CN102383413A - Method for constructing strengthened saturated-flow plastic silt soft soil foundation - Google Patents
Method for constructing strengthened saturated-flow plastic silt soft soil foundation Download PDFInfo
- Publication number
- CN102383413A CN102383413A CN2011102542398A CN201110254239A CN102383413A CN 102383413 A CN102383413 A CN 102383413A CN 2011102542398 A CN2011102542398 A CN 2011102542398A CN 201110254239 A CN201110254239 A CN 201110254239A CN 102383413 A CN102383413 A CN 102383413A
- Authority
- CN
- China
- Prior art keywords
- silt
- main
- construction
- backfill
- trench
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Road Paving Structures (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
技术领域 technical field
本发明属于土木建筑领域,具体涉及一种加固饱和流塑淤泥软土地基的施工方法。 The invention belongs to the field of civil engineering and construction, and in particular relates to a construction method for reinforcing saturated fluid plastic silt soft soil foundation.
背景技术 Background technique
我国沿海地区多有较厚的海积淤泥质粘土层,大部分淤泥质粘土具有一定连结作用,在未受到开掘时常处于软塑状态,有一定的结构性,但一经开挖,其结构就会被完全破坏,呈现流动状态,类似于“芝麻糊”状,从而导致施工人员和机械塌陷,施工困难,易引发安全事故,造成经济损失。 Most of the coastal areas in my country have relatively thick marine silt clay layers. Most of the silt clay has a certain connection effect. When it is not excavated, it is often in a soft plastic state and has a certain structure. However, once excavated, its structure will change. It is completely destroyed and presents a flowing state, similar to "sesame paste", which leads to the collapse of construction personnel and machinery, making construction difficult, easily causing safety accidents, and causing economic losses.
目前,我国淤泥软土地基的主要处理方法有:1.桩基法2.换土法3.灌浆法4.排水固结法5.加筋法。对于桩基法,当淤泥层较厚,难以大面积进行深处理,可采用打桩办法进行加固处理,但桩基法造价比较高而且此工程的淤泥层的厚度不是太厚,所以此法不适用;对于换土法,由于地下水位较高, 淤泥深度较深,全部清淤换填施工难度大, 场地限制,淤泥弃砟场难找,不利于环保, 且该方法施工慢, 工期会滞后;对于灌浆法,其适用性与灌浆方法和浆液性能有关,一般可用于处理砂土、砂砾石、湿陷性黄土及饱和粘性土等地基,灌浆技术的关键是灌浆压力的选择和控制、浆材配比和灌浆工艺; 灌浆参数的选择是一个复杂的问题, 只有通过现场试验才能切实地确定,其技术要求高,经济、工期、环境污染问题需要克服;对于排水固结法,考虑到排水固结需要一定的时间,工期会滞后;对于加筋法,由于造价比较高和工期比较长,所以不适用。考虑到工期、造价和环境污染的问题,以上几种方法不太适合。
At present, the main treatment methods of silt soft soil foundation in my country are: 1.
发明内容 Contents of the invention
本发明为了克服上述不足,提出一种加固饱和流塑淤泥软土地基的施工方法,解决在饱和流塑淤泥中开挖沟槽困难的问题,利用抛石挤淤控制加载综合法处理饱和流塑淤泥软土地基相应的设计、施工参数和质量控制等问题,同时进一步提出抛石挤淤控制加载综合法处理饱和流塑淤泥地基的加固效果的关键技术参数。 In order to overcome the above deficiencies, the present invention proposes a construction method for reinforcing the soft soil foundation of saturated flow plastic silt, solves the problem of difficulty in excavating trenches in saturated flow plastic silt, and uses riprap to squeeze silt to control loading comprehensive method to treat saturated flow plastic Corresponding design, construction parameters and quality control of silt soft soil foundation. At the same time, the key technical parameters of the reinforcement effect of the saturated fluid plastic silt foundation are further proposed by the comprehensive method of riprapping and silting control and loading.
实现本发明的技术方案是:本发明利用的抛石挤淤控制加载综合法是指在淤泥中, 通过向淤泥中抛填开山料的整式挤淤方式,将较大块径的单块体抛入淤泥中,并用振动碾逐层加载, 使较大块径的单块体在淤泥中形成骨架,然后在骨架上部及间隙采用大小级配良好、透水不透泥的爆破开山料进行整式压载挤淤置换, 形成散式骨架与整式挤淤平台结合的复合地基。 The technical scheme for realizing the present invention is: the comprehensive method of riprap silting control and loading used in the present invention refers to the integral silting method of throwing and filling the mountain material into the silt, and throwing the monolithic body with a larger diameter into the silt. into the silt, and loaded layer by layer with a vibrating roller, so that a single block with a larger diameter forms a skeleton in the silt, and then uses blasting materials with good size gradation, water permeability and mud impermeability for integral ballasting on the upper part of the skeleton and in the gap Squeeze silt replacement to form a composite foundation combining the scattered skeleton and the integral silt squeeze platform.
本发明的技术方案按照以下步骤进行: Technical scheme of the present invention carries out according to the following steps:
(1)在指定的施工作业区域内,在开挖主沟槽前,先设定好主沟槽的两条上边线,在其中一条上边线的一侧铺设施工便道,施工便道与沟槽之间的安全距离为2-3m;然后在施工便道远离主沟槽的一侧和主沟槽另一条上边线的一侧分别预留出区域,用以堆放开挖出的表面沙土和黏土土方,淤泥和耕植土;沿主沟槽纵向每400m设置一处汇车点; (1) In the designated construction work area, before excavating the main trench, first set the two upper lines of the main trench, lay a construction access road on one side of one of the upper lines, and lay the construction access road between the construction access road and the trench. The safe distance between them is 2-3m; then reserve areas on the side of the construction access road away from the main ditch and on the side of the other upper edge of the main ditch to pile up the surface sand and clay excavated. Silt and cultivated soil; set a junction every 400m along the longitudinal direction of the main trench;
(2)施工便道铺设后开挖主沟槽,开挖的主沟槽放坡系数在1:(0.6~0.8)之间,第一次开挖至地表下2~3m,并将挖掘出的耕植土、沙土和黏土土方分别抛掷到主沟槽两侧预留出的区域并形成回填槽,将开挖的淤泥搁置在回填槽里,在主沟槽中每隔50-100m设置一个集水坑,利用水泵抽水降水,使主沟槽内24小时内无积水; (2) After the construction access road is laid, the main trench is excavated. The grading coefficient of the excavated main trench is between 1: (0.6~0.8). Cultivated soil, sand and clay soil are thrown to the reserved areas on both sides of the main trench to form a backfill trough, and the excavated silt is placed in the backfill trough, and a collector is set every 50-100m in the main trench. For puddles, use water pumps to pump water and dewater, so that there is no water in the main trench within 24 hours;
(3)待主沟槽内降水至淤泥固结后,在第一次开挖的主沟槽内铺设0.7 m厚、5米宽的回填料,形成第二次开挖施工便道; (3) After the main trench is dewatered until the silt is consolidated, lay backfill of 0.7 m thick and 5 m wide in the main trench excavated for the first time to form the second excavation construction access road;
