CN104652426B - A kind of saline soil area waterglass anticorrosion pile foundation construction method - Google Patents
A kind of saline soil area waterglass anticorrosion pile foundation construction method Download PDFInfo
- Publication number
- CN104652426B CN104652426B CN201410786171.1A CN201410786171A CN104652426B CN 104652426 B CN104652426 B CN 104652426B CN 201410786171 A CN201410786171 A CN 201410786171A CN 104652426 B CN104652426 B CN 104652426B
- Authority
- CN
- China
- Prior art keywords
- concrete
- waterglass
- steel bushing
- construction method
- pile foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/385—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/60—Piles with protecting cases
Abstract
The present invention relates to a kind of power system construction field, particularly a kind of saline soil area waterglass anticorrosion pile foundation construction method. A kind of saline soil area provided by the invention waterglass anticorrosion pile foundation construction method includes making bored concrete pile boring and concrete hand-hole, steel bushing is placed in described bored concrete pile is holed, waterglass is poured into described steel bushing, then penetration concrete in described concrete hand-hole, concrete pour into along with described, utilize and described in elevator, described steel bushing is slowly lifted up, described waterglass continues to pour into described steel bushing, after having constructed, described steel bushing is extracted, is all wrapped up by described waterglass outside described concrete. A kind of saline soil area provided by the invention waterglass anticorrosion pile foundation construction method, solve the problem using traditional anticorrosive difference of pile foundation construction method in saline soil area, achieving anticorrosive construction integration, have the features such as efficiency height, speed of application be fast, application prospect is extensive.
Description
Technical field
The present invention relates to a kind of power system construction field, particularly a kind of saline soil area waterglass anticorrosion pile foundation construction method.
Background technology
Power system mainly includes the electromotor in power plant, step-up substation, transmission line of electricity, stepdown substation, distribution system and user's composition, and wherein transmission line of electricity is the important component part of whole system.
Along with the fast development of electric utility, transmission line construction has been extended to salting soil, but the corrosion that the salinized soil in these areas is to tower bar basis, it is an insoluble big problem for a long time. Traditional method of executing is excavation pit, formwork in foundation ditch, then carries out reinforcing bar configuration, casting concrete, removes mould after concrete setting, finally also concrete foundation is carried out maintenance, construction period is longer, and the maximum problem in this basis is cannot be anticorrosive. The compound of the particularly sulfate of the salt in saline soil area, soil, villaumite and magnesium salt corrodes the most serious so that the life-span on basis, being less than a year of having just produced crack less than 10 years.
For solving these problems, need to invent a kind of suitable in saline soil area waterglass anticorrosion pile foundation construction method.
Summary of the invention
The problem that it is an object of the invention to use traditional anticorrosive difference of pile foundation construction method in saline soil area, it is provided that a kind of saline soil area waterglass anticorrosion pile foundation construction method.
A kind of saline soil area provided by the invention waterglass anticorrosion pile foundation construction method includes making bored concrete pile boring and concrete hand-hole, steel bushing is placed in described bored concrete pile is holed, waterglass is poured into described steel bushing, then penetration concrete in described concrete hand-hole, concrete pour into along with described, utilize and described in elevator, described steel bushing is slowly lifted up, described waterglass continues to pour into described steel bushing, after having constructed, described steel bushing is extracted, is all wrapped up by described waterglass outside described concrete.
Further, described steel bushing is double-deck.
Further, described steel bushing surrounds described concrete hand-hole.
Further, before pouring into described concrete in described concrete hand-hole, described waterglass should fill the bottom of described concrete hand-hole by described steel bushing.
Further, when utilizing described elevator slowly to be lifted up by steel bushing, it is ensured that lower than the described TOC poured into bottom described steel bushing.
A kind of saline soil area provided by the invention waterglass anticorrosion pile foundation construction method, solve the problem using traditional anticorrosive difference of pile foundation construction method in saline soil area, achieve anticorrosive construction integration, especially when work transmission line king-pile length is shorter, having the features such as efficiency height, speed of application be fast, application prospect is extensive.
Other features and advantages of the present invention will be set forth in the following description, and, partly become apparent from description, or understand by implementing the present invention. The purpose of the present invention and other advantages can be realized by structure specifically noted in the description write, claims and accompanying drawing and be obtained.
Accompanying drawing explanation
Accompanying drawing described herein is used for providing a further understanding of the present invention, constitutes the part of the application, and the schematic description and description of the present invention is used for explaining the present invention, is not intended that inappropriate limitation of the present invention. In the accompanying drawings:
Fig. 1 is the workflow diagram of a kind of saline soil area of the present invention waterglass anticorrosion pile foundation construction method;
Fig. 2 is the construction schematic cross-section of a kind of saline soil area of the present invention waterglass anticorrosion pile foundation construction method;
Fig. 3 is the construction plan structure schematic diagram of a kind of saline soil area of the present invention waterglass anticorrosion pile foundation construction method.
Wherein: 1, elevator; 2, injected hole; 3, concrete hand-hole; 4, concrete; 5, waterglass; 6, steel bushing.
Detailed description of the invention
Functional overview
Consider to use the problem of traditional anticorrosive difference of pile foundation construction method to make the present invention in saline soil area, it is provided that a kind of saline soil area waterglass anticorrosion pile foundation construction method, to solve relevant issues.
Below in conjunction with accompanying drawing, embodiments of the invention are illustrated. It should be noted that when not conflicting, embodiments of the invention and the technical characteristic in embodiment can be combined with each other, all within protection scope of the present invention. In addition, for the ease of describing, step number used below, but this should not be construed as limitation of the present invention, additionally, although illustrate logical order in flow charts in each step described in following methods, but in some cases, it is possible to perform shown or described step with the order being different from herein.
Embodiment of the method
According to embodiments of the invention, it is provided that a kind of saline soil area waterglass anticorrosion pile foundation construction method.
Fig. 1 illustrates the flow chart of the sound wave monitoring method according to the inventive method embodiment, comprises the steps:
Step S102, makes bored concrete pile boring and concrete hand-hole;
Step S104, places steel bushing in described bored concrete pile is holed, waterglass pours into described steel bushing, then penetration concrete in described concrete hand-hole, concrete pouring into along with described, utilize and slowly lifted up by described steel bushing described in elevator, described waterglass continues to pour into described steel bushing;
Step 106, after having constructed, extracts described steel bushing, is all wrapped up by described waterglass outside described concrete.
The details of above-mentioned process is described in detail below in conjunction with Fig. 2, Fig. 2 includes elevator (1), injected hole (2), concrete (4), waterglass (5), steel bushing (6).
(1) step S104
Described steel bushing is double-deck, and described steel bushing surrounds described concrete hand-hole.
It is preferred that before pouring into described concrete in described concrete hand-hole, described waterglass should fill the bottom of described concrete hand-hole by described steel bushing.
It is preferred that when utilizing described elevator slowly to be lifted up by steel bushing, it is ensured that lower than the described TOC poured into bottom described steel bushing.
A kind of saline soil area provided by the invention waterglass anticorrosion pile foundation construction method, solve the problem using traditional anticorrosive difference of pile foundation construction method in saline soil area, achieve anticorrosive construction integration, especially when work transmission line king-pile length is shorter, having the features such as efficiency height, speed of application be fast, application prospect is extensive.
The foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, for a person skilled in the art, the present invention can have various modifications and variations. All within the spirit and principles in the present invention, any amendment of making, equivalent replacement, improvement etc., should be included within protection scope of the present invention.
Claims (3)
1. a saline soil area waterglass anticorrosion pile foundation construction method, including: make bored concrete pile boring and concrete hand-hole, in described bored concrete pile is holed, place steel bushing, waterglass is poured into described steel bushing, then penetration concrete in described concrete hand-hole, concrete pour into along with described, utilizing elevator slowly to be lifted up by described steel bushing, described waterglass continues to pour into described steel bushing, after having constructed, described steel bushing is extracted, is all wrapped up by described waterglass outside described concrete; Described steel bushing is double-deck; Described steel bushing surrounds described concrete hand-hole.
2. method according to claim 1, before pouring into described concrete in described concrete hand-hole, described waterglass should fill the bottom of described concrete hand-hole by described steel bushing.
3. method according to claim 1, when utilizing described elevator slowly to be lifted up by steel bushing, it is ensured that lower than the described TOC poured into bottom described steel bushing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410786171.1A CN104652426B (en) | 2014-12-18 | 2014-12-18 | A kind of saline soil area waterglass anticorrosion pile foundation construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410786171.1A CN104652426B (en) | 2014-12-18 | 2014-12-18 | A kind of saline soil area waterglass anticorrosion pile foundation construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104652426A CN104652426A (en) | 2015-05-27 |
CN104652426B true CN104652426B (en) | 2016-06-08 |
Family
ID=53244020
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410786171.1A Active CN104652426B (en) | 2014-12-18 | 2014-12-18 | A kind of saline soil area waterglass anticorrosion pile foundation construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104652426B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638166B (en) * | 2016-12-02 | 2019-01-04 | 中铁二院工程集团有限责任公司 | A kind of richness salt weakness saline soil area non-fragment orbit embankment structure |
CN110618254B (en) * | 2019-10-22 | 2021-11-23 | 中铁七局集团第三工程有限公司 | Test device for measuring saline soil collapsibility |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3104170A1 (en) * | 1980-09-29 | 1982-05-13 | Günter 5608 Radevormwald Helmdach | LOAD-BASED BASE ELEMENT, ESPECIALLY FROM STEEL CONCRETE |
CN101538868A (en) * | 2009-02-06 | 2009-09-23 | 青海省电力设计院 | Everfrost and saline soil region transmission line pole glass fiber reinforced plastic foundation construction method |
CN102966095A (en) * | 2011-08-31 | 2013-03-13 | 邹洁 | Compound pile cast with concrete on site and filled with sand and construction method thereof |
CN102926398B (en) * | 2012-10-10 | 2016-09-07 | 青海省电力设计院 | A kind of for Salt Lake Area iron tower of power transmission line bolts of inclined column type anti-corrosion foundation construction method |
CN203514342U (en) * | 2013-10-22 | 2014-04-02 | 青海省电力设计院 | Corrosion resistant precast pile for gas insulated substation (GIS) device foundation in transformer substation in salt lake area |
-
2014
- 2014-12-18 CN CN201410786171.1A patent/CN104652426B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104652426A (en) | 2015-05-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104652443B (en) | Construction method of the interim horizontal support of deep basal pit as permanent structure beam | |
CN104805854A (en) | Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment | |
CN103290811A (en) | Combined type groove with building formwork structure | |
CN103485370B (en) | A kind of concrete construction control method preventing wallboard harmful cracks | |
CN101538868A (en) | Everfrost and saline soil region transmission line pole glass fiber reinforced plastic foundation construction method | |
CN105155562B (en) | For the construction method of deep basal pit spring sealing | |
CN104652426B (en) | A kind of saline soil area waterglass anticorrosion pile foundation construction method | |
CN204040026U (en) | For the prefabricated sleeve-perfusion compound pile of strong corrosive environment | |
CN107090848A (en) | A kind of ripple steel arch retaining wall | |
CN103967006A (en) | Prefabricated sleeve and cast-in-place pile combination used for highly-corrosive environment and construction method thereof | |
CN103741651B (en) | A kind of concrete teeth groove stiling basin and construction method thereof | |
CN103590508B (en) | A kind of construction method of composite thermal-insulating wall | |
CN104890434A (en) | Plastic-stone landscape making method | |
CN205677030U (en) | A kind of drainage inspection well backfill structure | |
CN204418229U (en) | Poured band of outer wall of basement concrete draw-in groove | |
CN204000919U (en) | A kind of novel from drainage type tower-crane foundation structure | |
CN202247924U (en) | Assembled steel structure open caisson in pipe jacking construction | |
CN207260295U (en) | A kind of steel caisson template for being used for underwater big permeable geology drainage inspection well and pouring | |
CN105484260A (en) | Design and construction method for resisting crack, preventing seepage and stopping floating for large-area basement structure bodies | |
CN203848836U (en) | Column type marking pier | |
CN209260687U (en) | A kind of assembled marine hydrology station structure | |
CN103924614B (en) | A kind of shaft tower split raft foundation fast-assembling basis | |
CN206829176U (en) | A kind of prefabricated block brick assembled plastic drainage pipeline basis | |
CN106480896A (en) | Open caisson preliminary sedimentation method when large-scale well-sinking sinks | |
CN208267067U (en) | A kind of building basement bottom plate catch pit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |