CN105155562B - For the construction method of deep basal pit spring sealing - Google Patents

For the construction method of deep basal pit spring sealing Download PDF

Info

Publication number
CN105155562B
CN105155562B CN201510476177.3A CN201510476177A CN105155562B CN 105155562 B CN105155562 B CN 105155562B CN 201510476177 A CN201510476177 A CN 201510476177A CN 105155562 B CN105155562 B CN 105155562B
Authority
CN
China
Prior art keywords
spring
catchment covers
deep basal
pit
basal pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510476177.3A
Other languages
Chinese (zh)
Other versions
CN105155562A (en
Inventor
郭华新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei 20 Smelting Construction Co Ltd
Original Assignee
Hebei 20 Smelting Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei 20 Smelting Construction Co Ltd filed Critical Hebei 20 Smelting Construction Co Ltd
Priority to CN201510476177.3A priority Critical patent/CN105155562B/en
Publication of CN105155562A publication Critical patent/CN105155562A/en
Application granted granted Critical
Publication of CN105155562B publication Critical patent/CN105155562B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a kind of construction method for deep basal pit spring sealing, concretely comprise the following steps:A, to needing the spring for being blocked to position in deep basal pit bottom, lead is set between spring and center spring around each;B, at the spring of center dig catch pit;C, making catchment covers, flange is provided with the opening of catchment covers, is clasped center spring with catchment covers, and water pump is put into inside catchment covers;After d, catchment covers are installed, water pump is opened, the water burst collected in catchment covers is persistently extracted into outside catchment covers;E, the concreting to deep basal pit and catch pit are carried out in three steps, and the openend to catchment covers before the 3rd step concrete is poured blocks.The present invention is by afflux, confluxing, draw water, block etc. preferably resolves the gush problem that the deep basal pit bottom faced after the completion of regional deep pit digging coastal or along the lake occurs.The construction method is easily operated, efficiency of construction is high, it can also be used to the treatment of other regional spring problems.

Description

For the construction method of deep basal pit spring sealing
Technical field
It is specifically a kind of to be used for deep basal pit spring back cover the present invention relates to a kind of method of foundation ditch partial water burst treatment The construction method for the treatment of.
Background technology
With the development of urban underground space, the industrial infrastructure such as metallurgy, the electric power in coastal and along the lake area is built If during the deep foundation facility such as pump house, pond and open caisson it is more and more, the depth of China's deep basal pit is also deepened therewith.When Substrate is too deep below horizontal plane, and when area of base is larger, precipitation facility can then be subject to certain restrictions, and influences dewatering effect, Now substrate is it is possible that multiple springs water burst, the basic back cover construction of influence deep basal pit, not only schedule delays, also result in Great economic loss.
The patent of Patent No. 200920080532.5 be directed to such case, there is provided it is a kind of can be to the partial water burst of foundation ditch Act the polywater cover for damming, limit the flow direction that intercepts water, facilitate follow-up diversion and drainage works, the polywater cover includes that the whole body is sealed Close, the cover body of bottom opening, outlet pipe is provided with cover body, cover body is clasped the water burst position on foundation ditch, and will cover when using Body bottom insertion base soil certain depth, now water burst gradually assemble in mask body intracavity, air in cover body and be gathered in cover body Interior intercepting water enter diversion and drainage arrangement by outlet pipe.This method simple structure, can be very good to solve the office of foundation ditch Portion's burst problem, but air in cover body and intercept water and can not be completely exhausted out outside cover body, and to that can not be carried out at water burst thoroughly Closure.
The content of the invention
It is an object of the invention to provide a kind of construction method for deep basal pit spring sealing, to solve existing skill Construction effect present in treatment of the art at deep basal pit spring not substantially and the halfway problem of back cover.
What the present invention was realized in:
A kind of construction method for deep basal pit spring sealing, comprises the following steps:
A, according to site operation situation to needing the spring for being blocked to position in deep basal pit bottom, mark center spring Eye and the position at surrounding spring, are respectively provided with lead, by lead rubble around each between spring and center spring Fill into french drain;
B, catch pit is dug at the center spring at deep basal pit bottom, the size of catch pit according in deep basal pit bottom spring point Cloth and determine;
C, with steel plate make catchment covers, flange is provided with the opening on catchment covers top, with catchment covers by catch pit Center spring is clasped, and water pump is put into inside catchment covers and is installed from the opening on catchment covers top;
After d, catchment covers are installed, water pump is opened, by gushing for being collected from spring around and center spring in catchment covers Water is persistently extracted into outside catchment covers;
E, concreting is carried out to deep basal pit and catch pit and spring is blocked:To on catch pit in deep basal pit and catch pit Other spaces carry out the first step of concrete and pour in deep basal pit beyond side space;By in hole bottom to the catchment covers of catch pit The second step that portion position carries out concrete is poured, and prevents water from gushing out from catchment covers outside;After the completion of pumping for water pump in catchment covers, Water pump is taken out, is sealed with the top end opening under the cooperation of flange of the blank flange at catchment covers top end opening to catchment covers Stifled, the middle part after the completion of closure to catchment covers in catch pit carries out concrete with the space on surface on the basis of up to deep basal pit 3rd step is poured.
The thickness range of the steel plate for making the catchment covers is 6cm ~ 10cm.
The water pump being arranged in the catchment covers elects immersible pump as.
The particle size range of the rubble for lead to be filled into french drain is 20mm ~ 40mm.
The present invention sets lead by between spring around each and center spring, in the center spring at deep basal pit bottom Catch pit is dug at eye, the water burst at center spring and surrounding spring is pooled in the catchment covers of special facture, it is possible thereby to will The water burst at spring carries out centralized Control, and the concreting of large area sole plate can be carried out during central drainage.Catchment After the completion of pumping for water pump in cover, closed by blank flange, the construction of final stage concrete floor can be carried out, and And without increasing the expense of well-points dewatering again, operation is simple, effect is good.Lead rubble is filled into french drain, surrounding spring The water of intraocular does not interfere with pouring for its top concrete during flowing into catch pit by gutter, make the coagulation of deep basal pit Soil pours the draining with spring while carrying out, and shortens the construction period.
The present invention is preferably resolved in regional deep base coastal or along the lake by afflux, the process such as conflux, draw water, block The gush problem that the deep basal pit bottom that hole is faced after the completion of excavating occurs.The construction method is easily operated, efficiency of construction is higher, its Used tool makes relatively simple, it can also be used to the treatment of the spring problem of other regional soil layers.
Brief description of the drawings
Fig. 1 is the structural representation of deep basal pit spring of the present invention sealing.
Fig. 2 be deep basal pit spring back cover A-A to profile.
In figure:1st, deep basal pit, 2, deep basal pit bottom, 3, lead, 4, catch pit, 5, catchment covers, 6, flange, 7, water pump, 8, Blank flange, 9-1, the first casting concrete, 9-2, the second casting concrete, 9-3, the 3rd casting concrete, 10, basic upper table Face.
Specific embodiment
As depicted in figs. 1 and 2, the present invention comprising the concrete steps that for the construction method of deep basal pit spring sealing:
(1)According to site operation situation to needing the spring for being blocked to position in deep basal pit bottom 2, center is marked Spring and the position at surrounding spring, center spring be it is all need to block the spring in center in spring, surrounding spring is The spring of the need closure in addition to the spring of center.Lead 3 is respectively provided between spring and center spring around each, entirely The distribution of lead 3 is radial in center, and lead 3 is filled into french drain with rubble, and french drain can pass through the water in spring around Gutter does not interfere with pouring for its top concrete during flowing into catch pit 4, make the concreting of deep basal pit and spring The draining of eye is carried out simultaneously, efficiency of construction is improve, while shortening the construction period.The section of the lead 3 in the present embodiment It is square-section, its width is 500 millimeters, depth is 500 millimeters;Particle diameter model for lead 3 to be filled into the rubble of french drain Enclose is 20 millimeters ~ 40 millimeters.
(2)Catch pit 4 is dug at the center spring at deep basal pit bottom 2, the size of catch pit 4 is according to the Zhongquan of deep basal pit bottom 2 Eye distribution and determine.The length of catch pit 4 is 2 meters in the present embodiment, and width is 2 meters, is highly 2 meters.
(3)Catchment covers 5 are made with steel plate, flange 6 is provided with the opening on the top of catchment covers 5, with catchment covers 5 by catch pit Center spring in 4 is clasped, and water pump 7 is put into inside catchment covers 5 and is installed from the opening on the top of catchment covers 5.For The thickness range for making the steel plate of the catchment covers 5 is 6 centimetres ~ 10 centimetres.The lower shape of catchment covers 5 is vertical in the present embodiment Cube, its top is shaped as tetrapyamid shape, a diameter of 300 millimeters of flange 6 at the top end opening of catchment covers 5, makes catchment covers 5 What steel plate thickness was adopted is 8 centimetres.
(4)After catchment covers 5 are installed, water pump 7 is opened, will be collected from spring around and center spring in catchment covers 5 Water burst be persistently extracted into outside catchment covers 5.What the water pump 7 in the present embodiment was used is the suitable immersible pump 7 of lift.Catchment covers 5 The water burst at center spring and surrounding spring is pooled in catchment covers 5, the water burst at center spring and surrounding spring can be carried out Centralized Control, can carry out the concreting of large area sole plate during central drainage.
(5)Concreting is carried out to deep basal pit 1 and catch pit 4 and spring is blocked, its process point step of position three:To deep basal pit Other spaces carry out the first step of concrete and pour in deep basal pit 1 in 1 beyond catch pit 4 and the superjacent air space of catch pit 4, and it is mixed Solidifying soil is referred to as the first casting concrete 9-1;The second of concrete is carried out by hole bottom to the medium position of catchment covers 5 of catch pit 4 Step is poured, and prevents water from gushing out from the outside of catchment covers 5, and its casting concrete turns into the second casting concrete 9-2;In catchment covers 5 Water pump 7 draw water after the completion of, water pump 7 is taken out, it is right under the cooperation with flange 6 of the blank flange 8 at the top end opening of catchment covers 5 The top end opening of catchment covers 5 is blocked, to the middle part of catchment covers 5 in catch pit 4 with the base of up to deep basal pit 1 after the completion of closure The 3rd step that the space of plinth upper surface 10 carries out concrete is poured, and its concrete for being poured is referred to as the 3rd casting concrete 9-3. 3rd step concrete pour it is middle catchment covers 5 are carried out with blank flange 8 first to block closed measure, then poured, it was poured Without being further added by the precipitation well point of other forms in journey, the input cost for well-points dewatering is reduced, operation is simple, imitated It is really good.
The present invention solves the problems, such as gush well after the completion of the deep pit digging in area coastal or along the lake, the construction party Method is easily operated, it can also be used to the treatment of spring problem in other regional soil layers.

Claims (3)

1. a kind of construction method for deep basal pit spring sealing, it is characterized in that, comprise the following steps:
A, according to site operation situation to needing the spring for being blocked to position in deep basal pit bottom, mark center spring and The position at surrounding spring, lead is respectively provided with around each between spring and center spring, and lead is filled into rubble French drain;
B, catch pit is dug at the center spring at deep basal pit bottom, the size of catch pit is according to the distribution at spring in deep basal pit bottom Determine;
C, catchment covers are made with steel plate, flange is provided with the opening on catchment covers top, with catchment covers by the center in catch pit Spring is clasped, and water pump is put into inside catchment covers and is installed from the opening on catchment covers top, for making described catchmenting The thickness range of the steel plate of cover is 6cm ~ 10cm, catchment covers(5)Lower shape be cube, its top is shaped as rectangular pyramid Shape, catchment covers(5)Flange at top end opening(6)A diameter of 300 millimeters;
After d, catchment covers are installed, water pump is opened, the water burst collected from spring around and center spring in catchment covers is held It is continuous to be extracted into outside catchment covers;
E, concreting is carried out to deep basal pit and catch pit and spring is blocked:It is empty to catch pit in deep basal pit and catch pit top Between beyond deep basal pit in other spaces carry out the first step of concrete and pour;By hole bottom to the middle position of catchment covers of catch pit Putting carries out the second step of concrete and pours, and prevents water from gushing out from catchment covers outside;After the completion of pumping for water pump in catchment covers, by water Pumping goes out, and is blocked with the top end opening under the cooperation of flange of the blank flange at catchment covers top end opening to catchment covers, Middle part after the completion of closure to catchment covers in catch pit carries out the of concrete with the space on surface on the basis of up to deep basal pit Three steps are poured.
2. the construction method for deep basal pit spring sealing according to claim 1, it is characterised in that be arranged on institute The water pump stated in catchment covers elects immersible pump as.
3. the construction method for deep basal pit spring sealing according to claim 1, it is characterised in that for that will draw The particle size range that ditch fills into the rubble of french drain is 20mm ~ 40mm.
CN201510476177.3A 2015-08-06 2015-08-06 For the construction method of deep basal pit spring sealing Active CN105155562B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510476177.3A CN105155562B (en) 2015-08-06 2015-08-06 For the construction method of deep basal pit spring sealing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510476177.3A CN105155562B (en) 2015-08-06 2015-08-06 For the construction method of deep basal pit spring sealing

Publications (2)

Publication Number Publication Date
CN105155562A CN105155562A (en) 2015-12-16
CN105155562B true CN105155562B (en) 2017-05-31

Family

ID=54796580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510476177.3A Active CN105155562B (en) 2015-08-06 2015-08-06 For the construction method of deep basal pit spring sealing

Country Status (1)

Country Link
CN (1) CN105155562B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107604954A (en) * 2017-09-29 2018-01-19 上海宝冶集团有限公司 Ttom of pipe plugging construction method after deep basal pit push pipe
CN108677982A (en) * 2018-05-24 2018-10-19 中铁隧道局集团有限公司 Complex geological condition foundation pit substrate excavates Tunnel gushing treatment method
CN108824464A (en) * 2018-07-24 2018-11-16 北京首钢建设集团有限公司 A kind of whirling well deep building pit piping bottom sealing method
CN110847199A (en) * 2019-11-12 2020-02-28 中国二十冶集团有限公司 Construction method for drainage of underground water of deep foundation pit
CN114045848A (en) * 2021-11-17 2022-02-15 中建八局第四建设有限公司 Construction method for pit foundation in water inrush pit

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2147645C1 (en) * 1998-05-15 2000-04-20 Закрытое акционерное общество Промышленно-строительная фирма "Содружество" Method and device for lowering of ground water level in construction and operation of underground structures
CN101550701B (en) * 2009-04-30 2010-09-08 中冶实久建设有限公司 Method and device for treating partial water burst of foundation ditch
CN202610819U (en) * 2012-05-11 2012-12-19 天津二十冶建设有限公司 Foundation pit drainage system
CN203475467U (en) * 2013-08-28 2014-03-12 中建七局第二建筑有限公司 Base plate concrete bottom sealing structure
CN104060622B (en) * 2014-07-14 2016-02-10 云南建工第四建设有限公司 Steel drum Yield rainfall relation method is cheated in a kind of hole

Also Published As

Publication number Publication date
CN105155562A (en) 2015-12-16

Similar Documents

Publication Publication Date Title
CN105155562B (en) For the construction method of deep basal pit spring sealing
CN103510528B (en) For the blind drainage structure of underground structure anti-floating
CN109898533A (en) The built-in Precipitation Structure of raft plate, the shut-in well structure of dewatering well and shut-in well method
CN104805854A (en) Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment
CN103437379B (en) Post-cast strip construction and drainage method for base plate of basement
CN106677198A (en) Well plugging method under dynamic water level state
CN202577326U (en) Water lowering device for mine pit
CN202730785U (en) Anti-floating blind ditch water drainage structure for underground structure
CN105133619A (en) Construction method for deep foundation pit of elevator shaft
CN202202335U (en) Flow guiding and water draining structure in deep foundation pit
CN109723071A (en) The construction method of the double-deck steel drum Yield rainfall relation system built in basement bottom plate rear pouring tape
CN206538775U (en) The plugging structure of foundation ditch blind drainage
CN102425156A (en) Cross section-variable underground continuous wall and construction method thereof
CN207672587U (en) A kind of bedrock surface subsurface pressure water burst dredges structure
CN204080750U (en) Box-type suction foundation sluice structure
CN110185051A (en) Deep narrow excavation water discharge method
CN207143965U (en) Steel plate concrete combined type anti-floating water sealing structure
CN202055248U (en) Pile foundation mud pit
CN104652426B (en) A kind of saline soil area waterglass anticorrosion pile foundation construction method
CN204509922U (en) Underpasses structure
CN106013254B (en) A kind of construction method of the concrete works swaging die with skeleton
CN203213129U (en) Controllable non-return drainer
CN206706793U (en) A kind of combined relief well for being used to reduce artesian head pressure
CN207436077U (en) A kind of drainage of foundation pit structure
CN206829176U (en) A kind of prefabricated block brick assembled plastic drainage pipeline basis

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant