CN105260491A - 管道综合布管建模方法 - Google Patents
管道综合布管建模方法 Download PDFInfo
- Publication number
- CN105260491A CN105260491A CN201410343347.6A CN201410343347A CN105260491A CN 105260491 A CN105260491 A CN 105260491A CN 201410343347 A CN201410343347 A CN 201410343347A CN 105260491 A CN105260491 A CN 105260491A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- modeling
- professional
- modeling method
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Sink And Installation For Waste Water (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
一种管道综合布管建模方法,使用SolidWorks机械设计软件,其特征在于包括以下步骤:a整理电子版施工图纸,b统一标注、基础建模,c各专业修改、优化本专业图纸时,应明确原图中的管线示意走向及尺寸,d各机电安装专业修改图纸后,从专业技术规范,设计意图,实施单位,监理的要求出发,对完成的初稿进行自审,e在绘制综合平面图前要确定标高及平面位置和f各机电安装专业图纸和建筑结构图纸梁、板、柱尺寸核对。本发明具有将建筑物中的通风空调风管、空调水管等所有占据顶部空间的大型管线进行合理布局,提升施工工期、质量、成本、观感等方面的要求和最大限度合理协调、满足实施单位、监理、设计等相关方的各项要求的优点。
Description
技术领域
本发明涉及一种在建筑物中机电安装工程中的管线布置,具体地说,是一种管道综合布管建模方法。
背景技术
一个大型综合性的民用、公用建筑涉及到机电安装工程中的管线通常包括:生活给水系统、消防给水系统、空调水系统、排水系统(可能还有采暖系统)、电气照明系统、动力系统、防雷接地系统、火灾报警系统、有线电视、电话、宽带网络、楼宇对讲、空调系统、送排风系统、防排烟系统等一系列的其它智能化控制专业的管线。在以往的管线施工过程中,各机电安装专业以自我为中心,造成管线无序,层次混乱,为满足局部标高,位置的要求,多次施工停顿讨论、整改,结果造成了质量与安全的隐患,并且耽误工期,在使用和维修时带来诸多不便。
因此已知的管线施工过程中存在着上述种种不便和问题。
发明内容
本发明的目的,在于提出一种采用SolidWorks综合布管建模技术,在施工前按施工图进行1:1比例建模,能够非常直观观察各专业间空间布置情况,进一步优化设计,细化及合理化施工图纸的各项机电安装项目过程的管道综合布管建模方法。
本发明的另一目的,在于提出一种对机电工程的各专业管线位置进行合理布置,对各专业的施工工艺及施工工序的要求进行合理安排,力求最大限度的实现设计与施工之间的合理衔接,有效的协调各机电专业的各项施工活动的管道综合布管建模方法。
本发明的又一目的,在于提出一种SolidWorks可以建立自己的设计库的管道综合布管建模方法。
为实现上述目的,本发明的技术解决方案是:
一种管道综合布管建模方法,使用SolidWorks机械设计软件,管道施工图纸由各专业技术人员对施工图认真审核,发现问题及时记录,当进行图纸会审时,积极与设计人员交流、充分沟通、完善节点设计和施工详图设计,其特征在于包括以下步骤:
a、整理电子版施工图纸
准备好电子版的施工图纸,并通过对施工图纸的审核及与设计人员的沟通对电子版的施工图纸进行优化整改,将不需要的尺寸线及构筑物线条去掉,并将土建的结构图纸与机电安装图纸进行合并检查,并形成记录;
b、统一标注、基础建模
进行管线综合统一标注,电气和设备专业中地下采用绝对标高,地上采用相对标高;考虑水管的外径尺寸、风管的厚度、桥架的高度、风管和空调水管保温层的厚度,将一点式标注改为两点式,即空间占位的上顶和下底标高;
c、各专业修改、优化本专业图纸时,应对原图中的管线示意走向及尺寸明确出来,在符合规范及原设计意图的前提下,从便于施工及实际操作等方面出发对图纸进行合理化的修改,并形成修改记录,技术负责人对各专业管线的制图颜色标准提出要求,便于区分;
