CN108182298A - 基于bim的虚拟和现实交互校验系统 - Google Patents

基于bim的虚拟和现实交互校验系统 Download PDF

Info

Publication number
CN108182298A
CN108182298A CN201710993801.6A CN201710993801A CN108182298A CN 108182298 A CN108182298 A CN 108182298A CN 201710993801 A CN201710993801 A CN 201710993801A CN 108182298 A CN108182298 A CN 108182298A
Authority
CN
China
Prior art keywords
bim model
bim
scene
virtual
delivery module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710993801.6A
Other languages
English (en)
Inventor
戴鸣
戴一鸣
黄晓冬
张大镇
张月燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Architectural Design Research Institute Co Ltd
Original Assignee
Fujian Architectural Design Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Architectural Design Research Institute Co Ltd filed Critical Fujian Architectural Design Research Institute Co Ltd
Publication of CN108182298A publication Critical patent/CN108182298A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T13/00Animation
    • G06T13/203D [Three Dimensional] animation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明为一种基于BIM的虚拟和现实交互校验系统。它包括BIM模型数据库、信息转化模块、场景交付模块,BIM模型数据库:用于储存各类型BIM模型数据信息;信息转化模块:用来将BIM模型数据库内的BIM模型转化为场景交付模块能够表达的方式;场景交付模块:将BIM模型转化后的数据进行表达;BIM模型数据库、信息转化模块、场景交付模块依序连接。本发明用于设计各节点成果交付阶段,基于BIM模型数据,提供AR模式的图纸交付校验形式、VR模式的虚拟场景交付校验形式、3D打印模式的实体模型交付校验形式等三大类型,为项目各参与方沟通、交流、磋商、定案、决策等提供多种三维可视化形式。

Description

基于BIM的虚拟和现实交互校验系统
技术领域
本发明设计BIM领域,特别是一种基于BIM的虚拟和现实交互校验系统。
背景技术
传统形式的成果交付时按照合同约定的时间节点,召开项目成果交付(方案评审、图纸评审、技术交底等)会议,其展示设计成果方法主要是通过设计师针对方案本、图纸、图片、动画视频等文件进行讲解汇报。这种形式就存在表达不到位、理解不全面、效果与实际之间存在差距等问题。传统的多专业图纸校验,是通过图纸叠加,校验人员凭经验进行图纸校验,容易存在漏项、判断错误等问题。
发明内容
本实用新型的目的在于提供一种解决设计阶段成果向建设项目相关参与方“虚实”交付、校验问题的基于BIM的虚拟和现实交互校验系统。
本实用新型的目的通过如下技术方案实现:它包括BIM模型数据库、信息转化模块、场景交付模块,
BIM模型数据库:用于储存各类型BIM模型数据信息;
信息转化模块:用来将BIM模型数据库内的BIM模型转化为场景交付模块能够表达的方式;
场景交付模块:将BIM模型转化后的数据进行表达;
BIM模型数据库、信息转化模块、场景交付模块依序连接。
较之现有技术而言,本实用新型的优点在于:解决设计阶段成果向建设项目相关参与方“虚实”交付、校验问题;用于设计各节点成果交付阶段,基于BIM模型数据,提供AR(增强现实)模式的图纸交付校验形式、VR(虚拟现实)模式的虚拟场景交付校验形式、3D打印模式的实体模型交付校验形式等三大类型,为项目各参与方沟通、交流、磋商、定案、决策等提供多种三维可视化形式,减少因图纸表达不到位、专业知识欠缺等因素影响沟通、决策的情况。
附图说明
图1系本发明的基础示意图;
图2系本发明的工作原理图;
具体实施方式
下面结合说明书附图和实施例对本实用新型内容进行详细说明:
它包括BIM模型数据库、信息转化模块、场景交付模块,
BIM模型数据库:用于储存各类型BIM模型数据信息;
信息转化模块:用来将BIM模型数据库内的BIM模型转化为场景交付模块能够表达的方式;
场景交付模块:将BIM模型转化后的数据进行表达;
BIM模型数据库、信息转化模块、场景交付模块依序连接。
本系统主要解决设计阶段成果向建设项目相关参与方“虚实”交付、校验问题,使用者为建设项目各参与方。
根据使用方式,可以延伸出以下几种实施方式
实施例1
所述的信息转化模块为含有Lumion、Smart+、Fuzor中至少一种处理软件的处理设备;场景交付模块为VR设备。
VR(virtual reality)即虚拟现实,具有构想性(Imagination)、沉浸感(Immersion)、实时交互性(Interactivity)三大重要特征,是一种基于立体显示和传感器技术、动态环境建模技术、实时三维图形生成技术等多项核心技术,围绕虚拟环境表示的准确性、虚拟环境感知信息合成的真实性、人与虚拟环境交互的自然性、实时显示、图像生成等特性使得用户能够身临其境地感知虚拟环境,达到探索、认识客观事物的目的。
与传统形式对比,VR模式的虚拟场景交付校验形式是以BIM模型数据为基础,将其导入支持VR技术的设计软件中(如:Lumion、Smart+、Fuzor等设计软件)。通过相应软件平台与VR设备连接,建立虚拟交付场景,模拟建筑内外部空间的真实场景、制作漫游动画以及效果图。建设项目各参与方可身临其境的感知未来建筑的每一个构件信息及实际状态,并根据自身感受提供优化、改进方案,有利于决策层做出合理决策。
实施例2
所述的信息转化模块为含有3Dmax、Rhino、MakerBot中至少一种处理软件的处理设备;场景交付模块为3D打印设备。
因3D打印技术现状问题,如打印设备成本高、打印耗时长、打印耗材贵、打印精度受限等,3D打印模式的实体模型交付校验形式不作为"BIM+"模式下的主体交付形式,但可作为AR模式和VR模式的补充形式。
虽然3D打印技术存在一些瓶颈问题,但与手动切割模型方式对比,3D打印技术还是有准确率高、精度高等优势。3D打印模式的实体模型是依据BIM模型数据,按比例缩放,通过3D打印机打印实体模型,或按1:1比例,打印满足规范要求、可供实际使用的实体建筑。根据实际交付需求可选择采用粉末状金属材料的全彩3D打印实体模型或采用PLA粘合材料的单色3D打印实体模型。3D打印模式的实体模型交付校验形式主要用于建筑外部方案对比校验展示、内部关键节点关系对比校验展示等方向。
实施例3
所述的信息转化模块为对表现图制作、三维动画制作、VR模拟真实空间、文本制作的后期制作;场景交付模块为AR设备。
AR(Augmented Reality)即增强现实,将虚拟信息与实体信息进行无缝集成,使得“虚实”信息之间相互补充、相互交互、相互叠加,两者信息在同一画面或空间同时存在。
传统形式的成果交付时按照合同约定的时间节点,召开项目成果交付(方案评审、图纸评审、技术交底等)会议,其展示设计成果方法主要是通过设计师针对方案本、图纸、图片、动画视频等文件进行讲解汇报。这种形式就存在表达不到位、理解不全面、效果与实际之间存在差距等问题。传统的多专业图纸校验,是通过图纸叠加,校验人员凭经验进行图纸校验,容易存在漏项、判断错误等问题。
AR模式的图纸交付校验形式是将BIM模型信息叠加到工程图纸信息上,通过多媒体、场景融合、多传感融合等技术手段,实现“虚实”信息集成,具有实时交互性,其三维可视化的图纸交付形式能有效避免非本专业人员理解不到位的问题。软件自动校验图纸的表达内容是否存在违反标准、规范以及设计漏项,多专业间通过模型整合进行软件自动校验是否存在碰撞问题。
本系统主要解决设计阶段成果向建设项目相关参与方“虚实”交付、校验问题,使用者为建设项目各参与方。
系统用于设计各节点成果交付阶段,基于BIM模型数据,提供AR(增强现实)模式的图纸交付校验形式、VR(虚拟现实)模式的虚拟场景交付校验形式、3D打印模式的实体模型交付校验形式等三大类型,为项目各参与方沟通、交流、磋商、定案提供多种三维可视化形式,减少因图纸表达不到位、专业知识欠缺等因素影响沟通的情况。

Claims (4)

1.一种基于BIM的虚拟和现实交互校验系统,其特征在于:它包括BIM模型数据库、信息转化模块、场景交付模块,
BIM模型数据库:用于储存各类型BIM模型数据信息;
信息转化模块:用来将BIM模型数据库内的BIM模型转化为场景交付模块能够表达的方式;
场景交付模块:将BIM模型转化后的数据进行表达;
BIM模型数据库、信息转化模块、场景交付模块依序连接。
2.根据权利要求1所述的基于BIM的虚拟和现实交互校验系统,其特征在于:所述的信息转化模块为含有Lumion、Smart+、Fuzor中至少一种处理软件的处理设备;场景交付模块为VR设备。
3.根据权利要求1所述的基于BIM的虚拟和现实交互校验系统,其特征在于:所述的信息转化模块为含有3Dmax、Rhino、MakerBot中至少一种处理软件的处理设备;场景交付模块为3D打印设备。
4.根据权利要求1中任意一项所述的基于BIM的虚拟和现实交互校验系统,其特征在于:所述的信息转化模块为对表现图制作、三维动画制作、VR模拟真实空间、文本制作的后期制作;场景交付模块为AR/VR设备。
CN201710993801.6A 2016-10-25 2017-10-23 基于bim的虚拟和现实交互校验系统 Pending CN108182298A (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2016109390007 2016-10-25
CN201610939000 2016-10-25

Publications (1)

Publication Number Publication Date
CN108182298A true CN108182298A (zh) 2018-06-19

Family

ID=62545144

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710993801.6A Pending CN108182298A (zh) 2016-10-25 2017-10-23 基于bim的虚拟和现实交互校验系统

Country Status (1)

Country Link
CN (1) CN108182298A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109741010A (zh) * 2018-12-14 2019-05-10 四川省交通运输厅交通勘察设计研究院 一种基于bim和ar技术的道路交互式外业调查系统
CN111753353A (zh) * 2020-05-19 2020-10-09 中国一冶集团有限公司 基于bim技术的装配式住宅pc构件吊装模拟系统及方法
CN112487525A (zh) * 2020-11-18 2021-03-12 中国电建集团昆明勘测设计研究院有限公司 一种基于bim和ar的引水工程运行安全远程管控及会诊方法
CN112990860A (zh) * 2021-03-09 2021-06-18 中国电建集团华东勘测设计研究院有限公司 数字化移交方法及系统
CN114872324A (zh) * 2022-04-15 2022-08-09 华中科技大学 一种基于多维信息耦合调控性能的激光增材制造方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040257361A1 (en) * 2003-06-17 2004-12-23 David Tabakman Zale Lewis System, computer product, and method for creating and communicating knowledge with interactive three-dimensional renderings
CN105204793A (zh) * 2015-09-23 2015-12-30 中国十七冶集团有限公司 一种将bim和3d打印技术应用在施工中的方法
CN105938613A (zh) * 2016-06-27 2016-09-14 锐创(唐山)生态建筑科技有限公司 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法
CN106021674A (zh) * 2016-05-10 2016-10-12 扬州大学 一种基于bim技术的建设工程交互设计方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040257361A1 (en) * 2003-06-17 2004-12-23 David Tabakman Zale Lewis System, computer product, and method for creating and communicating knowledge with interactive three-dimensional renderings
CN105204793A (zh) * 2015-09-23 2015-12-30 中国十七冶集团有限公司 一种将bim和3d打印技术应用在施工中的方法
CN106021674A (zh) * 2016-05-10 2016-10-12 扬州大学 一种基于bim技术的建设工程交互设计方法
CN105938613A (zh) * 2016-06-27 2016-09-14 锐创(唐山)生态建筑科技有限公司 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109741010A (zh) * 2018-12-14 2019-05-10 四川省交通运输厅交通勘察设计研究院 一种基于bim和ar技术的道路交互式外业调查系统
CN111753353A (zh) * 2020-05-19 2020-10-09 中国一冶集团有限公司 基于bim技术的装配式住宅pc构件吊装模拟系统及方法
CN111753353B (zh) * 2020-05-19 2024-05-17 中国一冶集团有限公司 基于bim技术的装配式住宅pc构件吊装模拟系统及方法
CN112487525A (zh) * 2020-11-18 2021-03-12 中国电建集团昆明勘测设计研究院有限公司 一种基于bim和ar的引水工程运行安全远程管控及会诊方法
CN112990860A (zh) * 2021-03-09 2021-06-18 中国电建集团华东勘测设计研究院有限公司 数字化移交方法及系统
CN114872324A (zh) * 2022-04-15 2022-08-09 华中科技大学 一种基于多维信息耦合调控性能的激光增材制造方法
CN114872324B (zh) * 2022-04-15 2023-09-29 华中科技大学 一种基于多维信息耦合调控性能的激光增材制造方法

Similar Documents

Publication Publication Date Title
CN108182298A (zh) 基于bim的虚拟和现实交互校验系统
Shen et al. Augmented reality for collaborative product design and development
Wang et al. Mixed reality in architecture, design, and construction
Yue et al. WireDraw: 3D Wire Sculpturing Guided with Mixed Reality.
Ratti et al. Tangible User Interfaces (TUIs): a novel paradigm for GIS
Verlinden et al. Development of a flexible augmented prototyping system
CN102609991B (zh) 三维实体模型轻量化优化方法
CN109003325A (zh) 一种三维重建的方法、介质、装置和计算设备
CN106600709A (zh) 基于装修信息模型的vr虚拟装修方法
CN105679169A (zh) 一种铁路电子沙盘系统
CN110379240A (zh) 一种基于虚拟现实技术的水电站检修仿真培训系统
CN108881886A (zh) 一种基于相机矩阵技术实现在显示端进行大数据无损交互应用的方法
Tuker Training spatial skills with virtual reality and augmented reality
Laing Digital participation and collaboration in architectural design
Shakeri et al. How metaverse evolves the architectural design
Irlitti et al. Validating constraint driven design techniques in spatial augmented reality
Johnson et al. Human perception, virtual reality and the built environment
Liu The virtual reality technology in art design
Allen et al. Computer Aided Design: Past, Present, Future
Bennett et al. InstructiBlocks: Designing with Ambiguous Physical-Digital Models
Kuka et al. Deep space: high resolution VR platform for multi-user interactive narratives
Choi et al. Optimal close‐up views for precise 3D manipulation
Kulkarni et al. Virtual tools for safety and ergonomic evaluations of electric vehicle architecture
Yang et al. Application of augmented reality technology in smart cartoon character design and visual modeling
Huang et al. 3D Communication of Animated Character Image Visualization Based on Digital Media Perspectives

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination