CN105350417A - High-cold roadbed frozen soil heat insulation construction method - Google Patents
High-cold roadbed frozen soil heat insulation construction method Download PDFInfo
- Publication number
- CN105350417A CN105350417A CN201510649896.0A CN201510649896A CN105350417A CN 105350417 A CN105350417 A CN 105350417A CN 201510649896 A CN201510649896 A CN 201510649896A CN 105350417 A CN105350417 A CN 105350417A
- Authority
- CN
- China
- Prior art keywords
- roadbed
- ice
- height
- subgrade
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/06—Methods or arrangements for protecting foundations from destructive influences of moisture, frost or vibration
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
- Railway Tracks (AREA)
Abstract
The present invention discloses a high-cold roadbed frozen soil heat insulation construction method comprising the following steps: (1) according to whole-line frozen soil exploration data, a whole-line frozen soil roadbed is divided into three sections, namely, a less-ice and much-ice frozen soil area, a rich-ice and full-ice frozen soil area and a soil-containing ice layer road section, (2) the less-ice and much-ice frozen soil area is constructed, (3) the rich-ice and full-ice frozen soil area is constructed, and (4) the soil-containing ice layer road section is constructed. By control of the key technology, the problem of discharge of water in the slope toe of a roadbed with large ground lateral slope, and a frozen layer on the top of a cutting slope can be well solved, water sources can be effectively led away from the roadbed bottom to ensure the permafrost roadbed and the cutting slope are not eroded by overground water, permafrost region roadbed frost heaving and thaw collapse damage can be effectively prevented, permafrost region roadbed and road construction is normalized and standardized, the mechanistic organization is reasonable, and by sectional parallel operation and in-section assembly line operation, work efficiency is improved, construction quality is ensured, and the benefits are more prominent.
Description
Technical field
The present invention relates to a kind of high and cold roadbed frozen soil thermal-insulation construction method.
Background technology
Along with the fast development of highway in China building cause, high latitude in recent years, extremely frigid zones starts to build highway successively, because highway alignment permafrost distribution is wider, complicated hydrogeological conditions, when highway is implemented, generally only implement roadbed, bridges and culverts, the engineering such as draining and protection, road pavement is not implemented temporarily, all the other sections equal makings asphalt concrete pavement, through runing for many years, above section major part roadbed situation is better, but due to the non-making in road surface, roadbed end face is uneven, and there is the diseases such as frost boiling in various degree in local roadbed, govern the resource transport traffic capacity, the present invention is in conjunction with the disease conditions of existing highway and hydrogeological characteristics, Disease Treatment process is carried out to above section, unimpeded to ensure the transport of highway completely, improve highway capacity along the line.
Summary of the invention
The present invention is exactly for the problems referred to above, provides a kind of high and cold roadbed frozen soil thermal-insulation construction method, can ensure subgrade in permafrost soil zone and cutting not by the erosion of ground water, effectively can prevent and treat the generation of permafrost area embankment frost heave, thaw collapse disease.
For realizing above-mentioned purpose of the present invention, the present invention adopts following technical scheme, and the heat insulation construction of a kind of high and cold roadbed frozen soil, is characterized in that, comprise the following steps:
(1) according to all fronts frozen soil prospecting data, be divided into three section by frozen earth roadbed completely, be respectively few ice, many ice permafrost region, Fu Bing, full ice permafrost region and contain native ice sheet section;
(2) few ice, many ice permafrost region are constructed: by adding elevated formation level analysis to former Subgrade of old road height and this, section is high-end is all greater than 2.0m for major part, and according to field investigation, roadbed filling fills with boulder and cobble soil, gravelly soil substantially, and roadbed situation is better, therefore this no longer carries out specially treated, by general subgrade process, only strengthen draining, preventive works, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affects subgrade stability;
(3) rich ice, full ice permafrost region are constructed: by adding elevated formation level analysis to former Subgrade of old road height and this, major part section is high-end is all greater than rational height of roadbed as calculated and critical height of subgrade, therefore for ensureing subgrade stability, take roadbed both sides that insulation banket is set, banket width and height, when roadbed height is greater than 3.0m, banket width 3.0m, height 1.5m; When roadbed height is less than 3.0m, banket width 3.0m, height 1.2m, and strengthen roadbed both sides waterproof and drainage design, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affects subgrade stability;
(4) construct to containing native ice sheet section:
A () is less than the embankment of 1.8m for roadbed raising, partly fill out and partly dig and cut subgrade, consider in Permafrost Area, grit Pavement Improvement is after flexible pavement, ever-frozen ground will occur significantly to degenerate, frozen earth roadbed heat stability constantly worsens, therefore for ensureing roadbed temperature, this design 50cm place below bed course arranges thick layer 6cmXSP warming plate isolation layer, with the subgrade defect that protection of permafrost steady change causes, and strengthen roadbed both sides waterproof and drainage design, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affect subgrade stability, simultaneously according to roadbed height, topographic features is provided with wide 3.0m, high 1.2 ~ 1.5m is incubated banket,
B () is for the filled-up ground of roadbed raising 1.8 < H≤2.5m, for ensureing subgrade stability, this adopts the existing old road of cutouts and arranges sheet, block stone ventilated embankment, sheet, block stone ventilation thickness 0.8m, on it thick macadam of making 20cm levelling after carry out heavy type and roll, then making 20cm grit leveling, loaded filter, the levelling size controlling of rubble is at 5 ~ 10cm;
C () is for roadbed raising H > 2.5m, this considers that roadbed height is higher, and old road based filler is better, and existing old road base resistance to overturning is better, therefore take to arrange insulation banket in roadbed both sides, the wide 3.0m of banket, high 1.2 ~ 1.5m;
D () is for section of bursting and become muddy when a thaw sets in along the line, take according to roadbed raising and topographic features: 1.8m section is greater than for roadbed raising, after taking to excavate old road frost boiling part to stabilized zone position, rubble ventilation embankment is set, sheet, block stone ventilation thickness 0.8m, it carries out heavy type after thick macadam leveling layer of making 20cm roll, then making 20cm grit leveling, loaded filter, the levelling size controlling of rubble is at 5 ~ 10cm; Roadbed raising is less than to embankment and the excavation section of 1.8m, after taking to excavate old road part, roadbed scope (80cm) is changed and fills out grit process, and thick layer 6cmXSP warming plate isolation layer is set at 50cm place, bottom surface, road surface.
The invention has the beneficial effects as follows: this high and cold roadbed frozen soil thermal-insulation construction method, by the control of key technology, solve the roadbed toe that lateral slope of ground is larger preferably, the rafting problem of cutting top suprapermafrost water, effectively water source is deflected from the bottom of roadbed, ensure subgrade in permafrost soil zone and cutting not by the erosion of ground water, can effectively prevent and treat permafrost area embankment frost heave, the generation of thaw collapse disease, permafrost area embankment, pavement construction standardizes, standardization, mechanization tissue is reasonable, by piecewise-parallel operation, continuous productive process in section, increase work efficiency, ensure construction quality, its benefit is more outstanding.
Detailed description of the invention
A kind of method utilizing earthworm to raise chickens of the present invention:
(1) according to all fronts frozen soil prospecting data, be divided into three section by frozen earth roadbed completely, be respectively few ice, many ice permafrost region, Fu Bing, full ice permafrost region and contain native ice sheet section;
(2) few ice, many ice permafrost region are constructed: by adding elevated formation level analysis to former Subgrade of old road height and this, section is high-end is all greater than 2.0m for major part, and according to field investigation, roadbed filling fills with boulder and cobble soil, gravelly soil substantially, and roadbed situation is better, therefore this no longer carries out specially treated, by general subgrade process, only strengthen draining, preventive works, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affects subgrade stability;
(3) rich ice, full ice permafrost region are constructed: by adding elevated formation level analysis to former Subgrade of old road height and this, major part section is high-end is all greater than rational height of roadbed as calculated and critical height of subgrade, therefore for ensureing subgrade stability, take roadbed both sides that insulation banket is set, banket width and height, when roadbed height is greater than 3.0m, banket width 3.0m, height 1.5m; When roadbed height is less than 3.0m, banket width 3.0m, height 1.2m, and strengthen roadbed both sides waterproof and drainage design, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affects subgrade stability;
(4) construct to containing native ice sheet section:
A () is less than the embankment of 1.8m for roadbed raising, partly fill out and partly dig and cut subgrade, consider in Permafrost Area, grit Pavement Improvement is after flexible pavement, ever-frozen ground will occur significantly to degenerate, frozen earth roadbed heat stability constantly worsens, therefore for ensureing roadbed temperature, this design 50cm place below bed course arranges thick layer 6cmXSP warming plate isolation layer, with the subgrade defect that protection of permafrost steady change causes, and strengthen roadbed both sides waterproof and drainage design, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affect subgrade stability, simultaneously according to roadbed height, topographic features is provided with wide 3.0m, high 1.2 ~ 1.5m is incubated banket,
B () is for the filled-up ground of roadbed raising 1.8 < H≤2.5m, for ensureing subgrade stability, this adopts the existing old road of cutouts and arranges sheet, block stone ventilated embankment, sheet, block stone ventilation thickness 0.8m, on it thick macadam of making 20cm levelling after carry out heavy type and roll, then making 20cm grit leveling, loaded filter, the levelling size controlling of rubble is at 5 ~ 10cm;
C () is for roadbed raising H > 2.5m, this considers that roadbed height is higher, and old road based filler is better, and existing old road base resistance to overturning is better, therefore take to arrange insulation banket in roadbed both sides, the wide 3.0m of banket, high 1.2 ~ 1.5m;
D () is for section of bursting and become muddy when a thaw sets in along the line, take according to roadbed raising and topographic features: 1.8m section is greater than for roadbed raising, after taking to excavate old road frost boiling part to stabilized zone position, rubble ventilation embankment is set, sheet, block stone ventilation thickness 0.8m, it carries out heavy type after thick macadam leveling layer of making 20cm roll, then making 20cm grit leveling, loaded filter, the levelling size controlling of rubble is at 5 ~ 10cm; Roadbed raising is less than to embankment and the excavation section of 1.8m, after taking to excavate old road part, roadbed scope (80cm) is changed and fills out grit process, and thick layer 6cmXSP warming plate isolation layer is set at 50cm place, bottom surface, road surface.
To those skilled in the art, obviously the invention is not restricted to the details of above-mentioned one exemplary embodiment, and when not deviating from spirit of the present invention or essential characteristic, the present invention can be realized in other specific forms.Therefore, no matter from which point, all should embodiment be regarded as exemplary, and be nonrestrictive, scope of the present invention is limited by claims instead of above-mentioned explanation, therefore all changes be intended in the implication of the equivalency by dropping on claim and scope are included in the present invention, any Reference numeral in claim should be considered as the claim involved by limiting.
The above; be only the present invention's preferably detailed description of the invention; but protection scope of the present invention is not limited thereto; anyly be familiar with those skilled in the art in the technical scope that the present invention discloses; be equal to according to technical scheme of the present invention and inventive concept thereof and replace or change, all should be encompassed within protection scope of the present invention.
Claims (1)
1. a high and cold roadbed frozen soil thermal-insulation construction method, is characterized in that, comprise the following steps:
(1) according to all fronts frozen soil prospecting data, be divided into three section by frozen earth roadbed completely, be respectively few ice, many ice permafrost region, Fu Bing, full ice permafrost region and contain native ice sheet section;
(2) few ice, many ice permafrost region are constructed: by adding elevated formation level analysis to former Subgrade of old road height and this, section is high-end is all greater than 2.0m for major part, and according to field investigation, roadbed filling fills with boulder and cobble soil, gravelly soil substantially, and roadbed situation is better, therefore this no longer carries out specially treated, by general subgrade process, only strengthen draining, preventive works, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affects subgrade stability;
(3) rich ice, full ice permafrost region are constructed: by adding elevated formation level analysis to former Subgrade of old road height and this, major part section is high-end is all greater than rational height of roadbed as calculated and critical height of subgrade, therefore for ensureing subgrade stability, take roadbed both sides that insulation banket is set, banket width and height, when roadbed height is greater than 3.0m, banket width 3.0m, height 1.5m; When roadbed height is less than 3.0m, banket width 3.0m, height 1.2m, and strengthen roadbed both sides waterproof and drainage design, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affects subgrade stability;
(4) construct to containing native ice sheet section:
A () is less than the embankment of 1.8m for roadbed raising, partly fill out and partly dig and cut subgrade, consider in Permafrost Area, grit Pavement Improvement is after flexible pavement, ever-frozen ground will occur significantly to degenerate, frozen earth roadbed heat stability constantly worsens, therefore for ensureing roadbed temperature, this design 50cm place below bed course arranges thick layer 6cmXSP warming plate isolation layer, with the subgrade defect that protection of permafrost steady change causes, and strengthen roadbed both sides waterproof and drainage design, to dredge roadbed periphery charge for remittance, anti-sealing infiltrates roadbed, affect subgrade stability, simultaneously according to roadbed height, topographic features is provided with wide 3.0m, high 1.2 ~ 1.5m is incubated banket,
B () is for the filled-up ground of roadbed raising 1.8 < H≤2.5m, for ensureing subgrade stability, this adopts the existing old road of cutouts and arranges sheet, block stone ventilated embankment, sheet, block stone ventilation thickness 0.8m, on it thick macadam of making 20cm levelling after carry out heavy type and roll, then making 20cm grit leveling, loaded filter, the levelling size controlling of rubble is at 5 ~ 10cm;
C () is for roadbed raising H > 2.5m, this considers that roadbed height is higher, and old road based filler is better, and existing old road base resistance to overturning is better, therefore take to arrange insulation banket in roadbed both sides, the wide 3.0m of banket, high 1.2 ~ 1.5m;
D () is for section of bursting and become muddy when a thaw sets in along the line, take according to roadbed raising and topographic features: 1.8m section is greater than for roadbed raising, after taking to excavate old road frost boiling part to stabilized zone position, rubble ventilation embankment is set, sheet, block stone ventilation thickness 0.8m, it carries out heavy type after thick macadam leveling layer of making 20cm roll, then making 20cm grit leveling, loaded filter, the levelling size controlling of rubble is at 5 ~ 10cm; Roadbed raising is less than to embankment and the excavation section of 1.8m, after taking to excavate old road part, roadbed scope (80cm) is changed and fills out grit process, and thick layer 6cmXSP warming plate isolation layer is set at 50cm place, bottom surface, road surface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510649896.0A CN105350417B (en) | 2015-10-10 | 2015-10-10 | A kind of high and cold roadbed frozen soil thermal-insulation construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510649896.0A CN105350417B (en) | 2015-10-10 | 2015-10-10 | A kind of high and cold roadbed frozen soil thermal-insulation construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105350417A true CN105350417A (en) | 2016-02-24 |
CN105350417B CN105350417B (en) | 2019-02-12 |
Family
ID=55326471
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510649896.0A Expired - Fee Related CN105350417B (en) | 2015-10-10 | 2015-10-10 | A kind of high and cold roadbed frozen soil thermal-insulation construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105350417B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112342858A (en) * | 2020-10-27 | 2021-02-09 | 东南大学 | Permafrost region precast hollow slab base pavement structure |
CN115627668A (en) * | 2022-10-27 | 2023-01-20 | 重庆交通大学 | Drainage ventilation structure of deep soil-containing heavy ice layer block stone roadbed at alpine and high altitude |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2006110433A (en) * | 2006-03-31 | 2007-10-10 | Александр Владимирович Конюхов (RU) | ROAD DESIGN |
CN102433814A (en) * | 2011-12-29 | 2012-05-02 | 中交第一公路勘察设计研究院有限公司 | Permafrost region expressway flaky and blocky stone ventilation roadbed and construction method thereof |
CN203229849U (en) * | 2013-04-19 | 2013-10-09 | 中交第一公路勘察设计研究院有限公司 | Highway excavation roadbed of road segment rich in ice, full of ice and containing soil-ice layer |
-
2015
- 2015-10-10 CN CN201510649896.0A patent/CN105350417B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2006110433A (en) * | 2006-03-31 | 2007-10-10 | Александр Владимирович Конюхов (RU) | ROAD DESIGN |
CN102433814A (en) * | 2011-12-29 | 2012-05-02 | 中交第一公路勘察设计研究院有限公司 | Permafrost region expressway flaky and blocky stone ventilation roadbed and construction method thereof |
CN203229849U (en) * | 2013-04-19 | 2013-10-09 | 中交第一公路勘察设计研究院有限公司 | Highway excavation roadbed of road segment rich in ice, full of ice and containing soil-ice layer |
Non-Patent Citations (3)
Title |
---|
王福明等: "高纬度多年冻土地区公路路基施工技术", 《道路工程》 * |
章金钊等: "新藏公路新疆段多年冻土的分布特征与路基设计对策", 《公路交通科技》 * |
陈家忠: "多年冻土路基施工技术", 《铁道道路》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112342858A (en) * | 2020-10-27 | 2021-02-09 | 东南大学 | Permafrost region precast hollow slab base pavement structure |
CN115627668A (en) * | 2022-10-27 | 2023-01-20 | 重庆交通大学 | Drainage ventilation structure of deep soil-containing heavy ice layer block stone roadbed at alpine and high altitude |
Also Published As
Publication number | Publication date |
---|---|
CN105350417B (en) | 2019-02-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103510441A (en) | Three-dimensional-drainage roadbed structure for preventing water damage of road in cold region and construction method thereof | |
CN105569058A (en) | Expansive soil cutting structure and construction method thereof | |
CN104264557A (en) | Semi-filling and semi-excavating ecological subgrade structure and construction method | |
CN105887606B (en) | Alpine meadow region heavy cut insulation infiltration combined type underdrain and its construction method | |
CN102383413A (en) | Method for constructing strengthened saturated-flow plastic silt soft soil foundation | |
CN109811748B (en) | Freeway roadbed processing method in frozen soil area | |
CN109736141A (en) | The anti-freeze expansion structural body and paving method of Railway Roadbed in Permafrost Regions | |
CN203741666U (en) | Roadbed structure for preventing cut-fill section of highway in cold region from frost boiling | |
CN110924254A (en) | Construction process for filling carbonaceous shale roadbed | |
CN113250211A (en) | Construction method for highway cutting slope in permafrost region | |
CN203212962U (en) | Expressway cut and fill subgrade on segment with less ice or more ice | |
CN107152012A (en) | Sluice construction technique | |
CN103015283A (en) | Novel roadbed structure for phreatic high inland sulphate salty soil | |
CN105350417A (en) | High-cold roadbed frozen soil heat insulation construction method | |
CN203229849U (en) | Highway excavation roadbed of road segment rich in ice, full of ice and containing soil-ice layer | |
CN105735328B (en) | Ventilation embankment step mortar flag stone completely spreads the construction method of bank protection | |
CN205775687U (en) | Alpine meadow region heavy cut insulation infiltration combined type covered conduit | |
CN208167421U (en) | A kind of underground water cutting location Ballast track high-speed railway anti-freeze expansion road structure | |
CN205875176U (en) | Ventilation embankment step grouts slabstone and completely spreads slope protection structure | |
CN105178133B (en) | Permafrost region dish Demonstration for Ecological Sanitation facility and its construction process | |
CN203212966U (en) | Excavation subgrade of expressway in section with less/more ice | |
CN105525551B (en) | Transformation method for temporary construction road of wind power field and grass planting pavement structure | |
CN210238158U (en) | Plateau high-ice-content frozen soil section railway cutting structure | |
CN103898824B (en) | The method that Cold And Frozen-soil Regions roadbed processes substrate with plastic draining board | |
CN207227880U (en) | A kind of cheuch phase weak soil combined type, which is changed, fills out structure and cheuch is mutually soft soil roadbed |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190212 Termination date: 20191010 |