d、各机电安装专业修改图纸后,从专业技术规范,设计意图,实施单位,监理的要求出发,对完成的初稿进行自审,其间要注意垂直管线位置,如管道竖井,电气竖井要出到平面的标高与位置;
e、在绘制综合平面图前要与查看施工现场的具体状况依照“临时管线让永久性管线,小管线让大管线,有压管线让无压管线,非主要管线让主要管线,可弯曲管线让不可弯曲管线,技术要求低的管线让技术要求高的管线”的原则确定标高及平面位置;
f、各机电安装专业图纸和建筑结构图纸梁、板、柱尺寸核对,无论何种管线均不得撞梁、穿梁,否则需调整管线标高,使之在建筑结构允许的空间内进行。
本发明的管道综合布管建模方法还可以采用以下的技术措施来进一步实现。
前述的方法,其中所述基础建模依据综合布管区域的建筑图和结构图按柱、梁、板、墙尺寸进行草图绘制,并建立柱、梁、板、墙之间尺寸的属性关系。
前述的方法,其中所述设备专业建模以设备图为依据单体进行建模。
前述的方法,其中所述管件建模以标准样本为依据利用管件规格的相互属性建立函数关系进行建模。
采用上述技术方案后,本发明的管道综合布管建模方法具有以下优点:
1、将建筑物中的通风空调风管、空调水管、给排水及消防水管、强弱电桥架等所有占据顶部空间的大型管线进行合理布局,使之在满足使用功能的前提下,提升施工工期、质量、成本观感等方面的要求;
2、最大限度合理协调各安装专业、机电安装与土建、结构、装修之间的问题,以满足实施单位、监理、设计等相关方的各项要求,缩短工期,增加安装的经济效益和社会效益。
附图说明
图1为本发明实施例的第一施工示意图;
图2为本发明实施例的第二施工示意图;
图3为本发明实施例的第三施工示意图;
图4为本发明实施例的第四施工示意图;
图5为本发明实施例的圌山温泉度假村工程第一建模示意图;
图6为本发明实施例的圌山温泉度假村工程第二建模示意图;
图7为本发明实施例的圌山温泉度假村工程第三建模示意图。
具体实施方式
以下结合实施例及其附图对本发明作更进一步说明。
实施例1
现请参阅图1-4,图1为本发明实施例的第一施工示意图,图2为本发明实施例的第二施工示意图,图3为本发明实施例的第三施工示意图,图4为本发明实施例的第四施工示意图。
本发明的管道综合布管建模方法,使用SolidWorks机械设计软件,管道施工图纸由各专业技术人员对施工图认真审核,发现问题及时记录,当进行图纸会审时,积极与设计人员交流、充分沟通、完善节点设计和施工详图设计,其特征在于包括以下步骤:
a、整理电子版施工图纸
准备好电子版的施工图纸,并通过对施工图纸的审核及与设计人员的沟通对电子版的施工图纸进行优化整改,将不需要的尺寸线及构筑物线条去掉,并将土建的结构图纸与机电安装图纸进行合并检查,并形成记录;
b、统一标注、基础建模
由于各专业的习惯不同,在表示空间位置时各有各的表达方式。一般风管标注的是风管顶面标高,空调水管为管底标高,空调风管、水管所表示的均是不含保温层的标高,消防和给排水管标高表示的是管中心标高,电缆桥架标注的是下底相对该层地面的标高。设备专业地下部分采用绝对标高,地上部分是以各层地面为参考点的相对标高,而电气专业全部以本楼层地面为参考点,标注的是相对楼层地面的桥架下底标高。为了进行管线综合,必须统一标注。首先电气和设备专业的做法统一,和设备专业一样,地下采用绝对标高,地上采用相对标高。考虑水管的外径尺寸、风管的厚度、桥架的高度、风管和空调水管保温层的厚度,将一点式标注改为两点式,即空间占位的上顶和下底标高。只有这样才便于比较,便于绘制管线综合图;
c、各专业修改、优化本专业图纸时,应对原图中的管线示意走向及尺寸明确出来,在符合规范及原设计意图的前提下,从便于施工及实际操作等方面出发对图纸进行合理化的修改,并形成修改记录,技术负责人对各专业管线的制图颜色标准提出要求,便于区分;
d、各机电安装专业修改图纸后,从专业技术规范,设计意图,甲方,监理的要求出发,对完成的初稿进行自审,其间要注意垂直管线位置(如管道竖井,电气竖井),出到平面的标高与位置;
e、在绘制综合平面图前要与查看施工现场的具体状况依照“临时管线让永久性管线,小管线让大管线,有压管线让无压管线,非主要管线让主要管线,可弯曲管线让不可弯曲管线,技术要求低的管线让技术要求高的管线”的原则确定标高及平面位置;
f、各机电安装专业图纸和建筑结构图纸梁、板、柱尺寸核对,无论何种管线均不得撞梁、穿梁,否则,则调整管线标高,使之在建筑结构允许的空间内进行。
本发明的管道综合布管建模操作中遵循:所述基础建模依据综合布管区域的建筑图和结构图按柱、梁、板、墙尺寸进行草图绘制,并建立柱、梁、板、墙之间尺寸的属性关系;所述设备专业建模以设备图为依据单体进行建模;所述管件建模以标准样本为依据利用管件规格的相互属性建立函数关系进行建模。
请参见图5-7,图5为本发明实施例的圌山温泉度假村工程第一建模示意图,图6为本发明实施例的圌山温泉度假村工程第二建模示意图,图7为本发明实施例的圌山温泉度假村工程第三建模示意图。
本发明具有实质性特点和显著的技术进步,本发明的本发明的管道综合布管建模方法能够提升施工工期、质量、成本观感等方面的要求。最大限度合理协调各安装专业、机电安装与土建、结构、装修之间的问题,满足建设单位等相关方的各项要求,缩短工期,从而增加安装工程的经济效益和社会效益等方面的利益。
本发明的管道综合布管建模方法在圌山温泉度假村工程中运用,效果显著,得到了实施单位、监理单位和业主充分肯定。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变化。因此,所有等同的技术方案也应该属于本发明的范畴,应由各权利要求限定。
Claims (4)
1.一种管道综合布管建模方法,使用SolidWorks机械设计软件,管道施工图纸由各专业技术人员对施工图认真审核,发现问题及时记录,当进行图纸会审时,积极与设计人员交流、充分沟通、完善节点设计和施工详图设计,其特征在于包括以下步骤:
a、整理电子版施工图纸
准备好电子版的施工图纸,并通过对施工图纸的审核及与设计人员的沟通对电子版的施工图纸进行优化整改,将不需要的尺寸线及构筑物线条去掉,并将土建的结构图纸与机电安装图纸进行合并检查,并形成记录;
b、统一标注、基础建模
进行管线综合统一标注,电气和设备专业中地下采用绝对标高,地上采用相对标高;考虑水管的外径尺寸、风管的厚度、桥架的高度、风管和空调水管保温层的厚度,将一点式标注改为两点式,即空间占位的上顶和下底标高;
c、各专业修改、优化本专业图纸时,应对原图中的管线示意走向及尺寸明确出来,在符合规范及原设计意图的前提下,从便于施工及实际操作等方面出发对图纸进行合理化的修改,并形成修改记录,技术负责人对各专业管线的制图颜色标准提出要求,便于区分;
d、各机电安装专业修改图纸后,从专业技术规范,设计意图,实施单位,监理的要求出发,对完成的初稿进行自审,其间要注意垂直管线位置,如管道竖井,电气竖井要出到平面的标高与位置;
e、在绘制综合平面图前要与查看施工现场的具体状况依照“临时管线让永久性管线,小管线让大管线,有压管线让无压管线,非主要管线让主要管线,可弯曲管线让不可弯曲管线,技术要求低的管线让技术要求高的管线”的原则确定标高及平面位置;
f、各机电安装专业图纸和建筑结构图纸梁、板、柱尺寸核对,无论何种管线均不得撞梁、穿梁,否则需调整管线标高,使之在建筑结构允许的空间内进行。
2.如权利要求1所述的管道综合布管建模方法,其特征在于,所述基础建模依据综合布管区域的建筑图和结构图按柱、梁、板、墙尺寸进行草图绘制,并建立柱、梁、板、墙之间尺寸的属性关系。
3.如权利要求1所述的管道综合布管建模方法,其特征在于,所述设备专业建模以设备图为依据单体进行建模。
4.如权利要求1所述的管道综合布管建模方法,其特征在于,所述管件建模以标准样本为依据利用管件规格的相互属性建立函数关系进行建模。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410343347.6A CN105260491B (zh) | 2014-07-18 | 2014-07-18 | 管道综合布管建模方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410343347.6A CN105260491B (zh) | 2014-07-18 | 2014-07-18 | 管道综合布管建模方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105260491A true CN105260491A (zh) | 2016-01-20 |
CN105260491B CN105260491B (zh) | 2018-06-29 |
Family
ID=55100181
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410343347.6A Active CN105260491B (zh) | 2014-07-18 | 2014-07-18 | 管道综合布管建模方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105260491B (zh) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106066917A (zh) * | 2016-06-03 | 2016-11-02 | 江苏苏源光科技有限公司 | 一种基于JavaScript在能效管理系统中实现3D空调自动排布的方法 |
CN106295019A (zh) * | 2016-08-15 | 2017-01-04 | 上海宝冶集团有限公司 | 基于bim的暖通空调系统安装方法 |
CN108229037A (zh) * | 2018-01-10 | 2018-06-29 | 广东工业大学 | 一种基于bim的建模方法及装置 |
CN109614723A (zh) * | 2018-12-14 | 2019-04-12 | 中建二局第建筑工程有限公司 | 一种基于bim技术的综合施工方法 |
CN110489875A (zh) * | 2019-08-21 | 2019-11-22 | 天津住总机电设备安装有限公司 | 一种空调出风口布局设计方法 |
CN110727983A (zh) * | 2019-09-27 | 2020-01-24 | 贵州百胜工程建设咨询有限公司 | 一种关于公共医疗建筑的bim建模方法 |
CN111444585A (zh) * | 2020-03-13 | 2020-07-24 | 河南博维建筑规划设计有限公司 | 一种利用建模优化车库管线占用空间的方法 |
CN115750912A (zh) * | 2022-11-11 | 2023-03-07 | 陈强 | 一种机电综合管线安装施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004110443A (ja) * | 2002-09-19 | 2004-04-08 | Kubota Corp | 管路情報の更新方法 |
CN103758272A (zh) * | 2014-01-08 | 2014-04-30 | 永生建设集团有限公司 | 蒸压加气混凝土砌块墙体内置管线预埋施工方法 |
CN103791156A (zh) * | 2012-10-29 | 2014-05-14 | 五冶集团上海有限公司 | 大直径玻璃钢管道超高空快速安装方法 |
CN104668245A (zh) * | 2013-11-27 | 2015-06-03 | 五冶集团上海有限公司 | 一种液压管道酸洗吹扫方法 |
-
2014
- 2014-07-18 CN CN201410343347.6A patent/CN105260491B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004110443A (ja) * | 2002-09-19 | 2004-04-08 | Kubota Corp | 管路情報の更新方法 |
CN103791156A (zh) * | 2012-10-29 | 2014-05-14 | 五冶集团上海有限公司 | 大直径玻璃钢管道超高空快速安装方法 |
CN104668245A (zh) * | 2013-11-27 | 2015-06-03 | 五冶集团上海有限公司 | 一种液压管道酸洗吹扫方法 |
CN103758272A (zh) * | 2014-01-08 | 2014-04-30 | 永生建设集团有限公司 | 蒸压加气混凝土砌块墙体内置管线预埋施工方法 |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106066917A (zh) * | 2016-06-03 | 2016-11-02 | 江苏苏源光科技有限公司 | 一种基于JavaScript在能效管理系统中实现3D空调自动排布的方法 |
CN106066917B (zh) * | 2016-06-03 | 2023-02-17 | 光一科技股份有限公司 | 一种基于JavaScript在能效管理系统中实现3D空调自动排布的方法 |
CN106295019A (zh) * | 2016-08-15 | 2017-01-04 | 上海宝冶集团有限公司 | 基于bim的暖通空调系统安装方法 |
CN108229037A (zh) * | 2018-01-10 | 2018-06-29 | 广东工业大学 | 一种基于bim的建模方法及装置 |
CN109614723A (zh) * | 2018-12-14 | 2019-04-12 | 中建二局第建筑工程有限公司 | 一种基于bim技术的综合施工方法 |
CN110489875A (zh) * | 2019-08-21 | 2019-11-22 | 天津住总机电设备安装有限公司 | 一种空调出风口布局设计方法 |
CN110727983A (zh) * | 2019-09-27 | 2020-01-24 | 贵州百胜工程建设咨询有限公司 | 一种关于公共医疗建筑的bim建模方法 |
CN111444585A (zh) * | 2020-03-13 | 2020-07-24 | 河南博维建筑规划设计有限公司 | 一种利用建模优化车库管线占用空间的方法 |
CN111444585B (zh) * | 2020-03-13 | 2023-08-22 | 博维筑成设计有限公司 | 一种利用建模优化车库管线占用空间的方法 |
CN115750912A (zh) * | 2022-11-11 | 2023-03-07 | 陈强 | 一种机电综合管线安装施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105260491B (zh) | 2018-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105260491A (zh) | 管道综合布管建模方法 | |
CN103093061B (zh) | 一种地铁机电工程综合管线碰撞优化方法 | |
CN105930973A (zh) | 基于bim的施工现场网格化管理系统及其控制方法 | |
CN104966154A (zh) | 一种基于bim技术的临水临电管理方法及系统 | |
CN105938613A (zh) | 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 | |
CN204303029U (zh) | 用于地铁管线碰撞检测及后期运营维护的bim数据库系统 | |
CN112507442A (zh) | 一种bim项目物料及工程造价统计方法 | |
CN112365246A (zh) | 一种基于ai+gis+bim的智慧管廊综合管理平台 | |
CN112765701A (zh) | 一种农民新村设计施工一体化建设方法 | |
CN116882014A (zh) | 一种基于bim技术的建筑自动设计方法 | |
CN108984876A (zh) | 一种基于bim的预埋套管自动化建模方法和系统 | |
CN115659564A (zh) | 一种基于三维设计的输变电工程模型构建方法 | |
CN201908403U (zh) | 室内电气设计及管线敷设结构系统 | |
Ge et al. | Research report on the Utility Tunnel Engineering based on BIM technology | |
CN104636520A (zh) | 楼宇工程综合管线布置安装方法 | |
CN203823319U (zh) | 一种带伸缩节的h管 | |
CN210857599U (zh) | 一种管线分离防水保温一体化墙体及其构成的建筑物 | |
CN107142958B (zh) | 双盾构型综合管廊节点井 | |
CN206545293U (zh) | 一种3d模块帽型龙骨墙体与墙体的连接结构 | |
Li et al. | Application research on construction management of urban underground utility tunnel based on BIM | |
CN111460549A (zh) | 一种室内给排水管线的快速布置方法 | |
Xie et al. | Incorporating building information modeling (BIM) into the super high-rise industrialized housing project: A case study | |
CN215632098U (zh) | 一种工程临时场地电力布置系统 | |
CN113971304B (zh) | 一种基于bim的可转换功能建筑修建方法及建筑 | |
Mu et al. | Smart Fire Safety Early Warning System of Large Complex Building based on Data Collection and Processing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |