CN105938613A - 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 - Google Patents
一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 Download PDFInfo
- Publication number
- CN105938613A CN105938613A CN201610476375.4A CN201610476375A CN105938613A CN 105938613 A CN105938613 A CN 105938613A CN 201610476375 A CN201610476375 A CN 201610476375A CN 105938613 A CN105938613 A CN 105938613A
- Authority
- CN
- China
- Prior art keywords
- management
- bim
- model
- platform
- control
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/10—Services
- G06Q50/26—Government or public services
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Abstract
本发明公开一种基于BIM和VR智慧城市管网综合平台及其管理方法和构建方法,包括:监测设备,部署于城市管网的关键监测位置,且与BIM中心服务平台无线通信;管控阀,部署于城市管网的关键管控位置,且与BIM中心服务平台无线通信;BIM中心服务平台,由城市管网相关的三维真实城市场景模型数据库和管控模块组成;以及VR虚拟现实平台,与BIM中心服务平台进行信息交互。本发明通过三维真实城市场景模型结合VR虚拟现实平台实现对城市管网的监测和管控,以提供管控效率和及时性,降低人力、物力成本。
Description
技术领域
本发明涉及城市管网监控技术领域,特别涉及一种基于BIM和VR智慧城市管网综合平台及其管理方法和构建方法。
背景技术
城市地下管线历来是城市的“血管”和“神经”,地下管线涉及给水、雨水、污水、燃气、电力、路灯、有线电视、工业等十多种地下管线,形成了一张错综复杂的地下管线网络(即城市管网),传统的二维管理方式难以准确、直观地显示地下电力管线交叉排列的空间位置关系。
“数字城市”(digital city) 是以计算机技术、多媒体技术和大规模存储技术为基础,以宽带网络为纽带,运用遥感、全球定位系统、地理信息系统、遥测、仿真-虚拟等技术,对城市进行多分辨率、多尺度、多时空和多种类的三维描述,即利用信息技术手段把城市的过去、现状和未来的全部内容在网络上进行数字化虚拟实现。在数字城市中融入三维管网,即结合地理信息系统(GIS)技术、数据库技术和三维技术,直观显示地下管线的空间层次和位置,以仿真方式形象展现地下管线的埋深、材质、形状、走向以及工井结构和周边环境,极大地方便了排管、工井占用情况、位置等信息的查找,为今后地下电力管线资源的统筹利用和科学布局、管线占用审批等工作提供了准确、直观、高效的参考。
但是,目前城市管网系统只能针对监测的数据建模并输入数字城市模型展示,在城市管网的综合管理工作中,在管网设计施工阶段,需要根据管线设计参数(包括标高,尺寸,型号等)对施工和材料生产进行管理,在运营管理阶段,需要对城市管网的运行状况进行实时的监测和管控,其手段一般是通过监测设备对各管线状态进行监测,以及通过管控开关对各管线进行开关控制,目前仅在数字城市模型中无法实现实时监测和快速反应管控的功能。
有鉴于此,本发明人提出一种基于BIM和VR智慧城市管网综合平台。
发明内容
本发明的目的在于提供一种基于BIM和VR智慧城市管网综合平台及其管理方法和构建方法,其通过三维真实城市场景模型结合VR虚拟现实平台实现对城市管网的监测和管控,为城市管网的施工和运营管理提供依据。
为了实现上述目的,本发明的技术方案如下:
一种基于BIM和VR智慧城市管网综合平台,包括:
监测设备,部署于城市管网的关键监测位置,且与BIM中心服务平台无线通信,用于采集城市管网的监测数据并将其发送至BIM中心服务平台;
管控阀,部署于城市管网的关键管控位置,且与BIM中心服务平台无线通信,用于接收并执行BIM中心服务平台的管控指令;
BIM中心服务平台,BIM中心服务平台由城市管网相关的三维真实城市场景模型数据库和管控模块组成;
其中,所述三维真实城市场景模型数据库中包含一融合了城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型的三维真实城市场景模型,所述三维真实城市场景模型数据库用于向VR虚拟现实平台发送轻量的可视化模型数据;
所述管控模块内置管控策略,其用于接收监测设备回传的监测数据,并将监测数据并入三维真实城市场景模型数据库中,还用于接收VR虚拟现实平台的管控指令对内置的管控策略进行修正,并将监测数据结合内置的管控策略得到管控执行指令,并发送给管控阀,用于对管控阀实施管控;以及
VR虚拟现实平台,与BIM中心服务平台进行信息交互,VR虚拟现实平台接受并展示来自BIM中心服务平台的轻量的可视化模型数据;VR虚拟现实平台还用于输入管控指令。
所述监测数据包括给水水质数据、地下道水位数据、燃气泄漏数据和漏电数据。
所述虚拟现实平台为一虚拟现实设备,其包括数据收发模块、显示屏和指令输入模块,所述指令输入模块为一按键输入板,数据收发模块通过无线或有线网络与BIM中心服务平台连接,显示屏用于显示三维真实城市场景模型数据,指令输入模块用于输入管控指令,数据收发模块用于接收模型数据和发送管控指令。
一种基于BIM和VR智慧城市管网综合平台的管理方法,包括以下步骤:
S1.监测设备将其采集到的监测数据发送至BIM中心服务平台的管控模块,管控模块将监测数据并入三维真实城市场景模型数据库中,与其存储的模型数据进行融合后,提供与三维真实城市场景模型对应的轻量的可视化模型数据给VR虚拟现实平台,进行虚拟实景显示;
S2. 管控人员通过VR虚拟现实平台可以看到与城市管网实时监测相关的三维真实城市场景模型,若需要可以向BIM中心服务平台的管控模块发送管控指令用于修正其内置的管控策略;
S3.管控模块将监测数据结合内置的管控策略得到管控执行指令,并将该管控执行指令发送至管控阀,对城市管网中的管控阀依据管控执行指令实施管控。
一种基于BIM和VR智慧城市管网综合平台的构建方法,包括以下步骤:
步骤一、通过数字摄影测量获得城市三维信息,通过工程测量获得工程测量数据,结合城市三维信息和工程测量数据建立三维真实城市场景模型、城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型,将城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型融合进三维真实城市场景模型中,并在BIM中心服务平台建立三维真实城市场景模型数据库来管理三维真实城市场景模型,还在BIM中心服务平台设立内置了管控策略的管控模块;
步骤二、根据监测设备BIM模型和管控阀BIM模型部署城市管网各关键位置的监测设备和管控阀,并使监测设备和管控阀与三维真实城市模型数据库中的监测设备BIM模型和管控阀BIM模型相对应;
步骤三、建立VR虚拟现实平台,VR虚拟现实平台与BIM中心服务平台建立信息交互关系;
步骤四、BIM中心服务平台向VR虚拟现实平台输出融合了城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型融合的三维真实城市模型数据,三维真实城市模型在VR虚拟现实平台向用户展示出来。
所述步骤一中,三维真实城市场景模型的构建方式为:数字摄影测量从航片上采集城市三维信息,生成数字城市模型和正射影像,将正射影像映射到数字城市模型上,形成三维真实城市场景模型。
所述步骤一中,各BIM模型与三维真实城市场景模型融合过程是:将城市管网各专业BIM模型、监测设备BIM模型、管控开关BIM模型放置到三维真实城市场景模型时,指定专业BIM三维模型、监测设备BIM模型、管控阀BIM模型放置在三维真实城市场景模型中的BIM三维模型的比例尺、坐标系标准及模型族库建立规则。
所述步骤二中,根据常年城市管网事故和维修统计数据分析得出城市管网关键部位并设置监测设备和管控阀,其中监测设备包含水质监测设备、地下道水位监测设备、燃气泄漏检测设备和漏电监测设备。
采用上述方案后,本发明的有益效果是:本发明的BIM中心服务平台中的三维真实城市场景模型数据库对所有模型数据进行统一管理,这些模型数据通过发送给VR虚拟现实平台实现可视化,BIM中心服务平台中的管控模块则将监测数据进行处理,通过将监测数据并入模型数据并转发至VR虚拟现实平台,让管控人员在三维真实城市场景模型查看城市管网内的数据变化,依此在VR虚拟现实平台下达管控指令,经管控模块的处理后实现对管控阀的控制,因此本发明结合BIM与VR,将BIM模型与数字城市融合于一体,并入监测数据后能够更为直观的展示城市管网运行状态及其变化情况,大大减少城市管网问题排查的时间和问题响应的时间,降低了人力、物力的耗损,使城市管网问题处于安全预防状态,相比以往的数字城市,大大降低城市管网问题发生。
以下结合附图和具体实施方式对本发明做进一步说明。
附图说明
图1是本发明的结构示意图。
具体实施方式
如图1所示,本发明揭示的一种基于BIM和VR智慧城市管网综合平台,包括:
监测设备1,部署于城市管网的关键监测位置,且与BIM中心服务平台无线通信,用于采集城市管网的监测数据并将其发送至BIM中心服务平台;
管控阀2,部署于城市管网的关键管控位置,且与BIM中心服务平台无线通信,用于接收并执行BIM中心服务平台的管控指令;
BIM中心服务平台3,BIM中心服务平台由城市管网相关的三维真实城市场景模型数据库31和管控模块32组成;
其中,所述三维真实城市场景模型数据库31中包含一融合了城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型的三维真实城市场景模型,所述三维真实城市场景模型数据库用于向VR虚拟现实平台发送轻量的可视化模型数据;
所述管控模块32内置管控策略,其用于接收监测设备回传的监测数据,并将监测数据并入三维真实城市场景模型数据库中,还用于接收VR虚拟现实平台的管控指令对内置的管控策略进行修正,并将监测数据结合内置的管控策略得到管控执行指令,并发送给管控阀,用于对管控阀实施管控;以及
VR虚拟现实平台4,与BIM中心服务平台进行信息交互,VR虚拟现实平台接受并展示来自BIM中心服务平台的轻量的可视化模型数据;VR虚拟现实平台还用于输入管控指令。
所述监测数据包括给水水质数据、地下道水位数据、燃气泄漏数据和漏电数据。
所述虚拟现实平台为一虚拟现实设备,其包括数据收发模块、显示屏和指令输入模块,所述指令输入模块为一按键输入板,数据收发模块通过无线或有线网络与BIM中心服务平台连接,显示屏用于显示三维真实城市场景模型数据,指令输入模块用于输入管控指令,数据收发模块用于接收模型数据和发送管控指令。
一种基于BIM和VR智慧城市管网综合平台的管理方法,包括以下步骤:
S1.监测设备1将其采集到的监测数据发送至BIM中心服务平台3的管控模块31,管控模块31将监测数据并入三维真实城市场景模型数据库32中,与其存储的模型数据进行融合后,提供与三维真实城市场景模型对应的轻量的可视化模型数据给VR虚拟现实平台4,进行虚拟实景显示;
S2. 管控人员通过VR虚拟现实平台4可以看到与城市管网实时监测相关的三维真实城市场景模型,若需要可以向BIM中心服务平台3的管控模块发送管控指令用于修正其内置的管控策略;
S3.管控模块31将监测数据结合内置的管控策略得到管控执行指令,并将该管控执行指令发送至管控阀,对城市管网中的管控阀依据管控执行指令实施管控。
一种基于BIM和VR智慧城市管网综合平台的构建方法,包括以下步骤:
步骤一、通过数字摄影测量获得城市三维信息,通过工程测量获得工程测量数据,结合城市三维信息和工程测量数据建立三维真实城市场景模型、城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型,将城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型融合进三维真实城市场景模型中,并在BIM中心服务平台建立三维真实城市场景模型数据库来管理三维真实城市场景模型,还在BIM中心服务平台设立内置了管控策略的管控模块;
步骤二、根据监测设备BIM模型和管控阀BIM模型部署城市管网各关键位置的监测设备和管控阀,并使监测设备和管控阀与三维真实城市模型数据库中的监测设备BIM模型和管控阀BIM模型相对应;
步骤三、建立VR虚拟现实平台,VR虚拟现实平台与BIM中心服务平台建立信息交互关系;
步骤四、BIM中心服务平台向VR虚拟现实平台输出融合了城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型融合的三维真实城市模型数据,三维真实城市模型在VR虚拟现实平台向用户展示出来。
所述步骤一中,三维真实城市场景模型的构建方式为:数字摄影测量从航片上采集城市三维信息,生成数字城市模型和正射影像,将正射影像映射到数字城市模型上,形成三维真实城市场景模型。
所述步骤一中,各BIM模型与三维真实城市场景模型融合过程是:将城市管网各专业BIM模型、监测设备BIM模型、管控开关BIM模型放置到三维真实城市场景模型时,指定专业BIM三维模型、监测设备BIM模型、管控阀BIM模型放置在三维真实城市场景模型中的BIM三维模型的比例尺、坐标系标准及模型族库建立规则。
所述步骤二中,根据常年城市管网事故和维修统计数据分析得出城市管网关键部位并设置监测设备和管控阀,其中监测设备包含水质监测设备、地下道水位监测设备、燃气泄漏检测设备和漏电监测设备。
以上仅为本发明的具体实施例,并非对本发明的保护范围的限定。凡依本案的设计思路所做的等同变化,均落入本案的保护范围。
Claims (8)
1.一种基于BIM和VR智慧城市管网综合平台,其特征在于,包括:
监测设备,部署于城市管网的关键监测位置,且与BIM中心服务平台无线通信,用于采集城市管网的监测数据并将其发送至BIM中心服务平台;
管控阀,部署于城市管网的关键管控位置,且与BIM中心服务平台无线通信,用于接收并执行BIM中心服务平台的管控指令;
BIM中心服务平台,BIM中心服务平台由城市管网相关的三维真实城市场景模型数据库和管控模块组成;
其中,所述三维真实城市场景模型数据库中包含一融合了城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型的三维真实城市场景模型,所述三维真实城市场景模型数据库用于向VR虚拟现实平台发送轻量的可视化模型数据;
所述管控模块内置管控策略,其用于接收监测设备回传的监测数据,并将监测数据并入三维真实城市场景模型数据库中,还用于接收VR虚拟现实平台的管控指令对内置的管控策略进行修正,并将监测数据结合内置的管控策略得到管控执行指令,并发送给管控阀,用于对管控阀实施管控;以及
VR虚拟现实平台,与BIM中心服务平台进行信息交互,VR虚拟现实平台接受并展示来自BIM中心服务平台的轻量的可视化模型数据;VR虚拟现实平台还用于输入管控指令。
2.如权利要求1所述的一种基于BIM和VR智慧城市管网综合平台,其特征在于:所述监测数据包括给水水质数据、地下道水位数据、燃气泄漏数据和漏电数据。
3.如权利要求1所述的一种基于BIM和VR智慧城市管网综合平台,其特征在于:所述虚拟现实平台为一虚拟现实设备,其包括数据收发模块、显示屏和指令输入模块,所述指令输入模块为一按键输入板,数据收发模块通过无线或有线网络与BIM中心服务平台连接,显示屏用于显示三维真实城市场景模型数据,指令输入模块用于输入管控指令,数据收发模块用于接收模型数据和发送管控指令。
4.一种基于BIM和VR智慧城市管网综合平台的管理方法,其特征在于,包括以下步骤:
S1.监测设备将其采集到的监测数据发送至BIM中心服务平台的管控模块,管控模块将监测数据并入三维真实城市场景模型数据库中,与其存储的模型数据进行融合后,提供与三维真实城市场景模型对应的轻量的可视化模型数据给VR虚拟现实平台,进行虚拟实景显示;
S2. 管控人员通过VR虚拟现实平台可以看到与城市管网实时监测相关的三维真实城市场景模型,若需要可以向BIM中心服务平台的管控模块发送管控指令用于修正其内置的管控策略;
S3.管控模块将监测数据结合内置的管控策略得到管控执行指令,并将该管控执行指令发送至管控阀,对城市管网中的管控阀依据管控执行指令实施管控。
5.一种基于BIM和VR智慧城市管网综合平台的构建方法,其特征在于,包括以下步骤:
步骤一、通过数字摄影测量获得城市三维信息,通过工程测量获得工程测量数据,结合城市三维信息和工程测量数据建立三维真实城市场景模型、城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型,将城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型融合进三维真实城市场景模型中,并在BIM中心服务平台建立三维真实城市场景模型数据库来管理三维真实城市场景模型,还在BIM中心服务平台设立内置了管控策略的管控模块;
步骤二、根据监测设备BIM模型和管控阀BIM模型部署城市管网各关键位置的监测设备和管控阀,并使监测设备和管控阀与三维真实城市模型数据库中的监测设备BIM模型和管控阀BIM模型相对应;
步骤三、建立VR虚拟现实平台,VR虚拟现实平台与BIM中心服务平台建立信息交互关系;
步骤四、BIM中心服务平台向VR虚拟现实平台输出融合了城市管网各专业BIM模型、监测设备BIM模型和管控阀BIM模型融合的三维真实城市模型数据,三维真实城市模型在VR虚拟现实平台向用户展示出来。
6.如权利要求5所述的一种基于BIM和VR智慧城市管网综合平台的构建方法,其特征在于:所述步骤一中,三维真实城市场景模型的构建方式为:数字摄影测量从航片上采集城市三维信息,生成数字城市模型和正射影像,将正射影像映射到数字城市模型上,形成三维真实城市场景模型。
7.如权利要求5所述的一种基于BIM和VR智慧城市管网综合平台的构建方法,其特征在于:所述步骤一中,各BIM模型与三维真实城市场景模型融合过程是:将城市管网各专业BIM模型、监测设备BIM模型、管控开关BIM模型放置到三维真实城市场景模型时,指定专业BIM三维模型、监测设备BIM模型、管控阀BIM模型放置在三维真实城市场景模型中的BIM三维模型的比例尺、坐标系标准及模型族库建立规则。
8.如权利要求5所述的一种基于BIM和VR智慧城市管网综合平台的构建方法,其特征在于:所述步骤二中,根据常年城市管网事故和维修统计数据分析得出城市管网关键部位并设置监测设备和管控阀,其中监测设备包含水质监测设备、地下道水位监测设备、燃气泄漏检测设备和漏电监测设备。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610476375.4A CN105938613B (zh) | 2016-06-27 | 2016-06-27 | 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610476375.4A CN105938613B (zh) | 2016-06-27 | 2016-06-27 | 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105938613A true CN105938613A (zh) | 2016-09-14 |
CN105938613B CN105938613B (zh) | 2021-08-20 |
Family
ID=56872051
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610476375.4A Active CN105938613B (zh) | 2016-06-27 | 2016-06-27 | 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105938613B (zh) |
Cited By (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106569595A (zh) * | 2016-10-19 | 2017-04-19 | 上海市城市建设设计研究总院 | 基于vr和bim的虚拟工程体验方法及装置 |
CN106681191A (zh) * | 2017-01-06 | 2017-05-17 | 西安思源学院 | 一种基于bim模型的教室供电控制系统及方法 |
CN106706041A (zh) * | 2017-03-08 | 2017-05-24 | 天津梅迪亚科技有限公司 | 基于虚拟现实技术的地铁综合管网控制系统 |
CN106951083A (zh) * | 2017-03-20 | 2017-07-14 | 任芳 | 基于bim的vr展示方法及系统 |
CN107103078A (zh) * | 2017-04-25 | 2017-08-29 | 国网上海市电力公司 | 基于bim的变电站建设全周期数字化管控系统 |
CN107194861A (zh) * | 2017-07-02 | 2017-09-22 | 四川藏区高速公路有限责任公司 | 一种基于3dgis+bim的路网运营综合监控管理平台及方法 |
CN108182298A (zh) * | 2016-10-25 | 2018-06-19 | 福建省建筑设计研究院有限公司 | 基于bim的虚拟和现实交互校验系统 |
CN108629037A (zh) * | 2018-05-11 | 2018-10-09 | 河南工业和信息化职业学院 | 一种智慧城市服务平台及其管理方法 |
CN108764668A (zh) * | 2018-05-15 | 2018-11-06 | 浙江大学 | 一种基于bim技术的设施管理系统及方法 |
CN108776837A (zh) * | 2018-04-09 | 2018-11-09 | 上海大学 | 基于建筑信息模型和虚拟现实技术的建筑运维管理系统和方法 |
CN109067822A (zh) * | 2018-06-08 | 2018-12-21 | 珠海欧麦斯通信科技有限公司 | 线上线下融合的实时混合现实城市服务实现方法及系统 |
CN109165329A (zh) * | 2018-07-09 | 2019-01-08 | 中兵勘察设计研究院有限公司 | 一种融合增强现实和物联网的地下管网智能管控技术及系统 |
CN109246195A (zh) * | 2018-08-13 | 2019-01-18 | 孙琤 | 一种融合增强现实、虚拟现实的管网智能管控方法及系统 |
CN109359751A (zh) * | 2018-10-26 | 2019-02-19 | 上海达实联欣科技发展有限公司 | 智能建筑运维管理系统及其管理方法 |
CN109460834A (zh) * | 2018-10-26 | 2019-03-12 | 上海达实联欣科技发展有限公司 | 建筑运维管理系统及其管理方法 |
CN109685704A (zh) * | 2019-01-14 | 2019-04-26 | 博拉网络股份有限公司 | 基于vr的管网巡检系统 |
CN110069045A (zh) * | 2019-04-11 | 2019-07-30 | 广州番禺职业技术学院 | 基于bim、vr及物联网的污水处理厂无人值守方法和智能管理平台 |
CN110222434A (zh) * | 2019-06-12 | 2019-09-10 | 璞耐特(大连)科技有限公司 | 基于工业4.0的防水卷材智能制造加工安装方法 |
CN111562547A (zh) * | 2020-07-13 | 2020-08-21 | 中铁第一勘察设计院集团有限公司 | 一种监测元件3d可视化方法及系统 |
CN111782756A (zh) * | 2020-09-04 | 2020-10-16 | 万基泰科工集团(四川)有限公司 | 一种城市地下管网全生命周期安全管控集成系统 |
CN113656858A (zh) * | 2021-07-02 | 2021-11-16 | 中建七局安装工程有限公司 | 基于激光扫描点云与bim模型的双球嵌套结构数模比对方法 |
CN114910125A (zh) * | 2022-05-12 | 2022-08-16 | 武汉理工大学 | 一种基于AR和IoT的管道监测系统及方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100560699B1 (ko) * | 2005-10-04 | 2006-03-17 | (주)아세아항측 | 모형항공촬영시스템 및 gps/ins 시스템을 이용한3차원 가상현실 수치지도의 제작방법 |
CN101256590A (zh) * | 2008-04-03 | 2008-09-03 | 北京艺龙天地文化传播有限公司 | 结合WebGis的三维在线虚拟现实生态环境仿真系统及其方法 |
CN103472788A (zh) * | 2013-09-06 | 2013-12-25 | 上海大学 | 基于bim的运营隧道维护健康监测管理方法 |
CN103699731A (zh) * | 2013-12-19 | 2014-04-02 | 中铁第一勘察设计院集团有限公司 | 一种铁道工程真实场景模型协同设计平台的构建方法 |
CN104484033A (zh) * | 2014-11-21 | 2015-04-01 | 上海同筑信息科技有限公司 | 基于bim的虚拟现实展示方法和系统 |
CN105488839A (zh) * | 2015-12-07 | 2016-04-13 | 上海市政工程设计研究总院(集团)有限公司 | 三维场景交互式操作系统及其操作方法 |
-
2016
- 2016-06-27 CN CN201610476375.4A patent/CN105938613B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100560699B1 (ko) * | 2005-10-04 | 2006-03-17 | (주)아세아항측 | 모형항공촬영시스템 및 gps/ins 시스템을 이용한3차원 가상현실 수치지도의 제작방법 |
CN101256590A (zh) * | 2008-04-03 | 2008-09-03 | 北京艺龙天地文化传播有限公司 | 结合WebGis的三维在线虚拟现实生态环境仿真系统及其方法 |
CN103472788A (zh) * | 2013-09-06 | 2013-12-25 | 上海大学 | 基于bim的运营隧道维护健康监测管理方法 |
CN103699731A (zh) * | 2013-12-19 | 2014-04-02 | 中铁第一勘察设计院集团有限公司 | 一种铁道工程真实场景模型协同设计平台的构建方法 |
CN104484033A (zh) * | 2014-11-21 | 2015-04-01 | 上海同筑信息科技有限公司 | 基于bim的虚拟现实展示方法和系统 |
CN105488839A (zh) * | 2015-12-07 | 2016-04-13 | 上海市政工程设计研究总院(集团)有限公司 | 三维场景交互式操作系统及其操作方法 |
Cited By (27)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106569595A (zh) * | 2016-10-19 | 2017-04-19 | 上海市城市建设设计研究总院 | 基于vr和bim的虚拟工程体验方法及装置 |
CN108182298A (zh) * | 2016-10-25 | 2018-06-19 | 福建省建筑设计研究院有限公司 | 基于bim的虚拟和现实交互校验系统 |
CN106681191A (zh) * | 2017-01-06 | 2017-05-17 | 西安思源学院 | 一种基于bim模型的教室供电控制系统及方法 |
CN106706041A (zh) * | 2017-03-08 | 2017-05-24 | 天津梅迪亚科技有限公司 | 基于虚拟现实技术的地铁综合管网控制系统 |
CN106951083A (zh) * | 2017-03-20 | 2017-07-14 | 任芳 | 基于bim的vr展示方法及系统 |
CN107103078A (zh) * | 2017-04-25 | 2017-08-29 | 国网上海市电力公司 | 基于bim的变电站建设全周期数字化管控系统 |
CN107194861A (zh) * | 2017-07-02 | 2017-09-22 | 四川藏区高速公路有限责任公司 | 一种基于3dgis+bim的路网运营综合监控管理平台及方法 |
CN107194861B (zh) * | 2017-07-02 | 2020-11-06 | 四川藏区高速公路有限责任公司 | 一种基于3dgis+bim的路网运营综合监控管理平台及方法 |
CN108776837A (zh) * | 2018-04-09 | 2018-11-09 | 上海大学 | 基于建筑信息模型和虚拟现实技术的建筑运维管理系统和方法 |
CN108629037A (zh) * | 2018-05-11 | 2018-10-09 | 河南工业和信息化职业学院 | 一种智慧城市服务平台及其管理方法 |
CN108764668A (zh) * | 2018-05-15 | 2018-11-06 | 浙江大学 | 一种基于bim技术的设施管理系统及方法 |
CN109067822A (zh) * | 2018-06-08 | 2018-12-21 | 珠海欧麦斯通信科技有限公司 | 线上线下融合的实时混合现实城市服务实现方法及系统 |
CN109165329A (zh) * | 2018-07-09 | 2019-01-08 | 中兵勘察设计研究院有限公司 | 一种融合增强现实和物联网的地下管网智能管控技术及系统 |
CN109246195A (zh) * | 2018-08-13 | 2019-01-18 | 孙琤 | 一种融合增强现实、虚拟现实的管网智能管控方法及系统 |
CN109246195B (zh) * | 2018-08-13 | 2023-11-24 | 孙琤 | 一种融合增强现实、虚拟现实的管网智能管控方法及系统 |
CN109359751A (zh) * | 2018-10-26 | 2019-02-19 | 上海达实联欣科技发展有限公司 | 智能建筑运维管理系统及其管理方法 |
CN109460834A (zh) * | 2018-10-26 | 2019-03-12 | 上海达实联欣科技发展有限公司 | 建筑运维管理系统及其管理方法 |
CN109685704A (zh) * | 2019-01-14 | 2019-04-26 | 博拉网络股份有限公司 | 基于vr的管网巡检系统 |
CN109685704B (zh) * | 2019-01-14 | 2023-07-25 | 博拉网络股份有限公司 | 基于vr的管网巡检系统 |
CN110069045A (zh) * | 2019-04-11 | 2019-07-30 | 广州番禺职业技术学院 | 基于bim、vr及物联网的污水处理厂无人值守方法和智能管理平台 |
CN110222434A (zh) * | 2019-06-12 | 2019-09-10 | 璞耐特(大连)科技有限公司 | 基于工业4.0的防水卷材智能制造加工安装方法 |
CN110222434B (zh) * | 2019-06-12 | 2023-05-12 | 璞耐特(大连)科技有限公司 | 基于工业4.0的防水卷材智能制造加工安装方法 |
CN111562547A (zh) * | 2020-07-13 | 2020-08-21 | 中铁第一勘察设计院集团有限公司 | 一种监测元件3d可视化方法及系统 |
CN111782756A (zh) * | 2020-09-04 | 2020-10-16 | 万基泰科工集团(四川)有限公司 | 一种城市地下管网全生命周期安全管控集成系统 |
CN113656858A (zh) * | 2021-07-02 | 2021-11-16 | 中建七局安装工程有限公司 | 基于激光扫描点云与bim模型的双球嵌套结构数模比对方法 |
CN113656858B (zh) * | 2021-07-02 | 2024-01-30 | 中建七局安装工程有限公司 | 基于激光扫描点云与bim模型的双球嵌套结构数模比对方法 |
CN114910125A (zh) * | 2022-05-12 | 2022-08-16 | 武汉理工大学 | 一种基于AR和IoT的管道监测系统及方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105938613B (zh) | 2021-08-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105938613A (zh) | 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 | |
Liu et al. | Dynamic BIM-augmented UAV safety inspection for water diversion project | |
CN108399652B (zh) | 城市地下管线三维监测模型建立的方法、装置、存储介质与终端设备 | |
US20190371055A1 (en) | 3d monitoring server using 3d bim object model and 3d monitoring system comprising it | |
CN106407540B (zh) | 一种基于三维gis技术的地下管线辅助规划审核方法 | |
CN103778566A (zh) | 基于三维可视化展示的火电厂监测方法 | |
CN106595565A (zh) | 一种基于bim的智能化监测系统 | |
CN103632240B (zh) | 一种输电线路三维可视化运行系统及其建立方法 | |
CN104899922A (zh) | 一种智能电网可视化应用的三维全息生成方法 | |
CN101630419A (zh) | 一种用于城市综合管网三维可视化系统的架构方法 | |
KR101450133B1 (ko) | 증강현실기반 지하매설물의 단면정보 제공 시스템 및 방법 | |
KR101876114B1 (ko) | 3d 모델링 구현을 위한 단말기, 서버, 이들을 포함하는 시스템 및 이를 이용하는 3d 모델링 방법 | |
CN104820759A (zh) | 管线设施的数据采集方法和系统 | |
CN107153744B (zh) | 地下三维管线决策系统 | |
CN104679822A (zh) | 一种地理国情外业调绘方法 | |
CN108491649A (zh) | 一种风电场数字化平台的设计方法以及处理设备 | |
KR20200005951A (ko) | 3차원 bim 객체 모델링 서버 및 이를 포함하는 3차원 bim 객체 모델링 시스템 | |
CN103383556B (zh) | 综合管线数据内外业一体化实时更新质量控制方法 | |
CN107944203A (zh) | 一种风速流线可视化的建筑设计方法 | |
CN108957507A (zh) | 基于增强现实技术的燃气管道泄漏处置方法 | |
CN109210383A (zh) | 基于nb-iot的城市燃气管线监测方法与系统 | |
CN105741340A (zh) | 一种用于网页展示的输电线路三维场景仿真方法和系统 | |
CN111914332A (zh) | 一种基于bim+ar技术地下管线识别和警示方法 | |
Li et al. | Mobile augmented reality-based visualization framework for lifecycle O&M support of urban underground pipe networks | |
KR101280210B1 (ko) | 이동 단말에서의 증강현실 기반 정보 제공 방법 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20200514 Address after: 361006 23 / F, 266 Lujiang Road, Siming District, Xiamen City, Fujian Province Applicant after: XIAMEN RUICHUANG ENERGY SAVING TECHNOLOGY Co.,Ltd. Address before: 063000 Hebei Province, Tangshan City Caofeidian Industrial Zone equipment manufacturing park Applicant before: RUICHUANG (TANGSHAN) ECOLOGICAL BUILDING TECHNOLOGY Co.,Ltd. |
|
TA01 | Transfer of patent application right | ||
GR01 | Patent grant | ||
GR01 | Patent grant |