(4)第二次开挖施工便道铺设完毕后,进行第二次开挖,深度为地表以下4~6m,将挖掘出的淤泥倒运、抛掷到主沟槽两侧的回填槽内沥水,同时在主沟槽内挖设主排水沟和集水坑,并及时降水,主排水沟的位置设在主沟槽中间,和主沟槽平行,同时在主沟槽靠近边线两侧挖设两条小的排水沟; (4) The second excavation After the paving of the access road is completed, the second excavation is carried out at a depth of 4~6m below the surface. The main drainage ditch and sump are dug in the main trench, and the water is deposited in time. The position of the main drainage ditch is set in the middle of the main trench, parallel to the main trench. small gutters;
(5)待主沟槽内再次降水至淤泥固结后,开始铺设回填开山料至设计标高,将单块体抛入淤泥中, 单块体靠自重不能下沉时,并用振动碾逐层加载至至少120kpa的压力, 使较大块径的单块体在淤泥中形成骨架,然后在骨架上部及间隙采用直径5~50cm、级配良好、透水不透泥的回填料进行整式压载挤淤置换, 形成散式骨架与整式挤淤平台结合的复合地基;回填料挤淤换填完成后,在填换的回填料上部表层人工铺设一层无纺布,然后在无纺布上铺设砂垫层; (5) After the main trench is dewatered again until the silt is consolidated, start laying backfill mountain materials to the design elevation, throw the monolith into the silt, and when the monolith cannot sink due to its own weight, load it layer by layer with a vibrating roller To a pressure of at least 120kpa, make the monolith with a larger diameter form a skeleton in the silt, and then use backfill with a diameter of 5~50cm, good gradation, water permeability and mud impermeability on the upper part of the skeleton and the gap to carry out integral ballast extrusion Replacement, forming a composite foundation combined with a scattered skeleton and an integral silting platform; after the backfilling is completed, a layer of non-woven fabric is artificially laid on the upper surface of the filled backfill, and then sand pads are laid on the non-woven fabric layer;
(6)利用挖机在主沟槽内开挖管道的焊接工作坑; (6) Use an excavator to excavate the welding pit of the pipeline in the main trench;
(7)安装输水管道,回填管槽,压实回填的土层。 (7) Install the water pipeline, backfill the pipe groove, and compact the backfilled soil layer.
其中所述的回填料为开山料、施工废弃片石或碎石;所述的单块体块径为20-50cm;所述的砂垫层为200~250mm厚,选用的细砂含水率小于1~3%。 Wherein said backfilling is mountain material, construction waste flakes or crushed stones; the diameter of the single block is 20-50cm; the sand cushion is 200-250mm thick, and the selected fine sand has a moisture content less than ~3%.
本发明的有益效果是: The beneficial effects of the present invention are:
本发明的创新之处在于将排水固结法、抛石挤淤和控制加载相结合提出一种加固饱和流塑淤泥软土地基的施工方法; The innovation of the present invention is to propose a construction method for reinforcing saturated flow-plastic silt soft soil foundation by combining drainage consolidation method, riprap silting and controlled loading;
本发明通过在饱和流塑淤泥中抛填开山料,并结合降水固结和控制加载的方法,从而达到提高地基承载力的效果; The invention achieves the effect of improving the bearing capacity of the foundation by throwing and filling the mountain material in the saturated fluid plastic silt, combined with the method of precipitation consolidation and controlled loading;
本发明针对饱和流塑淤泥软土地基具有节省工程投资、缩短建设工期、少占土地、保护环境、适应性广、加固效果好和可冬季施工的优点。 The invention has the advantages of saving engineering investment, shortening the construction period, occupying less land, protecting the environment, wide adaptability, good reinforcement effect and being suitable for construction in winter, aiming at the soft soil foundation of saturated flow plastic silt.
说明书附图Instructions attached
图1为本发明实施例的管道沟槽开挖及回填标准断面图; Fig. 1 is the excavation and backfilling standard sectional view of pipeline trench according to the embodiment of the present invention;
图2为本发明实施例挖槽作业区域的平面布置图; Fig. 2 is the plane layout diagram of the trenching operation area according to the embodiment of the present invention;
图3为本发明实施例第一次开挖沟槽标准断面图; Fig. 3 is a standard cross-sectional view of the trench excavated for the first time in an embodiment of the present invention;
图4为本发明实施例第二次开挖沟槽标准断面图; Fig. 4 is the standard cross-sectional view of the trench excavated for the second time according to the embodiment of the present invention;
其中1:换填料;2:主管区回填区;3:一般回填区;4:淤泥;5:输水管道;6:砂垫层;7:主排水沟槽;8无纺布;9:开挖主沟槽;9a:第一次开挖主沟槽;9b:第二次开挖主沟槽;10a,10b:主沟槽上边线;11:施工便道;12a,12b:土方堆放区域;13a,13b:淤泥土堆放区域;14a,14b:耕植土堆放区域;15a:场区红线,15b:场区红线;16:汇车点。 Among them, 1: Filling replacement; 2: Backfill area of the competent area; 3: General backfill area; 4: Silt; 5: Water pipeline; 6: Sand cushion; 7: Main drainage trench; 8 Non-woven fabric; 9: Open Digging the main trench; 9a: excavating the main trench for the first time; 9b: excavating the main trench for the second time; 10a, 10b: the upper line of the main trench; 11: construction access road; 12a, 12b: earthwork stacking area; 13a, 13b: silt stacking area; 14a, 14b: plowing soil stacking area; 15a: red line of the field, 15b: red line of the field; 16: junction point.
具体实施方式 Detailed ways
实施例1Example 1
本发明实施例中使用的挖机型号为CAT320和SV100-1。 The models of excavators used in the embodiment of the present invention are CAT320 and SV100-1.
本发明的沟槽开槽方法为二次开挖,具体步骤如下: The trench grooving method of the present invention is secondary excavation, and concrete steps are as follows:
(1) 在指定的施工作业区域内,设定好开挖主沟槽的两条上边线,在其中一条上边线的一侧铺设一条3m宽的施工便道,施工便道与主沟槽上边线之间预留出3m的安全距离,保证边坡不塌方;在施工便道远离主沟槽的一侧和主沟槽另一条上边线的一侧分别预留出至少12m的区域,用以堆放开挖出的沙土和黏土土方、淤泥及耕植土;沿主沟槽纵向没400m设置一处汇车点; (1) In the designated construction work area, set the two upper lines of the main trench for excavation, and lay a 3m wide construction access road on one side of one of the upper lines. Set aside a safety distance of 3m between them to ensure that the slope does not collapse; reserve an area of at least 12m on the side of the construction access road away from the main trench and on the side of the other upper edge of the main trench for stacking and excavation sand and clay soil, silt and cultivated soil; set a junction point within 400m longitudinally of the main trench;
(2)施工便道铺设后开挖主沟槽,主沟槽两侧预设的坡度分别为1:1.5和1:1.25,第一次开挖至地表下2~3m,在主沟槽一侧配置一台挖机,将耕植土、沙土和黏土土方分别抛掷到主沟槽两侧预留出的区域并形成回填槽,将开挖的淤泥搁置在回填槽里,在主沟槽内每隔50-100m挖设一个集水坑,利用水泵24h抽水降水,使主沟槽内24h无积水; (2) After the construction access road is laid, the main trench is excavated. The preset slopes on both sides of the main trench are 1:1.5 and 1:1.25 respectively. Configure an excavator to throw cultivated soil, sand and clay to the reserved areas on both sides of the main trench to form a backfill groove, and place the excavated silt in the backfill groove. Dig a sump every 50-100m, use the water pump to pump water for 24 hours, so that there is no water in the main trench for 24 hours;
(3)待主沟槽内降水至淤泥固结后,在开挖的沟槽内铺设0.7 m厚、5米宽的开山料,形成第二次开挖施工便道; (3) After the main trench has been dewatered until the silt is consolidated, a 0.7 m thick and 5 meter wide mountain opening material is laid in the excavated trench to form a second excavation construction access road;
(4)第二次开挖施工便道铺设完毕后,进行第二次开挖,开挖深度为地表以下4~6m,在开挖过程中主沟槽两侧各配置一台挖机配合施工,将开挖出的淤泥倒运、抛掷到主沟槽两侧的回填槽内沥水,同时在主沟槽内人工挖设主排水沟和集水坑,并及时降水,主排水沟的位置设在主沟槽中间,和主沟槽平行,同时在主沟槽靠近上边线底部两侧挖设两条小的排水沟,并需要人工及时清理,防止水沟阻塞; (4) The second excavation After the paving of the access road is completed, the second excavation will be carried out. The excavation depth will be 4~6m below the surface. Transport and throw the excavated silt into the backfill grooves on both sides of the main ditch to drain water. At the same time, manually dig the main drainage ditches and sumps in the main ditch, and dewater in time. The location of the main drainage ditch is set at the main In the middle of the groove, parallel to the main groove, two small drainage ditches are dug on both sides of the main groove near the bottom of the upper line, and need to be cleaned manually in time to prevent the ditch from being blocked;
(5)待主沟槽内再次降水至淤泥固结后,开始铺设回填开山料至设计标高1.5m,将块径为20-50cm的单块体抛入淤泥中, 单块体靠自重不能下沉时,并用振动碾逐层加载至120kpa以上, 使较大块径的单块体在淤泥中形成骨架,然后在骨架上部及间隙采用直径5~50cm,级配良好、透水不透泥的爆破开山石渣进行整式压载挤淤置换, 形成散式骨架与整式挤淤平台结合的复合地基;开山料挤淤换填完成后,在填换的开山料上部表层人工铺设一层无纺布,然后在无纺布上铺设200~25mm厚的砂垫层,砂垫层选用含水率小1~3%的优质细砂; (5) After the main trench is dewatered again until the silt is consolidated, start to lay the backfill mountain material to the design elevation of 1.5m, and throw a single block with a diameter of 20-50cm into the silt, and the single block cannot be lowered by its own weight. When sinking, use a vibrating roller to load layer by layer to above 120kpa, so that a single block with a larger diameter forms a skeleton in the silt, and then adopts a blasting blasting with a diameter of 5-50cm on the upper part of the skeleton and in the gap, with good gradation, water permeability and mud impermeability The mountain slag is replaced by integral ballasting and silting to form a composite foundation combined with a scattered skeleton and an integral silting platform; after the silting and replacement of the mountain materials is completed, a layer of non-woven fabric is artificially laid on the surface of the replaced mountain materials. Then lay a 200~25mm thick sand cushion on the non-woven fabric, and the sand cushion is made of high-quality fine sand with a moisture content of 1~3%;
(6)利用挖机挖掘管道焊接工作坑; (6) Use an excavator to dig a pipe welding pit;
(7)安装输水管道,回填管槽,压实回填的土层。 (7) Install the water pipeline, backfill the pipe groove, and compact the backfilled soil layer.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011102542398A CN102383413B (en) | 2011-08-31 | 2011-08-31 | Method for constructing strengthened saturated-flow plastic silt soft soil foundation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011102542398A CN102383413B (en) | 2011-08-31 | 2011-08-31 | Method for constructing strengthened saturated-flow plastic silt soft soil foundation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102383413A true CN102383413A (en) | 2012-03-21 |
| CN102383413B CN102383413B (en) | 2013-11-20 |
Family
ID=45823214
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2011102542398A Active CN102383413B (en) | 2011-08-31 | 2011-08-31 | Method for constructing strengthened saturated-flow plastic silt soft soil foundation |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102383413B (en) |
Cited By (16)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103031838A (en) * | 2012-12-07 | 2013-04-10 | 中铁四局集团第三建设有限公司 | Bridge site deep-layer displacement method |
| CN103850239A (en) * | 2014-04-01 | 2014-06-11 | 兰州理工大学 | Guided water-jet mountain-cutting land reclaiming and mud solidifying treatment construction method |
| CN104358245A (en) * | 2014-11-12 | 2015-02-18 | 中国电建集团华东勘测设计研究院有限公司 | Method for processing soft foundation of hydraulic structure |
| CN104895111A (en) * | 2015-06-16 | 2015-09-09 | 中建五局土木工程有限公司 | Construction method of integrated pipe trench in soft soil |
| CN105297700A (en) * | 2015-10-15 | 2016-02-03 | 中国建筑第八工程局有限公司 | Method for treating sludge or quicksand foundation |
| CN105735245A (en) * | 2016-03-17 | 2016-07-06 | 上海交通大学 | Soil body reinforcement method for trenching construction in stratum of seaside hydraulic fill mud layer |
| CN106284283A (en) * | 2016-08-12 | 2017-01-04 | 马鞍山十七冶工程科技有限责任公司 | A kind for the treatment of of soft foundation is changed and is filled out natural soft-clay control debulking methods |
| CN107460866A (en) * | 2017-09-01 | 2017-12-12 | 东南大学 | A kind of big mud sump original position step curing processing method of depth |
| CN108457277A (en) * | 2018-03-01 | 2018-08-28 | 中国水利水电第十工程局有限公司 | A kind of a wide range of deep & thick silt excavation construction method |
| CN108797759A (en) * | 2018-06-15 | 2018-11-13 | 中国冶集团有限公司 | Hanging soft base underwater dumped rockfill grouting reinforcement method below immersed tube |
| CN110029626A (en) * | 2019-03-20 | 2019-07-19 | 中水电第十一工程局(郑州)有限公司 | A kind of bank revetment foundation consolidation process technology in soft formation side slope |
| CN110080233A (en) * | 2019-04-08 | 2019-08-02 | 上海宝冶集团有限公司 | The processing method of soft foundation |
| CN110862210A (en) * | 2019-11-26 | 2020-03-06 | 中国二十冶集团有限公司 | Method for efficiently and rapidly harmlessly reducing plain soil by sludge |
| CN111455969A (en) * | 2020-03-24 | 2020-07-28 | 中国五冶集团有限公司 | A kind of super thick peat soil and saturated silt foundation treatment method |
| CN111472359A (en) * | 2020-03-19 | 2020-07-31 | 中国二十冶集团有限公司 | Method for replacing and filling peat soil soft foundation box culvert foundation |
| CN116623702A (en) * | 2020-07-28 | 2023-08-22 | 中交路桥华南工程有限公司 | Construction method of underwater bearing platform |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0820941A (en) * | 1994-07-05 | 1996-01-23 | Yojiro Uike | Method for improving wet soft ground |
| JPH11181751A (en) * | 1997-12-17 | 1999-07-06 | Taihei Kogyo Co Ltd | Strengthening method for soft ground using slag |
| CN101302757A (en) * | 2008-03-07 | 2008-11-12 | 张伯谦 | Method for quickly processing heavy layer soft soil foundation |
| CN101761065A (en) * | 2009-12-17 | 2010-06-30 | 上海岩土工程勘察设计研究院有限公司 | Soft soil foundation treatment method |
-
2011
- 2011-08-31 CN CN2011102542398A patent/CN102383413B/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0820941A (en) * | 1994-07-05 | 1996-01-23 | Yojiro Uike | Method for improving wet soft ground |
| JPH11181751A (en) * | 1997-12-17 | 1999-07-06 | Taihei Kogyo Co Ltd | Strengthening method for soft ground using slag |
| CN101302757A (en) * | 2008-03-07 | 2008-11-12 | 张伯谦 | Method for quickly processing heavy layer soft soil foundation |
| CN101761065A (en) * | 2009-12-17 | 2010-06-30 | 上海岩土工程勘察设计研究院有限公司 | Soft soil foundation treatment method |
Non-Patent Citations (2)
| Title |
|---|
| 朱逢春等: "抛石挤淤综合法及其在加固浅层淤泥质地基中的应用", 《治淮》, no. 06, 30 June 2001 (2001-06-30), pages 26 - 27 * |
| 靳九贵: "抛石挤淤地基承载力的试验方法", 《河南科技》, no. 01, 15 January 2004 (2004-01-15), pages 32 * |
Cited By (23)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103031838B (en) * | 2012-12-07 | 2014-10-08 | 中铁四局集团第三建设有限公司 | Bridge site deep-layer displacement method |
| CN103031838A (en) * | 2012-12-07 | 2013-04-10 | 中铁四局集团第三建设有限公司 | Bridge site deep-layer displacement method |
| CN103850239A (en) * | 2014-04-01 | 2014-06-11 | 兰州理工大学 | Guided water-jet mountain-cutting land reclaiming and mud solidifying treatment construction method |
| CN103850239B (en) * | 2014-04-01 | 2015-08-05 | 兰州理工大学 | The punching of guiding water is cut mountain and is made ground and slurry curing process construction method |
| CN104358245A (en) * | 2014-11-12 | 2015-02-18 | 中国电建集团华东勘测设计研究院有限公司 | Method for processing soft foundation of hydraulic structure |
| CN104358245B (en) * | 2014-11-12 | 2016-06-29 | 中国电建集团华东勘测设计研究院有限公司 | A kind of method of hydraulic structure treatment of soft foundation |
| CN104895111A (en) * | 2015-06-16 | 2015-09-09 | 中建五局土木工程有限公司 | Construction method of integrated pipe trench in soft soil |
| CN105297700B (en) * | 2015-10-15 | 2018-06-29 | 中国建筑第八工程局有限公司 | A kind of mud, drift sand ground processing method |
| CN105297700A (en) * | 2015-10-15 | 2016-02-03 | 中国建筑第八工程局有限公司 | Method for treating sludge or quicksand foundation |
| CN105735245A (en) * | 2016-03-17 | 2016-07-06 | 上海交通大学 | Soil body reinforcement method for trenching construction in stratum of seaside hydraulic fill mud layer |
| CN105735245B (en) * | 2016-03-17 | 2018-05-01 | 上海交通大学 | The soil stabilization method of trenching construction in the hydraulic reclamation mud layer stratum of seashore |
| CN106284283A (en) * | 2016-08-12 | 2017-01-04 | 马鞍山十七冶工程科技有限责任公司 | A kind for the treatment of of soft foundation is changed and is filled out natural soft-clay control debulking methods |
| CN107460866A (en) * | 2017-09-01 | 2017-12-12 | 东南大学 | A kind of big mud sump original position step curing processing method of depth |
| CN107460866B (en) * | 2017-09-01 | 2019-02-05 | 东南大学 | In-situ step-by-step solidification treatment method for deep and large mud pits |
| CN108457277A (en) * | 2018-03-01 | 2018-08-28 | 中国水利水电第十工程局有限公司 | A kind of a wide range of deep & thick silt excavation construction method |
| CN108797759A (en) * | 2018-06-15 | 2018-11-13 | 中国冶集团有限公司 | Hanging soft base underwater dumped rockfill grouting reinforcement method below immersed tube |
| CN110029626A (en) * | 2019-03-20 | 2019-07-19 | 中水电第十一工程局(郑州)有限公司 | A kind of bank revetment foundation consolidation process technology in soft formation side slope |
| CN110029626B (en) * | 2019-03-20 | 2020-12-01 | 中电建十一局工程有限公司 | A kind of reinforcement treatment method of bank protection foundation on soft stratum slope |
| CN110080233A (en) * | 2019-04-08 | 2019-08-02 | 上海宝冶集团有限公司 | The processing method of soft foundation |
| CN110862210A (en) * | 2019-11-26 | 2020-03-06 | 中国二十冶集团有限公司 | Method for efficiently and rapidly harmlessly reducing plain soil by sludge |
| CN111472359A (en) * | 2020-03-19 | 2020-07-31 | 中国二十冶集团有限公司 | Method for replacing and filling peat soil soft foundation box culvert foundation |
| CN111455969A (en) * | 2020-03-24 | 2020-07-28 | 中国五冶集团有限公司 | A kind of super thick peat soil and saturated silt foundation treatment method |
| CN116623702A (en) * | 2020-07-28 | 2023-08-22 | 中交路桥华南工程有限公司 | Construction method of underwater bearing platform |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102383413B (en) | 2013-11-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102383413B (en) | Method for constructing strengthened saturated-flow plastic silt soft soil foundation | |
| CN104131575B (en) | A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation | |
| CN105178125B (en) | A kind of lake region High-filled emkankment is blown sand embankments construction method and embankment structure | |
| CN103283335B (en) | Filling reclamation method for reclaiming coal mining subsidence lands by Yellow River sediment | |
| CN111733842A (en) | Cofferdam construction method and cofferdam structure | |
| CN107288120A (en) | A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash | |
| CN106884427A (en) | Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water | |
| CN105804007B (en) | A kind of reinforced earth quaywall structure based on the soft base of beach | |
| CN101029490B (en) | Method for preventing and managing rock/upper side slope | |
| CN117569263A (en) | Dam anti-seepage wall and construction method thereof | |
| CN102518136A (en) | Flexible reinforced combined protection structure for preventing and treating humidifying damage of soft rock strongly weathered zone | |
| CN217782100U (en) | Full-section cofferdam access way structure of river-crossing underground tunnel | |
| CN108797759A (en) | Hanging soft base underwater dumped rockfill grouting reinforcement method below immersed tube | |
| CN108277815B (en) | Cofferdam structure for construction of water taking head structure in river and construction method thereof | |
| CN104164883B (en) | A kind of loose unsaturated soil side slope superficial again compacting in conjunction with vegetative coverage means of defence | |
| CN103276717B (en) | The method of composite earthwork synthetic materials reinforcement cushion soft soil foundation | |
| CN205062597U (en) | Road bed embankment structure of blowing sand is filled out to lake region height | |
| CN102425179B (en) | Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile | |
| CN221895800U (en) | Ecological protection structure of flexible retaining wall for coastal sand excavation side slope | |
| CN116516898B (en) | High-groundwater excavation channel side slope drainage system and construction method | |
| CN219080361U (en) | A topographical channel structure on a steep slope next to a mountain | |
| CN111501681A (en) | TRD construction method continuous wall and earth-rock cofferdam combined composite temporary water retaining structure and construction method | |
| CN104947630A (en) | Over-current slag collecting weir for water conservancy and hydropower engineering and construction method thereof | |
| CN215594063U (en) | Compound side slope reinforced structure | |
| CN115506215A (en) | Dredger fill fluid silt roadbed excavation construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C53 | Correction of patent of invention or patent application | ||
| CB02 | Change of applicant information |
Address after: 412004 No. 1308, No. 158, Zhongyi Road, Yuhua District, Hunan, Changsha Applicant after: CCFEB Civil Engineering Co., Ltd. Applicant after: Northeastern University Address before: 110819 Heping Road, Heping District, Liaoning, Shenyang, Lane No. 11, No. 3 Applicant before: Northeastern University Applicant before: CCFEB Civil Engineering Co., Ltd. |
|
| CB03 | Change of inventor or designer information |
Inventor after: Li Zhihua Inventor after: Sun Jie Inventor after: Wang Shuhong Inventor after: Liu Xiangyuan Inventor after: Chen Wenhui Inventor before: Chen Wenhui Inventor before: Sun Jie Inventor before: Wang Shuhong Inventor before: Liu Xiangyuan Inventor before: Yu Zhihua |
|
| COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: CHEN WENHUI SUN KAI WANG SHUHONG LIU XIANGYUAN YU ZHIHUA TO: LI ZHIHUA SUNKAI WANG SHUHONG LIU XIANGYUAN CHEN WENHUI Free format text: CORRECT: APPLICANT; FROM: NORTHEAST UNIV. TO: THE CIVIL ENGINEERING COMPANY OF CHINA FIFTH ENGINEERING BUREAU LTD. |
|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |