wall components;
3)第二块剪力墙构件装配作业: 3) Assembly of the second shear wall component:
因复合抗剪键3作用,第二块剪力墙构件1在装配时由第一块剪力墙构件1的复合抗剪键3支承,无需等待楼板混凝土达到强度后再进行第二块剪力墙构件装配,可大大缩短施工周期。装配时用吊车将第二块剪力墙构件吊装到第一块剪力墙的预定位置上方,然后降低构件位置,使第一块剪力墙的纵向钢筋2能够插入到第二块剪力墙的灌浆套筒7中,并使露出于叠合楼板12之上的第一块剪力墙构件1的抗剪键嵌入部分4插入第二块剪力墙构件1的键槽8中。因为键槽8与抗剪键嵌入部分4周围的四个侧面均为斜面且形状相互吻合,第二块剪力墙构件1将在自重作用下依靠键槽8和抗剪键嵌入部分4之间的相互作用而自动准确地落到预定的平面位置,无需再进行人工调整;之后,只需检查调整第二块剪力墙的垂直度即可; Due to the action of the compound shear key 3, the second shear wall element 1 is supported by the compound shear key 3 of the first shear wall element 1 during assembly, and there is no need to wait for the floor concrete to reach strength before performing the second shear force The assembly of wall components can greatly shorten the construction period. During assembly, hoist the second shear wall component above the predetermined position of the first shear wall with a crane, and then lower the position of the component so that the longitudinal reinforcement 2 of the first shear wall can be inserted into the second shear wall grouting sleeve 7, and insert the shear key embedded part 4 of the first shear wall component 1 exposed above the laminated floor 12 into the key groove 8 of the second shear wall component 1. Because the four sides around the keyway 8 and the shear key embedded part 4 are inclined planes and the shapes match each other, the second shear wall member 1 will rely on the interaction between the keyway 8 and the shear key embedded part 4 under its own weight. It automatically and accurately falls to the predetermined plane position without manual adjustment; after that, it is only necessary to check and adjust the verticality of the second shear wall;
4)灌浆连接: 4) Grouting connection:
在第二块剪力墙构件1安装完毕后,对其进行灌浆连接,使两块剪力墙构件1连接成整体。采用压力注浆的方式对灌浆套筒7进行压力注浆,为保证灌浆料密实地填满整个灌浆套筒7,从注浆孔9向灌浆套筒7内注入灌浆料,待出浆孔10流出灌浆料之后即可封闭出浆孔和注浆孔;待灌浆料凝结硬化后,上下剪力墙墙体即连接成整体。连接完成的剪力墙如图8所示。 After the second shear wall component 1 is installed, it is connected by grouting, so that the two shear wall components 1 are connected into a whole. The grouting sleeve 7 is pressure grouted by means of pressure grouting. In order to ensure that the grouting material fills the entire grouting sleeve 7 densely, the grouting material is injected into the grouting sleeve 7 from the grouting hole 9 until the grouting hole 10 After the grouting material flows out, the grouting hole and the grouting hole can be closed; after the grouting material is solidified and hardened, the upper and lower shear walls are connected into a whole. The completed shear wall is shown in Figure 8.
重复步骤1-4,即能装配需要的层数。 Repeat steps 1-4 to assemble the required layers.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521012719.3U CN205242683U (en) | 2015-12-09 | 2015-12-09 | Shear wall structure is connected to combined type |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521012719.3U CN205242683U (en) | 2015-12-09 | 2015-12-09 | Shear wall structure is connected to combined type |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205242683U true CN205242683U (en) | 2016-05-18 |
Family
ID=55941761
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201521012719.3U Withdrawn - After Issue CN205242683U (en) | 2015-12-09 | 2015-12-09 | Shear wall structure is connected to combined type |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205242683U (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105442727A (en) * | 2015-12-09 | 2016-03-30 | 浙江大学 | Compound type connection shear wall structure and assembling method thereof |
CN107023071A (en) * | 2017-03-15 | 2017-08-08 | 温州市阳光建设有限公司 | A kind of assembled architecture of modularized design |
CN107740509A (en) * | 2017-11-13 | 2018-02-27 | 杭萧钢构股份有限公司 | A kind of splicing node of steel plate combined shear wall |
CN109667351A (en) * | 2019-01-16 | 2019-04-23 | 中南大学 | Assembled architecture prefabricated panel horizontal joint mud jacking Alveolus type waterproof connecting structure |
CN110359450A (en) * | 2019-07-29 | 2019-10-22 | 中铁二院工程集团有限责任公司 | Assembled circle pilework and construction method |
CN111663676A (en) * | 2020-06-08 | 2020-09-15 | 浙江大道建设工程有限公司 | Heat-insulating wall and construction method thereof |
CN112095777A (en) * | 2020-09-15 | 2020-12-18 | 湖北正茂新材料科技股份有限公司 | High-strength prefabricated part convenient to install |
CN114427269A (en) * | 2022-03-02 | 2022-05-03 | 深圳市景鹏建设工程有限公司 | Green energy-saving prefabricated component for assembly type building wall |
CN115822133A (en) * | 2022-12-20 | 2023-03-21 | 同济大学 | Single row bolt precast concrete shear wall structure and construction method using UHPC concealed beams |
-
2015
- 2015-12-09 CN CN201521012719.3U patent/CN205242683U/en not_active Withdrawn - After Issue
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105442727A (en) * | 2015-12-09 | 2016-03-30 | 浙江大学 | Compound type connection shear wall structure and assembling method thereof |
CN107023071A (en) * | 2017-03-15 | 2017-08-08 | 温州市阳光建设有限公司 | A kind of assembled architecture of modularized design |
CN107023071B (en) * | 2017-03-15 | 2019-11-15 | 温州市阳光建设有限公司 | A kind of assembled architecture of modularized design |
CN107740509B (en) * | 2017-11-13 | 2023-09-12 | 杭萧钢构股份有限公司 | Splicing node of steel plate combined shear wall |
CN107740509A (en) * | 2017-11-13 | 2018-02-27 | 杭萧钢构股份有限公司 | A kind of splicing node of steel plate combined shear wall |
CN109667351A (en) * | 2019-01-16 | 2019-04-23 | 中南大学 | Assembled architecture prefabricated panel horizontal joint mud jacking Alveolus type waterproof connecting structure |
CN109667351B (en) * | 2019-01-16 | 2024-01-30 | 中南大学 | Tooth socket type waterproof connecting structure of prefabricated wallboard horizontal joint grouting method of assembled building |
CN110359450A (en) * | 2019-07-29 | 2019-10-22 | 中铁二院工程集团有限责任公司 | Assembled circle pilework and construction method |
CN110359450B (en) * | 2019-07-29 | 2024-03-08 | 中铁二院工程集团有限责任公司 | Assembled round pile structure and construction method |
CN111663676A (en) * | 2020-06-08 | 2020-09-15 | 浙江大道建设工程有限公司 | Heat-insulating wall and construction method thereof |
CN111663676B (en) * | 2020-06-08 | 2022-02-11 | 浙江大道建设工程有限公司 | Heat-insulating wall and construction method thereof |
CN112095777B (en) * | 2020-09-15 | 2021-08-31 | 湖北正茂新材料科技股份有限公司 | High-strength prefabricated part convenient to install |
CN112095777A (en) * | 2020-09-15 | 2020-12-18 | 湖北正茂新材料科技股份有限公司 | High-strength prefabricated part convenient to install |
CN114427269A (en) * | 2022-03-02 | 2022-05-03 | 深圳市景鹏建设工程有限公司 | Green energy-saving prefabricated component for assembly type building wall |
CN115822133A (en) * | 2022-12-20 | 2023-03-21 | 同济大学 | Single row bolt precast concrete shear wall structure and construction method using UHPC concealed beams |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105442727B (en) | Composite connection shear wall structure and its assembly method | |
CN205242683U (en) | Shear wall structure is connected to combined type | |
EP3670778B1 (en) | Prefabricated frame | |
CN103104039B (en) | Assembled framework beam-column joint adopting cover plate connection and construction method thereof | |
CN103104053B (en) | A kind of assembly concrete shear wall and construction method | |
CN104264786B (en) | Steel bar connection mode of prefabricated concrete member and application thereof | |
CN105804241A (en) | Single-layer prefabricated assembly type reinforced concrete beam-column joint | |
CN104594500B (en) | Integrated slab column formwork structure system and construction method | |
CN105839846A (en) | Prefabricated reinforced concrete composite beam | |
CN108316522A (en) | The prefabricated double board wall units of one kind, assembly concrete shear wall and preparation method thereof | |
CN109518858A (en) | Fabricated Beam-Slab connection structure and its construction method | |
CN103470040A (en) | Splicing method of composite floor slab and beam | |
CN108104284B (en) | Wall panel connection structure and assembly method with steel arm of shear wall embedded in floor slab | |
CN107905424B (en) | Full-prefabricated one-way plate structure with splicing grooves, manufacturing and assembling methods | |
CN102352668B (en) | Prefabricated reinforced concrete assembled column and its manufacturing method | |
CN108086488B (en) | Assembled frame shear structure wall staggered connection structure and assembling method | |
KR101227099B1 (en) | Hybrid Column Composed of Centrifugal Concrete Cylinder with Steel Skeleton & Steel Bars | |
CN108018972B (en) | Full prefabricated floor slab and composite floor slab combined structure, manufacturing and assembling method | |
KR101211332B1 (en) | Connecting Structure between Pre-Stressed Concrete Girder and Precast Panel | |
CN211312950U (en) | Assembled integral elevator shaft prefabricated part | |
CN217711170U (en) | A kind of precast concrete slab splicing joint based on tenon and tenon joint | |
CN108775086A (en) | The additional assembled integral beam-column node structure and construction method for being closed connection reinforcing bar | |
CN209227836U (en) | Prefabricated concrete structure wall-column full steel key connection structure | |
CN215166455U (en) | Low, multi-layer fully prefabricated assembled concrete structure | |
CN212772979U (en) | Prestress assembly type shear wall system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20160518 Effective date of abandoning: 20170804 |
|
AV01 | Patent right actively abandoned |
Granted publication date: 20160518 Effective date of abandoning: 20170804 |