CN202202335U - Flow guiding and water draining structure in deep foundation pit - Google Patents
Flow guiding and water draining structure in deep foundation pit Download PDFInfo
- Publication number
- CN202202335U CN202202335U CN2011202836594U CN201120283659U CN202202335U CN 202202335 U CN202202335 U CN 202202335U CN 2011202836594 U CN2011202836594 U CN 2011202836594U CN 201120283659 U CN201120283659 U CN 201120283659U CN 202202335 U CN202202335 U CN 202202335U
- Authority
- CN
- China
- Prior art keywords
- water draining
- deep foundation
- flow guiding
- foundation pit
- weeper drain
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances data:image/svg+xml;base64,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 data:image/svg+xml;base64,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 O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title abstract description 13
- 238000005266 casting Methods 0.000 claims abstract description 6
- 230000002093 peripheral Effects 0.000 claims abstract description 3
- 239000004575 stone Substances 0.000 claims description 5
- 239000004576 sand Substances 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 13
- 238000005516 engineering process Methods 0.000 abstract description 5
- 238000004062 sedimentation Methods 0.000 abstract 2
- 238000004519 manufacturing process Methods 0.000 abstract 1
- 238000009435 building construction Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
Abstract
This utility model discloses a flow guiding and water draining structure in a deep foundation pit, relating to the field of engineering constructions, specifically to flow guiding and water draining construction technology in a deep foundation pit; the flow guiding and water draining structure disclosed by this utility model comprises water draining blind ditches and water collecting wells, wherein the water draining blind ditches are arranged below a back casting zone and arranged in an inner circumferential side of a shear wall of a peripheral basement respectively; intersection points of the water draining blind ditches are provided with the water collecting wells; according to the water draining structure disclosed by this utility model, accumulated sedimentation of a building is controlled within 30mm without uneven sedimentation or serious potential safety hazards; all basements are not leaked, thus, the structure disclosed by this utility model is accorded with a demand of safety production.
Description
Technical field
The utility model relates to the engineering construction field, especially drainage in the deep foundation ditch, drainage construction technology.
Background technology
In the building construction of drainage in deep foundation ditch, draining, if engineering is positioned at the area that building is concentrated, the job location surrounding building is more; Then under the deep situation of job location foundation depth; Do not possess and adopt the conventional drainage and construction method that falls, if, will cause sinking of ground because adopted the conventional drainage construction that falls; Make the ground building settlement that sink, thereby cause the generation of security incident.Therefore, for exempting the surrounding enviroment influence and satisfying construction requirement, need solve drainage, the drainage problem in the deep foundation ditch with specific construction technology.
Summary of the invention
The utility model job location to be solved surrounding building more for a long time; If adopted the conventional drainage construction that falls; Will cause sinking of ground, make the ground building settlement that sink, thereby cause the problem of the generation of security incident; A kind of drainage in the job location surrounding building deep foundation ditch more for a long time, discharge structure of being suitable for is provided, and this structure is guaranteed the problem of basic concrete quality, environmental protection.
Drainage discharge structure in the deep foundation ditch of the utility model is characterized in that comprising weeper drain and collecting well, and weeper drain is separately positioned on below, ater-casting and peripheral basement shear wall inner rim, and the weeper drain interface point is provided with collecting well.
Described weeper drain is to be filled by third kind of stone of 50~100mm, spreads one deck Dense mesh screen above that as forming at a distance from sand bed.On the draining blind shaft the more square one-tenth of backfill secretly put drainage channel.This blind shaft is so that the not infiltration of closed period of underground water during the pump drainage foundation construction and ater-casting.
Third kind of stone packed height of described weeper drain is 50cm, and width is 50~70cm.
Retaining wall seepage part and base plate seep water in a large number and a little can take to concentrate water conservancy diversion in the ponding well with many plastic pipes around the foundation ditch.The uninterrupted pump drainage of concentrating recharges, and guarantees that falling draining can not cause security implication to the foundation ditch retaining wall, simultaneously to the retaining wall shape observation of fissioning, guarantees that sole plate construction period does not produce seeping phenomenon.Guarantee the smooth implementation of base concrete pouring quality and engineering.
Adopt the discharge structure of the utility model, building adds up settlement Control in 30mm, and differential settlement and major safety risks do not occur; None seepage of basement, engineering is accomplished according to the requirement of Construction unit, designing unit smoothly, has not only guaranteed the quality and the progress of engineering; Effectively controlled engineering cost; And improved the construction technology level, and to have controlled preferably with the influence of construction neighboring buildings and resident, the economic security effect is good.
Description of drawings
Fig. 1 is the structural representation of the utility model embodiment 1.
Fig. 2 is the utility model embodiment 1 section structure sketch map.
Wherein, weeper drain 1, collecting well 2, ater-casting 3.Basement shear wall 4.
The specific embodiment
Embodiment 1: drainage in the deep foundation ditch, discharge structure, and weeper drain 1 is set below building ater-casting 3, and is peripherally descending chamber shear wall 4 inner rims that weeper drain 1 is set, weeper drain 1 interface point is provided with collecting well 2.Weeper drain 1 is filled third kind of stone of 50~100mm, and packed height is 50cm, and width is 50cm, spreads one deck Dense mesh screen above that as separated sand bed, and the square one-tenth of backfill is secretly put drainage channel more afterwards.
Claims (3)
1. drainage discharge structure in the deep foundation ditch; It is characterized in that comprising weeper drain (1) and collecting well (2); Weeper drain (1) is separately positioned on below, ater-casting (3) and peripheral basement shear wall (4) inner rim, and weeper drain (1) interface point is provided with collecting well (2).
2. drainage discharge structure in a kind of deep foundation ditch as claimed in claim 1 is characterized in that described weeper drain (1) is to be filled by third kind of stone of 50~100mm, spreads one deck Dense mesh screen above that as forming at a distance from sand bed.
3. drainage discharge structure in a kind of deep foundation ditch as claimed in claim 1 is characterized in that third kind of stone packed height of described weeper drain (1) is 50cm, and width is 50~70cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011202836594U CN202202335U (en) | 2011-08-05 | 2011-08-05 | Flow guiding and water draining structure in deep foundation pit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011202836594U CN202202335U (en) | 2011-08-05 | 2011-08-05 | Flow guiding and water draining structure in deep foundation pit |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202202335U true CN202202335U (en) | 2012-04-25 |
Family
ID=45966467
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011202836594U Expired - Lifetime CN202202335U (en) | 2011-08-05 | 2011-08-05 | Flow guiding and water draining structure in deep foundation pit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202202335U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102677702A (en) * | 2012-06-11 | 2012-09-19 | 昆明一建建设集团有限公司 | Precipitation blocking method for post-cast strip of basement baseplate |
CN103628490A (en) * | 2013-12-16 | 2014-03-12 | 广东省建工设计院 | Underground water level precision adjustment system on earthen archaeological site |
CN106480979A (en) * | 2016-12-20 | 2017-03-08 | 江西中联建设集团有限公司 | A kind of active antiseepage basement shear wall and its construction technology |
CN110387908A (en) * | 2019-07-26 | 2019-10-29 | 深圳市建工集团股份有限公司 | The rear pouring tape construction method of multilayer constraint antiseep |
-
2011
- 2011-08-05 CN CN2011202836594U patent/CN202202335U/en not_active Expired - Lifetime
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102677702A (en) * | 2012-06-11 | 2012-09-19 | 昆明一建建设集团有限公司 | Precipitation blocking method for post-cast strip of basement baseplate |
CN103628490A (en) * | 2013-12-16 | 2014-03-12 | 广东省建工设计院 | Underground water level precision adjustment system on earthen archaeological site |
CN103628490B (en) * | 2013-12-16 | 2016-01-06 | 广东省建工设计院 | Underground water level precision adjustment system on earthen archaeological site |
CN106480979A (en) * | 2016-12-20 | 2017-03-08 | 江西中联建设集团有限公司 | A kind of active antiseepage basement shear wall and its construction technology |
CN106480979B (en) * | 2016-12-20 | 2019-07-09 | 中联建设集团股份有限公司 | A kind of active antiseepage basement shear wall and its construction technology |
CN110387908A (en) * | 2019-07-26 | 2019-10-29 | 深圳市建工集团股份有限公司 | The rear pouring tape construction method of multilayer constraint antiseep |
CN110387908B (en) * | 2019-07-26 | 2021-07-06 | 深圳市建工集团股份有限公司 | Multi-layer restraining anti-leakage post-pouring belt construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102116033B (en) | Method and device for dewatering and draining water collecting well of blind drain of deep foundation pit | |
CN103510528B (en) | For the blind drainage structure of underground structure anti-floating | |
CN202202335U (en) | Flow guiding and water draining structure in deep foundation pit | |
CN100510281C (en) | Semi-inverse construction method of super large diameter, ultra-burial depth storage pond | |
CN209923959U (en) | Open caisson structure for dry-process operation of high-groundwater-level soft soil field | |
CN101713197A (en) | Method for sealing foundation pit pressure reduction well | |
CN110847199A (en) | Construction method for drainage of underground water of deep foundation pit | |
CN104775439A (en) | Foundation pit support and water stop integrated structure and construction method thereof | |
CN212477844U (en) | Basement drainage decompression anti-floating structure | |
CN103967015B (en) | A kind of water seal for deep foundation pit excavation method and structure thereof | |
CN105155562A (en) | Construction method for bottom sealing treatment of spring openings of deep foundation pit | |
CN202730785U (en) | Anti-floating blind ditch water drainage structure for underground structure | |
CN103321233B (en) | The preparation method of groundwater resources retracting device in landslide deep layer draining and sliding mass | |
CN100575616C (en) | Vacuum curtain water stop and atmospheric pressure support deep pit digging construction method | |
CN105421498B (en) | A kind of foundation ditch water-impervious and subsidence control method based on three-dimensional curtain gang of wells system | |
CN203939036U (en) | A kind of steel sheet pile cofferdam structure that is applicable to river course | |
CN203320576U (en) | Waterproof and drainage system for basement external wall of super high-rise buildings | |
CN202247922U (en) | Water lowering and discharging device for water collecting well in blind ditch with deep base pit | |
CN107700434A (en) | A kind of dome grating formula armored concrete mud-rock flow blocking dam and its construction process | |
CN203939032U (en) | A kind of for upper lower the formula deep footing groove enclosing structure of wall of ground consisting of hard rock | |
CN203654332U (en) | Novel water prevention and dredge construction structure of basement | |
CN104846837A (en) | Construction method for ultra-deep well pit in surface drainage foundation pit | |
CN203320538U (en) | Water resource recycling and deep drainage device for landslides and underground water inside landslides | |
CN203475453U (en) | Deeply-buried type bearing platform curtain structure of bridge | |
CN207047796U (en) | A kind of light-duty mud-rock flow arch blocking dam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
C14 | Grant of patent or utility model | ||
CX01 | Expiry of patent term |
Granted publication date: 20120425 |
|
CX01 | Expiry of patent term |